IR 05000266/2024002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000266/2024002 and 05000301/2024002
ML24225A232
Person / Time
Site: Point Beach  
(DPR-024, DPR-027)
Issue date: 08/13/2024
From: Hartman T
NRC/RGN-III/DORS/RPB2
To: Durbin M
Point Beach
References
IR 2024002
Download: ML24225A232 (1)


Text

SUBJECT:

POINT BEACH NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000266/2024002 AND 05000301/2024002

Dear Michael Durbin:

On June 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant. On July 15, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Point Beach Nuclear Plant.

August 13, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Thomas C. Hartman, Acting Branch Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000266 and 05000301

License Numbers:

DPR-24 and DPR-27

Report Numbers:

05000266/2024002 and 05000301/2024002

Enterprise Identifier:

I-2024-002-0064

Licensee:

NextEra Energy Point Beach, LLC

Facility:

Point Beach Nuclear Plant

Location:

Two Rivers, WI

Inspection Dates:

April 01, 2024 to June 30, 2024

Inspectors:

J. Masse, Resident Inspector

V. Myers, Senior Health Physicist

V. Petrella, Project Manager

J. Robbins, Senior Resident Inspector

M. Stafford, Senior Resident Inspector

Approved By:

Thomas C. Hartman, Acting Branch Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Point Beach Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Translate Design Basis for Diesel Generator Operability Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266,05000301/2024002-01 Open/Closed None (NPP)71111.18 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 CFR, Part 50, Appendix B, Criterion III, Design Control, when the licensee failed to assure that the applicable design basis was correctly translated into instructions. Specifically, the licensee failed to translate the maximum allowable outside air temperature to maintain emergency diesel generator operability into Operating Instruction 168, Emergency Diesel Generator Operability.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 train B safety injection system on May 9, 2024
(2) Unit 1 train A residual heat removal system on June 27, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (10 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire zones 318, 326, 333, 334, 335, 336, and 337 on April 9, 2024
(2) Fire zones 305, 306, 307, 308, 309, and 310 on April 9, 2024
(3) Fire zones 304N, 304S, and 311 on April 9, 2024
(4) Fire zones 106, 110, 115, 119, 141, 142A, 143, 144, 145, and 147 on April 22, 2024
(5) Fire zones 113, 114, and 118 on April 22, 2024
(6) Fire zones 137, 138, 139, and 140 on April 22, 2024
(7) Fire zones 142, 149, 150, and 151 on April 22, 2024
(8) Fire zones 152, 153, 154, 155, 156, 156A, 158, and 159 on April 23, 2024
(9) Fire zones 162, 163, 164, 165, and 166 on April 23, 2024
(10) Fire zones 304N and 304S during hot work on May 8, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on May 16, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the cable vaults in manholes 1, 2, 66A, 66B, and 67B on April 29, 2024, April 30, 2024, and May 2, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a power reduction following the loss of power to the 2B-41 480V motor control center on May 7, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator simulator training on May 15, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Air accumulator, 1T-223A, for main feedwater isolation valve 1CS-3124
(2) Unit 2 480 volt alternating current system following the temporary loss of power to distribution bus 2B-41

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 elevated risk due to independent overspeed protection system analog and train A and B logic test on May 8, 2024
(2) Unit 2 elevated risk due to nuclear instrumentation power range axial offset channel calibration on June 20, 2024
(3) Elevated risk due to rigging and lifting activities over the spent fuel pool on June 24, 2024
(4) Elevated risk due to maintenance on the D-09 battery charger and D-305 125-volt battery on June 26, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability determination for the Unit 2 main steam non-return check valve, 2MS-2017A, following a packing leak on April 11, 2024
(2) Operability determination for the SW-2977, HX-98 residual heat removal pump area cooling coil inlet control, not opening on May 17, 2024
(3) Operability determination for the Unit 1 white channel temperature average, Tavg, indication on May 31, 2024
(4) Functionality determination for reactor coolant system makeup portable diesel driven pumps on June 17, 2024
(5) Operability determination for underground cabling after a manhole was found full of water on June 20, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (3 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Removal of the seal well outlet motor operated valve and the impact to circulating water and service water ice melt lineups
(2) Temporary modification to address containment accident recirculation fan operability
(3) Emergency diesel generator rooms for G-01 and G-02 temperature limit change

