MONTHYEARML20217E0461997-09-25025 September 1997 Forwards RAI to Complete Review of Licensee Request to Increase Sfsp Capacity at Plant,Unit 3 Project stage: RAI ML20211L6531997-10-0808 October 1997 Advises That Info Submitted Per 970327 Amend Application Re Increasing Spent Fuel Pool Storage Capacity & Increasing Maximum Fuel Enrichment Will Be Withheld from Public Disclosure,Per 10CFR2.790 Project stage: Other IR 05000382/19970171997-10-23023 October 1997 Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program Evaluation Project stage: Request ML20199F3081997-11-19019 November 1997 Forwards RAI Re Request to Increase Sf Storage Capacity at Plant,Unit 3.Response Requested within 30 Days from Date of Ltr Project stage: RAI ML20198H3421997-12-31031 December 1997 Forwards Request for Addl Info Re 970327 & 1023 Requests to Increase Spent Fuel Storage Capacity at Waterford Steam Electric Station,Unit 3 Project stage: RAI ML20217K4081998-04-0202 April 1998 Forwards RAI Re Ltr, as Supplemented by 970403, 1023,1212 & s,Requesting Increase in Sf Storage Capacity at Plant,Unit 3.Addl Info Requested Re Adequacy Radiological Assessment for Spent Fuel Pool Reracking Project stage: RAI ML20205J0901999-04-0202 April 1999 Informs That Info Submitted by & 970313 Affidavit Will Be Withheld from Public Disclosure,Per 10CFR2.790(b) (5) Project stage: Other 1997-12-31
[Table View] |
Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program EvaluationML20217K888 |
Person / Time |
---|
Site: |
Waterford |
---|
Issue date: |
10/23/1997 |
---|
From: |
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
---|
To: |
|
---|
Shared Package |
---|
ML20217K868 |
List: |
---|
References |
---|
50-382-97-17, NUDOCS 9710300105 |
Download: ML20217K888 (14) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000382/19980021998-03-20020 March 1998 Insp Rept 50-382/98-02 on 980202-20.No Violations Noted. Major Areas Inspected:Current Performance & Effectiveness of Corrective Action Program Including Audits & Assessments, Operations & Engineering ML20216E1461998-03-12012 March 1998 Insp Rept 50-382/98-07 on 980302-06.Violations Noted.Major Areas Inspected:Plant Support ML20216E5991998-03-12012 March 1998 Insp Rept 50-382/98-05 on 980202-12.Violations Noted.Major Areas Inspected:Licensee Physical Security Program ML20216E7621998-03-12012 March 1998 Insp Rept 50-382/97-25 on 971201-980205.Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000382/19980031998-03-10010 March 1998 Insp Rept 50-382/98-03 on 980216-20.No Violations Noted. Major Areas Inspected:Operational Status of Emergency Preparedness Program ML20203L2171998-03-0303 March 1998 Insp Rept 50-382/98-04 on 980202-06.Violations Noted.Major Areas Inspected:Radiation Protection Program Including External Exposure Controls,Training Qualifications, Facilities & Equipment & Procedures & Documentation IR 05000382/19970281998-02-11011 February 1998 Insp Rept 50-382/97-28 on 971214-980131.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Activities IR 05000382/19980011998-01-29029 January 1998 Insp Rept 50-382/98-01 on 980112-15.No Violations Noted. Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radwaste/Matls Transportation Program.Quality Assurance Oversight,Training & Procedural Guidance Were Also Reviewed ML20198M2801998-01-12012 January 1998 Insp Rept 50-382/97-24 on 971102-1213.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20198C8871998-01-0505 January 1998 Insp Rept 50-382/97-26 on 971117-1205.No Violations Noted. Major Areas Inspected:Operator Activities Re Failure to Return Valve ACC-126A,auxiliary Component CWS Flow Control Valve,To Automatic Operation When Restoring CWS ML20198C4561998-01-0202 January 1998 Insp Rept 50-382/97-27 on 971117-1205.Violations Noted. Major Areas Inspected:Review of Licensee Identification That Plant Ventilation Sys Could Adversely Affect Level Indication for Refueling Water Storage Pool IR 05000382/19970181997-12-0505 December 1997 Insp Rept 50-382/97-18 on 971104-07.Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures Performed IR 05000382/19970211997-12-0202 December 1997 Insp Rept 50-382/97-21 on 970922-26 & 1006-10.Violation Noted.Major Areas Inspected:Engineering,Maintenance & Mgt Meetings IR 05000382/19970221997-11-19019 November 1997 Insp Rept 50-382/97-22 on 970921-0001.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970231997-11-0404 November 1997 Insp Rept 50-382/97-23 on 971006-10.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Waste Mgt Program Including Organization & Mgt Controls & Radioactive Effluent Monitoring IR 05000382/19970191997-10-24024 October 1997 Partially Withheld Insp Rept 50-382/97-19 on 970922-26 (Ref 10CFR73.21).No Violations Identified.Major Areas Inspected: Plant Support Re Land Vehicle Control Measures & Security Program IR 05000382/19970171997-10-23023 October 1997 Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program Evaluation IR 05000382/19970161997-10-17017 October 1997 Insp Rept 50-382/97-16 on 970810-0920.Violations Noted: Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970201997-10-0909 October 1997 Insp Rept 50-382/97-20 on 970922-26.Violations Noted.Major Areas Inspected:External & Internal Exposure Control Programs,Surveys,Monitoring & Control of Radioactive Matl & Quality Assurance 1999-09-08
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000382/19980021998-03-20020 March 1998 Insp Rept 50-382/98-02 on 980202-20.No Violations Noted. Major Areas Inspected:Current Performance & Effectiveness of Corrective Action Program Including Audits & Assessments, Operations & Engineering ML20216E1461998-03-12012 March 1998 Insp Rept 50-382/98-07 on 980302-06.Violations Noted.Major Areas Inspected:Plant Support ML20216E5991998-03-12012 March 1998 Insp Rept 50-382/98-05 on 980202-12.Violations Noted.Major Areas Inspected:Licensee Physical Security Program ML20216E7621998-03-12012 March 1998 Insp Rept 50-382/97-25 on 971201-980205.Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000382/19980031998-03-10010 March 1998 Insp Rept 50-382/98-03 on 980216-20.No Violations Noted. Major Areas Inspected:Operational Status of Emergency Preparedness Program ML20203L2171998-03-0303 March 1998 Insp Rept 50-382/98-04 on 980202-06.Violations Noted.Major Areas Inspected:Radiation Protection Program Including External Exposure Controls,Training Qualifications, Facilities & Equipment & Procedures & Documentation IR 05000382/19970281998-02-11011 February 1998 Insp Rept 50-382/97-28 on 971214-980131.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Activities IR 05000382/19980011998-01-29029 January 1998 Insp Rept 50-382/98-01 on 980112-15.No Violations Noted. Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radwaste/Matls Transportation Program.Quality Assurance Oversight,Training & Procedural Guidance Were Also Reviewed ML20198M2801998-01-12012 January 1998 Insp Rept 50-382/97-24 on 971102-1213.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20198C8871998-01-0505 January 1998 Insp Rept 50-382/97-26 on 971117-1205.No Violations Noted. Major Areas Inspected:Operator Activities Re Failure to Return Valve ACC-126A,auxiliary Component CWS Flow Control Valve,To Automatic Operation When Restoring CWS ML20198C4561998-01-0202 January 1998 Insp Rept 50-382/97-27 on 971117-1205.Violations Noted. Major Areas Inspected:Review of Licensee Identification That Plant Ventilation Sys Could Adversely Affect Level Indication for Refueling Water Storage Pool IR 05000382/19970181997-12-0505 December 1997 Insp Rept 50-382/97-18 on 971104-07.Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures Performed IR 05000382/19970211997-12-0202 December 1997 Insp Rept 50-382/97-21 on 970922-26 & 1006-10.Violation Noted.Major Areas Inspected:Engineering,Maintenance & Mgt Meetings IR 05000382/19970221997-11-19019 November 1997 Insp Rept 50-382/97-22 on 970921-0001.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970231997-11-0404 November 1997 Insp Rept 50-382/97-23 on 971006-10.