IR 05000266/2024011
ML24256A032 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 09/18/2024 |
From: | April Nguyen NRC/RGN-III/DORS/RPB2 |
To: | Durbin M Point Beach |
References | |
EPID I-2024-011-0038 IR 2024011 | |
Download: ML24256A032 (1) | |
Text
SUBJECT:
POINT BEACH - BIENNIAL PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION REPORT 05000266/2024011 AND 05000301/2024011
Dear Michael Durbin:
On September 10, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed a problem identification and resolution inspection at Point Beach and discussed the results of this inspection with Kim Locke, Principal Engineering Analyst. The results of this inspection are documented in the enclosed report.
The NRC inspection team reviewed the stations problem identification and resolution program to confirm that the station was complying with NRC regulations and licensee standards. Based on the samples reviewed, the team determined that your program complies with NRC regulations and applicable industry standards such that the Reactor Oversight process can continue to be implemented.
The team also evaluated the stations effectiveness in identifying, prioritizing, evaluating, and correcting problems, reviewed licensee audits and self-assessments, and its use of industry and NRC operating experience information. The results of these evaluations are in the enclosure.
Finally, the team reviewed the stations programs to establish and maintain a safety-conscious work environment and interviewed station personnel to evaluate the effectiveness of these programs. Based on the teams observations and the results of these interviews, the team found no evidence of challenges to your organizations safety-conscious work environment. Your employees appeared willing to raise nuclear safety concerns through at least one of the several means available.
One finding of very low safety significance (Green) is documented in this report. This finding did not involve a violation of NRC requirements.
If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Point Beach.
September 18, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, April M. Nguyen, Team Leader Palisades Restart Team Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000266 and 05000301 License Numbers:
DPR-24 and DPR-27 Report Numbers:
05000266/2024011 and 05000301/2024011 Enterprise Identifier:
I-2024-011-0038 Licensee:
Nextera Energy Facility:
Point Beach Location:
Two Rivers, WI Inspection Dates:
July 15, 2024, to September 10, 2024 Inspectors:
M. Garza, Acting Team Lead J. Masse, Resident Inspector R. Ng, Senior Project Engineer A. Price, Resident Inspector Approved By:
April M. Nguyen, Team Leader Palisades Restart Team Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a biennial problem identification and resolution inspection at Point Beach, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Failure to Follow Corrective Action Program Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000266,05000301/2024011-01 Open/Closed
[H.1] -
Resources 71152B The inspectors identified a finding associated with the licensees failure to follow the Corrective Action Program procedure, PI-AA-101-100, Condition Reporting, to correct a procedural deficiency on Environmental Qualification (EQ) engineering change reviews.
Specifically, corrective actions to update the EQ program procedure, ER-AA-112, to include a detailed standard for more comprehensive EQ engineering change reviews, and to brief the engineering staff on the issue, were not initiated per the corrective action program procedure.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES - BASELINE
71152B - Problem Identification and Resolution Biennial Team Inspection (IP Section 03.04)
- (1) The inspectors performed a biennial assessment of the effectiveness of the licensees Problem Identification and Resolution program, use of operating experience, self-assessments and audits, and safety-conscious work environment.
- Problem Identification and Resolution Effectiveness: The inspectors assessed the effectiveness of the licensees Problem Identification and Resolution program in identifying, prioritizing, evaluating, and correcting problems. The inspectors also conducted a 5-year review Control Room Emergency Filtration System (CREFS). The corrective actions for the following non-cited violations were evaluated as part of the assessment: NCV 2022003-01, NCV 2022011-01, NCV 2022404-06, NCV 2023010-03, NCV 2023401-01, and NCV 2023404-02
- Operating Experience: The inspectors assessed the effectiveness of the licensees processes for use of operating experience.
- Self-Assessments and Audits: The inspectors assessed the effectiveness of the licensees identification and correction of problems identified through audits and self-assessments.