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1) Unit 1 wide range reactor vessel level indicator after module lug replacement on April 16, 2024
(2) Service water pump discharge check valve, SW-32D, after replacement of the valve disc on April 19, 2024
(3) Unit 1 blue channel average temperature after 1TM-403BB module replacement on May 1, 2024
(4) Unit 2 containment accident recirculation fan, 2W-1A1, after flange installation over containment cooling fan backdraft damper on May 23, 2024
(5) Station blackout gas turbine generator, G-05, after various mechanical and electrical maintenance activities on May 30, 2024
(6) Emergency diesel generator, G-03, exhaust fan post-maintenance test, on June 10, 2024
(7) Radiation monitor post-maintenance testing, on June 10, 2024

Surveillance Testing (IP Section 03.01) (1 Sample)

(1) TS-84, G-04 emergency diesel generator run on June 18, 2024

Inservice Testing (IST) (IP Section 03.01) (2 Samples)

(1) IT 45 Train B, safety injection valve tests, on April 12, 2024
(2) IT 04 Train A, low head safety injection pump test, on May 29, 2024

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) Steam generator injection portable diesel driven pump surveillance, on June 17, 2024

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Emergency preparedness drill conducted to practice the new combined emergency plan implementation on April 30,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (9 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) AMP 50 for the demineralizer valve gallery
(2) AMP 50 for the unit 1 demineralizer cubicle
(3) AMS 4 for the unit 2 charging pump cubicles
(4) Cronos 4 at the radiologically controlled area exit
(5) SAM at the radiation protection release station (6)iSolos in the counting room
(7) MGP Telepole staged for use
(8) Ludlum 9-3 staged for use
(9) Ludlum 3 staged for use

Calibration and Testing Program (IP Section 03.02) (12 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) AMS-4, SN 330692
(2) Low Volume Air Sampler, SN 330785 (3)iSolo, SN 361202
(4) Ludlum 9-3, SN 333119
(5) Thermo RO-20, SN 472971
(6) Telepole II, SN 427020-061 and 428020-061
(7) Ludlum 3, SN 327581
(8) Ludlum 177, SN 348303
(9) Escort ELF, SN A2-41247
(10) ARGOS 5AB, SN 712-048/0480461
(11) Cronos-4, SN 1511-197
(12) GEM 5, SN 480458 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 1 Service Water Monitor, 1RE-229
(2) Unit 2 Containment SPING, SPING-22

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative (GPI) program to identify incomplete or discontinued program elements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2023 through March 31, 2024)
(2) Unit 2 (April 1, 2023 through March 31, 2024)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (April 1, 2023 through March 31, 2024)
(2) Unit 2 (April 1, 2023 through March 31, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Fuel assembly grid strap damaged during fuel moves.
(2) Emergency diesel generator, G-01, temperature outside normal band while running
(3) Main feed isolation valve air accumulator Part 21 applicability

INSPECTION RESULTS

Failure to Translate Design Basis for Diesel Generator Operability Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266,05000301/2024002-01 Open/Closed None (NPP)71111.18 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 CFR, Part 50, Appendix B, Criterion III, Design Control, when the licensee failed to assure that the applicable design basis was correctly translated into instructions. Specifically, the licensee failed to translate the maximum allowable outside air temperature to maintain emergency diesel generator operability into Operating Instruction 168, Emergency Diesel Generator Operability.

Description:

During an endurance run for the G-01 emergency diesel generator (EDG) in August of 2023, the licensee noted elevated temperatures in the diesel generator room. The highest recorded readings in this room were 113.4 degrees Fahrenheit (°F), taken from TI-6616A, a digital thermometer located in this room. This value was within 6.6 F of the operability limit of 120 °F for equipment in the room. This led the inspectors to investigate the maximum allowable room temperatures and outside air temperatures to maintain diesel generator operability.

The licensee maintains calculation 2005-0054, Control Building GOTHIC Temperature Calculation. Revision 9, Section 9.2, calculates the maximum allowable outside air temperature to maintain the G-01 and G-02 diesel generator room temperatures below 120 °F to be 97.4 °F. The calculation assumes two room exhaust fans are running and three open fire dampers.