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Waste Mgt Program Including Organization & Mgt Controls & Radioactive Effluent Monitoring IR 05000382/19970191997-10-24024 October 1997 Partially Withheld Insp Rept 50-382/97-19 on 970922-26 (Ref 10CFR73.21).No Violations Identified.Major Areas Inspected: Plant Support Re Land Vehicle Control Measures & Security Program IR 05000382/19970171997-10-23023 October 1997 Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program Evaluation IR 05000382/19970161997-10-17017 October 1997 Insp Rept 50-382/97-16 on 970810-0920.Violations Noted: Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970201997-10-0909 October 1997 Insp Rept 50-382/97-20 on 970922-26.Violations Noted.Major Areas Inspected:External & Internal Exposure Control Programs,Surveys,Monitoring & Control of Radioactive Matl & Quality Assurance 1999-09-08
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program PNO-IV-99-038A, on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily1999-10-0101 October 1999 PNO-IV-99-038A:on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support PNO-IV-99-038, on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 9908101999-09-15015 September 1999 PNO-IV-99-038:on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 990810 IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support PNO-IV-99-032A, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed1999-08-12012 August 1999 PNO-IV-99-032A:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs PNO-IV-99-032, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor1999-08-0303 August 1999 PNO-IV-99-032:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments ML20196C9461999-06-15015 June 1999 Notice of Violation from Insp Completed on 990422.Violation Noted:Licensee Failed to Consider Info Contained During Background Investigation Before Granting Temporary Unescorted Access to Contractor Employee IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20209B8581999-05-25025 May 1999 EN-98-046A:on 990524,staff Withdrew Proposed Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Severity Level III Problems Associated with ECCS & Afws IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support ML20207F1581999-03-0303 March 1999 Notice of Violation from Insp on 990125-29 & 0208-12. Violation Noted:Inspector Determined That Waterford Audits SA-98-025.1 & SA-98-036.1,dtd 980916,were Conducted by Individuals Not Independent of Program Mgt Being Audited IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities PNO-IV-98-054, on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area1998-11-19019 November 1998 PNO-IV-98-054:on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D0411998-10-29029 October 1998 Notice of Violation from Insp on 981005-08.Violation Noted: Inspectors Identified That Radiation Surveys to Evaluate Extent of Radiation Levels Had Not Been Performed Prior to Operations Personnel Entering Area ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20155D5021998-10-27027 October 1998 Notice of Violation from Insp on 980914-18.Violation Noted: Performance Tests of Protected Area Detection Sys Identified That Two Detection Zones Did Not Meet Design Criteria to Detect Test Individuals ML20154L0831998-10-0909 October 1998 Notice of Violation from Insp on 980726-0905.Violation Noted:On 980721,NRC Inspectors Found Door 206,vital Area Portal,Unlocked & Not in Alarm at Central Alarm Station ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-IV-98-045, on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site1998-09-28028 September 1998 PNO-IV-98-045:on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site PNO-IV-98-040, on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 9809231998-09-18018 September 1998 PNO-IV-98-040:on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 980923 IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles ML20236P2431998-07-10010 July 1998 Notice of Violation from Insp on 980503-0613.Violation Noted:On 980521,AP UNT-005-013 Was Not Implemented in That Impairment to Fire Door D150 Was Not Controlled IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place