- Safety Conscious Work Environment: The inspectors assessed the effectiveness of the stations programs to establish and maintain a safety-conscious work environment.
INSPECTION RESULTS
Assessment 71152B Corrective Action Program Based on the samples reviewed, the team concluded that the licensees implementation of the Corrective Action Program (CAP) was generally effective and supported nuclear safety.
Effectiveness of Problem Identification:
Based on the samples reviewed, the team concluded that the licensee continued to identify issues at a low threshold and was appropriately entering these issues into the CAP. The team determined that the licensee usually entered problems into the CAP in a timely manner and with adequate information.
The team noted that issues were being identified by all levels of the organization and with varying degrees of safety significance. Some deficiencies were identified by external organizations, including the NRC, and they were subsequently entered into the CAP for resolution. The licensee also utilized a number of CAP support processes to identify problems, including the self-assessment and audit processes and the Operating Experience (OE) Program. Any identified deficiencies or improvement opportunities were entered into the CAP for resolution.
The team performed a 5-year review of the Control Room Emergency Filtration System (CREFS). As part of this review, the team reviewed plant health reports, selected corrective action and condition evaluation documents, and interviewed the system engineer. The team also performed a system walkdown to assess the material condition of system piping, selected components, and surrounding areas. The team concluded that, in general, deficiencies and concerns were identified and entered into the CAP at a low threshold.
Corrective actions appeared to be adequate and timely, commensurate with their safety significance.
The team determined that the station was generally effective at identifying negative trends that could potentially impact nuclear safety. For the areas reviewed, the team did not identify any issues of significance in problem identification.
Effectiveness of Prioritization and Evaluation of Issues:
Based on the samples reviewed, the team determined that licensee performance was generally effective at prioritizing and evaluating issues commensurate with the safety significance of the identified problem. The issue screening team and the management review committee meetings were generally thorough and intrusive in reviewing issues and prioritizing actions. In addition, the team observed a healthy dialogue between the members of these committees and the members challenged each other when dispositioning issues.
The inspectors also did a selective review of issues identified by the NRC either documented as observations, or for which findings or other enforcement was issued. These issues were properly documented and screened in the CAP. In general, the licensee thoroughly evaluated issues to ensure that resolutions address causes and extent of condition evaluations commensurate with their safety, security, and radiological significance in accordance with their CAP procedure.
Effectiveness of Corrective Actions:
Based on the samples reviewed, the team determined that the licensee was generally effective in corrective action implementation. In general, corrective actions for deficiencies that were safety significant were implemented in a timely manner. Problems requiring the performance of evaluations were resolved in accordance with CAP requirements. The team sampled assignments associated with violations and issues that were previously identified by the NRC. The team determined that the corrective actions sampled were generally effective and timely.
During their inspection, the team identified two issues related to implementation of corrective actions that needed to be dispositioned in the significance determination program because they potentially constituted more-than-minor safety significance. The evaluation of these issues are described in more detail in the section below.
Assessment 71152B Use of Operating Experience Based on the samples reviewed, the team determined that the licensees performance in the use of operating experience (OE) was generally effective. The licensee screened industry and NRC OE information for applicability to the station. When applicable, condition reports were written, and actions were developed and implemented to prevent similar issues from occurring. Overall, OE lessons learned were communicated and incorporated into plant operations. For the areas reviewed, the team did not identify any issues of significance with the use of operating experience.
Assessment 71152B Self-Assessments and Audits Based on the samples reviewed, the team determined that the licensees performance of self-assessments and audits was generally effective. The licensee performed department self-assessments and Quality Assurance audits throughout the organization on a periodic basis. These self-assessments and audits were generally effective at identifying issues and enhancement opportunities at an appropriate threshold. The team did not identify any issues of significance in the area of self-assessments and audits.
During the inspection, the team identified one issue related to corrective actions as a result of a self-assessment identified deficiency that that needed to be dispositioned in the significance determination program. The evaluation of this issue is described in more detail in the section below.
