IR 05000266/2022004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000266/2022004 and 05000301/2022004
ML23023A220
Person / Time
Site: Point Beach  
Issue date: 01/24/2023
From: Billy Dickson
NRC/RGN-III/DORS/EB2
To: Strope M
Point Beach
References
IR 2022004
Download: ML23023A220 (1)


Text

SUBJECT:

POINT BEACH NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000266/2022004 AND 05000301/2022004

Dear Michael Strope:

On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant. On January 6, 2023, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Point Beach Nuclear Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Point Beach Nuclear Plant.

January 24, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Billy C. Dickson, Jr., Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000266 and 05000301

License Numbers:

DPR-24 and DPR-27

Report Numbers:

05000266/2022004 and 05000301/2022004

Enterprise Identifier:

I-2022-004-0052

Licensee:

NextEra Energy Point Beach, LLC

Facility:

Point Beach Nuclear Plant

Location:

Two Rivers, WI

Inspection Dates:

October 01, 2022 to December 31, 2022

Inspectors:

R. Baker, Senior Operations Engineer

J. Cassidy, Senior Health Physicist

J. Corujo-Sandin, Senior Reactor Inspector

G. Hansen, Sr. Emergency Preparedness Inspector

T. Hartman, Senior Resident Inspector

V. Petrella, Senior Resident Inspector

G. Roach, Senior Operations Engineer

E. Rosario, Reactor Inspector

D. Turpin, Resident Inspector

J. Weigandt, Resident Inspector

Approved By:

Billy C. Dickson, Jr., Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Point Beach Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Licensee Failed to Evaluate All Credited Functions When a Safety-Related Valve Failed to Operate Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-01 Open/Closed

[P.1] -

Identification 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of Point Beach Nuclear Plant Unit 1, Renewed Operating License Condition 4.F. (fire protection), for the failure to evaluate all credited functions of a failed component as required by EN-AA-203-1001, Operability Determinations/Functionality Assessments. Specifically, when 1RC-427, RC loop B cold leg to CVCS letdown isolation, was unable to close remotely from the control room, the licensee evaluated the safety-related pressure boundary function but failed to assess the functions associated with fire protection and the emergency operating procedures (EOPs).

Licensee Preconditioned Valve Prior to Testing Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-02 Open/Closed

[H.5] - Work Management 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion XI, Test Control, because the licensee established unevaluated preconditioning prior to performing stroke time testing of valve 1RC-427, RC loop B cold leg to CVCS letdown isolation. Specifically, the licensee, in several cases, manipulated 1RC-427 prior to the performance of the required IST surveillance, which potentially masked degraded conditions.

Inadequate Maintenance Rule Monitoring of the Reactor Coolant System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-03 Open/Closed

[H.9] - Training 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of 10 CFR 50.65(a)(1), Maintenance Rule, for the failure to monitor the performance of the Unit 1 reactor coolant system (RCS) against licensee-established goals.

Specifically, the licensee did not identify and properly account for failures of 1RC-427,

RC loop B cold leg to CVCS letdown isolation, to close remotely from the control room, which demonstrated that the performance of the Unit 1 RCS was not being effectively monitored and controlled through appropriate preventive maintenance, such that the SSC remains capable of performing its intended function.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000266/2020004-01 Letdown Isolation Valve, 1RC-427, Failed to Close from Main Control Room 71111.12 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated station readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) G-04 emergency diesel generator starting air and the glycol cooling systems on October 5, 2022
(2) Unit 2 train B component cooling water system on November 17, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)fire zones 763, 764, 770, 772, 773, 778, 780, and 785 on November 14, 2022 (2)fire zones 775, 776, 777, 783, 784, and 786 on November 14, 2022 (3)fire zones 138, 139, 141, 142, 143, and 150 on November 15, 2022 (4)fire zones 162, 163, 164, 165, and 166 on November 18, 2022

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on October 31, 2022.

71111.07T - Heat Exchanger/Sink Performance Heat Exchanger (Service Water Cooled) (IP Section 03.02)

The inspectors evaluated heat exchanger performance on the following:

(1)1D containment fan motor cooler (1HX-15D)

Ultimate Heat Sink (IP Section 03.04) (1 Sample)

The inspectors evaluated the ultimate heat sink performance on the following:

(1) The ultimate heat sink, specifically Sections 03.04.b and 03.04.e were completed.

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification program annual operating tests and biennial written exams administered from October 10, 2022, through November 11, 2022.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on Wednesday, November 2, 2022.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during G-02 emergency diesel generator testing on November 13, 2022, and December 11, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator simulator requalification exam on October 18, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) B52-DB50-040, 480 Volt DB-50 switchgear breaker
(2) DY-0C, White 125V DC/120V AC inverter
(3) Unit 1 spray additive eductor suction valve, 1SI836A
(4) G-05 gas turbine generator

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk due to reduced coincidence on reactor protection logic during testing, on September 27, 2022 (2)elevated risk due to entry into a shutdown statement, reduced logic coincidence, and testing outside a protected train for Unit 2 engineered safety features (ESF) system logic train B testing, on September 29, 2022 (3)elevated risk due to entry into a 6-hour shutdown statement, entry into an 8-hour shutdown statement, and racking and tripping reactor trip breaker and reactor trip bypass breaker, on September 29, 2022 (4)elevated station risk due to G-04 diesel generator testing on October 4, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1 Tave/Tref error meter cycling (2)white substance found during the inspection of HX-13B spent fuel pool heat exchanger
(3) Unit 2 turbine-driven auxiliary feedwater pump discharge flow indicator reads slightly over 20 gpm with no flow
(4) Unit 1 train B safety injection pump oil bubbler empty (5)high vibrations on the control room emergency filtration system
(6) Unit 1 train A component cooling water pump motor temperature is high

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) EC 297510, EC 291725 As-Built Calculation Pending Changes, Revision 0

Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)

