Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010
ML24036A265
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 02/05/2024
From: Hartman T
NRC/RGN-III/DORS/ERPB
To: Durbin M
Point Beach
References
IR 2024010
Download: ML24036A265 (1)


See also: IR 05000266/2024010

Text

Michael Durbin

Site Vice President

NextEra Energy Point Beach, LLC

6610 Nuclear Road

Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR PLANT - NOTICE OF INSPECTION AND

REQUEST FOR INFORMATION FOR THE NRC AGE-RELATED

DEGRADATION INSPECTION: INSPECTION REPORT 05000266/2024010

AND 05000301/2024010

Dear Michael Durbin:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

staff will conduct IP 71111.21N.04, Age-Related Degradation baseline inspection at Point

Beach Nuclear Plant, Units 1 and 2, in April 2024. The inspection team will be led by Thomas

Hartman from the NRC Region 3 Office. The team will be composed of personnel from the

NRC Region 3 Office. The inspection will be conducted in accordance with IP 71111.21N.04.

The schedule for the inspection is as follows:

Information gathering visit - week of March 4, 2024

On-site inspection - weeks of April 29, 2024, and May 13, 2024

The purpose of the information gathering visit is to become familiar with the station

maintenance, surveillance, testing, inspection, and condition monitoring programs, become

familiar with plant layout, support identification of structures, systems, and components (SSCs)

that will be reviewed during the inspection, and, as necessary, obtain plant-specific site access

training and badging for unescorted site access. An initial list of documents that the team will

review during the information gathering visit are listed in enclosure 1, section III.A.

During the information gathering visit, the team will also discuss the following inspection support

administrative details: office space size and location; specific documents requested to be made

available to the team in their office spaces; arrangements for reactor site access (including

radiation protection training, security, or safety); and the availability of knowledgeable plant staff

and licensing organization personnel to serve as points of contact during the inspection.

For SSCs that the inspection will review, an initial list of the documents the team will review

during the conduct of the inspection are listed in enclosure 1, section III.B. The team leader will

contact you with identified SSCs. Also, personnel should be available at the site during the

inspection who are knowledgeable regarding maintenance, surveillance, testing, inspection, and

condition monitoring programs.

February 5, 2024

M. Durbin

2

This letter contains voluntary information collections that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)

approved these information collections (approval number 3150-0011). The burden to the public

for these information collections is estimated to average 42 hours4.861111e-4 days <br />0.0117 hours <br />6.944444e-5 weeks <br />1.5981e-5 months <br /> per response. Send

comments regarding this information collection to the FOIA, Library and Information Collection

Branch, Office of the Chief Information Officer, Mail Stop: T6-A10M, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001, or by email to Infocollects.Resource@nrc.gov, and

to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011)

OMB, Washington, DC 20503.

In accordance with 10 CFR 2.390 of the NRC rules and practices, a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC public document

room or from the publicly available records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Website.

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection, or the inspection teams information or logistical needs, please

contact Thomas Hartman, the team leader, in the Region 3 Office at 630-829-9884.

Sincerely,

Thomas Hartman

Senior Project Engineer

Engineering & Reactor Projects Branch

Division of Operating Reactor Safety

Docket Nos. 05000266 and 05000301

License Nos. DPR-24 and DPR-27

Enclosure:

Age-Related Degradation Inspection

Request for Information

cc w/ encl: Distribution via LISTSERV

Signed by Hartman, Thomas

on 02/05/24

M. Durbin

3

Letter to Michael Durbin from Thomas Hartman dated February 5, 2024.

SUBJECT:

POINT BEACH NUCLEAR PLANT - NOTICE OF INSPECTION AND REQUEST

FOR INFORMATION FOR THE NRC AGE-RELATED DEGRADATION

INSPECTION: INSPECTION REPORT 05000266/2024010 AND

05000301/2024010

DISTRIBUTION:

Jeffrey Hamman

RidsNrrDorlLpl3

RidsNrrPMPointBeach

RidsNrrDroIrib Resource

John Giessner

Mohammed Shuaibi

Diana Betancourt-Roldan

Allan Barker

David Curtis

Jared Heck

R3-DORS

ADAMS Accession Number: ML24036A265

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

OFFICE

RIII

NAME

THartman:sw

DATE

02/05/2024

OFFICIAL RECORD COPY

Enclosure

AGE-RELATED DEGRADATION INSPECTION

REQUEST FOR INFORMATION

I.

ADMINISTRATIVE INSPECTION INFORMATION

Inspection Report Number:

05000266/2024010 and 05000301/2024010

Onsite Inspection Dates:

April 29-May 3, 2024, and May 13-17, 2024

Inspection Procedure:

IP 71111.21N04, Age-Related Degradation

Lead Inspector:

Thomas Hartman, Senior Project Engineer, RIII/DORS

630-829-9884

Thomas.Hartman@nrc.gov

Teammates:

Joon Park, Reactor Inspector, RIII/DORS

Kevin Fay, Reactor Inspector, RIII/DORS

II.