The licensee also has Operating Instruction 168, Emergency Diesel Generator Operability, Revision 31, which discusses when to consider the EDGs operable or inoperable. The inspectors noted that step 5.1.3 states, When outside air temperature is greater than 97.5 F, then G-01 and G-02 are to be considered INOPERABLE. The value of 97.5 °F does not match the calculated design value of 97.4 °F from calculation 2005-0054.

Further, if the value of 97.5 °F were utilized in the calculation it would result in a required air flow that would exceed the available air flow assumed in the calculation. Based on Operating Instruction 168, the licensee would not declare G-01 or G-02 inoperable until outside temperatures exceeded 97.5 °F, which could have resulted in the licensee operating outside of their design requirements.

Corrective Actions: The licensee has entered this issue into their corrective action program to determine changes needed in their required procedures.

Corrective Action References: AR 02490693

Performance Assessment:

Performance Deficiency: The inspectors determined the licensees failure to properly translate the emergency diesel generator air temperature limits into procedures was contrary to 10 CFR Part 50, Appendix B, Criterion III Design Control, and was a performance deficiency. Specifically, the licensee failed to translate the design value for maximum outside air temperature into Operating Instruction 168, Emergency Diesel Generator Operability.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, if the Operating Instruction is followed, between 97.4 °F and 97.5 °F, the licensee would not declare the equipment inoperable, but the G-01 and G-02 emergency diesel generators might not be capable of performing their safety function.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, the inspectors determined the finding was of very low safety significance (Green)because the inspectors answered no to all of the screening questions in Exhibit 2.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires in part that measures be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions.

Contrary to the above, since June 16, 2016, the licensee failed to assure that applicable regulatory requirements and the design basis were correctly translated into specifications, drawings, procedures, and instructions. Specifically, the licensee failed to correctly translate the maximum allowable outside air temperature to maintain emergency diesel generator operability into Operating Instruction 168, Emergency Diesel Generator Operability.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 15, 2024, the inspectors presented the integrated inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.
  • On April 11, 2024, the inspectors presented the radiation protection inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.
  • On June 6, 2024, the inspectors presented the radiation protection inspection results to Michael Durbin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

110E017 Sheet 1

P&ID Safety Injection System

110E017 Sheet 2

P&ID Safety Injection System

110E018 Sheet 1

P&ID Auxiliary Coolant System

110E035 Sheet 1

P&ID Safety Injection System

71111.04

Drawings

110E035 Sheet 2

P&ID Safety Injection System

2486448

AR to Purchase Aerating Nozzles for FBG Foam Use

05/16/2024

Corrective Action

Documents

2486449

FB Foam Cart Needs Rails

05/16/2024

2478188

PFP-0-CB - Pre-Frie Plan Control Building ELE

V. 8 ft, 26 ft

2/02/2024

2478468

PBC-218 Sheet 2,3,6,8 VS PFP-0-CB - Identified

by NRC PT 1

2/06/2024

2478470

PBC-218 Sheet 2,3,6,8 VS PFP-0-CB - Identified by

NRC PT 2

2/06/2024

2482008

(P) PFP-0-CB - Pre-Fire Plan Control Building (In Review)

03/21/2024

2483596

Potential Minor Violation Related to Pre-Fire Plans

04/09/2024

2483599

Potential Minor Violation Related to PBC 218 Series

FP DWGS

04/09/2024

2484697

Red Lock Improperly Installed on Entrance to Fire Zone 146

04/22/2024

2487710

Clarify OM 3.27 Verbiage to NP 1.9.14 Regarding CMFWS

06/04/2024

Corrective Action

Documents

Resulting from

Inspection

2487711

OM 3.27 - Control of Fire Protection and NFPA 805 Equipment

06/04/2024

PBC-218, Sheet 2

Fire Protection for Turbine Building, AUX Building &

Containment ELEV. 8'-0" Point Beach N.P. Units 1 & 2

PBC-218, Sheet

Fire Barrier Locations for Turbine Building,

Aux Building & Containment Elev 8 ft

PBC-218, Sheet 3

Fire Protection for Turbine Building, Aux Building &

Containment ELEV. 26'-0" Point Beach N.P. Units 1 & 2

Drawings

PBC-218, Sheet 8

Fire Protection for Control Room ELEV. 44'-0" & Computer

Room ELEV. 60'-0 Point Beach Nuclear Plant Unit 1 & 2

PFP-0-CB

Pre-Fire Plan Control Building Elev 8 ft, 26 ft, 44 ft, and 66 ft

Fire Plans

PFP-0-PAB-8

Pre-Fire Plan Primary Auxiliary Building Elevations 8 ft and

Below

71111.05

Miscellaneous

Fire Drill Scenario

Crew C: 2nd Quarter 2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NP 1.9.13