(1) The inspectors verified the site Severe Accident Management Guidelines were updated in accordance with the PWR generic sever accident technical guidelines and validated.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1)1ICP 13.004B, SPEC 200, Reactor Vessel Level and Subcooling Post Accident Monitoring Instruments 18 Month Calibration, after the calibration of the reactor vessel water level and subcooling post-accident monitoring instruments on September 19, 2022 (2)1RMP 9056-4, B-04 Safety Related and Technical Specification Relay Calibrations, after the calibration of the loss-of-voltage relays 1-271/B04, 1-272/B04, and 1-273/B04 on October 24, 2022

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the licensees compliance with the requirements specified in the Federal Emergency Management Agency (FEMA)-approved Alert and Notification System (ANS) Design Report.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency response organization.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:

PCR No. 2388138, 07/15/2021

PCR No. 2388248, 07/15/2021

PCR No. 2388292, 07/15/2021

PCR No. 2388405, 07/15/2021

PCR No. 2396565, 07/15/2021

PCR No. 2371336, 08/24/2021

PCR No. 2395711, 08/24/2021

PCR No. 2371891, 12/06/2021

PCR No. 2393791, 12/07/2021 PCR No. 2387151, 12/16/2021

PCR No. 2411811, 12/16/2021

PCR No. 2413964, 06/06/2022

PCR No. 2425960, 06/06/2022 This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Shift Manager emergency action level determination and notification during simulator requalification on October 18,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (7 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1)area radiation monitors in the auxiliary building (2)friskers used at the main exit from the radiologically controlled area (3)portable radiation protection equipment stored ready for use at the radiation protection checkpoint entrance (4)personal contamination monitors 'ready for use' at the exit from the radiologically controlled area (5)personal contamination monitors 'ready for use' at the primary access facility exit (6)continuous air monitors in the auxiliary building (7)tool and equipment monitors 'ready for use' at the exit from the radiologically controlled area

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Mirion iSolo PBNP# 472932
(2) FASTSCAN whole body counter
(3) Ludlum 177 serial number 348303
(4) Canberra GEM serial number 480459 (0712-118)
(5) Mirion Cronos serial number 1511-198 (6)tool and equipment monitor identification number 330699
(7) Escort Elf serial number A4-19921
(8) MGP AMP-50 serial number 479301
(9) Eberline AMS-4 serial number 330687
(10) Canberra ARGOS 5AB serial number 712-048/0480461 (11)high volume air sampler serial number 330842 (12)low volume air sampler serial number 330800
(13) Ludlum 9-3 serial number 333086 Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1)waste disposal system liquid monitor RE-218 (2)auxiliary building ventilation monitor SPING

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS09: Residual Heat Removal Systems (IP Section 02.08)===

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2021 through June 30, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 1, 2021 through June 30, 2022 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)

The site is in compliance with ANS performance indicator reporting requirements. The site's primary ANS is the Integrated Public Alert Warning System (IPAWS), therefore, for the period of this inspection, no siren performance testing data was available or required. In accordance with EPFAQ 21-03, Revision 1, "Reporting ANS Data Following a Transition to IPAWS," the performance of the licensees ANS was evaluated using NRC Inspection Procedure 71114 Attachment 2, Alert and Notification System" with the results documented in the corresponding section of this inspection report.

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) AR 02429535, 2SC-955 Boric Acid Identified During Containment Walkdown

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program from June 1 to November 30, 2022, for potential adverse trends that might be indicative of a more significant safety issue

INSPECTION RESULTS

Licensee Failed to Evaluate All Credited Functions When a Safety-Related Valve Failed to Operate Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-01 Open/Closed

[P.1] -

Identification 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of Point Beach Nuclear Plant Unit 1, Renewed Operating License Condition 4.F. (fire protection), for the failure to evaluate all credited functions of a failed component as required by EN-AA-203-1001, Operability Determinations/Functionality Assessments. Specifically, when 1RC-427, RC loop B cold leg to CVCS letdown isolation, was unable to close remotely from the control room, the licensee evaluated the safety-related pressure boundary function but failed to assess the functions associated with fire protection and the emergency operating procedures (EOPs).

Description:

On October 4, 2020, while performing a plant shutdown of Unit 1 for refueling, the licensee attempted to close 1RC-427, RC loop B cold leg to CVCS letdown isolation, from the control room as directed by the plant shutdown procedure. The valve showed dual indication but failed to close fully. The licensee re-opened the valve and immediately received a "Full Open" indication indicating the valve had barely moved from its "Full Open" position. A second attempt showed the same indications. The licensee entered the condition in the corrective action program so it plant staff could evaluate it for operability and functionality to determine if follow-up actions were warranted.

The licensee determined the valve was "Operable." They determined that the valve maintained its safety-related function as a reactor coolant system pressure boundary valve.

However, the valve has other functions, some of which are risk significant. The licensee did not evaluate the valve's functionality against any other functions, notably the loss of coolant accident (LOCA) mitigation actions as directed by the EOPs and fire protection. 1RC-427 has an augmented quality function requirement to close in support of the NFPA 805 post-fire safe shutdown assessment. After questions from the resident inspectors about the non-safety-related functions and how they were affected, the licensee evaluated the additional credited functions and determined that the valve was not functional for several functions.

Corrective Actions: The licensee re-evaluated the valve against all credited functions and determined it could not perform some of those functions and declared it non-functional. The licensee took the necessary actions, including establishing compensatory measures for the NFPA 805 (fire protection) vulnerability.

Corrective Action References: AR 2378631

Performance Assessment:

Performance Deficiency: The inspectors determined the licensee's failure to evaluate all credited functions for a failed component as required by EN-AA-203-1001, "Operability Determinations/Functionality Assessments," was a performance deficiency. Specifically, when 1RC-427 failed to close remotely from the control room, the licensee only evaluated the safety-related function even though the valve had other credited risk-significant functions.

Screening: Even though there were multiple functions not evaluated, the fire protection function was the most significant. The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the valve was not able to perform its required non-safety-related fire protection function for which the licensee failed to implement the required compensatory measures.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Because the issue was related to the post-fire safe shutdown (SSD) category, the inspectors answered the questions in step 1.4.7. The inspectors answered "no" to questions A and B and "yes" to question C.

