EN-98-046:on 980616,notice of Proposed Imposition of Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Level III Problem Involving HPSI Flow Issues at Waterford-3 FacilityML20151R913 |
Person / Time |
---|
Site: |
Waterford |
---|
Issue date: |
06/09/1998 |
---|
From: |
Reis T, Satorius M NRC OFFICE OF ENFORCEMENT (OE) |
---|
To: |
|
---|
References |
---|
EN-98-046, EN-98-46, SECY-97-205-C, NUDOCS 9809010061 |
Download: ML20151R913 (2) |
|
|
---|
Category:ENFORCEMENT ACTION NOTIFICATIONS
MONTHYEARML20209B8581999-05-25025 May 1999 EN-98-046A:on 990524,staff Withdrew Proposed Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Severity Level III Problems Associated with ECCS & Afws ML20151R9131998-06-0909 June 1998 EN-98-046:on 980616,notice of Proposed Imposition of Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Level III Problem Involving HPSI Flow Issues at Waterford-3 Facility ML20140G4411997-05-0606 May 1997 EN-97-033:on 970509,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on Violation Re Cooling Water Flows to Containment Fan Coolers at Unit 3 Facility ML20133D0001996-12-20020 December 1996 EN-96-095:proposed Imposition of Civil Penalty of $50,000 Will Be Issued to Entergy Operations Inc.State of La Will Be Notified ML20058M6251993-12-0202 December 1993 EN-93-119:on 931207,notice of Proposed Imposition of Civil Penalty in Amount of $25,000 Isssued to Licensee.Action Based on Two Violations Associated W/Inoperability of One of Two Trains of Containment Spray ML20245H7971989-06-23023 June 1989 EN-89-065:on 890628,notice of Violation & Proposed Imposition of Civil Penalty in Amount of $50,000 Will Be Issued,Based on Failure to Properly Evaluate ASME Section XI Test Results for HPSI Pump B ML20151V1661988-08-15015 August 1988 EN-88-067:on 880818,notice of Proposed Imposition of Civil Penalty in Amount of $50,000 Issued to Licensee Based on Event in Which Inaccurate Reactor Vessel Water Level Indication Twice Resulted in Cavitation of Cooling Pump ML20212N2601986-08-27027 August 1986 EN-86-022A:on 860827,order Imposing Civil Penalty in Amount of $50,000 Issued.Action Based on Consideration of Util 860516 Response to EN-86-022 Re 851216 Changing of Operational Modes W/Inoperable Train ML20203B6221986-04-11011 April 1986 EN-86-022:on 860416,notice of Violation & Proposed Imposition of Civil Penalty in Amount of $50,000 Will Be Issued to Licensee.Action Based on Operational Modes on 851216 W/Inoperable Train of Containment Spray Sys ML20128D7271985-05-21021 May 1985 En-85-040:on or About 850524,notice of Violation & Proposed Imposition of Civil Penalties in Amount of $130,000 Will Be Issued to Licensee.Action Based on Violation Re Unacceptable Quality of End Product ML20202G0601985-04-10010 April 1985 EN-85-040A:on 850410,order Imposing Civil Penalties in Amount of $110,000 Issued.Action Based on Significant Weaknesses in Util Implementation of QA Program During Const 1999-05-25
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program PNO-IV-99-038A, on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily1999-10-0101 October 1999 PNO-IV-99-038A:on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support PNO-IV-99-038, on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 9908101999-09-15015 September 1999 PNO-IV-99-038:on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 990810 IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support PNO-IV-99-032A, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed1999-08-12012 August 1999 PNO-IV-99-032A:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs PNO-IV-99-032, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor1999-08-0303 August 1999 PNO-IV-99-032:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments ML20196C9461999-06-15015 June 1999 Notice of Violation from Insp Completed on 990422.Violation Noted:Licensee Failed to Consider Info Contained During Background Investigation Before Granting Temporary Unescorted Access to Contractor Employee IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20209B8581999-05-25025 May 1999 EN-98-046A:on 990524,staff Withdrew Proposed Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Severity Level III Problems Associated with ECCS & Afws IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support ML20207F1581999-03-0303 March 1999 Notice of Violation from Insp on 990125-29 & 0208-12. Violation Noted:Inspector Determined That Waterford Audits SA-98-025.1 & SA-98-036.1,dtd 980916,were Conducted by Individuals Not Independent of Program Mgt Being Audited IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities PNO-IV-98-054, on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area1998-11-19019 November 1998 PNO-IV-98-054:on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D0411998-10-29029 October 1998 Notice of Violation from Insp on 981005-08.Violation Noted: Inspectors Identified That Radiation Surveys to Evaluate Extent of Radiation Levels Had Not Been Performed Prior to Operations Personnel Entering Area ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20155D5021998-10-27027 October 1998 Notice of Violation from Insp on 980914-18.Violation Noted: Performance Tests of Protected Area Detection Sys Identified That Two Detection Zones Did Not Meet Design Criteria to Detect Test Individuals ML20154L0831998-10-0909 October 1998 Notice of Violation from Insp on 980726-0905.Violation Noted:On 980721,NRC Inspectors Found Door 206,vital Area Portal,Unlocked & Not in Alarm at Central Alarm Station ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-IV-98-045, on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site1998-09-28028 September 1998 PNO-IV-98-045:on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site PNO-IV-98-040, on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 