NRC Bulletin 11-01, Mitigating Strategies

From kanterella
(Redirected from NRC Bulletin 11-01)
Jump to navigation Jump to search

Mitigating Strategies

May 11, 2022

text

OMB Control No.: 3150-0012

ML111250360

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, DC 20555-0001

May 11, 2011

NRC BULLETIN 2011-01: MITIGATING STRATEGIES

ADDRESSEES

All holders of operating licenses for nuclear power reactors, except those who have

permanently ceased operation and have certified that fuel has been removed from the reactor

vessel.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this bulletin to achieve the following

objectives:

1. To require that addressees provide a comprehensive verification of their compliance with the

regulatory requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section

50.54(hh)(2),

2. To notify addressees about the NRC staff’s need for information associated with licensee

mitigating strategies under 10 CFR 50.54(hh)(2) in light of the recent events at Japan’s

Fukushima Daiichi facility in order to determine if 1) additional assessment of program

implementation is needed, 2) the current inspection program should be enhanced, or

3) further regulatory action is warranted, and

3. To require that addressees provide a written response to the NRC in accordance with

10 CFR 50.54(f).

BACKGROUND

Following the terrorist events of September 11, 2001, the readiness of NRC-regulated facilities

to manage challenges to core cooling, containment and spent fuel pool cooling (SFP) following

large explosions or fires was enhanced through a series of orders and imposition of license

conditions. These requirements were formalized in the rulemaking of March 27, 2009, resulting

in 10 CFR 50.54(hh)(2).

The NRC conducted a comprehensive inspection of the implementation of the mitigating

strategies developed by licensees in 2008. Subsequently the NRC incorporated this

inspectable area into the baseline reactor oversight process on a sample basis as part of the

triennial fire protection inspection.

Events at the Fukushima - Daiichi Nuclear Power Station following the March 11, 2011,

earthquake and tsunami highlight the potential importance of B.5.b mitigating strategies in

responding to beyond design basis events.

The Commission has established a task force to consider the need for agency actions following

the events in Japan and is considering further actions that could improve operational safety.

DISCUSSION

The events in Japan highlight the importance and potential versatility of B.5.b mitigating

strategies. Therefore, the NRC seeks comprehensive confirmation that licensees are

maintaining equipment and strategies to satisfy 10 CFR 50.54(hh)(2).

In addition, the existing guidance on the implementation of the strategies, which was adopted by

all licensees to meet the regulatory requirements for mitigating strategies, does not describe in

detail the practices necessary for maintenance and testing of the equipment, training

requirements, and validation of feasibility of the strategies. Based upon the information

submitted by licensees in response to this bulletin, the NRC will determine if additional efforts

are needed to ensure compliance with existing regulatory requirements and/or whether

enhancement to the existing regulations and guidance are necessary.

APPLICABLE REGULATORY REQUIREMENTS

As a result of the terrorist events of September 11, 2001, the NRC issued EA-02-026, “Order for

Interim Safeguards and Security Compensatory Measures” (the ICM Order) dated February 25,

2002. The ICM Order, which is designated as Safeguards Information (SGI), modified

then-operating licenses for commercial power reactor facilities to require compliance with

specified interim safeguards and security compensatory measures. Section B.5.b of the ICM

Order requires licensees to adopt mitigation strategies using readily available resources to

maintain or restore core cooling, containment, and SFP cooling capabilities to cope with the loss

of large areas of the facility due to large fires and explosions from any cause, including

beyond-design-basis aircraft impacts.

By letter dated February 25, 2005, the NRC staff provided guidance for implementing Section

B.5.b of the ICM Order. This Phase 1 Guidance, designated as SGI, included best practices for

mitigating losses of large areas of the plant and measures to mitigate fuel damage and minimize

releases. Following issuance of the B.5.b Phase 1 Guidance, the NRC staff conducted

inspections at operating reactor sites using TI 2515/164 (SGI) and subsequently TI 2515/168

(SGI) to ensure compliance with Section B.5.b of the ICM Order.

In December 2006, the Nuclear Energy Institute (NEI) issued NEI 06-12, Revision 2, “B.5.b

Phase 2 & 3 Submittal Guideline,” formerly designated for Official Use Only – Security Related

Information (OUO-SRI), Agencywide Documents Access and Management System (ADAMS)

Accession No. ML070090060. The NRC endorsed NEI 06-12, Revision 2, by letter dated

December 22, 2006, as an acceptable means for developing and implementing the mitigation

strategies requirement in Section B.5.b of the ICM Order. NEI 06-12, Revision 2, provides

guidance for implementing a set of strategies intended to maintain or restore core cooling,

containment, and SFP cooling capabilities under the circumstances associated with the loss of a

large area of the plant due to explosions or fire. NEI 06-12 provides guidance in the following

areas:

  • Adding make-up water to the SFP,
  • Spraying water on the spent fuel,
  • Enhanced initial command and control activities for challenges to core cooling and containment, and
  • Enhanced response strategies for challenges to core cooling and containment.