ML20249A9611998-06-16016 June 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $100,000.Violation Noted:Licensee Identified That Calculated Peak Fuel Cladding Temp Would Have Exceeded 2200 F Using Licensing Basis Analysis & HPSI Flow ML20151R9131998-06-0909 June 1998 EN-98-046:on 980616,notice of Proposed Imposition of Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Level III Problem Involving HPSI Flow Issues at Waterford-3 Facility IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20248F6801998-05-29029 May 1998 Notice of Violation from Insp on 980322-0502.Violation Noted:Licensee Failed to Establish Adequate Procedures for Operation of EDG When in No or Low Electrical Loading Condition in That No Specific Guidance Provided IR 05000382/19980991998-04-24024 April 1998 SALP Rept 50-382/98-99 for 961201-980321 ML20217B6731998-04-21021 April 1998 Notice of Violation from Insp on 980201-0321.Violation Noted:On Past Occasions,Engineer Operated Governor Valve on Emergency Feedwater Turbine W/O Direction or Concurrence of Shift Superintendent or Control Room Supervisor ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering 1999-09-08
[Table view] |
Text
.9-i
.:
_
- ENCLOSURE 2 ;
l U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Docket No.: 50-382 License No.: NPF 38
Report No.: _ _50-382/97-17
- Licensee: Entergy Operations, In Facility: Waterford Steam Electric Station, Unit 3 Location: Hwy.18 Killona, Louisiana Dates: September 29 through October 3,1997
.
Inspectors: Ryan Lantz, Reactor Engineer, Operations Branch Tom _McKernon, Reactor Engineer, Operations Branch Approved By: John Pellet, Chief, Operations Branch
.
Division of Reactor Safety -
_ ATTACHMENT: _ Supplemental Information 9710300105 971023 PDR 8 ADOCK 05000382 PM
-
..
! .
EXECUTIVE SUMMARY Waterford Steam Electric Station, Unit 7 NRC Inspection Report 50 382/97-1~
This inspection inc!uded a review of the licensed operator requalification program following the guidelines in inspection Procedure 71001, " Licensed Operator Requalification Program Evaluation."
Q0erations The facility's annual operating test for licensed operator requalification during the inspection period was administered September 29 and 30. The biennial comprehensive requalification written examination was administered on October 2. Inspection results are as follows:
- Severalimprovements were noted in the licensed operator requalification progra The most significant changes required operations management to observe and evaluate licensed operator training and improved the quality of training review group meetings and program feedback (Sections 05.1 and 05.4).
- The licensed operator requalification facility examiners administered and evaluated 3 the examinations professionally. The inspectors concurred with the facility evaluations (Section 05.1).
- Requalification examinations and remedial examinations were comprehensive, discriminated at the appropriate level, and were responsive to identified weaknesses (Sections 05.2 and 05.3).
- Overall, the licensed operator requalification training program effectively implemented a systems approach to training (Section 05.4).
- Licensed operator requalificr/ ion f acility audits were comprehensive, self-crit l cal, and identified areas for potential improvement (Section 07.1).
- Two instances were noted where operators were challenged by proceoures. For instance, one f ailure to maintain the emergency operating procedures as required by Technical Specifications resulted in a violation (Section 04.1).
- Good operator performance was observed in all aspects of the examination with some significant exceptions noted. All operators participating in the licensed operator requalification tests passed their evaluated examinations (Section 05.1).
Three-legged communications, procedure use, and peer checks were noted strengths (Section 04.1).
,
. . . . . . . .
-
. -.
t
,
. s l
! -3-
Weaknesses were observed in crew direction and oversight on the part of senior operators in the control room supervisor position (Section 04.1).
x I
l
._
. . _ .