Ignition Control Procedure

NP 1.9.14

Fire Protection Plan

Procedures

OM 3.27

Control of Fire Protection and NFPA 805 Equipment

Work Orders

40802652-23

K-003B / Install Service Air Test Conn. North Aux Feed

05/03/2024

Calculations

2014-0007

Allowable Flood Levels

E-100, Sheet 1

Electrical Plot Plan Details

71111.06

Drawings

PBE-816

Cable Vault Locations

Corrective Action

Documents

2485848

2B-41 MCC Breaker 2B52-42D, the 2B02 to 2B41, Tripped

05/07/2024

Miscellaneous

PBN LOC24C

003S

CPE Style Scenario

AOP-17A Unit 2

Rapid Power Reduction

MDB 3.2.6 2B41

480 V AC Motor Control Centers

71111.11Q

Procedures

OP-2A Unit 2

Normal Power Operation Unit 2

2470986

1CS-232A Will Not Adjust in Band, Causing Accumulator

Hi Pres

10/28/2023

2470991

Gas Leakage from 1CS-3124 MFIV Accumulator/Operator

10/28/2023

2471106

Air Leak on 1CS-257A

10/30/2023

2471208

Contingency - Troubleshoot and Repair 1CS-03124

10/31/2023

2485848

2B-41 MCC Breaker 2B52-42D, 2B02 to 2B41, Tripped

05/07/2024

2486044

1K-29A Haskel Not Controlling Pressure as Set

05/10/2024

2486253

Received a 2B-03 Ground Fault Alarm

05/14/2024

Corrective Action

Documents

2486411

Inspect/Replace 1CS-242A to Support 1K-29A

Troubleshooting

05/15/2024

Drawings

M-209 Sheet 5

P&ID Instrument Air

Miscellaneous

EVT-480V-2024-

20106

Maintenance Rule Functional Failure Determination

05/22/2024

CMP 2.3

Relief/Safety Valves

ER-AA-100-2002

Maintenance Rule Program Administration

RMP 9303

DB-50 Breaker Routine Maintenance

Procedures

RMP 9369-1

Westector/Amptector Overload SerpointC Heck on Low

Voltage Breakers

71111.12

Work Orders

40785650-01

B52-DB50-018; Breaker Maint per RMP 9303 and

11/21/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RMP 9369-1

40954962-01

Gas Leakage from 1CS-3126A MFIV Accumulator/Operator

2/04/2023

40954962-06

1CS-03126A / Perform As-left Testing Prior to Installation

01/05/2024

40954966-01

1CS-232A - Bench Check Regulator and Replace if Necessary

10/29/2023

40956122-01

1K-29A Cycling Excessively

2/01/2024

2488806

Z-015 Pre-Lift Inspection

06/18/2024

Corrective Action

Documents

2489023

Z-015 Pre-Lift Inspection

06/20/2024

Guarded Equipment Log

06/25/2024

Miscellaneous

Rigging Lift Plans

06/21/2024

1ICP 03.016

Independent Overspeed Protection System Analog and

Train A and B Logic Test

2ICP 02.008-1

Nuclear Instrumentation Power Range Axial Offset Calibration

MA-AA-110-1000

Rigging Handbook and Inspection Procedure

MA-AA-212-1000

Rigging and Material Handling

OP-AA-102-1003

Guarded Equipment

SLP 4

Safe Load Path and Rigging Manual

Procedures

WM-AA-100-1000

Work Activity Risk Management

40905559-01

D-305/D-09; Bat Disch & Charger Maint and SR Tests

06/26/2024

40906507-01

1ICP 0.016 - IOPS Quarterly Trip and Logic Tests

05/07/2024

71111.13

Work Orders

40908448-03

(Contingency) Unit 2 NIs Power Range Axial Offset Cal

05/31/2024

2461599

Validate Tavg/Tref Deviation Meter

07/05/2023

2467128

Unexpected 1C04 1A 3-10 Reactor Coolant T AVG Deviation

Alarm

09/17/2023

2484255

White Channel Tavg Reads 577 Degrees Hot, Tech Spec Limit

04/17/2024

2485060

SW-2977 Did Not Open When TIC-2977 Setpoint was

Lowered

04/26/2024

2485200

Z-2005B Failed to Turn Over

04/29/2024

2485201

Z-2005C Failed to Turn Over

04/29/2024

2485250

Z-66A Manhole Full of Water and Cables Under Water

04/30/2024

2485547

FLEX Equipment Battery Low Electrolyte Level (Trend)

05/03/2024

2485971

WR Needed to Replace Sump Pump in Z-66A

05/09/2024

Corrective Action

Documents

2483008

Packing Leakage on 2MS-2017A Non-Return Valve

04/02/2024

71111.15

Corrective Action

2485342

MS-2017A/2018A Non-Return Check Valves Documentation

05/01/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

Issues

207034-H Sheet 1

30in. Main Steam Non-return Valve CV-2017A & CV-2018A

207034-H Sheet 2

30in Main Steam Isolation Check Valve

Drawings

M-2201 Sheet 1

P&ID Main & Reheat Steam System

Engineering

Changes

258496

EPU - MSIV and NRV Valve Disc Upgrades (U2)

2RMP 9306-1

Main Steam Non-Return Check Valve Inspection Without

Removing Cover (Unit 2)