This progressed the inspectors to Step 1.5. The inspectors determined the finding screened to Green (very low safety significance) because the licensee has a fire PRA [probability risk assessment] capable of adequately evaluating the risk and that evaluation indicated a delta-CDF [core damage frequency] of less than 1E-6 as determined by an SRA [senior reactor analyst].

Cross-Cutting Aspect: P.1 - Identification: The organization implements a corrective action program with a low threshold for identifying issues. Individuals identify issues completely, accurately, and in a timely manner in accordance with the program. Specifically, the licensee failed to completely identify the functions (both safety and non-safety-related) that the valve is required to perform.

Enforcement:

Violation: Point Beach Nuclear Plants 1, Renewed Operating License Condition 4.F, requires the licensee to implement and maintain in effect all provisions of the approved fire protection program that comply with 10 CFR 50.48(a) and 10 CFR 50.48(c), National Fire Protection Association Standard NFPA 805, as specified in the license amendment requests and as approved in the safety evaluation report dated September 8, 2016.

Contrary to the above, from October 4, 2020, through December 21, 2021, the licensee failed to implement and maintain in effect all provisions of the approved fire protection program.

Specifically, the licensee failed to implement required compensatory measures when 1RC-427 was unable to perform its credited fire protection function.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Licensee Preconditioned Valve Prior to Testing Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-02 Open/Closed

[H.5] - Work Management 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion XI, Test Control, because the licensee established unevaluated preconditioning prior to performing stroke time testing of valve 1RC-427, RC loop B cold leg to CVCS letdown isolation. Specifically, the licensee, in several cases, manipulated 1RC-427 prior to the performance of the required IST surveillance, which potentially masked degraded conditions.

Description:

On October 4, 2020, while performing a plant shutdown of Unit 1 for refueling, the licensee attempted to close valve 1RC-427, RC loop B cold leg to CVCS letdown isolation, from the control room as directed by the plant shutdown procedure. The valve showed dual indication but failed to close fully. The licensee re-opened the valve and immediately received a "Full Open" indication indicating the valve had barely moved from its "Full Open" position. A second attempt showed the same indications. The licensee entered the condition in the corrective action program to evaluate its operability and document the need for maintenance.

On October 11, 2020, the licensee went to the field, manually manipulated the valve to close and open, and left it mid-position. The licensee then stroked the valve several times electrically and determined that no maintenance was required since the valve was moving as expected. On October 19, 2021, the licensee timed the stroking of 1RC-427 as part of the post-maintenance testing and used it to satisfy the testing required by their inservice testing (IST) program. The valve successfully met the IST requirements and showed no signs of degradation during the testing.

One of the items noted in the condition report was a previous failure of this same valve during the last refueling outage. That condition report identified other times when this valve failed to close. Each time the licensee went into the field and performed work on the valve, either by actual maintenance or manipulating the valve to correct the issue. And each time, the licensee, within a few days of working on the valve, performed the timing of the valve to meet IST requirements. Each time, the valve passed the testing requirements and showed no significant signs of degradation. The licensee closed the issue as resolved with no further actions.

Corrective Actions: The licensee re-evaluated the condition and determined that the valve was unacceptably preconditioned before performing the IST surveillance. By the time of the re-evaluation, the valve was already considered non-functional based on other information. In addition, the licensee adopted a newer version of the ASME OM Code that no longer requires 1RC-427 to be included in the licensee's IST program.

Corrective Action References: AR 2384400

Performance Assessment:

Performance Deficiency: The inspectors determined the licensee's failure to evaluate and prevent unacceptable preconditioning on valve 1RC-427 in accordance with ER-AA-113-1000, Inservice Testing Procedure, was a performance deficiency. Specifically, the licensee manually (locally) and electronically (remotely) manipulated the valve several times to verify it was able to stroke prior to performing the inservice valve timing test without an evaluation to determine the effect of the preconditioning.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, on multiple occasions, the licensee manipulated (both manually and electrically) valve 1RC-427 prior to performing required inservice testing which masked actual degradation with the valve.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because the inspectors answered "no" to all the questions in Exhibit 2 - Mitigating Systems Screening Questions.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the licensee failed to schedule the maintenance and testing such that unacceptable preconditioning doesn't occur.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion XI, Test Control, states, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. It also states that test procedures shall include provisions for assuring that all prerequisites for the given test have been met.

Contrary to the above, on October 19, 2020, the licensee did not establish an adequate test program to assure that all testing required to demonstrate that 1RC-427 would function satisfactorily in service was properly performed. Specifically, the licensee allowed preconditioning or 1RC-427 prior to performing required inservice testing which masked actual degradation within the valve.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Maintenance Rule Monitoring of the Reactor Coolant System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000266/2022004-03 Open/Closed

[H.9] - Training 71111.12 The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation of 10 CFR 50.65(a)(1), Maintenance Rule, for the failure to monitor the performance of the Unit 1 reactor coolant system (RCS) against licensee-established goals.

Specifically, the licensee did not identify and properly account for failures of 1RC-427, RC loop B cold leg to CVCS letdown isolation, to close remotely from the control room, which demonstrated that the performance of the Unit 1 RCS was not being effectively monitored and controlled through appropriate preventive maintenance, such that the SSC remains capable of performing its intended function.

Description:

On October 24, 2020, the licensee performed a maintenance rule evaluation for the failure of 1RC-427 to close on October 4, 2020. In this evaluation, the licensee documented several functions that the valve performs. There is a passive safety-related function to maintain the reactor coolant system pressure boundary and several non-safety-related functions. The evaluation calls states that 1RC-427 has an augmented quality (AQ) to remotely close during an NFPA 805 event to support post-fire safe shutdown. It is also used within several of the licensee's abnormal operating procedures (AOPs) and emergency operating procedures (EOPs) to close to mitigate the consequences from a loss of coolant accident. However, despite documenting that 1RC-427 was required to close to perform these functions and the initial condition is that 1RC-427 failed to close remotely, the licensee did not consider the failure to be a maintenance rule functional failure (MRFF) as defined by licensee procedures ER-AA-100-2002, Maintenance Rule Program Administration, and NP 7.7.5, Maintenance Rule Monitoring, because the licensee was able to stroke the valve manually then electrically stroke the valve with no maintenance performed.