Reoort Details Summarv of Plant Status The f acility_was at 100 porcent power for the duration of the inspection, and all observations were conducted during the day shift, coincident with conduct of the walkthrough examinations, l. Onorations 01- ' Conduct of Operations-01.1 General Observations Insoection Scoce During the in plant' task walkthrough section of the examinations,-the oxaminars observed the on-shift operators during routine operations of the f acility, Observations and Findinas The on shif t crews exhibited professional demeanor and the senior operators m'aintained a position of crew direction and oversight. Shift operators were professional and aware of current plant evolutions and work in progress, Conclusions .
The control room staff exhibited professionalism and good awareness of work in progres _04 _ Operator Knowledge and Performance 04.1 Ooerator Performance on Annual Reaualification Examinations
- insoection Scooe (71001)
The inspectors observed the performance of two crews, one shif t and one staf f, of-licensed operators during the dynamic simulator and job performance measure portions of the annual requalification operating examinatio [o
,
-5-b. Observatioris and Findinos The crews in the dynamic simulator consisted of two reactor operators, two senior operators, and one shift engineer who acted as the shift technical adviser. Each licensed operator was administered five job performance measures and participated in two dynamic simulator scenarios. The inspectors observed the licensee staff administer the dynamic simulator scenarios and some job performance measure The inspectors observed generally good examinee performance during the job performance measure section of the operating tes During the dynamic simulator and job performance measure portions of the examination, the inspectors observed the following generic behaviors among the operato s:
- Three-legged communications, procedure usage, and peer checks were noted strength * Although adequate, operators in the control room supervisor position displayed waak direction and oversight of crew activities. In each case, the observed weakness was compensated for by other crew member * The staff crew was weak in sharing information, which significantly challanged their ability to perform a prompt diagnosis of plant condition The operators have adopted three-way communications as a natural and expected practice. The inspectors observed consistent use of this method among control room operators a; well as with other technicians or managemenit outside of the control roo The inspectors observed consistent and generally apptcpriate use of alarm response procedures, abnormal operating procedures, and the emergency operating proceduret. Two challenges to the operators were noted in procedural guidance; one in response to a secondary system leak, such as feedwater, into the containment, and another in the interpretation of conditions required to meet the containment isolation safety function. Given clear indications of a feedwater leak inside containment, both crews entered the abnormal operating procedure for a reactor coolant system leak, which only provided guidance to confirm a reactor coolant leak was not in progress. Neither crew entered the procedure for abnormal steam generator water level control, which was more appropriate and provided more effective guidance for the feedwater leak. Additionally, one crew f ailed to recognize the indications for a feedwater break inside containment until post-emergency operating procedure entry formal diagnosis was conducte I
p. - ,
li l
-
6-One crew f ailed to close Containment Spray isolation Valves CS125A(B) following a manually initiated containment isolation and spray actuation, with f ailure of the containment spray pumps to properly operate. The operators also, subsequently and erroneously, declared the containment isolation safety function to be satisfie The guidance for closure of these valves to meet the containment isolation safety function was provided in Emergency Plan Procedure EP-002100, "TSC Activation, Operation, and Deactivation," however, this procedure was not referenced by tSe operators prior to TSC activation and manning, and no additional guidance was provided in the emergency operating procedures to ensure the containment spray containment isolation valves were closed given the above conditions. The licensee had modified these valves during the past outage to allow overriding the permissive signal for closure, but had not revised the emergency operating procedure The inspectors considered this condition as a violation of Technical Specifications 6.8.1.a for a f ailure to maintain the emergency operating procedures (50-382/9717-01).
Additionally, the senior operators in the control room supervisor positions had to be prompted in several instances by the board operators or the shif t supervisor to provide specific, timely direction to the crew. One contral room supervisor gave several broad scope directions, such as, " perform a rapid down power," without providing pertinent limitations or procedural references. The board operators compensated by adding the specific limitations on rate and procedural reference in the repeat back communication, which the control room supervisor acknowledged as conect. Both crews' control room supervisors required prompting by the shift supervisor to initiate the required actions in several instances. For example, one control room supervisor was directed to perform a crew brief then conduct a rapid shutdown. Following the brief, the control room supervisor hesitated, then sought the shift supervisor's concurrence to begin the shutdown, in another instance, the control room supervisor was procedurally guided to start a low pressure safety injection pump to meet containment temperature / pressure safety function success path criteria. The control room surervisor again sought the shift supervisor's permission to initiate low pressure safety injection instead of first performing the action, then informing the shift supervisor, Conclusions Operators exhibited general! _ cod knowledge and ability in all aspects of the requalification examination? Three-way communications, peer checking, and procedural usage were not i strengths. Crew direction and oversight was effective, although challenged by observed control room supervisor weaknesses. Procedures were observed to challenge the crews' timely and effective diagnosis of plant condition h.
L
,
[ Operator Training c.d Qualification 0 ReauaP'. cation Examination Administration Insoection Scoce (710011
- The inspectors observed the administration of all aspects of the requalification examination to determine the evaluators' ability to administer an examination and assess adequate performance through measurable criteria. The inspectors conducted interviews to determine the knowledge level of the managers, supervisors, and instructors with regard to the requalification program implementation. The inspectors also observed the fidelity of the plant simulator to support training and examination administratio Observations and FindiDSS Six training staff evaluators were observed administering the examinations, including preexamination briefings, observations of operator performance, individual and group
, evaluations of observations, techniques for job performance measure cuing, and final ,
evaluation documentation. The evaluators conducted the examinations professionally, with no inadvertent cuing, and were thorough in their documentation of observed weaknesses and areas for improvement. The inspectors also noted that the timing of the malfunctions during the dynamic simulator evaluations enabled evaluation of senior operator competencies, such as crew direction and oversight,
- and ability to prioritize and integrate plant status. The plant simulator fidelity supported the examinations and no fidelity issues were observe '
The inspectors observed the post scenario crew evaluation process. The evaluations were led by the designated lead examiner, with the operations manager participating in the evaluation. Each of the examiners participated in discussions of event observations, and strengths and weaknesses observed. The operations manager provided immediate operations feedback for expectations, as well as, an independent observation of crew actions. The inspectors noted that the involvement of an operations department representative in examination observations and evaluations was a significant strength of the training program, and although not formally documented in program requirements, revisions were in the approval process to make the operations evaluation involvement a requirement of the licensed operator training progra The evaluators passed all of the operators on all portions of the examinations. The inspectors concurred with the f acility evaluation F}
.
- Conclusions -
-The f acility examiners administered and evaluated the requalification examinations professionally. - Operations management involvement in the observation and evaluation of dynamic simulator scenarior. was a noted strength. The inspectora concurred with the facility evaluation .2 Recualification Written Examinations insoection Scone (71001) '
The inspectors reviewed the biennial comprehensive written examination that was-administered October 2,-1997. The examination was reviewed to evaluate its-
-
-
validity and compliance with facility program requirements. The examinations were reviewed using guidance of NUREG 1021, " Operator Licensing Examiner Standards,"
for construction, scope of coverage, and cognitive leve Observations and Findinos The biennial examinatiori c',uestions tested at the appropriate level of comprehension and were linked to important leaming objectives. The questions were operationally oriented and realistic. The examinations were well structured and comprehensiv The inspectors noted that the sample plan for the biennial written examinations specifically identified senior reactor operator only questions. The inspectors reviewed the designated questions and agreed that they were senior reactor operator level questions, sampled appropriately from 10 CFR 55.43 items and met the program requirements as described in NTI-OP-004, " Examination / Quiz Development," Revirion 5, Section 5. Conclusions
_
'The comprehensive biennial written requalification examinations administered by the facility were valid examinations, with appropriate scope, depth and cognitive leve l 9 .
!