NP 7.7.28

Cable Condition Monitoring Program

and 8

NP 7.7.37

Surveillance Frequency Control Program Manual

OM 3.42

Control of WR SFP Level Instrumentation and Credited

FLEX Equipment

Procedures

PBF-2034

Control Room Log U1

105

40886741-01

PC-21.6 B.5.B Miscellaneous and FLEX Checks

04/11/2024

40888638

Yearly (Spring) Electrical Manhole Sump Inspections

05/09/2024

Work Orders

40955496

Investigate Reason for U1 White Channel Temperature Offset

04/04/2024

Calculations

2005-0054

Control Building GOTHIC Temperature Calculation

Corrective Action

Documents

2486793

2W-001A2-A Second Blade Disconnected from Damper Shaft

05/21/2024

2489616

Calc 2005-0054 Error

06/27/2024

2490407

Clarity of Basis for A Train EDG Room Heat Up Parameters

07/10/2024

Corrective Action

Documents

Resulting from

Inspection

2490693

Potential Green NCV, 10 CFR Appendix B, Criterion III

07/15/2024

297502

1CW-3 Seal Well Outlet MOV Temporary Configuration

Alignment

298378

1CW-3 Seal Well Outlet MOV TCC Conversion to

Permanent Mod

Engineering

Changes

299709

2W-1A2-A Backdraft Damper Temporary Duct Blank

Engineering

Evaluations

2015-0017

G-01 and G-02 Air Temperature Limit

71111.18

Miscellaneous

SCR 2013-0043-

Revise OI 168 Emergency Diesel Generator Operability,

TS B 3.8.1 and PBF-2035

08/21/2013

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AOP-13A

Circulating Water System Malfunction

AOP-13C

Severe Weather Conditions

AOP-9A

Service Water System Malfunction

OI 168

Emergency Diesel Generator Operability

Procedures

OI 38

Circulating Water System Operation

2486703

CR Vent Failed to Shift from Mode 5 to Mode 1

05/20/2024

2486861

Potentially Inadequate PMT on DAM 7 Restoration

05/22/2024

2486927

RMS Procedures and PMT

05/22/2024

2487042

Z-2004B FLEX Inj. Pump Failed to Start

05/23/2024

2483107

1LT-495 (RV Level, Wide Range) Failed Channel Check

04/03/2024

Corrective Action

Documents

2486793

2W-001A2-A Second Blade Disconnected from Damper Shaft

05/21/2024

Corrective Action

Documents

Resulting from

Inspection

2490694

Potential Minor PD - IT Series Procedures Signoffs Not

Consistent

07/15/2024

036032

2"-16" 150 Pound Swing Check Valve

BD-4

Block Diagram-Instrument Reactor Protection System

Delta T - T Average - Loop B-1

CD-6 JOB 10668

Sheet 1

Wiring Diagram-Interconnect Reactor Protection System Rack

1-1B (1C116) Top

Drawings

CD1-22

Connection Diagram Rack 1C173A-F

0-SOP-FLEX-004

FLEX Portable Diesel Steam Generator Injection Pump

Operation

1ICP-13.004B

Spec 200, Reactor Vessel Level and Subcooling Post Accident

Monitoring Instruments 18 Month Calibration

AD-AA-100-1006

Procedure and Work Instruction Use and Adherence

ER-AA-113-1000

Inservice Testing Procedure

HPIP 7.51.7

DAM/SPING Post-Startup Operational Verification

IT 01 Train A

High Head Safety Injection Pumps and Valves Train A Unit 1

IT 02 Train A

High Head Safety Injection Pumps and Valves Train A Unit 2

IT 03 Train A

Low Head Safety Injection Pumps and Valves Train A Unit 1

IT 04 Train A

Low Head Safety Injection Pumps and Valves Train A Unit 2

71111.24

Procedures

IT 04 Train B

Low Head Safety Injection Pumps and Valves Train B Unit 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IT 05 Train A