The inspectors questioned the motor-operated valve's ability to perform its functions to close remotely from the control room and automatically for NFPA 805 safe shutdown, AOPs, and EOPs, when it was unable to remotely close when transitioning reactor Unit 1 from hot standby to cold shutdown. Further investigation revealed that this valve has had failures to close multiple times over the course of the last 10 years. When the valve failed to close in 2019, no MRFF evaluation was performed (until 2021 when investigating the recent failure),and in 2020, it was determined not to be an MRFF and was not evaluated against the licensee's performance criteria for either date. Since the valves performance was not being adequately monitored, the licensee failed to recognize the significance of the valve failure, did not determine the cause of the failure, and did not take effective corrective actions for the failures.

Corrective Actions: The licensee re-evaluated the functional failure and determined that the valve failure was an MPFF, based on a historical review determined it was also a repeat functional failure (RMPFF) and that a 50.65(a)(1) assessment was required. On June 14, 2021, the licensee completed the assessment and determined that the reactor coolant system no longer met the 50.65(a)(2) requirements. By the time the licensee completed this assessment, the system was already in 50.65(a)(1) status for a different issue.

Corrective Action References: AR 2370332 AR 2387544

Performance Assessment:

Performance Deficiency: The inspectors determined the licensee's failure to monitor the performance of the Unit 1 reactor coolant system (RCS) against licensee-established goals in accordance with ER-AA-100-2002, Maintenance Rule Program Administration, was a performance deficiency. Specifically, the licensee did not identify and properly account for the failure of 1RC-427 to close remotely from the control room within the maintenance rule program.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, not properly evaluating equipment failures and tracking them with the maintenance rule program can lead to more significant concerns.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because the inspectors answered "no" to all the questions in Exhibit 2 - Mitigating Systems Screening Questions.

Cross-Cutting Aspect: H.9 - Training: The organization provides training and ensures knowledge transfer to maintain a knowledgeable, technically competent workforce and instill nuclear safety values. Specifically, the individual that performed the maintenance rule evaluation misdiagnosed the functional failure and had a misconception with the relationship between operability and functionality.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations 50.65 (a)(1), requires, in part, that the holders of an operating license shall monitor the performance of SSCs within the scope of the rule as defined by 10 CFR 50.65 (b), against licensee-established goals, in a manner sufficient to provide reasonable assurance that such SSCs are capable of fulfilling their intended functions. 10 CFR 50.65 (a)(2) states, in part, that monitoring as specified in 10 CFR 50.65 (a)(1) is not required where it has been demonstrated that the performance of an SSC is being effectively controlled through appropriate preventive maintenance, such that the SSC remains capable of performing its intended function.

Contrary to the above, from March 24, 2019, until June 14, 2021, the licensee failed to monitor the equipment against licensee-established goals when the performance of the Unit 1 reactor coolant system had not been effectively controlled through appropriate preventive maintenance. Specifically, the licensee did not identify and properly account for the maintenance preventable functional failures of the1RC-427 valve that occurred on March 24, 2019, and October 4, 2020.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

URI Letdown Isolation Valve, 1RC-427, Failed to Close from Main Control Room URI 05000266/2020004-01 71111.12

Description:

Three finding/violations were identified as described above/below Observation: Semiannual Trend Review 71152S The inspectors reviewed action requests entered into the corrective action program for the following:

complete, accurate, and timely documentation of the issue identified in the corrective action program

evaluation and timely disposition of operability and reportability issues

consideration of extent of condition and cause, generic implications, common cause, and previous occurrences

classification and prioritization of the problems resolution, commensurate with the safety significance

identification of corrective actions that are appropriately focused on correcting the problem

completion of corrective actions in a timely manner, commensurate with the safety significance of the issue

identification of negative trends associated with human or equipment performance that can potentially impact nuclear safety

operating experience is adequately evaluated for applicability, and applicable lessons learned are communicated to appropriate organizations, and implemented.

The inspectors completed the review and did not note any significant trends that needed to be identified and addressed by the licensee.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 6, 2023, the inspectors presented the integrated inspection results to M. Strope and other members of the licensee staff.

On October 26, 2022, the inspectors presented the radiation protection inspection results to D. Peterson, Radiation Protection and Chemistry Manager, and other members of the licensee staff.

On October 27, 2022, the inspectors presented the emergency preparedness inspection results to E. Schultz, Licensing Manager, and other members of the licensee staff.

On October 28, 2022, the inspectors presented the Triennial Heat Sink inspection results to B. Beltz, Organizational Effectiveness Site Director, and other members of the licensee staff.

On November 3, 2022, the inspectors presented the Biennial Licensed Operator Requalification Program inspection results to M. Strope, Site Vice President, and other members of the licensee staff.

On December 7, 2022, the inspectors presented the 2022 Licensed Operator Continuing Training Biennial Written Examination and Annual Operating Test summary review inspection results to A. Moore, Operations Training Supervisor, and other members of the licensee staff.

