IR 05000266/2022404
| ML22335A593 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 12/02/2022 |
| From: | Richard Skokowski NRC/RGN-III/DORS/EB2 |
| To: | Strope M Point Beach |
| References | |
| IR 2022404 | |
| Download: ML22335A593 (3) | |
Text
SUBJECT:
POINT BEACH NUCLEAR PLANT - CYBER SECURITY INSPECTION REPORT 05000266/2022404 AND 05000301/2022404
Dear Mr. Strope:
On October 21, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant and discussed the results of this inspection with Mr. Thad Edmonds, Site Operation Director, and other members of your staff. The results of this inspection are documented in the enclosed report.
Six findings of very low security significance (Green) are documented in this report. Six of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with section 2.3.2 of the Enforcement Policy.
If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Point Beach Nuclear Plant.
The following cross cutting aspects were assigned to findings using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: one [H.14] - Conservative Bias, one [H.3] - Change Management, one [H.5] - Work Management, one [H.7] - Documentation, one [H.8] - Procedure Adherence, and one [P.3] - Resolution.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Point Beach Nuclear Plant.
December 2, 2022 This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely, Richard A. Skokowski, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27 Enclosure:
As stated cc: M. Fencl, Security Manager B. Woyak, Engineering Director M. Nazar, President, Nuclear Division cc w/o encl: Distribution via LISTSERV Signed by Skokowski, Richard on 12/02/22
ML22335A593 Entire Report:
SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available Cover Letter Only:
SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RIII RIII NAME ADahbur RSkokowski DATE 12/01/2022 12/02/2022