|
---|
Category:Inspection Report
MONTHYEARIR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 IR 05000266/20233012023-03-28028 March 2023 NRC Initial Examination Report 05000266/2023301 and 05000301/2023301 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) IR 05000266/20230102023-02-23023 February 2023 Comprehensive Engineering Team Inspection Report 05000266/2023010 and 05000301/2023010 IR 05000266/20220042023-01-24024 January 2023 Integrated Inspection Report 05000266/2022004 and 05000301/2022004 ML23009B7002023-01-24024 January 2023 Review of the Spring 2022 Steam Generator Tub Inspections Report IR 05000266/20224012022-12-0808 December 2022 Security Baseline Inspection Report 05000266/2022401 and 05000301/2022401 IR 05000266/20224042022-12-0202 December 2022 Cyber Security Inspection Report 05000266/2022404 and 05000301/2022404 IR 05000266/20220032022-11-0707 November 2022 Integrated Inspection Report 05000266/2022003 and 05000301/2022003 ML22298A2972022-10-27027 October 2022 Review of the Fall 2021 Steam Generator Tube Inspections Report IR 05000266/20220122022-09-29029 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000266/2022012 and 05000301/2022012 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) IR 05000266/20220112022-08-0303 August 2022 Triennial Fire Protection Inspection Report 05000266/2022011 and 05000301/2022011 IR 05000266/20220022022-07-27027 July 2022 Integrated Inspection Report 05000266/2022002 and 05000301/2022002 IR 05000266/20220012022-05-0404 May 2022 Integrated Inspection Report 05000266/2022001 and 05000301/2022001 IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) IR 05000266/20220102022-02-0909 February 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000266/2022010 and 05000301/2022010 IR 05000266/20210042022-01-28028 January 2022 Integrated Inspection Report 05000266/2021004 and 05000301/2021004 and Exercise of Enforcement Discretion IR 05000266/20214022021-11-10010 November 2021 Security Baseline Inspection Report 05000266/2021402 and 05000301/2021402 IR 05000266/20210032021-10-20020 October 2021 Integrated Inspection Report 05000266/2021003 and 05000301/2021003 IR 05000266/20215012021-10-0505 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2021501 and 05000301/2021501 IR 05000266/20213012021-09-14014 September 2021 NRC Initial License Examination Report 05000266/2021301; 05000301/2021301, and 07200005/2021301 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) IR 05000266/20214032021-08-0404 August 2021 Security Baseline Inspection Report 05000266/2021403 and 05000301/2021403 IR 05000266/20210022021-07-29029 July 2021 Integrated Inspection Report 05000266/2021002, 05000301/2021002, and 07200005/2021001 IR 05000266/20210102021-07-0101 July 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000266/2021010 and 05000301/2021010 IR 05000266/20210012021-04-21021 April 2021 Integrated Inspection Report 05000266/2021001 and 05000301/2021001 IR 05000266/20214012021-03-16016 March 2021 Security Baseline Inspection Report 05000266/2021401; 05000301/2021401; Independent Spent Fuel Storage Security Inspection Report 07200005/2021401 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200902021-02-0909 February 2021 Final Significance Determination of a Green Finding; NRC Inspection Report 05000266/2020090 and 05000301/2020090 IR 05000266/20200042021-02-0808 February 2021 Integrated Inspection Report 05000266/2020004 and 05000301/2020004 IR 05000266/20204022020-12-14014 December 2020 Security Baseline Inspection Report 05000266/2020402 and 05000301/2020402 IR 05000266/20200032020-11-0404 November 2020 Integrated Inspection Report 05000266/2020003 and 05000301/2020003 2024-09-18
[Table view] Category:Letter
MONTHYEARIR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 ML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-043, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-03-25025 March 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) L-2024-020, Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections2024-02-22022 February 2024 Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 2024-09-09
[Table view] |
Text
Michael Strope Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516 SUBJECT:POINT BEACH NUCLEAR PLANT-SECURITY BASELINE INSPECTION REPORT 05000266/2023401; 05000301/2023401; INDEPENDENT SPENT FUEL STORAGE SECURITY INSPECTION REPORT 07200005/2023401
Dear Michael Strope:
On May 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant and discussed the results of this inspection with Mark Fencl, Security Director, and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low security significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Point Beach Nuclear Plant.
The following cross cutting aspect was assigned to a finding using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: [P.2] - Evaluation.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Point Beach Nuclear Plant.July 13, 2023 This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely, Steven K. Orth, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket Nos. 05000266; 05000301; 07200005 License Nos. DPR-24; DPR-27 General License (ISFSI)
Enclosure:
As stated cc: M. Fencl, Security Manager M. Paulson, State Liaison Officer, Radiation Section Manager, Wisconsin Department of Health Services cc w/o encl: Distribution via LISTSERV Signed by Orth, Steven on 07/13/23
ML23192A452 (Cover letter w/ enclosure(s))
ADAMS ACCESSION NUMBER: ML23192A453 (Cover letter)
Entire Report: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available Cover Letter Only: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RIII/DRSS RIII/DRSS RIII/DRSS NAME MZiolkowski:mcKMaloney SOrth DATE 7/12/2023 7/12/2023 7/13/2023