Assessment 71152B Safety Conscious Work Environment Based on a review of documents and interviews with licensee staff, the team did not identify any impediment to the establishment of a safety-conscious work environment. The team reviewed the results from recent safety culture self-assessments and had a discussion with the site Employee Concerns Program (ECP) Coordinator. The team also conducted one-on-one interviews with 25 licensee staff concerning the effectiveness of the CAP, the ability to raise issues, and the freedom from potential retaliation for raising issues. In general, the licensees staff was aware of and familiar with the CAP and other processes, such as the ECP, to raise nuclear safety concerns. Licensee staff indicated they could raise safety concerns without a fear of retaliation. Through the interviews and document reviews, the team did not identify, nor were any examples provided, of retaliation for raising nuclear safety concerns. The staff interviewed believed that operational issues and issues with high safety significance were being appropriately addressed in a timely manner. The team did not identify any issues of significance in the establishment of a safety-conscious work environment.
Failure to Follow Corrective Action Program Procedure Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000266,05000301/2024011-01 Open/Closed
[H.1] -
Resources 71152B The inspectors identified a finding associated with the licensees failure to follow the Corrective Action Program procedure, PI-AA-101-100, Condition Reporting, to correct a procedural deficiency on Environmental Qualification (EQ) engineering change reviews.
Specifically, corrective actions to update the EQ program procedure, ER-AA-112, to include a detailed standard for more comprehensive EQ engineering change reviews, and to brief the engineering staff on the issue, were not initiated per the corrective action program procedure.
Description:
During a review of the Environmental Qualification (EQ) Program for subsequent license renewal in 2022, the licensee identified that their EQ testing and analyses for the safety-related instrument cables to/from five EQ transmitters did not bound the postulated high energy line break conditions in all areas where these cables were routed. The licensee took immediate and long-term corrective actions to address the specific cabling issues.
However, during their evaluation of the deficiency, the licensee Organizational Effectiveness Investigation (OR) identified that the current EQ engineering change review process was too narrow and only focused on components installed in their specific locations. Specifically, licensee procedure, ER-AA-112, Environmental Qualification Program, did not provide a detailed standard for EQ engineering change reviews to consider respective power, control, or instrument cables potentially impacted by the change.
Per procedure PI-AA-101-100, Condition Reporting, Attachment 4, Guidance on the Classification of Condition Reports, a gap in program design or implementation of a 10 CFR 50 Appendix B or other regulatory required program, is a condition adverse to quality and is required to be corrected. To correct this specific procedural gap, which was a condition adverse to quality, the licensee prescribed corrective actions (CAs) to review the OR investigation as a case study with the fleet EQ engineering group and to update the program procedure, ER-AA-112, to include a detailed standard for more comprehensive EQ engineering change reviews. The licensees Management Review Committee, whose primary function was to provide oversight of corrective action program implementation, which included the review of new corrective actions, approved the OR and the CAs on February 15, 2023. However, the two prescribed CAs were not initiated in the Corrective Action Program and, as such, no actions were implemented to correct the procedure deficiency or to share the case study until the inspectors inquired about the status of these items on August 6, 2024.
Corrective Actions: The licensee initiated a condition report to correct the procedure deficiency, share learnings in a case study, and to conduct an extent of condition review for proper initiation of corrective actions.
Corrective Action References: AR 2492210
Performance Assessment:
Performance Deficiency: The licensee failed to follow the Condition Reporting procedure, PI-AA-101-100, to correct a condition adverse to quality related to safety-related EQ engineering change reviews.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the lack of a detailed standard for safety-related EQ engineering change reviews to consider respective power, control, or instrument cables of EQ components for potential impacts from engineering changes could result in safety-related cables not being able to withstand postulated environmental conditions along their routing.
Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding screened to Green because the finding is a deficiency affecting the design or qualification of a mitigating SSC, and the SSC maintains its operability or PRA functionality.
Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.
Specifically, the licensee did not ensure that procedure, ER-AA-112, Environmental Qualification Program, for EQ engineering change reviews was adequate to support nuclear safety since it lacked a detailed standard for safety-related EQ engineering change reviews to consider respective power, control, or instrument cables of EQ components for potential impact from engineering changes, and this could result in safety-related cables not being able to withstand postulated environmental conditions along their routing.
Enforcement:
Inspectors did not identify a violation of regulatory requirements associated with this finding.
Minor Performance Deficiency 71152B Work Request Was Not Performed Minor Performance Deficiency: On November 30, 2022, emergency diesel generator (EDG)
G-04 experienced a lock-out while in standby and was declared inoperable. The cause of the lock-out was due to spurious actuation of a differential current relay. The relay was replaced with a spare, and the old relay was sent to the vendor for analysis. The analysis found no anomalies and concluded that the actuation was an isolated incident. After reviewing the issue, the station generated work requests (WRs) to replace the differential current relays on both the G-03 and G-04 EDGs with newly manufactured relays. These work requests were generated as a conservative enhancement. They were not generated to correct a condition adverse to quality nor were the work requests necessary for EDG reliability. Specifically, the installed differential current relays at the time of the failure, along with the newly installed spare relay, were not at the end of their vendor recommended life; however, the corrective action was generated to ensure that aging issues would not be a concern. The inspectors reviewed the WRs associated with the replacement of these relays and noted that the WRs were marked completed. However, the workers only validated the date the relays were last replaced but did not replace them. The G-01 and G-02 EDGs do not have these relays installed as a part of their design and did not require a similar relay replacement.
Licensee procedure MA-AA-201, Minor Maintenance Process, section 4.0, step 7.A, states in part, performance of work will be in accordance with the Minor Work Request.
WR 94248769 states a replacement of the 87/G-04 relay should be performed with a new more recently manufactured relay to prevent any potential issues related to aging of the relay. WR 94248770 states a replacement of the 87/G-03 relay should be performed with a new more recently manufactured relay. Neither the 87/G-04 nor the 87/G-03 relays were replaced, and the inspectors determined that the failure to follow the WR instructions was a performance deficiency. There were no violations of regulatory requirements associated with this issue. The licensee wrote AR 2491823 to generate new work requests to replace the relays.
Screening: The inspectors determined the performance deficiency was minor. The inspectors answered no to all of the more-than-minor questions in IMC 0612 Appendix B.
Minor Performance Deficiency 71152B Corrective Actions Did Not Address Drivers Found Minor Performance Deficiency: In August 2022, the licensee performed an assessment of a number of catastrophic large electric motor failures across the NextEra fleet, including failure of the steam generator feed pump motor at Point Beach. The motor failure at Point Beach caused a plant scram and subsequently reduced power operations for about a week. The self-assessment identified two drivers (deficiencies) for the gap: 1. vendor quality on motor refurbishment/repairs, and 2. station monitoring of motor parameters such as temperature and insulation resistance.
The licensee assigned four corrective actions to address the identified deficiencies. These included establishing and validating critical characteristics for motors undergoing refurbishment or repair, reviewing the procedure for motor parameter trending, reviewing preventive maintenance strategies to increase motor reliability, and conducting electrical maintenance refresher training focusing on performance of insulation resistance testing and polarization index acceptance criteria. However, these four corrective actions created do not specifically address the deficiencies identified in the self-assessment as required per licensee procedure PI-AA-101-1001, Level 1 Core Business Assessments, step 4.2.I, which states include any actions to address drivers and close gaps as applicable. The licensee entered this issue into the Corrective Action Program as AR 2492210, and plans to reassign more specific and deliverable actions to address the drivers of the gap.
Screening: The inspectors determined the performance deficiency was minor. The inspectors answered no to all of the more-than-minor questions in IMC 0612 Appendix B.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On September 10, 2024, the inspectors presented the biennial problem identification and resolution inspection results to Kim Locke, Principal Engineering Analyst.
