Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005)
ML23235A287
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 08/24/2023
From: Karla Stoedter
NRC/RGN-III/DORS/RPB2
To: Durbin M
Point Beach
References
Download: ML23235A287 (1)


Text

SUBJECT:

UPDATED INSPECTION PLAN FOR POINT BEACH NUCLEAR PLANT (REPORT 05000266/2023005 AND 05000301/2023005)

Dear Mike Durbin:

The enclosed inspection plan lists the inspections scheduled through June 30, 2025, for Point Beach Nuclear Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).August 24, 2023 Please contact me at 630-829-9731 with any questions you have regarding this letter.

Sincerely, Karla K. Stoedter, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Stoedter, Karla on 08/24/23