On December 7, 2022, the inspectors presented the emergency action level and emergency plan changes inspection results to E. Schultz, Licensing Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PBNP Seasonal Readiness Memo - Winter 2022-23

11/11/2022

Miscellaneous

Winter Seasonal Readiness Work List

10/18/2022

71111.01

Procedures

OP-AA-102-102

Seasonal Readiness

110E029 Sheet 2

Auxiliary Coolant System

110E029 Sheet 3

Auxiliary Coolant System

M-209 Sheet 15

P&ID Starting Air System Diesel Generator Building

Drawings

M-227 Sheet 2

P&ID Glycol Cooling System Diesel Generator Building

2-CL-CC-001

Component Cooling Unit 2

71111.04

Procedures

CL 11A G-04

G-04 Diesel Generator Checklist

PFP-0-PAB-66

Pre-Fire Plan Unit 1 & Unit 2 Auxiliary Building 66 Ft

PFP-0-PAB-8

Pre-Fire Plan Primary Auxiliary Building Elevation 8' and

Below

Fire Plans

PFP-0-PAN

Pre-Fire Plan Protected Area North (Inside the Fence)

71111.05

Miscellaneous

Crew B 4Q 2022 Fire Drill

10/31/2022

Calculations

98-0020

Containment Recirculation Fan Motor Cooler Service

Water Flow vs. Temperature Requirements for Normal and

Accident Modes of Operation

2423963

1CW-00003, Seal Well Outlet MOV Damage

04/06/2022

Corrective Action

Documents

2425351

U1R4 - HX-15D1-8 Containment Fan Coolers EC

Inspection

04/18/2022

2440412

Rust on Floor Directly Under the U1 and U2 CFC Service

Water Supply Piping

10/26/2022

Corrective Action

Documents

Resulting from

Inspection

2440530

2HX-15B Service Water Return Vibration - Inspect Pipe

Support (HB-19-2H119)

10/27/2022

EPB31S07001802103

Water Intake Facility General Arrangement

M-207 SH.1

P&ID Service Water System

Drawings

M-207 SH.4

P&ID Service Water System

Engineering

Evaluations

2008-0005

Containment Fan & Fan Motor Coolers HX Tube Plugging

Criteria

71111.07T

Miscellaneous

PBW-WMP-700

Westinghouse Letter on Service Water Strainer Power

Supply

05/02/1968

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AOP-13A

Circulating Water System Malfunction

AOP-9A

Service Water System Malfunction

OI-70

Service Water System Operation

OI-72

Containment Air Recirculation System

RMP 9155

Diver's Inspection Report - Intake Structure

Procedures

TS-33

Containment Accident Recirculation Fan-Cooler Units Unit

40472820-01

1HX-015D - GL 89-13 Motor Cooling Coil Eddy Current

05/01/2019

40472820-02

1HX-015D - GL 89-13 Motor Cooling Coil Eddy Current

05/01/2019

40588444-01

1HX-015D - GL 89-13 Motor Cooling Coil Internal

10/29/2020

40631295-01

1HX-015D - GL 89-13 Motor Cooling Coil

Inspection/Cleaning

05/04/2019

40667905-01

GL 89-13 Inspect and Clean Pumphouse Forebay

11/02/2020

40753062-02

Unit 1 Diving Activities per RMP 9155-2

05/04/2022

40757304-01

GL 89-13 Inspect Crib/Remove Buoys and Fish Deterrent

10/19/2021

Work Orders

40801224-01

TS-33 U1C Accident Fan Cooler Units Surveillance Test

09/08/2022

71111.11A

Miscellaneous

22 Annual Licensed

Operator Requal

Testing Results

Point Beach 2022 Annual LORT Exam Summary Results

11/22/2022

AR 2405194

1RE-212 Made Inoperable Following Testing (TS and

ODCM)

09/26/2021

AR 2417908

Inadequate Operability Assessment-Degraded RCS

Insulation

2/03/2022

AR 2417996

Operability Basis Lacked Documentation of Impact of

Degraded Condition

2/04/2022

AR 2418266

Immediate Operability Determination Lacks Required

Considerations

2/08/2022

Corrective Action

Documents

AR 2431752

Guarded Equipment Postings Related to G-02 Outage

07/11/2022

22 Week 4 RO A-

Top/C-Bottom

RO Written Examination

11/03/2022

22 Week 4 RO

Categories

RO Question Selections from 2022 LOC Biennial Master

Exam Bank

10/19/2022

71111.11B

Miscellaneous

22 Week 4 SRO A-

Top/C-Bottom

SRO Written Examination

11/03/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

22 Week 4 SRO

Categories

SRO Question Selections from 2022 LOC Biennial Master

Exam Bank

10/19/2022

Attendance Records

Licensed Operator Continuous Training Attendance

Records (Various)