- On August 8, 2024, the inspectors presented the preliminary biennial problem identification and resolution inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Security CDAS Outside the PA Not Meeting E5 Controls
06/04/2024
2038281
Assumption For Consideration to be Added to
Calc 2014-0007
09/26/2022
299091
WO 40583984 Did Not Address Eccentric Pulley
01/24/2019
2334120
W-13B1 Failed to Auto Start
11/03/2019
2357821
Westinghouse NSAL-20-1 OE Evaluation
06/24/2020
2375662
Glycol Leak on HX-38B, CR AC Unit, Piping
11/15/2020
2385966
WEC Tech Bulletin TB-19-5 Thermal Shield Bolt OE,
Revision 1
03/04/2021
2386179
ANI Information Bulletin 11-01 (Rev.1)
03/8/2021
2393356
Discrepancy Between 0-SOP-VNCR-002 and Posted
Information
05/15/2021
2418343
Phone Issues Identified with Quarterly Communications Test
2/09/2022
20177
1C-76 RCP Vibration Display is Erratic
03/01/2022
20483
W-14B Backdraft Damper VNCR-04856B Found Open
03/03/2022
23644
Update Site Response to NRC Bulletin 2011-01
04/04/2022
24060
NRC Identified: Alpha Characterization
04/07/2022
27224
Satellite Phones Are Not Functioning
05/10/2022
27363
Nuclear Safety Culture Monitoring Panel 1Q22
05/09/2022
28406
Typo Found on Paperwork
05/25/2022
29445
22 TFP Inspection EC 292093 Did Not Evaluate Cable
Routing
06/08/2022
2431209
Boric Acid Residue at Packing on 2SI-870A
07/03/2022
2432355
Rework Required on Monthly Communications Drill
07/20/2022
2432448
1AF-4000, 1P-29 AFP DISCH SG B INLET MOV
Fails to Open
07/21/2022
2432448
Apparent Cause Evaluation for AFP Discharge SG B Inlet
MOV Fails to Open
07/21/2022
2433749
G-04 Crankcase Oil Level Low
08/07/2022
71152B
Corrective Action
Documents
2435191
22 PBN PI&R - WO Associated with OE Action Not
Scheduled
08/25/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2435364
Tech Spec Station Battery Surveillance
08/29/2022
2435397
1W-3B CRDM Shroud Fan Tripped Off, Motor Overload Light
Lit
08/29/2022
2436859
Security Timeline Administrative Error
09/15/2022
2437178
Drawing Error Identified
09/19/2022
2437479
1P-10A RHR Pump P1H Vibration Point was Elevated
09/22/2022
2438281
23 CETI: 1SI-897A Weak Link Analysis and Part 21
Review
01/26/2023
2439267
Inadequate Y System Maintenance Rule Performance
Criteria
10/12/2022
2439315
NA Finding - Physical Plant Changes Made Not Per CMP
10/12/2022
2439667
22 PBN Cyber - E5 Controls for Warehouse 6
10/17/2022
2439668
22 PBN Cyber NRC Question CDA Status of Switchstack6
10/17/2022
2439881
22 PBN Cyber Warehouse Xray Mitigations Not
Implemented
10/19/2022
2440339
Unexplained Level Rise in Unit 1 PRT
10/26/2022
2440412
22 UHS Observation
10/26/2022
2441138
T3 - NSCMP Meeting Minutes
11/02/2022
2441157
Notebook Entry Does Not Meet OM 3.13 Requirement
11/04/2022
2441203
SEL (4-22-06) Equipment Condition Affecting CCTV
11/06/2022
2441409
South Control Room Door-61 Not Latching Properly
11/08/2022
2441987
Degraded Inboard Fan Bearing
11/16/2022
2442066
New Radios Present Multiple Challenges
11/18/2022
2442792
Received Unexpected C02E 1-10 G-04 Diesel Trip or
Lockout