Train A Containment Spray Pump and Valves Unit 1

IT 45 Train B

Safety Injection Valves Train B Unit 2

MA-AA-203-1000

Maintenance Testing

MI 32.13

Belts and Pulleys

OI 81

RMS Troubleshooting and Startup

OI 81

RMS Troubleshooting and Startup

OP-AA-100-1000

Conduct of Operations

PC-29

Gas Turbine and Auxiliary Diesel Load Test

Procedure

Writer's Guide

Procedure Writers Guide

RMP 9328

SW-32A-F Service Water Pump Discharge Check Valve

Inspection

TS 34

Containment Accident Recirculation Fan-Cooler Units Unit 2

TS 84

Emergency Diesel Generator G-04 Monthly

40824334-01

SW-00032D Disassemble/Visually Inspect Check Valve

03/28/2024

40824334-02

SW-00032D Ops PMT/RTS

03/29/2024

40849151-01

1ICP 13.4 -- Spec 200 Tech Spec - Train B

04/05/2024

40862003-01

PC-29; G-05 Gas Turbine Generator Load Testing

05/17/2024

40882213-01

IT 04 Train A

03/13/2024

40886696-01

IT 45 Train B

04/15/2024

40905557

W-183A - Grease Fan Bearings

05/30/2024

40933119-01

0-SOP-FLEX-004/Z-2004A and B Quarterly Run

06/13/2024

40933123-01

TS-84, G-04 Emergency Diesel Generator Operability Test

06/03/2024

40951650

RE-214 Spikes When Source Checking RE-218

05/23/2024

40966458-08

D-500; Battery Charger Maint and Testing

05/13/2024

40973263-01

1LM-495-1 Replace Lugs

04/04/2024

40976153-02

1TM-403BB - Bench Check Replacement Module

04/27/2024

40976153-04

1TM-403BB - Replace Module with Bench Checked Spare

04/30/2024

Work Orders

40978994-06

2W-001A2-A, OPS PMT/RTS

05/22/2024

Miscellaneous

2Q24 CEP

Installation

Practice Drill

Drill Spreadsheet

04/25/2024

71114.06

Procedures

AOP-28

Seismic Event

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

HP-100-012623

Basis for GEM-5 Portal Monitor Alarm Setpoint Change

01/27/2023

27020-0610-

231219

Calibration Certificate for Telepole II SN 427020-061 and

28020-061

2/19/2023

PBF-4020

Low Volume Air Sampler Maintenance and Calibration Record

for SN 330785

2/07/2023

PBF-4020d

Escort ELF Air Sampling Pump Calibration Record for

SN A2-41247

11/09/2023

PBF-4055a

ARGOS 5AB Calibration Worksheet for SN 712/048/0480461

06/16/2023

PBF-4055b

Calibration Data Sheet for GEM 5 SN 480458

04/30/2024

PBF-4085ff

Calibration Data Sheet for iSolo SN 361202

06/04/2023

PBF-4085j

Calibration Data Sheet for Ludlum 3 SN 327581

11/13/2023

PBF-4085J

Calibration Data Sheet for Ludlum 177 SN 348303

08/02/2023

PBF-4085u

Calibration Data Sheet for AMS-4 SN 330692

01/09/2024

PBF-4085y

Calibration Data Sheet for Thermo RO-20 SN 472971

05/23/2023

PBF-4085y

Calibration Data Sheet for Ludlum 9-3 SN 333119

03/05/2024

Calibration

Records

RP-AA-110-1000-

F01

Cronos Calibration Data Sheet for SN 1511-197

09/07/2023

2465046

MSL Rad Monitor Calculation 99-0106 Not Updated for New

Source Term

08/21/2023