21-2022

Medical Records

Licensed Operator Medical Records for 6 Operators

11/01/2022

P000.004A

Job Performance Measure

Rev 1

P000.008B

Job Performance Measure

Rev 11

P000.027D

Job Performance Measure

Rev 2

P000.027F

Job Performance Measure

Rev 1

P000.039E

Job Performance Measure

Rev 5

P000.041

Job Performance Measure

Rev 3

P000.044A

Job Performance Measure

Rev 5

P000.055

Job Performance Measure

Rev 5

P012.001C

Job Performance Measure

Rev 5

P061.001A

Job Performance Measure

Rev 5

P061.005

Job Performance Measure

Rev 4

PBN DT 94.0,

Simulator Health

Management

Transient Testing - Manual Reactor Trip

04/24/2021

PBN DTG 94.0,

Simulator Health

Management

Transient Testing - Simultaneous Trip of Both Reactor

Coolant Pumps

04/24/2021

PBN DTG 94.0,

Simulator Health

Management

Transient Testing - Maximum Rate Power Ramp 100% to

75% to 100% U1C40

04/24/2021

PBN DTG 94.0,

Simulator Health

Management

Transient Testing - Maximum Design Load Rejection

04/24/2021

PBN LC 000.046E

Dynamic Scenario Guide

Rev 2

PBN LOC 000.049E

Dynamic Scenario Guide

Rev 2

PBN LOC 000.049E

Simulator Scenario Based Testing NRC Annual Operating

Exam Scenario

Rev 0

PBN LOC 000.051E

Dynamic Scenario Guide

Rev 3

PBN LOI NRC 22E

Simulator Scenario Based Testing 2021 NRC Exam

Rev 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Scenario 1

PBN LPC 000.008E

Dynamic Scenario Guide

Rev 6

PBN SIMGL C1.4

Unit 1 Cycle 41 Core Reload Simulator Modification

2/23/2021

Remediation Records

22 Annual Operating Test Failure Remediation

Packages for 4 Individuals

11/02/2022

Remediation Records

22 Biennial Written Examination Failure Remediation

Package for 1 Individual

11/02/2022

Simulator Review

Committee Meeting

Meeting Minutes

03/15/2022

Simulator Review

Committee Meeting

Meeting Minutes

09/26/2022

Watch Proficiency

Records

eSOMS Credit for Standing Watch 04/01/2022 to

09/30/2022 Reports

11/02/2022

FL-LOC-TPD

Licensed Operator Continuing Training Program

Description

Rev 4

OP-AA-100-1001

License Maintenance and Activation

Rev 8

TR-AA-220-1002

NRC Licensed Operator Exam Security

Rev 6

TR-AA-220-1004

Licensed Operator Continuing Training Annual Operating

and Biennial Written Exams

Rev 8

TR-AA-220-1004-F04

Dynamic Simulator Exam Scenario Review Checklist

Rev 0

TR-AA-230-1007

Conduct of Simulator Training and Evaluation

Rev 15

TR-AA-230-1007-F01

Crew Simulator Evaluation Forms for 2022 Annual

Operating Test - Staff Crew

Rev 2

TR-AA-230-1007-F02

Individual Simulator Evaluation Forms for 2022 Annual

Operating Test - Staff Crew-All Operators

Rev 3

Procedures

TR-AA-230-1009

Training Examination Security

Rev 5

Simulator Work

Requests

List of Open Simulator Work Requests

Work Orders

Simulator Work

Requests

List of Closed Simulator Work Requests Since Previous

Biennial Requalification Program Inspection

71111.11Q

Miscellaneous

PBN LOC 000 051E

NRC Annual Operating Exam

AR 01316991

1SI-836A Spray Eductor Suction Valve Strokes Too Slow

04/26/2007

AR 01335849

Stroke Timing of Valves After Hardware Replacement

01/19/2008

71111.12

Corrective Action

Documents

AR 02111007

Trip Bar Gap Out of Tolerance on Left Side of Breaker

2/17/2016

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 02424310

D-108 Battery Charger Trouble Coincident with 1P-11B

Start

04/09/2022

AR 02425025

SR Breaker Repaired with Wire from NNS Breaker

04/14/2022

AR 02425158

1SI-836A Failed IST Stroke Time

04/16/2022

AR 02425175

Validation of Safety Related Parts - Refocus

04/16/2022

AR 02425348

B52-DB50-040; Check Control Wiring Stud Posts

04/18/2022

AR 02437121

DY-0C White Spare Inverter Failed

09/18/2022

AR 02437781

DY-0C X3 Gate Transformer Board Cracked Solder Joints

09/23/2022

AR 02437843

G05 HMI Panel Screen Says Operating System Not Found

09/24/2022

AR 02439267

Inadequate Y System Maintenance Rule Performance

Criteria

10/12/2022

AR 1895061

1RC-427 Indicates Intermediate Following Attempted

Closure

08/07/2013

AR 1895363

1RC 427 Failed to Shut

08/07/2013

AR 2307067

1RC-427, RC Loop to CVCS Letdown, Does Not Close

03/24/2019

AR 2370332

1RC-427 Will Not Stroke From 1C04 in Control

10/04/2020

AR 2423513

1RC-427 Close Stroke During 1R40 Shutdown Review

04/02/2022

AR 2424723

Perform Forensics Examination on Removed Actuator

1RC-427

04/12/2022

AR 02440995

N/A Missed in Procedure 9369-1

11/03/2022

AR 2378631

Screening Question Adequacy Questioned for 1RC-427

MOV Fail to Close

2/16/2020

AR 2384400

Valve 1RC-427 Pre-Conditioned Prior to PMT Inservice

Test

03/31/2021

Corrective Action

Documents

Resulting from

Inspection

AR 2387544

Repeat MRFF requires (A)(1) Eval Based on MRFF

Determination

03/22/2021

Drawings

110E017 Sheet 3

P&ID Safety Injection System Point Beach N.P. Unit 1

Engineering

Evaluations

Maintenance Rule (a)(1) Action Plan for Unit 1 RC System

09/13/2021

Fleet Maintenance Rule Scoping Document for System Y

1RC-427 Maintenance Rule Timeline

11/03/2022

Maintenance Rule (a)(1) Action Plan for Gas Turbine

Miscellaneous

Unavailability Time for G-05

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-AA-203-1207-F01

CFR Applicability Determination Form for Standing

Order for 1RC-427, Rev 0

2/22/2020