11/30/2022
2443786
SAMG SAG-7 Review Documentation Missing
2/13/2022
2444014
CR Backup URI Laptop Not Functioning
2/15/2022
2444039
HELB Reanalysis Impacts on EQ Cables (EQCK Open
Items)
2/15/2022
2444690
OE: Information Notice 2022-02: Operating Experience
Related
2/27/2022
2445800
23 CETI - Document Analysis for IN 2016-06
01/12/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2446862
23 CETI - DBD-02 Lacks Clarity on CCW License Basis
01/26/2023
2446907
23 CETI - FO-3983A Identified Not Included in IST
Program
01/26/2023
2447003
CETI 2023: OM 4.3.8 Time Critical Action 12 Methodology
01/27/2023
2448032
23 - 2024 CNRB North Action Items
2/09/2023
2449366
CR 2449366 Level 3 PCE
2/24/2024
2449833
Generate GDRs for Off Color Engineering Indicators
03/01/2023
2450312
T1 - PBN NSCMP Meeting Minutes
2/24/2023
2450559
2P-1B No. 2 Seal Leakage RCDT Level Increase
03/09/2023
2450753
AOP-25 Turbine Trip Without Reactor Trip Unit 2
03/11/2023
2451012
2PIPE CH 0601R-01, RMI Insulation End Caps Loose
03/13/2023
245123
OE: NRC Information Notice 2023-01
03/15/2023
2454009
Unit 2 Feedwater Flow Oscillations
04/10/2023
2454872
U2 B MRFV Not Controlling as Expected
04/18/2023
2455516
Very Unsafe Condition - Safety Concern
04/24/2023
2455535
RMS Trailer Smoke Pit Butt Canister Potential Combustion
04/24/2023
2459924
SW-776 Packing Leak and Corrosion
06/13/2023
2460008
2RH-626 Flow Control Valve Did Not Function as Expected
06/14/2023
2460182
Cyber: IDS Inspection Results Gap
06/15/2023
2461016
U2 RCS IN Failed Fuel Action Level 1
06/26/2023
2461971
Fire Inspection Found E-Lights Not on Batt Power
07/10/2023
2462588
CRs Not Yet Screened by MRC
07/18/2023
2463303
MDAFW Discharge Piping Vibration Assessment
07/27/2023
2464138
AOP-12A Current Revision is Technically Incorrect
08/08/2023
2465051
Very Warm Conditions in EOF Front Foyer and
IT Equipment Rm
08/21/2023
2465214
Reduction of Effectiveness Identified in EC
08/23/2023
2465342
WANO Peer Review in Contrast Statements - FP
08/23/2023
2466345
Procedure Step Not Written to Standard
09/06/2023
2467670
Seal Leakage on P-12A, SFP Pump
09/22/2023
2469130
1RH-720, BA Active Leak During 1R41 As-Found
10/10/2023
2469361
Unexpected G-05 Alarm
10/12/2023
2469748
NEO SCRFS Not Allowed on PMCRs for Some Reason
10/16/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2469753
1CC-753 Valve Liner is Worn
10/16/2023
2470427
1RH-706A Pressure Seal Leak
10/23/2023
2470515
MILSTONE OE - PTN AR2470431 - 68% RCP Seal Face
Mismachined
10/24/2023
2470612
Non-Active Leak with Residue Identified on 1CC-764A
10/25/2023
2470891
T2 PBN NSCMP Meeting Minutes
10/06/2023
2471266
Nonconformance with IST PMT Criteria
10/31/2023
2471727
ISI Inspection Potential Violation App B Criterion V
11/06/2023
2471776
Fire Gear Missing from Storage Location
11/07/2023
2473217
CA Untimely Due to Inappropriate Closure of PMCR
11/28/2023
2473454
AOP-31 Cart Electrical Connection Not Reading Properly
2/01/2023
2475136
KINETRICS (AES) Notification of Potential Part 21 Concern
2/21/2023
2475233