The specific strategies covered in NEI 06-12, Revision 2, were developed based on the results

of assessments conducted at currently licensed power reactor facilities for the purpose of

enhancing plant specific mitigation capability for damage conditions caused by a large explosion

or fire. These assessments identified a wide spectrum of potential plant specific strategies.

NEI 06-12, Revision 2, specifies one set of strategies applicable to all pressurized-water

reactors and another set applicable to all boiling-water reactors. Both sets are derived from the

results of the plant specific assessments.

The B.5.b Phase 1 Guidance and NEI 06-12, Revision 2, were used by each licensee in

preparing information submitted to the NRC that describes a plant specific approach to

implementing mitigating strategies and supports each plant specific license condition. The NRC

staff completed its review of the information submitted by each licensee, as well as information

obtained during prior NRC inspections, and issued an OUO-SRI safety evaluation (SE) that

documents the bases for its approval of the license condition for each facility. The SE issued for

each licensee includes regulatory guidance in Section 3.0 of Appendix A, “Phase 1

Assessment,” that recites the generic B.5.b Phase 1 Guidance, as clarified in TI 2515/168, in an

OUO-SRI form rather than SGI.

By publishing new requirements in the Federal Register dated March 27, 2009 (74 FR 13926),

the NRC amended 10 CFR Part 50, 10 CFR Part 52, “Licenses, Certifications, and Approvals

for Nuclear Power Plants,” and 10 CFR Part 73, “Physical Protection of Plants and Materials.”

This rulemaking added paragraph (i) to 10 CFR 50.34, “Contents of Applications; Technical

Information,” and paragraph (d) to 10 CFR 52.80 “Contents of Applications; Additional Technical

Information,” to require submittal of a “description and plans for implementation of the guidance

and strategies intended to maintain or restore core cooling, containment, and spent fuel pool

cooling capabilities under the circumstances associated with the loss of large areas of the plant

due to explosions or fire as required by § 50.54(hh)(2) of this chapter.” This rulemaking also

added 10 CFR 50.54(hh)(2) to impose mitigating strategies requirements similar to those

imposed by the ICM Order and associated license conditions on all reactor applicants and

licensees.

REQUESTED ACTION

In order to confirm continued compliance with 10 CFR 50.54(hh)(2), within 30 days of the date

of this bulletin, the NRC requests that licensees provide the following information on their

mitigating strategies programs.

1. Is the equipment necessary to execute the mitigating strategies, as described in your

submittals to the NRC, available and capable of performing its intended function?

2. Are the guidance and strategies implemented capable of being executed considering the

current configuration of your facility and current staffing and skill levels of the staff?

Within 60 days of the date of this bulletin, the NRC requests that licensees provide information

regarding their mitigation strategies programs for 10 CFR 50.54(hh)(2).

In responding to the following questions, licensees should provide information that addresses

measures that are currently in place, noting any additional planned actions with expected

completion dates.

1. Describe in detail the maintenance of equipment procured to support the strategies and

guidance required by 10 CFR 50.54(hh)(2) in order to ensure that it is functional when

needed.

Examples of the types of information to include when providing your response to

Question (1) are:

a. Measures implemented to maintain the equipment, including periodicity.

b. Basis for establishing each maintenance item (e.g., manufacturer’s

recommendation, code or standard applicable to the craft). This should include

consideration of storage environment impact on the maintenance necessary.

These examples are not meant to limit your response if you use other methods to

address the issues described above.

2. Describe in detail the testing of equipment procured to support the strategies and

guidance required by 10 CFR 50.54(hh)(2) in order to ensure that it will function when

needed.

Examples of the types of information to include when providing your response to

Question (2) are:

a. A description of any testing accomplished to ensure the strategies were initially

feasible.

b. A description of any periodic testing instituted for the equipment, along with the

basis for establishing that test requirement.

c. A description of the corrective action process used when the equipment fails to

adequately perform its test.

These examples are not meant to limit your response if you use other methods to

address the issues described above.

3. Describe in detail the controls for assuring that the equipment is available when needed.

Examples of the types of information to include when providing your response to

Question (3) are:

a. A description of any inventory requirements established for the equipment.

b. A listing of deficiencies noted in inventories for the equipment and corrective

actions taken to prevent loss.

These examples are not meant to limit your response if you use other methods to

address the issues described above.

4. Describe in detail how configuration and guidance management is assured so that

strategies remain feasible.

Examples of the types of information to include when providing your response to

Question (4) are:

a. Measures taken to evaluate any plant configuration changes for their effect on

feasibility of the mitigating strategies.

b. Measures taken to validate that the procedures or guidelines developed to

support the strategies can be executed. These measures could include drills,

exercises, or walk through of the procedures by personnel that would be

expected to accomplish the strategies.

c. Measures taken to ensure procedures remain up-to-date and consistent with the

current configuration of the plant.

d. A description of the training program implemented in support of the mitigating

strategies and the manner in which you evaluate its effectiveness.

These examples are not meant to limit your response if you use other methods to

address the issues described above.