EN-AA-203-1001

Operability Determinations / Functionality Assessments

ER-AA-100-2002

Maintenance Rule Program Administration

FPTE 2016-003

NFPA 805 Nuclear Safety Capability Assessment

NP 7.7.5

Maintenance Rule Monitoring

Procedures

OM 3.27

Control of Fire Protection and NFPA 805 Equipment

WO 00326638

1SI-836A-O - Diagnostic Check

07/21/2008

WO 00333747

1SI-836A-O Replace Linkage Arm Bolting

01/18/2008

WO 0300947

Perform Diagnostic Check of 1SI-836A Valve

06/23/2004

WO 40356873

1SI-836A-O - Diagnostic Check

07/03/2016

WO 40757011

1RC-00427 Open and Inspect Valve During 1R40

04/02/2022

WO 40776646

B52-DB50-040; Breaker Maint Per RMP 9303 and RMP

9369-1

11/13/2022

WO 40823575

SR Breaker Repaired with Wire from NNS Breaker

07/24/2022

Work Orders

WO 40823644

1SI-836A Failed IST Stroke Time

07/24/2022

Corrective Action

Documents

Resulting from

Inspection

AR 02438079

AOP-31 - Solar Magnetic Disturbance Alert Response

09/27/2022

PBF-2102c for AOP-31 Rev 4 Periodic Review

01/06/2021

Work Activity Risk Management Plan for the 1(2) ICP

2.005 A(B) Safeguards Logic Test

09/29/2022

Work Activity Risk Management Plan for 1(2) ICP

2.003A(B) Reactor Protection Logic Testing

09/29/2022

PDC for the U1 ICP 02.013 4.16KV Undervoltage Matrix

Relays Surveillance Test

09/27/2022

Miscellaneous

NP 10.3.7

On-line Safety Assessment

AOP-31

Solar Magnetic Disturbance Alert Response

AOP-31

Solar Magnetic Disturbance Alert Response

Procedures

OP-AA-102-1003

Guarded Equipment

WO 40835378

2ICP 2.3B - Reactor Protection Logic Test - Train B

09/30/2022

71111.13

Work Orders

WO 40835379

2ICP 2.5B -- Safeguards Logic Test - Train B

09/29/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 02438054

HX-13B SFP HX White Substance Found During

Inspection

09/27/2022

AR 02438454

1P-11A Motor Temp High

10/02/2022

AR 02438778

TWR To Document Info Share on 1P-11A-M Higher Temps

10/05/2022

AR 02439049

2FI-4002 Indicates 20 GPM, while it Should Read 0

10/08/2022

AR 02440200

HX-13A/B GL 89-13 Shell Side Borescope Inspection

Improvement

10/24/2022

AR 02441918

High Vibrations Noticed in the Control Room From CREFS

11/16/2022

AR 02441987

Degraded Inboard Fan Bearing

11/16/2022

AR 2439491

Tave Error Meter Reading +0.9 F

10/14/2022

Corrective Action

Documents

AR 2440923

Bubbler Found Empty on 1P-015B

11/02/2022

Miscellaneous

CCW Pump Motors IR Temperature

10/03/2022

Procedures

GL 89-13

GL 89-13 Program Document

WO 40775032

HX-013B / Video-Probe Inspect Shell Side of SFP Cooler

10/06/2022

71111.15

Work Orders

WR 94240261

Tave Error Meter Reading +0.9 F

10/14/2022

11Q0060-C-022

Thermal Evaluation of Unit 1 Containment Dome Truss in

Support of Risk Informed LAR

001-A

11Q0060-C-024

Seismic Evaluation of Unit 1 Containment Dome Truss in

Support of Risk Informed LAR

001-A

11Q0060-C-028

Seismic Fragility Analysis of Containment Dome Trusses

000-A

Calculations

11Q0060-C-030

Probability of Failure vs. Temperature for Unit 1

Containment Dome Truss in Support of Risk Informed LAR

000-A

AR 02055248

SAMG SACRG-1 - (P) RFI 10/12

06/19/2015

AR 02224032

SAMG SAG-4 - RFI 1/7

09/08/2017

Corrective Action

Documents

AR 02276394

SAMG SAG-7 - RFI 1/7

08/16/2018

Corrective Action

Documents

Resulting from

Inspection

AR 02443786

SAMG SAG-7 Review Documentation Missing

2/13/2022

EP Review using Point Beach Nuclear Plant EOP/AOP

Verification Review Form for AR 02055248

71111.18

Miscellaneous

SRO Review using Point Beach Nuclear Plant EOP/AOP

Verification Review Form for AR 02055248

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Technical Review using Point Beach Nuclear Plant

EOP/AOP Verification Review Form of AR 02055248

08/14/2015

Training Impact Review for AR 02055248

09/24/2015

Validation Review Using Point Beach Nuclear Plant

EOP/AOP Validation Form for AR 02055248

SRO Review using Point Beach Nuclear Plant EOP/AOP

Verification Review Form for AR 02224032

Validation Review using Point Beach Nuclear Plant

EOP/AOP Validation Form for AR 02224032

08/19/2018

L-2015-278

Commitment to Maintain Severe Accident Management

Guidelines

2/17/2015

OM 4.3.2

EOP/AOP Verification/Validation Process

SAMG SACRG-1

Severe Accident Control Room Guideline Initial Response

SAMG SAG-4

Inject Into Containment

Procedures

SAMG SAG-7

Reduce Containment Hydrogen

40678428-01

U1-Containment / Install Dome Truss Mod Per EC 291725,

Dome Truss #1 Modification

40678428-02

U1-Containment / Install Dome Truss Mod Per EC 291725,

Dome Truss #2 Modification

40678428-03

U1-Containment / Install Dome Truss Mod Per EC 291725,

Dome Truss #3 Modification

Work Orders

40678428-04

U1-Containment / Install Dome Truss Mod Per EC 291725,

Dome Truss #7 Modification

WO 40768242

1B-04, Calibrate 1B-04 Tech Spec Relays

10/24/2022

71111.19

Work Orders

WO 40772113

1ICP 13.4 - Spec 200 Tech Spec - Train B

09/23/2022

Point Beach Nuclear Plant Alert Notification System Design

Report

10/25/2020

71114.02

Miscellaneous

FEMA Letter - Approval of the Point Beach Nuclear Plant

(PBNP) Alert and Notification System Update

2/02/2021

Quarterly ERO Augmentation Drill (Call-In) Records

10/01/2020 -

06/30/2022

Miscellaneous

ERO Staff Training and Qualification Records (Sample

Size 15)