2465471

Documents Have Different MSL LLD Values

08/24/2023

2473296

Calibration Constant for MSL Radiation Detectors May Be

Incorrect

11/29/2023

Corrective Action

Documents

2473308

RMS Background Subtract Not Performed IAW Vendor

Instruction

11/29/2023

HPCAL 1.33

Maintenance and Calibration of Low Volume Air Samplers

HPCAL 1.49

Calibration of Portable Dose Rate Instruments

HPCAL 2.23

Portable Scaler Calibrations

HPCAL 2.24

Calibration of the ARGOS 5AB Alpha/Beta Whole Body

Contamination Monitor

HPCAL 2.25

Calibration of the GEM Whole Body Contamination Monitor

Procedures

RP-AA-110-1000

Operation and Calibration of the Cronos Contamination

Monitors

71124.05

Work Orders

40869430

1RE-229/229B Calibration

01/25/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

40873521

2RM-SPING-22 Calibration

01/19/2024

2432491

Potential Adverse Trend for Environmental Air Sampling

04/08/2024

Corrective Action

Documents

2465121

ODCM Reviews Against TS 5.6.2

08/22/2023

Offsite Dose Calculation Manual

L-2023-058

22 Annual Monitoring Report

04/10/2023

Miscellaneous

NRC 2022-0014

21 Annual Monitoring Report

04/14/2022

HPIP 3.58.1

Radiological Environmental Sampling

Procedures

NP 3.4.7

Groundwater Protection Program

71124.07

Self-Assessments

L1A 02419352

Year GWPP Self-Assessment

2/21/2022

2005-0049

Primary Auxiliary Building (PAB) and Control Building (CB)

Mechanical Heat Load Calculation

Calculations

2005-0054

Control Building GOTHIC Temperature Calculation

2450093

1K-29B Continuous Air Bleed Coming from Weep Hole

03/04/2023

2464991

G-01 Room Temperature Outside Band 50-105 F While

Running

08/20/2023

2471076

1K-29A Air Intensifier not Working Properly

10/29/2023

2471978

1K-29A Cycling Excessively

11/09/2023

2484218

Load Deflection during Fuel Moves at SFP

04/16/2024

2484271

Fuel Assembly 2D06 has Torn Grid Straps from

SFP Cell SS-21

04/17/2024

2486044

1K-29A Haskel not Controlling Pressure as Set

05/10/2024

2486411

Inspect/Replace 1CS-242A to Support 1K-29A

Troubleshooting

05/15/2024

2488284

1K-29A Cycling ~30 Times per Minute

06/11/2024

Corrective Action

Documents

2488322

ACMP: Check for Operator Challenge

06/11/2024

Corrective Action

Documents

Resulting from

Inspection

2489967

TI-6616A Contributing to Questions on G-01 Room Heat Up

07/03/2024

Miscellaneous

Letter from Engine System, Inc. to Point Beach

2/23/2007

0-SOP-FH-001

Fuel/Insert/Component Movement in the Spent Fuel Pool or

New Fuel Vault

71152A

Procedures

LI-AA-102-1002

Part 21 Reporting

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PBTP 259

G01 EDG Air Flow Measurement Test

09/20/2014

QI-7-NSC-1

Warehouse Receipt, Storage, Issuance and Maintenance

2A

Work Orders

40476004

Z-25A&B/Repair SFP Racks

06/05/2023