5. Describe in detail how you assure availability of off-site support.

Examples of the types of information to include when providing your response to

Question (5) are:

a. A listing of off-site organizations you rely on for emergency response.

b. Measures taken to ensure the continuity of memoranda of agreement or

understanding or other applicable contractual arrangements. This should include

a listing of periods of lapsed contractual arrangements.

c. A listing of any training or site familiarization provided to off-site responders. This

should include any measures taken to ensure continued familiarity of personnel

of the off-site responders in light of turnover and the passage of time.

These examples are not meant to limit your response if you use other methods to

address the issues described above.

REQUIRED RESPONSE

Licensees should address the required written response to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, 11555 Rockville Pike, Rockville, MD 20852,

pursuant to the provisions of 10 CFR 50.54(f). In addition, submit a copy of the response to the

appropriate Regional Administrator. Before submitting responses to the NRC, licensees must

evaluate them for proprietary, sensitive, safeguards, or classified information and mark such

information appropriately. The addressees have two options for submitting responses:

1. Addressees may choose to submit written responses providing the information

requested above within the requested time periods.

2. Addressees, who cannot meet the requested completion date must submit written

responses within 15 days of the date of this bulletin that address any alternative course

of action proposed, including the basis for the acceptability of the proposed alternate

course of action.

REASONS FOR INFORMATION REQUEST

The NRC is requesting information to confirm compliance with Order EA-02-026, the

subsequently imposed license conditions, and 10 CFR 50.54(hh)(2) and on the status of

licensee mitigating strategies programs. The staff will use the information received to inform the

Commission and to determine if further regulatory action is warranted.

RELATED DOCUMENTATION

Information Notice No. 11-05 “Tohoku-Taiheiyou-Oki Earthquake Effects on Japanese

Nuclear Power Plants,” March 18, 2011

BACKFIT DISCUSSION

Under the provisions of Section 182a of the Atomic Energy Act of 1954, as amended, and

10 CFR 50.54(f), this bulletin transmits an information request for the purpose of verifying

compliance with existing applicable regulatory requirements (see the Applicable Regulatory

Requirements section of this bulletin) and gathering information to determine the need for

additional regulatory action. No backfit is either intended or approved by the issuance of this

bulletin, and the staff has not performed a backfit analysis. If, as a result of information received

in response to this bulletin, the NRC determines that new guidance, orders or regulations are

needed, the NRC will prepare the necessary documentation to comply with the requirements of

the Backfit Rule and/or any applicable finality provisions in 10 CFR Part 52 as part of the

development of the new guidance, orders or regulations.

FEDERAL REGISTER NOTIFICATION

The NRC did not publish a notice of opportunity for public comment on a draft of this bulletin in

the Federal Register because the agency is requesting information from affected licensees on

an expedited basis to assess the adequacy and consistency of regulatory programs. There is no

legal requirement that the NRC publish for public comment such information requests.

CONGRESSIONAL REVIEW ACT

The NRC determined that this bulletin is not a rule under the Congressional Review Act.

PAPERWORK REDUCTION ACT STATEMENT

This bulletin contains information collections that are covered by the Office of Management and

Budget clearance number 3150-0012, which expires January 31, 2013. This collection of

information is mandatory under the provisions of Section 182a of the Atomic Energy Act of

1954, as amended, and 10 CFR 50.54(f). The burden to the public for these information

collections is estimated to average 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> per response, including the time for reviewing

instructions, searching existing data sources, gathering and maintaining the data needed, and

completing and reviewing the information collection.

Send comments regarding this burden estimate or any other aspect of these information

collections, including suggestions for reducing the burden, to the Information Services Branch

(T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet

electronic mail to Infocollects.Resource@NRC.GOV; and to the Desk Officer, Office of

Information and Regulatory Affairs, NEOB-10202, (3150-0012), Office of Management and

Budget (OMB), Washington, DC 20503.

PUBLIC PROTECTION NOTIFICATION

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a

currently valid OMB control number.

BL 2011-01

Page 8 of 8

CONTACT

Please direct any questions about this matter to the technical contact listed below.

/RA/

Timothy J. McGinty, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contact: Eric E. Bowman, NRR

301-415-2963

Eric.Bowman@nrc.gov

Note: NRC Generic Communications may be found on the NRC public Web site,

http://www.nrc.gov, under Electronic Reading Room/Document Collections

BL 2011-01

Page 8 of 8

CONTACT

Please direct any questions about this matter to the technical contact listed below.

/RA/

Timothy J. McGinty, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contact: Eric E. Bowman, NRR

301-415-2963

Eric.Bowman@nrc.gov

Note: NRC Generic Communications may be found on the NRC public Web site,

http://www.nrc.gov, under Electronic Reading Room/Document Collections

ADAMS Accession Number: ML111250360 NRR-052 * by e-mail

OFFICE NRR/DPR/PGCB TECH EDITOR* DPR/PGCB/LA NRR/DIRS/DD* PMDA*

NAME EBowman JDougherty CHawes BWestreich LHill

DATE 05/05/11 05/10/11 05/05/11 05/06/11 05/09/11

OFFICE OIS* OGC:NLO DPR/PGCB/BC NRR/DPR/D

NAME TDonnell

(KBenney for)

MSpencer SRosenberg TMcGinty

DATE 05/09/11 05/09/11 05/10/11 05/11/11

OFFICIAL RECORD COPY