IR 05000266/2024402
| ML24312A197 | |
| Person / Time | |
|---|---|
| Site: | Point Beach (DPR-024, DPR-027) |
| Issue date: | 11/14/2024 |
| From: | Michael Ziolkowski NRC/RGN-III/DRSS/SEPIR |
| To: | Durbin M Point Beach |
| References | |
| EPID I-2024-402-0046 IR 2024402 | |
| Download: ML24312A197 (1) | |
Text
SUBJECT:
POINT BEACH NUCLEAR PLANT - SECURITY BASELINE INSPECTION REPORT 05000266/2024402 AND 05000301/2024402
Dear Michael Durbin:
On October 1, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant and discussed the results of this inspection with Eric Schultz and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000266 and 05000301
License Numbers:
Report Numbers:
05000266/2024402 and 05000301/2024402
Enterprise Identifier:
I-2024-402-0046
Licensee:
NextEra Energy Point Beach, LLC
Facility:
Point Beach Nuclear Plant
Location:
Two Rivers, WI
Inspection Dates:
August 26, 2024, to October 01, 2024
Inspectors:
G. Bonano, Physical Security Inspector
N. Egan, Sr Physical Security Inspector
Approved By:
Michael E. Ziolkowski, Chief
Security, Emergency Preparedness, and Incident Response Branch
Division of Radiological Safety and Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Point Beach Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program. The following elements were evaluated:
Access Authorization
(1)
- Tier I: All Requirements
- Tier II: 02.05 a-b; 02.06 a-b; 02.08 a-b
- Tier III: 02.10 a-c; 02.11 a
71130.04 - Equipment Performance, Testing, and Maintenance
The inspectors evaluated the security equipment testing and maintenance program. The following elements were evaluated:
Equipment Performance, Testing, and Maintenance (1 Sample)
(1)
- Tier I: All requirements
- Tier II: 02.09 a; 02.11 a, d; 02.12 a
- Tier III: 02.15 b, c
71130.08 - Fitness-For-Duty Program
The inspectors evaluated the fitness for duty program. The following elements were evaluated:
Fitness-For-Duty Program
(1)
- Tier I: All Requirements
- Tier II: 02.05 a-l, 02.06 a-g, 02.07, 02.08, 02.09 a-e
- Tier III: 02.11 a, 02.12 a, 02.13 a, 02.14 a-c
71130.09 - Security Plan Changes
Security Plan Changes (1 Sample)
- (1) Since the last NRC baseline inspection of this program area, Security Plan Revision 18 to 19 was implemented. Based on the licensee's evaluation, and in accordance with 10 CFR 50.54(p)(2), the change(s) resulted in no decrease in safeguards effectiveness of the security plan and the revised security plan change(s) continues to meet the requirements of 10 CFR 73.55(b). The inspector(s) conducted a review of the security plan change(s) to evaluate for a potential decrease in safeguards effectiveness of the security plan; however, this review does not constitute formal NRC approval of those change(s). Therefore, the change(s) remain subject to future NRC inspection in their entirety.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)
- (1) June 30, 2023, through June 30,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 1, 2024, the inspectors presented the security baseline inspection results to Eric Schultz and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
Nuclear Fleet Security Baseline Inspection Matrix
01/01/2024
Record Retention and Protection of Confidential Information
FFD and Access Program Personnel Training Requirements
Behavior Observation
Access Authorization Program
Procedures
Guidelines for Determining Suitability for Unescorted Access
JNA 23-003
Fleet Nuclear Assurance Report - Fitness-for-Duty and
Access Authorization
04/28/2023
JQA-23-013
NextEra Energy Audit Report PQA 23-073 of Private
Professional Services, Inc.'s (PPS) Background Investigation
Screening Program
05/24/2023
JQA-23-0303
NextEra Energy Audit Report PQA 23-077 of Information
Reporting Services Inc.'s (IRSI) Background Investigation
Program
09/26/2023
Self-Assessments
JQA-23-40
NextEra Energy Audit Report of Brownstone Psychological
Associates' Psychological Services Program -- NextEra
Energy Audit # PQA 23-006
10/27/2023
Corrective Action
Documents
Resulting from
Inspection
2495703
09/18/2024
Miscellaneous
Nuclear Fleet Security Baseline Inspection Matrix: 71130.04,
Equipment Performance, Testing, and Maintenance
09/01/2024
ICP 03.002
Security System Hardware Functional Test
PBSAP 1.24
Security Equipment Maintenance Program (SEMP)
PBSAP 2.1
Walk-Through Metal Detector Testing
PBSAP 2.12
Entry Scan Testing
PBSAP 2.13
Body Scanner
PBSAP 2.2
Hand-Held Metal Detector Testing
PBSAP 2.4
X-Ray Device Testing
PBSAP 2.7
Weapons and Ammunition
PBSAP 2.8
Itemizer 3
PBSAP 3.10
Owner Controlled Area Vehicle Barrier System (VBS)
Inspection
PBSAP 3.11
Active Pop-Up Vehicle Barrier Testing
PBSAP 3.2
Perimeter Testing
PBSAP 3.3
Security System Door Testing
PBSAP 3.5
Security System Card Reader and HGU Testing
PBSAP 3.6
Communications Testing
PBSAP 3.9
Vehicle Barrier System Patrol
Weapons Maintenance
Operation of Security Alarm Stations
Procedures
Security Equipment Testing
Work Hour Controls
NP-400
Nuclear Policy Fitness for Duty
Fitness for Duty Program
Selection and Notification for Drug/Alcohol Testing
Urinalysis Collection
Alcohol Testing
Blind Specimens
Processing and Reporting Test Results
NRC Event Reporting for the Fitness for Duty Program
For Cause Drug and Alcohol Testing Post Accident/Event or
Observed Behavior
Fatigue Management
Behavior Observation
Procedures
Determination of Fitness
Miscellaneous
NextEra Energy Point Beach, LLC.
Point Beach Nuclear Power Station
PSP, T&QP, SCP and ISFSI Security Program
71151
Procedures
Security Performance Assessment Program
13