LOGISTICS

Email the following inspection logistics to the lead inspector by April 15, 2024, or sooner:

1.

Entrance meeting time and location;

2.

Room number/name and location of the room to be used by the inspection team

while onsite;

3.

Current management and engineering organizational chart;

4.

Response team contact information (names and phone numbers) and team roles

(e.g., management sponsor, lead, inspector counterpart);

5.

Any potential resource conflicts during the inspection (e.g., emergency drills and

all-staff meetings).

III. INFORMATION REQUEST

Contact the lead inspector as soon as possible if you have any questions regarding this

information request. Provide the information electronically in PDF files, Excel, or other

searchable formats, preferably via an electronic sharing service (CERTREC, ShareFile, Box,

etc.). Specific Excel formats for various enclosure items may be requested to assist in

inspection sample selection. If you do not have access to any of these services or similar,

we can provide you access to Box, which can be used to upload/download and share

documents. The files should contain descriptive names and be indexed and hyperlinked to

facilitate ease of use. Information in lists should contain enough information to be easily

understood by someone who has knowledge of light-water reactor technology.

2

A. Information Requested to Support Information Gathering Visit

The documents and information requested below should generally be made available to the

inspection team for the teams use both on-site and off-site during the information gathering

visit. Electronic format is the preferred media. If electronic media is made available via an

internet based remote document management system, then the remote document access

should allow inspectors to download, save, and print the documents in the NRCs regional

office. Electronic media on compact disc or paper records (hard copy) are acceptable. At the

end of the inspection, the documents in the teams possession will not be retained.

This document request is based on typical documents that a generic plant might have. As

such, this document request is not meant to imply that any specific plant is required to have

all of the listed documents. In addition, your plant-specific document titles may vary from the

document titles listed below.

The following information is requested by February 26, 2024, or sooner, to facilitate the

sample selections.

Documents requested, if available:

1.

List of 50.65 (a)(1) SSCs from the past 5 years;

2.

List of maintenance rule functional failures (including preventable failures) from the

past 5 years;

3.

Most recent evaluation of maintenance effectiveness required per 10 CFR 50.65(a)(3);

4.

Maintenance rule scoping and performance criteria document;

5.

List of preventative maintenance deferrals and preventative maintenance change

requests in the last 5 years;

6.

Equipment reliability characterization and preventative maintenance program

procedures

7.

List of Title 10 CFR 21 Reports applicable to the site from the past 5 years;

8.

Site-specific corrective actions associated with component failures, or tagged with

aging, age-related, wear, accelerated wear, abnormal wear, accelerated

degradation, abnormal degradation, corrosion, degradation, etc.;

9.

List of technical specification operability determinations from the past 5 years;

10.

List of risk-significant long-lived passive SSCs (for licensees in the period of extended

operation (PEO));

11.

Aging management programs (AMPs) and any plant-specific or industry operating

experience reviews that have been used to update aging management activities

(for licensees in the period of extended operation);

3

12.

List of top 100 most risk-significant structures and components. If possible, designate

the component as active or passive in the risk ranking;

13.

Site-specific probabilistic risk assessment (PRA) identifying risk-significant functions;

14.

Technical specifications and technical requirements manual, including applicable

bases documents;

15.

List of systems (system numbers/designators and corresponding names).

B. Information Requested for Selected Samples:

The team lead will identify samples (i.e., structures and components) after the information

gathering visit. The documents and information requested below should generally be

made available to the inspection team for the teams use both onsite and offsite during the

inspection. Electronic format is the preferred media. If electronic media is made available

via an internet based remote document management system, then the remote document

access should allow inspectors to download, save, and print the documents in the NRCs

regional office. Electronic media on compact disc or paper records (hardcopy) are

acceptable. At the end of the inspection, the documents in the teams possession will not

be retained.

This document request is based on typical documents that a generic plant might have. As

such, this document request is not meant to imply that any specific plant is required to

have all the listed documents. In addition, your plant-specific document titles may vary

from the document titles listed below. We also request that the information provided be

sorted by the list below for each sample.

The following information is requested by April 22, 2024, or sooner, to facilitate the

inspection.

1.

List of corrective action documents for the last 10 years;

2.

Maintenance, surveillance, testing, inspection, and condition monitoring testing

requirements, acceptance criteria, and periodicities;

3.

Bases documents associated with maintenance, surveillance, testing, inspection, and

condition monitoring testing requirements, acceptance criteria, and periodicities;

4.

Last 2 years of maintenance, surveillance, testing, inspection, and condition monitoring

testing results; for periodicities greater than 2 years, the last two test results;

5.

Self-imposed and vendor recommendations;

6.

If available,

a)

Equipment reliability category/characterization (e.g., non-critical,

run-to-maintenance, etc.);

b)

Preventative maintenance templates for the maintenance strategy;

4

c)

System design-basis documents and the specific updated final safety analysis

report section that describes the function;

d)

P&IDs and electrical one-line drawings;

e)

Control circuit drawings;

f)

Design/procurement specifications;

g)

List of applicable modifications for the component.

If you have questions regarding the information requested, please contact the lead inspector.