1HX-90 Has a Steam Leak
2/22/2023
2475435
T3 PBN NSCMP Meeting Minutes
11/10/2023
2475463
Missing Spare Extinguisher
2/28/2023
2476782
IR Zones Require Maintenance
01/17/2024
2477285
NRC FTS Phone Line Issues
01/23/2024
2477288
NRC Identified: 2W-1B1 ACC Fan Discharge Temperature
Trend
01/23/2024
2477787
Fleet Cyber Security Supply Chain Controls Radios
01/30/2024
2477854
Temperatures in EOF IT Equipment Room Very Warm
01/31/2024
2478169
Non-DEP ERO Notification Would Have Been Late
2/02/2024
2478192
Security Officer Not in Assigned Location Per Procedure
2/02/2024
2478731
PS-6352C Failed to Auto Start K-4C, G03 Diesel Air Comp
2/08/2024
2478838
Calculations Impacted by Vendor Software Defect
2/06/2024
2479238
1D-205 Cell 57 Below Acceptance Criteria
2/15/2024
2480755
Identified a Leak
03/07/2024
2480769
RHR Pump Test Line Flow Indicator Transmitter Leakage
03/07/2024
2481393
Station Battery Pilot Cell Thermometers
03/14/2024
2481755
EQ Field Verification Identified Equipment as Non-EQ
03/19/2024
2481896
Reactor Coolant Tavg Deviation Alarm During 2ICP
2.001WH
03/20/2024
2482296
EQ Program Data Issues at PBN, SBK, and PSL.
03/25/2024
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2482467
Opening Radioactive Material Outside the RCA
03/27/2024
2483050
New NBFD31S Reactor Trip Relay Failed Initial Inspection
04/02/2024
2483905
T1 PBN NSCMP Meeting Minutes
2/29/2024
2484145
TSC/OSC Temp Running High During Normal Ops
04/15/2024
2484197
IA-3051B Relief Valve Replacement Capacity Difference
04/16/2024
2484349
U1 Rod Speed Control Indicating 1.2 Deg F Colder than
Process
04/17/2024
2484694
Approved Design did not Consider Service Level 1 Coatings
04/22/2024
2484868
Security Drills and Exercised Procedure Violation
04/24/2024
2485871
EC 299273 and EC 299358 Require Configurations to be
Gathered
05/08/2024
2485911
X-45 in Need of Repair
05/08/2024
2487093
PB Noncompliance with Operability Determination Procedure
05/24/2024
2487235
Trend Review - 50.59 and Operability Requirement
05/28/2024
2487796
SEL 2-24-11 Environmental Conditions Affecting PIDS
06/05/2024
2488820
Charging Pump Oil
06/18/2024
2490426
Boric Acid Found During Inspection
07/11/2024
2490427
Boric Acid Found During Inspection
07/11/2024
2490429
Boric Acid Found During Inspection
07/11/2024
2490430
Boric Acid Found During Inspection
07/11/2024
2490431
Boric Acid Found During Inspection
07/11/2024
2490432
Boric Acid Found During Inspection
07/11/2024
2490433
Boric Acid Found During Inspection
07/11/2024
2490484
Dry Boric Acid Leak on 1HX-3A in Contact with Bolting
07/11/2024
2491194
Monitor Tank Discharges Challenged by RE-218 Capability
07/23/2024
2490904
24 PI&R - Latch on VNCR Door Not Secured
07/18/2024
2490904
Latch on VNCR Door Not Secured
07/18/2024
2490905
24 PI&R - Light Left Near Seismic Equipment
07/18/2024
2490905
24 PI&R - Light Left Near Seismic Equipment
07/18/2024
2491821
Replace 87/G-04 Relay Due to Age (ER Checklist Action)
07/31/2024
2491822
Replace 87/G-03 Relay Due to Age (ER Checklist Action)
07/31/2024
2491823