-9-05.3 He. Qualification Annual Ooerating Test inmestfon Scone (71001)
The inspectors reviewed the annual operating test cdministered on September 29 and 30,1997. The inspectors used the guidance in NUilEG 1021 to determine the validity of the examinations to provide a basis for evaluating the examinee's knowledge of abnormal and emergency operating procedures and operation of plant systems. The inspectors also reviewed the licensee's administrative procedures for developing, administering, grading, and evaluating the examinations and conducted interviews with training management, instructors, evaluators, and examinees, Observations and Findings The licensee's training staff indicated that the guidelines of NUREG-1021 were substantially utilized for the development and edministration of the licensed operator requalification examination, in addition to the facility requalification training procedures. The licensee supplemented the guidance of NUREG-1021 with training instructions for the development, control, and cdministration of licensed operator requalification examinations and quizzes,2 year training plan development, makeup training, and remediation guidelines. The licensee's procedures were comprehensiv The job performance measures were in accordance with the guidance of NUREG-1021, contained performance standards that were clear and objective, and the critical task acceptance criteria were well defined and measurable. The scenarios were also developed using the guidance of NUREG 1021 and contained clearly stated objectives. The initial conditions of the scenarios were realistic and the scenarios consisted of related event The inspectors noted that a recent modif' cation to the plant involving the capability for remote closing of Containment Spray Containment Isolation Valves CS125A(B)
had been reviewed in training lectures, and was incorporated into the annual operating test dynamic simulator scenarios. However, the inspectors noted that, while t'.te design change package identified the emergency plan procedures for the technical support center requiring revision, it did not identify the emergency operating procedures. As such, the operators were required to rely upon memory and their training to close the valves rather than specific emergency operating procedure instructions. This condition was identified as a violation of regulatory requireinents and is further discussed in Section 04.1. Overall, dynamic simulator scenarios used during the requalification examination were adequately challenging and provided a good evaluative tool for operator competencie ,
(.
i-10- Conclusiorui The annuel operating examinations were comprehensive and discriminated at the appropriate leve .4. Review of Reaualification Prooram Guidance
^ IDsoection Scone (71001)
The inspection determined the effectiveness of the methodology used to develop and construct the requalification examinations and to assess the effectiveness of the examinations to identify retraining needs and measure the examinees' subject knowledge. The inspectors utilized the guidance of NUREG-1220, " Training Review Criteria and Procedures," Revision 1, to evaluate the requalification program's ability to meet Elements 4 and 5 of a systems approach to training. This evaluation included review of the feedback tracking system and remedial training progra Observations and Findinas The inspectors reviewed the requalification program guidance and verified that it met and implemented the requirements of 10 CFR 55.59, "Requalification."
The inspectors noted that program guidance contained in NTC-108, " Licensed Operator Requalification," Revision 5, contained specific guidance for development and securi:y of examinations, post examination activities, removal from shift for f ailures of examinations, and remedial training of individuals. The inspectors also noted that the program was planned for revision to additionally require that any operator who f ailed a periodic cycle simulator quiz would also be removed from on shift licensed duties until completion of remediation. The inspectors reviewed three remedial training programs that had beta established for operators that failed a training cycle examination. The remedial programs focuseo on identified weaknesses and adequately retested the operators prior to returning them to licensed dutie The inspectors noted that additional program revisions were planned by the licensee to address recent audit and self-assessment findings. The most significant of these
. changes involved mandatory operations management participation in evaluated dynamic simulator crew examinations and quizzes, a modification of the instructor feedback mechanism, and a more defined requirement for training review group meeting attendance and frequency. Although none of these changes had been formally adopted into the program, they were in the process of being implemented and the governing procedures were being rev%e ,
~
%
-
.
all-i 3'
-: .Conclusiog ,
. - The lice 1 sed operator requalification program effectively implemented a systems
_
approac h to training to identify operator performance and training weaknesses and *
,
modify the training and evaluation program to correct identified weaknesses.
,
07 ~ Quality Assurance in Operr. tor Training
!
