Category:Letter
MONTHYEARIR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23352A2752024-01-23023 January 2024 Issuance of Amendment Nos. 274 and 276 Regarding Revision to Technical Specification 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-174, Subsequent License Renewal Application - Third Annual Update2023-12-13013 December 2023 Subsequent License Renewal Application - Third Annual Update L-2023-176, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-159, Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 ML23279A0672023-11-0909 November 2023 Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 ML24120A1582023-10-0606 October 2023 Ile Proposed Outline Submittal Letter ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 ML23208A2262023-08-28028 August 2023 Exemption from the Requirements of 10 CFR 50,46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors (EPID L-2022-LLE-0026) - Letter ML23208A0952023-08-28028 August 2023 Issuance of Amendment Nos. 273 and 275 Regarding Revising Licensing Basis to Address Generic Safety Issue-191 and Respond to Generic Letter 2004-02 Using a Risk Informed Approach IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) 2024-08-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24215A2092024-08-0101 August 2024 NRR E-mail Capture - Final RAI - Point Beach 1 & 2 - License Amendment Request to Modify Containment Average Air Temperature Requirements ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 ML23136A2802023-05-0505 May 2023 SLRA Second Annual Update RAI Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22266A0872022-09-23023 September 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22172A1192022-06-27027 June 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-505 Provide Risk Informed Extended Complete Times - RITSTF Initiative 4B ML22130A5712022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6812021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML21362A6702021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21286A6042021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21273A0222021-09-29029 September 2021 SLRA Safety RAI Set 9 Final ML21287A0862021-09-29029 September 2021 SLRA Safety RAI Set 11 Final ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2472021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2202021-08-20020 August 2021 SLRA Safety RAI Set 7 Final ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A2392021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A0152021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2032021-08-12012 August 2021 Srla Safety RAIs Set 5 Final ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21242A0122021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 ML21285A1212021-08-0505 August 2021 SLRA Public Meeting Discussion Questions August 5 2021 ML21242A2002021-08-0505 August 2021 SLRA Draft Safety RAIs Set 5 Email ML21242A1992021-08-0505 August 2021 Srla Draft Safety RAIs Set 5 ML21238A2332021-08-0404 August 2021 SLRA Safety RAI Set 4 Final ML21238A2322021-08-0404 August 2021 SLRA Safety RAI Set 4 Final Email ML21237A0062021-08-0202 August 2021 SLRA Draft Safety RAIs Set 4 ML21208A1892021-07-27027 July 2021 SLRA Safety RAIs Set 2 Final 2024-08-01
[Table view] |
Text
Michael Durbin Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION
Dear Michael Durbin:
In a telephone conversation on June 18, 2024, between Troy Henning, Senior Operations Engineer, the NRC lead inspector for this inspection, and Arne Gustafson, LOR Supervisor, final arrangements were made for the U. S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Point Beach Nuclear Power Plant. The inspection is planned for the week of September 9, 2024, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations and annual operating tests as necessary to support the NRC's inspection program needs. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection.
Please furnish the items listed in the first group of the attached enclosure, needed to support our in-office inspection activities, to the NRC by August 30, 2024. Please have the items listed in the second group of the attached enclosure available for the inspectors during the onsite portion of the inspection activities. Arne Gustafson has been advised of this request.
Thank you for your cooperation in this matter. If there are any questions regarding either the inspection, or the material requested in the enclosure, please contact me at 630-829-9822 or via email at troy.henning@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.June 24, 2024 M. Durbin 2 This letter and its enclosure will be available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Troy J. Henning, Senior Operations Engineer Operations Branch Division of Operating Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24, DPR-27
Enclosure:
REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11) cc: Distribution via LISTSERV M. Hastings, Training Manager Signed by Henning, Troy on 06/24/24
M. Durbin 3
Letter to Michael Durbin from Troy J. Henning dated June 24, 2024.
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION
DISTRIBUTION:
Michelle Simmons RidsNrrDorlLpl3 RidsNrrPMPointBeach RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker David Curtis Karla Stoedter R3-DORS Ikeda Betts Maryia Bahdanovich-Kniazkova
ADAMS Accession Number: ML24176A224 OFFICE RIII/DORS/OB/CE NAME THenning:gmp DATE 06/24/24 OFFICIAL RECORD COPY REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11)
Please provide the following information on a CD/DVD, or document upload to the BOX if possible, by August 30, 2024
- 1. One complete version of a biennial requalification written examination administered during the training cycle.
- 2. Ten (10) job performance measures (JPMs) and four (4) simulator scenarios associated with an annual requalification operating test required by 10 CFR 55.59(a)(2). The JPMs and scenarios to be reviewed should include those that will be observed during the onsite portion of this inspection, with any remaining JPMs and scenarios selected from other weeks within the same training cycle.
- 3. Complete versions of the reference materials used to develop the administered written examinations and operating tests. (Refer to NUREG-1021, Rev. 12, ES-2.1 Section F.4.,
Specific Reference Material to Provide, for relevant materials and clarification.)
- 4. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios.
- 5. A list of licensee-identified issues associated with licensed operator performance problems which have occurred in the actual plant/main control room since the last biennial requalification program, their associated corrective actions, and if these issues were incorporated into requalification training. (These issues are likely documented in condition/problem identification reports, licensee-conducted audits, and assessments, and in industry operating experience reports, etc.)
- 6. Facility licensee procedures for licensed operator requalification training and examination, including examination security procedures.
- 7. A schedule of the licensees examination activities during the on-site inspection week.
Please have the following information available for NRC review on September 9, 2024
- 1. Licensed operator pass/fail statistics for any NRC-required requalification examinations that have been completed.
- 2. An overall schedule of the facility licensees requalification program since the last biennial inspection (cycle weeks, training topics, etc.).
- 3. A list and descriptions of any examination security problems since the last biennial inspection (likely documented in training department condition/problem identification reports).
- 4. Records for licensed operator requalification training attendance, licensed operator performance in requalification, licensed operator remedial training, individual licensed operator medical records, records for maintaining an active license, and any license reactivations for watch standing proficiency.
- 5. Simulator testing, maintenance, modification, and performance records. Simulator corrective action records, including lists of open/closed simulator deficiencies, and corrective actions taken.
- 6. A current list of all the licensed operators at the site, by license level, a current list of all licensed operator medical restrictions, and selected individual licensed operator medical files in support of the current license.
Enclosure