10/26/2022

71114.03

Procedures

PBNP On-Shift Staffing Analysis Report

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EPG 1.0, Attachment

Point Beach Nuclear Plant Shift Augmentation Drill

EPIP 2.1

Notifications - ERO, State & Counties, and NRC

EPIP 4.1

Technical Support Center (TSC) Activation and Evacuation

EPIP 4.1

Emergency Operations Facility (EOF) Activation and

Evacuation

EPIP 4.2

Operations Support Center (OSC) Activation and

Evacuation

PBN EP TP

Point Beach Nuclear Plant Emergency Preparedness

Training Program Description

PCR No. 2371336

50.54(q) Screen/Evaluation - Emergency Plan Appendix A

Revision

08/24/2021

PCR No. 2371891

50.54(q) Screen/Evaluation - Emergency Plan Appendix C

Revision

2/06/2021

PCR No. 2387151

50.54(q) Screen/Evaluation - EPIP 1.1 Revision

2/16/2021

PCR No. 2388138,

50.54(q) Screen/Evaluation - EPIP 5.0 Revision

07/15/2021

PCR No. 2388248

50.54(q) Screen/Evaluation - EPIP 6.0 Revision

07/15/2021

PCR No. 2388292

50.54(q) Screen/Evaluation - Emergency Plan Appendix M

Revision

07/15/2021

PCR No. 2388405

50.54(q) Screen/Evaluation - EPIP 4.1 Revision

07/15/2021

PCR No. 2393791

50.54(q) Screen/Evaluation - Emergency Plan Appendix L

Revision

2/07/2021

PCR No. 2395711

50.54(q) Screen/Evaluation - Emergency Plan Appendix A

Revision

08/24/2021

PCR No. 2396565

50.54(q) Screen/Evaluation - EPIP 7.0 Revision

07/15/2021

PCR No. 2411811

50.54(q) Screen/Evaluation - EPIP 6.1 Revision

2/16/2021

PCR No. 2413964

50.54(q) Screen/Evaluation - Emergency Plan Appendix C

Revision

06/06/2022

71114.04

Miscellaneous

PCR No. 2425960

50.54(q) Screen/Evaluation - Emergency Plan Appendix C

Revision

06/06/2022

Emergency Preparedness Program Exercise and Drill

Reports

11/01/2020 -

10/31/2022

71114.05

Miscellaneous

Point Beach Emergency Preparedness Public Information

Postcard

01/01/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radiation Protection Emergency Preparedness Quarterly

Inventory Records

10/01/2020 -

09/30/2022

Monthly Communication Test Records

10/31/2020 -

09/30/2022

Quarterly Communications Test Records

10/01/2020 -

09/30/2022

TSC, EOF, JIC, and OSC Emergency Preparedness

Supplies Quarterly Inventory Records

10/01/2020 -

09/30/2022

KLD-TR 1247

Point Beach Nuclear Plant Development of Evacuation

Time Estimates

09/12/2022

NPL 2020-0066

CY 2020 Emergency Action Level (EAL) Annual Review

2/11/2020

NPL 2021-0114

CY 2021 Emergency Action Level (EAL) Annual Review

2/14/2021

PBN 20-005

Nuclear Assurance Report - Emergency Preparedness

Audit

08/10/2020

PBN-22-003

Nuclear Assurance Report - Emergency Planning Audit

08/10/2022

EP 1.2.1

Emergency Action Levels and Technical Basis

Procedures

NP 1.5

Periodic Procedure Review

22 Calibration of the "FASTSCAN" Counting System at

the Point Beach Generating Station Two Rivers, Wisconsin

03/02/2022

Instrument S/N 1511-

198

Cronos Calibration Data Sheet

09/08/2022

Instrument S/N

330687

Eberline AMS-4 Calibration Data Sheet

Instrument S/N

479301

AMP-50 Calibration Data Sheet

05/31/2022

Instrument S/N 712-

048/0480461

Canberra ARGOS 5AB Calibration Data Sheet

06/15/2022

Instrument S/N A4-

19921

Escort Elf Air Sampling Pump Calibration Record

01/18/2022

Instrument Serial

Number 348303

Ludlum Model 177 Calibration Data Sheet

08/29/2022

71124.05

Calibration

Records

Instrument Serial

Number 480459

(0712-118)

Canberra GEM Calibration Data Sheet

05/31/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PBNP# 472932

iSolo Calibration Data Sheet

03/14/2022

PPBP Air Sampler

Number 330800

Low Volume Air Sampler Maintenance and Calibration

Record

06/08/2022

PPBP Air Sampler

Number 33084

High Volume Air Sampler Maintenance and Calibration

Record

01/04/2022

TEM Identification

Number 330699

Tool and Equipment Monitor Calibration Efficiency

08/17/2022

Corrective Action

Documents

Instrument S/N 33086

Calibration Data Sheet Ludlum 9-3

09/29/2022

Corrective Action

Documents

Resulting from

Inspection

A/R No 02440044

Observations Made During Inspection Procedure 71124.05

10/21/2022

HPCAL 1.1

Radiation Protection Instrument Calibration, Repair and

Functional Checks

HPCAL 1.1.2

Operation and Use of the RADCAL Accu-Dose Model 2186

HPCAL 1.54

Calibration of MGP Electronic Personnel Dosimeter Using

the MGP IDC-HF Electronic Dosimeter Calibrator

HPCAL 2.23

Portable Scaler Calibrations

HPIP 2.1.1

Functional Checks of Portable Survey Instruments

HPIP 2.41

Operation of MGP AMP Area Monitor

HPIP 5.69

Daily Operational Checks of the SAM-9/11

HPIP 7.53

Personnel Contamination Monitor (ARGOS 5 WBAB)

Source Response

Procedures

HPIP 7.54

Source Check of the GEM-5 Whole Body Contamination

Monitor

40746301 01

SPING-23 Calibration

08/11/2021

Work Orders

40760481 01

RE-218/RE-218B Waste Disposal System Liquid Monitor

Calibration

09/06/2022

NRC Performance Indicator Data; Emergency

Preparedness - Drill and Exercise Performance

07/01/2021 -

06/30/2022

Miscellaneous

NRC Performance Indicator Data; Emergency

Preparedness - ERO Drill Participation

07/01/2021 -

06/30/2022

71151

Procedures

PBN-BFJR-18-054

MSPI Basis Document for PBNP

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PBN-BFJR-18-054

MSPI Basis Document for PBNP

Corrective Action

Documents

AR 02429535

2SC-955 Boric Acid Identified During Containment

Walkdown

06/09/2022

Boric Acid Leak Screening for Unit 2 RCS Valve 2SC-955

for AR 2429535

71152A

Miscellaneous

Boric Acid Leak Screening for 2SC-955 for AR 2351202

04/03/2020