L .1 Review of Ooerations Quality Assurance Audits Insoection Scone (71001)
'he inspectors reviewed the asults of Qualie, Assurance Audit SA 97-003.1,
,
" Performance, Training, and Qualification." dated August 21,1997, which included
- an audit of the licensed operator requalification program. The inspectors reviewed i additional audits of the licensed operator requalification program dated August 7 and t
September 3,1997, that were conducted by peer groups and outside organization ,
c Qhsgivations and Findinas
! The qur.fity assurance audit and the additional audits both utilized perso'nnel from
,
out:.ide the licensee's organization. All three audits were comprehensive and -
critical, with items for improvement noted in the reports. Training requests were __
initiated and tracked regarding the identified areas for improvement, f' Conclusion The licensed operator requalification program audits were comprehensive, self-
- critical, and identified areu, for potential improvement, which were being
~ incorporated by the licensee.
p . [V. Plant Sunopri -
'
F8- Miscellaneous Fire Protection issues
- F General Comments The inspectors observed general plant housekeeping incident to administration of the in plant job performance _section of the operating test. The f acility was reasonably
- clean and welllighted and the floors were clear and free from debris. The applicants
< were conscientious to note discrepancies and inform the main control room.
,
4
, . . , - _ . - . , . - - . . , , , ,,
__ _ ___
..
-12-V. Managsment Mee]]Dgs X1 Exit Meeting Summary The inspectore presented the inspection results to members of the licensee management and s;aff at the conclusion of the inspection on October 3,1997. The licensee acknowled0ed the findings presente The licensee did not identify as proprietary any intermetion or materials examined during the inspectio >
.
. . . .
.
.
.
_
- - _ _ ,
f_*
_ _ ATTACHMENT
- SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSCNS CONTACTED -
Lingriten M. Brandon, Licensing Supervisor R. Burski, Director, Plant Modifications and Constructinn E. Ewing, Director, Nuclear Safety and Regulatory Aff airs R. Fletcher,- Operations Training Supervisor T. Gaudet, Licensing Manager J. Hoffpauir, Operations Manager S. Hymel, Licensed Operator Trainer
. R. Killian, Quality Engineering Supervisor
-
-- T. Leonard, General Manager, Plant Operations
_
J. Lewis, Emergency Planning Manager-
-J. O'Hern, Director, Training-
- O. Pipkins, Licensing Engineering W. Smith, Simulator Supervisor LIST OF INSPECTION PROCEDURES USED IP 71001 Licensed Operator Requalification Program Evaluation
'
-LIST OF ITEMS OPENED-Onened 50-382/9717-01.-- VIO Failure to maintain emergency operating procedures
,.
PROCEDURES REVIEWED Trainina Audits
.- "Waterford Tieree Operations Assessment" September 3,1997
. -WESlRAIN Assessment "W3 Requalification Program" August 4-7,1997
. "W3 Quality Assurance Audit SA 97-003.1, Performance, Training and Qualification" August 21,199 ;
.
.
. .
. .. .. .
.
.
. . . . ... . . . . .
.
-2 Trainino Procedures
. NTP-006, " Control and Administration of Examinations," Revision 8, March 21, 1997
. NTC-108, " Licensed Operator Requahfication," Revision 5, September 27,1995
- NTI-OP-004, " Examination / Quiz Developmer.t," Revision 5
. NTI-OP-005, " Examination Administration," Revision 5
. NTI-OP-008, " Licensed Operator Requalification," Revision 2 Ooeratina Procedurej
. OP 901-201, " Steam Generator Level Control System Malfunction"
. OP 500 012, Revision 12, Annunciator Response Procedure for L20 " Containment Water Leakage Hi"
. OP 902-008. Revision 10 " Safety Function Recovery Procedure" Other Documentation
. Condition Reports: 96-0281, 97-0770, 0771,-0781,-0812,-1702,-2381
,
'
'~ '
'