24 PI&R - WRs Closed Without Performing Work
07/31/2024
Corrective Action
Documents
Resulting from
Inspection
2491823
24 PI&R - WRs Closed Without Performing Work
07/31/2024
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2492210
24 PI&R - OR Issue Investigation Actions Not Initiated
08/06/2024
Engineering
Changes
Reroute U2 PORV/Block Valve Cables for Construction
Truss EC 292093 Supplementary Information
Fleet Maintenance Rule Scoping Document - System Y (120)
Miscellaneous
Calc 2014-0007
Allowable Flood Levels
Section 10 CFR 73.55 G.6.I, Errors on Key/Core Practices
05/24/2023
EOP-1.3 Unit 1
Transfer to Containment Sump Recirculation - Low Head
Injection
EOP-1.4 Unit 1
Transfer to Containment Sump Recirculation - High Head
Injection
Environmental Qualification Program
Minor Maintenance Process
Procedures
PI-AA104-10000
Condition Reporting
2432530
L1A RP 1st/2nd Quarter Trend Assessment
07/21/2022
2433588
Operations PU&A Performance
08/04/2022
2433613
Security Cyber Security Assessment
08/18/2022
2435548
Assessment of Recent NEE Fleet Motor Failures
08/31/2022
2437729
LOC EP Training Requirements
09/23/2022
2438367
L1A HRA Monitoring Plan Assessment
09/30/2022
2445989
EP Benchmarking - NRC Notifications
01/16/2023
2446214
L1A 4th Quarter 2022 CR Trending
01/18/2023
2452593
L1A Annual RP Program Review
03/28/2023
2454398
EP Program Assessment 2Q23
04/13/2023
2462850
L1A Leaks/BACC
07/20/2023
2468056
Vehicle Search and Access Control Processes
09/29/2023
2469032
OPs 3Q2023 Trend Report
10/09/2023
2470395
L1A GDAR Risk Mitigating Actions Assess Observations
10/23/2023
2474313
L1A AOV Program
2/12/2023
2474462
NRC Inspection Prep IP 71130.01, Access - IP 71130.08
2/13/2023
2475838
L1A 4Q23 CR Trend Review for PB Maintenance
01/04/2024
2479547
L1A Fire Brigade Leaders are not Critical of Fire Brigade
2/20/2024
Self-Assessments
2485837
NEE Nuclear Fleet Benchmarking for NDE/ISI/FAC
05/07/2024
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
JNA 24-002
Fleet Engineering Audit
05/08/2024
PBN 22-003
Nuclear Assurance Audit - Emergency Planning
11/30/2022
PBN 23-001
Security
05/09/2023
293986
1SAF-04067 - Contactor & Thermal Overload Testing
2/14/2014
40647601-05
W-014A PDM Engineering Review of Vibe Data
07/02/2020
40717180-01
Month Filter Testing
11/17/2021
40765002-01
OE IN 2007-21 Identity RMI and Inspect Piping for Wear (U2)
03/29/2023
40767857-07
1PPG AC 0152N-11/Replace Pipe
10/18/2023
40803149-01
Month Filter Testing
07/27/2023
40830518-02
1P-53 / NDE (PT) Welds Discharge Throttle Valve Drains
10/27/2023
40850121-01
NDE Inspect SW Piping After Insulation Removal
07/17/2023
40851738-07
W-13B1 Shaft Repair
07/31/2024
40879155-01
TS-9, Control Room H/V System Checks
2/21/2024
40907176-01
TS-9, Control Room H/V System Checks
05/21/2024
256065
F$IR Zones Require Maintenance
01/17/2024
257711
RCP Seal Injection Filter DPI Controller - Leak
03/07/2024
Work Orders
O-PC-081.4
To Perform the Periodic Verification of OM 4.3.8 Control of
Time Critical and Time Sensitive Operator Actions
2/09/2024