9809231998-09-18018 September 1998 PNO-IV-98-040:on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 980923 IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles ML20236P2431998-07-10010 July 1998 Notice of Violation from Insp on 980503-0613.Violation Noted:On 980521,AP UNT-005-013 Was Not Implemented in That Impairment to Fire Door D150 Was Not Controlled IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place ML20249A9611998-06-16016 June 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $100,000.Violation Noted:Licensee Identified That Calculated Peak Fuel Cladding Temp Would Have Exceeded 2200 F Using Licensing Basis Analysis & HPSI Flow ML20151R9131998-06-0909 June 1998 EN-98-046:on 980616,notice of Proposed Imposition of Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Level III Problem Involving HPSI Flow Issues at Waterford-3 Facility IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20248F6801998-05-29029 May 1998 Notice of Violation from Insp on 980322-0502.Violation Noted:Licensee Failed to Establish Adequate Procedures for Operation of EDG When in No or Low Electrical Loading Condition in That No Specific Guidance Provided IR 05000382/19980991998-04-24024 April 1998 SALP Rept 50-382/98-99 for 961201-980321 ML20217B6731998-04-21021 April 1998 Notice of Violation from Insp on 980201-0321.Violation Noted:On Past Occasions,Engineer Operated Governor Valve on Emergency Feedwater Turbine W/O Direction or Concurrence of Shift Superintendent or Control Room Supervisor ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering 1999-09-08
[Table view] |
Text
_ . . . . . _ _ .. __ _. _. - - _ - . _ . _ - _. _ . . _ . _
l I
i June 9,1999 i EN 98-046 l OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION j
, licensee: Entergy Operations, Inc.
Waterford 3 Steam Electric Station Docket No. 50-382 Subiect: ~ PROPOSED IMPOSITION OF CIVIL PENALTY - $110,000 AND EXERCISE OF ENFORCEMENT DISCRETION ,
This is to inform the Commission that a Notice of Violation and Proposed Imposition of .
Civil Penalty in the amount of $110,000, will be issued on or about June 16,1998 to l
- Entergy Operations, Inc. for a Severity Level 111 problem involving High Pressure Safety Injection (HPSI) flow issues at its Waterford-3 facility. This also informs the Commission that the staff intends to exercise discretion pursuant to Section Vll.B.6 of the Enforcement Policy and refrain from proposing a civil penalty for a violation of 10 CFR 50.59, which is cited at Severity Level lil, involving a change to design flow in the Emergency Feedwater (EFW) system.
The Severity Level 111 problem involving the HPSI flow issues involves failing to address uncertainties in HPSI flow values, resulting in operating the Waterford-3 facility without assurance, as required by 10 CFR 50.46, that the emergency core cooling system was capable of limiting peak cladding temperatures to 2200* F. Subsequent to recognition of the uncertainties, the licensee was able to demonstrate functionality of the HPSI system using an updated analysis methodology that was ultimately approved by the NRC.
However, the significance of the violation is that, given the uncertainties, the licensee could not meet the 10 CFR 50.46 acceptance criteria using the analysis approved in its licensing basis at the time.
Because this was not the first escalated action within the past two years, the staff considered whether credit was warranted for / dent /f/ cation and Correct /ve Act/on. Credit for / dent /fication was not warranted because the discovery of these violations and the licensee's pursuit of the issues were prompted by an NRC engineering team inspection.
Credit for Correct /ve Act/on was also not warranted because, despite significant efforts on the part of the licensee to resolve the issues, its initial actions upon recognition of the .
problem were not prompt and not in compliance with reporting requirements of 10 CFR 50.46. Therefore, application of the Enforcement Policy results in a proposed civil penalty of $110,000.
The violation of 10 CFR 50.59 involving the EFW system, which is being cited at Severity Levellit with no civil penalty being proposed, is based on the licensee having reduced design basis EFW flows after recognizing that the assumed design basis flows could not be achieved by the EFW pumps. The licensee's safety evaluation for reducing design basis EFW flow from 700 gpm to 575 gpm failed to conclude that such a reduction constituted a reduction in the margin of safety and therefore involved an unreviewed safety question.
l l ,so,otoo61 N PDR IbE PDR EN-98-o46
2 EN 98-046 However, based on the specific circumstances of this case, the staff's consideration of the information the licensee presented at the conference, and the guidance given the staff in SECY-97-205, the staff has determined that the exercise of discretion pursuant to Section Vll.B.6 of the Enforcement Policy is appropriate and no civil penalty is being proposed, it should be noted that the licensee has not been specifically informed of the enforcement decision. The schedule of issuance of the report and notification is:
Mailing of Inspection Report June 16,1998 Telephone Notification of Licensee June 16.1998 The State of Louisiana be notified.
The licensee has thirty days from the date of the Notice in which to respond. Following NRC evaluation of the response, the civil penalty may be remitted, mitigated, or imposed by Order.
Contacts: T. Reis, OE, 415-3281 M. Satorius, OE, 415-2747 Distribution OWFN OWFN TWFN Regional Offices Chairman Jackson EDO OC RI RIV Comm. Dicus DEDE AEOD Ril WCFO Comm. Diaz OE OP CTR Rill Comm. McGamgan OGC NMSS SECY NRR IRM Mall OCA Of OlG NUDOCS PA SP RES PUBLIC IP CFO ACRS CIO PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION