|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
Text
-- - - . . . . .. .
.
,
'
-
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
50-245/87-32 50-336/87-27 Report No /87-31 l 50-245 50-336 Docket No DPR-21 DPR-65 License No NPF-49 Licensee: Northeast Nuclear Energy Company ,
P. O. Box 270 Hartford, Connecticut 06141-0270
, Facility Name: Millstone Nuclear Power Station Units 1, 2 and 3 ;
'
' !
Inspection At: Waterford, Connecticut !
Inspection Cond ed: Novert9r 30 - December 4,1987 Inspectors:
'
/h8 ' # hY M, Dev, PE Reac or(Engineer n i 2f B6 d' ate r
L / {
w)w ' '7 i
~p"A.F Kel,SeniorReaEterEngineer ca/se date l
t
, p A lf/"'r D ' 27 38 l G. Napuda, Senior Reactor Engineer d&te
.
Approved b 2 ) 1h'S N. Blumberg, CVief, Operational d rograms date i Section, DRS !
,
Inspection Summary: Inspection on November 30 - December 4, 1987 (Combined Inspection Report Nos. 50-245/87-32, 50-336/87-27 and 50-423/87-31 Areas Inspected: Routine unannounced inspection of licensee's Surveillance *
! Test program - Complex Safety-related System, inplant instrument calibration,
measuring and test equipment, cold weather preparation, and QA/QC interfaces for Millstone Nuclear Power Station Units 1 and 2. The Testing of Containment Penetration Conductor Overcurrent Protection devices was also reviewed at Unit Results: No violations or deviations were identifie i 8802190003 000203
'
DR ADOCK0500g5
_- _ _ _ . . _ . . _ _ _ _ - - . _ _ __ _.. , _ _ . - . _ _ _ , . _ _ _ . . , _ . _ _ _ _ , . _ . . , _ . - .
. - -- . -
.
i
'
DETAILS 1.0 Persons Contacted Northeast Utility Service Company (NUSCO)
Northeast Nuclear Energy Company (NNECO)
R. Bates, Assistant Supervisor, Electrical Engineering, MP-2
- T. Brown, Assistant Supervisor, I&C, MP-1
- C. Clement, Unit Superintendent, MP-3
- Closius, Plant Quality Services Supervisor (NUSCO)
J. Criscione, Staff Engineer, MP-2
- F. DiCarlo, Assessment Services Specialist (NUSCO)
R. Enoch, I&C Supervisor, MP-3
- Gentry, Engineering Supervisor, MP-3 J. Harris, Operations Supervisor, MP-3
- H. Haynes, Millstone Station Service Superintendent (NUSCO)
J. Kennedy, Production Test Engineer, MP-2
' R. King, Assistant Supervisor, I&C, MP-1
'
- J. Leason, ISI Coordinator, HP-1
- C. Libby, Assessment Service Supervisor (NUSCO)
C. Monk, Control Operator, MP-1 G. Olson, Operations Engineer, MP-3
, P. Privizzone, Maintenance Engineer, MP-3 l
P. Przekop, I&C Supervisor, MP-1 R. Rathgeb, Maintenance Supervisor, MP-3 '
"S. Scace, Millstone Station Superintendent
- J. Stetz, Unit Superintendent, MP-1 l
"
United States Nuclear Regulatory Commission (USNRC)
- S. Barber, Resident Inspector, MP-1
- Raymond, Senior Resident Inspector
.
The inspectors also contacted licensee's other technical and adminis- L trative personnel during the course of this inspectio * Denotes those individuals who were present at the exit meeting on i 2.0 General The various documents / records such as procedures, data sheets, work )
orders, modification packages and Quality Assurance (QA) reports that '
were reviewed and used as reference requirements during the course of ;
this inspection are listed in Attachment 1. Also, implementing proce-dures were reviewed for technical adequacy and calibration / test results ,
were verified to meet acceptance criteri !
,
=
,
'
_ _ _ _ _ . _ _ _ _ _ _ . . __ _ . - . _ . _ ___,_ _-
.- - . . . - .
.
- 3
'
'
Paragraph 3.0 discusses the inspection of Units 1 and 2; paragraph applies to Unit 1; paragraph 5.0 applies to Unit 2; and, paragraph applies to Unit Observations of ongoing activities and independent examination of in plant conditions are identified within the appropriate paragrap ,
,
3.0 Surveillance and Calibration Program for Inplant Instrumentation (Units 1 and 2)
3.1 Program Review A review of administrative and calibration procedures and the master inplant calibration instrumentation schedules were made to verify tha .
f
- Requirements and commitments listed in Attachment 1 were met;
.
- Master inplant calibration schedules-and administrative control-systems had been established which identified the frequency of each calibration, the responsible group for performing each calibration and the status of each calibration of inplant
"
instrumentation;
- Responsibilities had been assigned for maintaining the master i calibration schedules up to date; '
Procedures, written to an approved format and technical specification requirements, existed for conducting each calibration;
Responsibilities had been assigned for reviewing and evaluating
,
,
the results of calibration data;
- Calibration requirements had been established and mainte.ined for equipment associated with safety related systems but which are
'
not specified in Technical Specifications as requiring calibration; i
Responsibility had been assigned for ensuring that required schedules for all calibrations were satisfied;
Technical content of calibration procedures complied with technical specifications requirements;
Procedures contained controls to insure limiting conditions for operation had been met during the calibration; i
!
i
, , . , . - . _ ._
, , , _ - . , _ _ - _ - - - , , - . - ,,.._._.m..- ....- ....- - - . .._. - _
>w ,-
.
. 4
+
Calibrations were performed to the required accuracy; and,
Measuring and test equipment used in the calibration was traceable to the work for which it was use .2 Implementation The master scheduling for Unit I has been incorporated inte the computerized Plant Maintenance Management System (PMMS) and the weekly published schedule lists those calibrations that must be done within the forthcoming four weeks. This printout provides the Work Order (WO) number, task, applicable procedure (s), system identifi-cation, instruments involved, QA/QC involvement and other pertinent i information. Discussions with the I&C Supervisor and planning staff indicated that refinement of the data base with respect to QA/QC designation and involvement is ongoing. The data base and existing calibration procedures have been crosschecked a number of time Several Technical Specificaticn (TS) Table 4.1.2 calibration require-ments were sampled to verify that a corresponding procedure existed; that the task was contaired in the data base including the correct calibration frequency; and completed calibrations met established i acceptance criteri The master scheduling for Unit 2 has been incorporated onto '
printed schedule sheets. These schedules have been formatted in ,
such a fashion that the issued monthly multisheet schedule lists all calibrations due the upcoming month (e.g., weekly, monthly,
" quarterly, semiannual, annual, refueling). Applicable procedures, ;
the dates within which the calibration must be done and other appro-priate information is provided on these sheets. Also, space is provided for technician comments and the date the task is complete ,
Several TS Table 4.3-1 calibration requirements were sampled to verify that a corresponding procedure existed; that the calibration and its frequency was reflected in the master schedules; and com-
.
pleted calibrations met established acceptance criteri The onsite I&C Metrology Lab calibrates most of the portable
,
~
measuring and test equipment (M&TE) that is used by each of the three units I&C Shops, Training Center and the Production Test
, group. Laboratories / Vendors approved by the QA organization must be used for M&TE that is sent offsite for calibration. Each of the groups is responsible for the M&TE it uses. The I&C Metrology Lab was toured and it was noted that some work on the physical facility and "equipment setup" remain to be completed because of a recent relocation of the laboratory.
'
__ _ _ _ _ _ _ _ _ _ _ _ _ - - - - _ _ _
.
.
. 5 The calibration of Unit 2 Excore/Incore Nuclear Instrument Channels C and D was observe The task steps have been programmed for the Personal Computer (PC) that the two I&C technicians were using. A few noteworthy aspects of using a computerized calibration procedure were the display of only one step at a time in chronological order as the previous step was completed and an entry made into the computer; automatic alert of the technicians when unacceptable results were recorded and the printout of a corrective action form; and, the necessity of correctly completing each step before the program allows advancement through the procedure. The technicians had a current printed procedure in their possession and demonstrated agreement between it and the computer program. Currently, calibration results are recorded manually on data sheets. Discussions with the Unit 2 I&C Supervisor indicated that this practice will be discontinued when full confidence in the computerized program is attained. The develop-ment of other such computer programs and the program validation (e.g., line by line verification, benchmark tests) were also
' discusse .3 Quality Assurance Interfaces and Overview Discussions were held with the onsite QA/QC management with respect to the auditing and surveillance of calibration activities associ-ated with installed in plant instrumentation. A major change in QC overview technique is currently being planned and this is basically expanding the unannounced observation of ongoing activities and reducing the number of hold / witness points previously inserted into implementing work procedures. Extensive research and analysis of past inspection results revealed the followin A review of Work Orders determined that 60-80% of established hold / witness points were within the skills of the worker to determine acceptabilit There was a very low incidence of unacceptable work associated -
with hold / witness point Other work steps were identified where independent inspection had never been performe An intense analysis of this information led to the conclusion of i licensee management that a more effective and efficient use of ;
resources could be realized by a restructuring of the QC overview
'
, approach. The change to place more emphasis on surveillance type of overview has begun and is to be implemented at a slow pace. It was noted that thirteen QC Quality Activity Observations (i.e.,
surveillances) have been conducted on in plant calibration and ten i QC observations had been conducted on plant TS surveillance testing I during the past yea j
l l
--- -- , _ . - , _
. _ _ , . _ -. ._ - - . , - - - _ - - . -
_ _ _ . - . _ __ . ..
.
. .6 A QA audit of plant ceiibration/ testing was ongoing ~during this inspection. The checklists were reviewed and the conduct and
,
planning ofLthe audit was discussedLand observed with QA auditors
~
and management. It was noted that an audit' attribute was the verification that sampled TS. requirements were indeed included in
'
existing procedures. This technique and other observation type attributes were determined to have been increased from the numbe previous in the checklists for this' functional are .4 Conclusions and Findings The program for calibration of in plant installed instrumentation asi ',
established is accurate, clearly described and well mana.ged. Both the computerized scheduling at Unit 1 and the schedule sheets used at Unit 2 control the assignment and completion of tasks. The I&C staff and supervision have a clear understanding of the administra-tive control system.
,
Technicians performing the calibrations are knowledgeable with
'
respect to their duties and procedures being used. Execution-of work steps were done conscientiously and in a confident manne The most notable human factors improvement in the conduct of in plant calibration of instrumentation is the use of a Personal Computer at Unit 2 to display work steps; guide the technician; ;
determine acceptability of results and automatically initiate a corrective action document when appropriate; prompt and require the worker to follow procedural steps; and, retain results for record purpose The research and analyses of inspection results history by the ,
Quality Assurance group in an effort to identify.a more effective and efficient use of their resources is commendable. An improvement was also noted in the auditing techniqu Management involvement and support is evident and reflected in the quality of the established program, the manner in which it is implemented and being improved, and the effort to enhance the QA overview effect;venes ! No violations oc deviations were identifie .0 Mp-1 Surveillance Test program and Cold Weather Preparation 4.1 MP-1 Surveillance Test Program 4. Scope and Criteria Emphasis in this inspection was placed on the review of the adequacy and effectiveness of the implementation of the licensee's TS related surveillances and inservice
.
- . - _ , . . . . - - . . .
.
. 7
.
inspection (ISI) program Calibration and. control of installed equipment and measuring and. test equipment was '
discussed.in paragraph 3. The program was reviewed to the_
following requirements:
--
10 CFR 50, Appendix B
--
MP-1 Technical Specifications (TS), Section 4, Surveillance Tests
--
MP-1 Final Safety Analysis Report (FSAR), Sections 6.3, Emergency Core Cooling System (ECCS), and 7.3- c Engineered Safety Feature Systems
--
Regulatory Guide 1.33, Quality Assurance Program (Operation)
'
--
ANSI N18.7-1976,- Administrative Controls and Quality Assurance for'the Operational Phase of Nuclear. Power Plants
--
ANSI N45.2.6-1978, Qualification of Nuclear Power Plant Inspection, Examination and Testing Personnel i
--
Appropriate MP-1 Administrative Control Procedures and Operations and I&C Surveillance Procedures as '
listed in Attachment 1- ,
'
4. Program Review f
The licensee's surveillance test-program, and inservice inspection and testing of pumps and valves were reviewed
to ensure that the licensee has established:
--
Overall control for surveillances, inservice inspec-tion, post-maintenance testing and post-modification
,
testing
'
--
Test procedures to meet the Technical Specifications requirements and objectives including test schedule and frequencies
--
Master test schedules for surveillances and ISIS
--
Mechanism for tracking of the completed tests
--
Responsibility and authority for review of the completed tests
,
, m-.. ,-_ .._, , _.,_ ,.,_e , _ . . ,, ._.y, , , , , . . , __,,_.,...,,.c_,,, ,._.._,. . , - -,. _.y-e. _ , . _ ,- , , , ..m,
. - -
.
< 8 4. Implementation Review and Findings 4.1.3.1- The inspector reviewed selected functional test-ing of the safety-related core spray (CS) and low pressure coolant injection (LPCI) (sub) systems of the emergency core cooling system (ECCS). Sec-tion 7.3 of the FSAR describes and analyzes the instrumentation and controls used to initiate and '
control the operation of the engineered safety feature (ESF) system which-includes ECC .1. The MP-1 I&C group conducts TS related surveil-lances, and the MP-1 engineering staff coordinates inservice inspections and testing of functional attributes of pumps and valves. These activities are accomplished through approved surveillance ;
procedures in accordance with the licensee's administrative procedures to meet the require-ments set forth in the facility's Technical Specification These procedures have estab-lished test objectives, acceptance criteria, i applicable references, prerequisites, initial conditions, test precaution, and delineated ,
steps to accomplish test activitie The pro-cedures are reviewed biennially by cognizant plant staffs and approved by the PORC and plant management prior to us Some of the I&C surveillance procedures reviewed were found to have referenced obsolete FSAR sec-tions and the licensee's department instruction The licensee representative acknowledged that the FSAR was recently updated, and currently the I&C
!
staff is reviewing the I&C procedures to verify the impact of the FSAR update, and incorporate any changes as require .1. The I&C and Inservice Inspection (ISI) engineer-ing coordination staff have established master surveillance schedules for TS related surveil-
lances and inservice inspections. The schedules are reviewed and the surveillance tests status updated periodically. The I&C surveillance test schedules are published weekly and a work order is initiated through the plant maintenance manage-ment system (PMMS). The I&C supervisory staff reviews the work order for its adequacy prior to the job assignment. The ISI staff follows similar controls in establishing inservice inspection requirements and performing the tests.
-. - _ - - - . --
, . , - - . __ .- - , , - - -
. . -. - .. .
. 9 4.1. The I&C staff performing the TS related surveil-lance tests reviews the associated procedures including the test data forms (I&C Form 400 series) before commencing the tests. Accordingly, minimum crew requirement, availability of cali-brated test equipment, operations approval and ,
coordination, and QA/QC. hold and witness points are established. The ISI activities'are limited in nature, and as such the ISI coordinating staff establishes coordination with I&C and operations staff to accomplish inservice inspections and testin ,
The inspector witnessed the TS related Reactor Low-Low Water Level Functional and Calibration ,
Test performed by the I&C staff. The low-low water level is detected by four independent level switches connected in a one-out-of-two taken twice logic array. These same devices also initiate starting of the diesel generator and the gas turbine on receipt of a low-low water level signal. The I&C surveillance procedure SP 412C provided for-the testing and calibration i of the reactor low-low water level instruments
'
LIS-263-72A, B, C, 0 and LITS-263-73A, i The inspector also witnessed the MP-1 engineering staff coordinate certain inservice inspections and testing in accordance with approved opera-tions surveillance procedures. The surveillance '
verification of the core spray system pumps and
,
valves was conducted in accordance with Procedure l
. SP 621.10, and the accuracy of the remote indi- !
cation of valve operation was checked in ac- !
cordance with Procedure SP 621.11. Similarly, the LPCI system pumps, motor operated valves and l check valves operational readiness verification l was conducted in accordance with Procedure SP l 622.7, and the accuracy of the remote indication I of valve operation was checked in accordance with Procedure SP 62 .
These tests were conducted in adherence with the I associated procedures, and were well coordinated among participating organizations, such as I&C, operations and engineering. Test data were ,
legibly recorded and independently verifie Post-testing system restoration was carefully completed and independently verified prior to returning the system to operatio j
.
4.1. The inspector also reviewed selected I&C surveil-lance tests, and inservice inspections conducted by the MP-1 engineering staff. In each instance, procedural steps, data recording, independent verification, test acceptance and test approval were properly documente The completed test reports were easily retrievable through the licensee's nuclear records management syste .1. The licensee's Quality Service Division (QSD)
is currently conducting an audit to verify the licensee's compliance of the Technical Specifi-cations related surveillances to the station Administrative Control Procedures (Attachment 1).
The audit covered the general overview of all three units, including MP-1, with respect to the licensee's surveillance testing progra The individuals performing these tests were found to have adequate training and experience, and were conversant with the tests' procedural and functional requirements. The inspector reviewed the training records and certifica-tions of selected individuals who were assigned to the surveillance test activities discussed in paragraph 4.1.3.4. They met the requirements delineated in ANSI N45.2.6-1978. The inspector i also verified that the I&C and inservice inspec- l tion coordinating groups were adequately staffe . Conclusion Based on the review of the licensee's surveillance test procedures, inservice inspection procedures, discussion with the licensee's cognizant individuals, and witness of the test programs, the inspector concluded that the licensee's surveillance program implementation is effectiv .2 MP-1 Cold Weather Preparation This inspection verified the effectiveness of the licensee's cold weather preparation program implementatio The licensee has established an off-normal operations procedure ONP-514 This incorporates a checklist based on the licensee's past cold weather experience and the plant specific requirement The procedure provides an outline of steps undertaken to maintain the plant in a safe condition in the event of sustained subfreezing
.
. 11 temperature In addition, the operations staff periodically makes rounds and verifies that equipment, system and process lines im-portant-to-safety are adequately protected against extreme cold weather conditions. This activity is accomplished in accordance with the Plant Equipment Check Log Form 1-0PS-10-0 The MP-1 I&C maintenance staffs also periodically make rounds and verify the operability of instrumentation and control circuitries, sensors, thermostats and other devices used for monitoring, heat tracing, protection and control of equipment, system and process lines. Any deficiencies identified are corrected and dispositioned through the maintenance work order ,
The inspector discu.; sed the MP-1 winterization program with the cognizant operations and I&C staffs and reviewed related activities and documentation. The inspector concluded that the licensee's action to implement MP-1 winterization program is adequat .0 Loss of Offsite Power / Black Out (LOP /BO) MP-2 :
~
The inspector performed an examination of selected portions of the Loss of Offsite Power / Black Out system components and the cold weather protection !
associated with this system. To enhance their system design, the licensee has installed new and modified existing equipment for the MP 1/2 Appendix R Backfeed; modified their emergency diesel generator automatic start sequence system; issued a Connecticut Valley Electric Exchange (CONVEX)
procedure and program; and performed enhancement changes in their 345kV station insulator i 5.1 Appendix R Modification - Millstone Units No. 1 and 2
'
AC Power Crosstie Northeast Nuclear Energy Company (NNECO) proposed to modify Mill- !
stone Unit No. 1 to provide a capability to connect the Unit No. 1 ,
emergency AC power system to the Unit No. 2 emergency bu The modification supports the Unit No. 2 alternate shutdown capability required to meet the provisions of 10 CFR 50 Appendix R, Section l III.G. During this review of the Unit No. 2 LOP /B0 design, the '
inspector reviewed the breakers, surveillance testing and the status
4 of the design modifications that were completed during the last Unit ,
No. 2 outage. The inspector, using the design criteria of Plant l
Design Change Reowst (PDCR) No.1-98-86, reviewed the following ;
installations t assure that they complied with the as-built draw-i ings, the PDCR requirements and station operation procedures: l
,
--
Replacement of the existing 4kV bus 2F with a vacuum breaker switchgear
!
i l
._ _ . __ _ _ . _ .
.
. 12
Modification of th~e existing RSST bus duct tie to align the bus
'
-
--
!
to the new switchgear lineup ;
--
Complete Phase 1 and Phase 2 testin ,
'
The inspection of the selected design modifications above and a-review of the test data taken during the system testing verified that the extent of the design change was complied wit r
5.2 Diesel Generator Automatic Start Sequenc '
The licensee has issued Plant Design Change Request (PDCR) .
___ ,
No. 2-87-86 which removed the Safety Inspection System (SIS) auto-_ -
matic start signal from both emergency diesel generators (EDGs). The reason for the change was the possibility of an EDG failure which can !
be caused by running their diesel unloaded when an SIS signal is .!
received. The licensee's original design automatically started their !
EDGs when either a Loss of Offsite Power (LOP) or an SIS is receive .
The emergency system automatic start sequence (ESAS) receives the l
- signal, processes it, and initiates the EDG control circuitry to !
! start the EDG Their original Final Safety Analysis Report (FSAR) r
] stated that an SIS nortrally causes both diesels to start as a pre-cautionary measure only. A Westinghouse report stated that removal i
! of their SIS auto start does not impact the design basis accident ,
t analytical assumptions. With the SIS aute start removed, the EDGs will auto start on a LOP. The inspector reviewed the Engineered Safety Feature System (ESF) Integrated Test procedure to verify that !
the TS requirements of the diesel system have been complied with and }
j that the test data recorded complies with the requirements of their I
- procedures. A review of their 50.59 safety analysis report indicated i that there was not any unreviewed safety questions associated with ,
i this change. The inspector reviewed the EDGs procedure to verify that l the following parameters of the diesel system were tested:
l l
--
A LOP signal starts the EDG ,
i
--
The required listed breakers opene !
-
--
The diesel generators start from an ambient condition and are ready for loading, with their output breakers closed, within 30
,
- '
'
seconds of the undervoltage ir,itiation signa I
--
The sequence operated to energize appropriate equipment within the specified time intervals.
1 --
That all non-emergency diesel generator trips are bypassed by I
the LOP start signal except overspeed, generator differential current, voltage restrained overcurrent and low lube oil j pressure (2 of 3).
l
d
.
The EDGs test data reviewed by the inspector verified that the test performed complied with the procedure requirements.
!
5.3 Connecticut Valley Electric Exchange (CONVEX)
l The licensee has taken action to place the plant in a safe condition t
during a severe storm, high winds or high tides. Administrative Operating Procedure (AOP) 2560 has established the action the licensee plans to take in the event certain criteria is reached. In conjunction with AOP 2560, the licensee has prepared a CONVEX operat-ing instruction (COI) 8601, which provides a method of deenergizing the entire Millstone 345kV substation. The physical location of the l
Millstone 345kV substation makes this station prone to salt contami- . nation. Site history data indicated that salt contamination can happen as quickly as 30 minutes from an operating substation to one that could short out from the accumulated salt deposits. A0P 2560 and the COI 8601 allow the EDGs to be brought c- line while shutting down the site reactor .4 345kV Station Coating Program Flashovers and heavy electrical discharge activity have occurred on external insulation at the Millstone site in periods when winds have carried salt from Long Island Sound. The licensee has been upgrading various insulators over the past few years but during a recent storm in the spring of 1986, frequent discharge activity was observed at this site. A joint program between Northeast Utilities and the '
Electric Power Research Institute (EPRI) High Voltage Transmission Research Center (HVTRC) was carried out in 1986 to determine a recom-mendation for improving their dry salt insulator tracking proble EPRI research project report No. RP 2472-3, December 1986, I recommended the c7ating of the 345kV Station Insulators with an j
RTV coating (Sylgard) material manufactured by the Dow Corning Corporation. The test report in general states that the RTV coated i j
insulators showed a dramatic improvement in performance in tests when compared with uncoated insulators. The test report also stated that af ter many hours of exposure to the severe salt mist environment, the coated insulators withstood the maximum live to ground operating voltage. Also, switching impulse tests were made to determine whether the RTV coatings would degrade insulation strength. It was documented in the report that no such degradation occurred at overvoltage levels )
i of 2.8 per unit. Approximately 75% of the Millstone site has been coated with the RTV material on the 345kV yard insulators. During this inspection, the inspector witnessed the application of the RTV coating being applied to 345kV insulators. The results of the RTV coating material on the 345kV insulators is being monitored by the Millstone Unit No. 2 electrical maintenance organi:atio ._ . . . . ~.
d
.
'
. 14 r
In addition to the COI 8601, A0P 2560, and.the RTV coating of.the 345kV insulators, the licensee has installed yard hydrants and dedi-cated hoses,-nozz)es, and wshdown equipment to maintain the 345kV
'
'
yard equipment clear of salt to, minimize flashovers and electrical discharges.
- 5.5 ConclusionandFindins; The licensee has demonstrtted by testing and analysis that.they have '
met their TS requirement for' verification that their EDGs will carry !
<
I th & plant loads when a LOP signal is received. They have also ,
performed o'esign changes and prepared procedures to enhance the '1 operation of their 345kV lines to the site. These changes should !
have a direct effect on the licensee's ability to safely shut this site down and protect the safety and health of the publi No violations or deviations were identified.
- 6.0 Containment Peretration Conductor Overcurrent orotective Devices (Circuit .
Breakers) - MP-3 ;
6.1 Proposed TS Change for Overcurrent Circuit Breakers i'
Northeast Nuclear Energy Company (NNECO) has proposed to amend its .
Millstone Unit No. 3 Operating License by requesting a change to ;
i Technical Specification Section 4.8.4.1.a.2. Specifically, the pro- '
'
posed changes to Technical Specification Section 4.8.4.1.a.2 will (
require that surveillance testing requirements for molded case '
circuit breakers and unitized starters which are used at Millstone
'
-
Unit No. 3 for containment oleqtrical penetration secondary over-current protection, comply with the NEMA AB2-1980 criteri ,
!
i ~
{ The existing Technical Speciffeation requires that testirg of molded l l case circuit breakers and unitized starters follow the same proce- l 4 dures as the electrically operated power air circait breakers.
- Testing of the electrically operated power air' circuit breakers j f consist of applying a current with a value equal to 300% of the i
, pickup of the long delay trip element and 150% of the pickup of the '
3 short-time delay trip element. The present Technical Specification j section also requires that the instantaneous elsment be Lested by applying a current equal to 20% of;the pickup value of the elemen (
l These specific values are not applicable to molded case circuit '
- breakers or unitized starters as these devices have only one time '
delay element and one instantaneous elemen .i i
NEMA AB2-1980 recognizes that it is impractical to field test circuit breakers in accordance with UL 489, therefore, NEMA AB2-198 ,
.
!
!
!
4 i
,
- ;
.. .
.
. 15 provides the following recommendations for selecting test parameters for field testing of molded case circuit breakers (250 AMP frame and less):
a) Instantaneous Test -25% to + 40% of low and high setting-(respectively)
b) Long Time Test 300% of concinuous rating The additicnal 40% tolerance is requested for testing of molded case breakers to assure operability of the instantaneous trip elemen This element is tested by applying a seven cycle (0.12 sec.)_ current _ pulse and verifying the breaSer trip tim Accordingly, NNEC0 proposes to make the following changes to Tech-nical Specification Section 4.8.e.l.a.2 for selection test current values:
Present Test Current per Proposed Test Device Technical Specification Current Molded Case Circuit % of long time % of continuous Breaker delay pickup rating or % of short time none Unitized Starters deley pickup % of tra. tan- % to +40% of taneeus element instantaneous element trip values or range limit The inspettor witnessed the surveillance testing of six different containment penetration overcurrent devices performed in accordance with Station Procedure (SP) 3712T. This surveillance station pro-
- edure requires the present testing tolerance ac defined in Technical Specitiertion section 4.8.4.1.a.2, but where the test data exceeds the 29% value but less than the -25% to +40% value, the licensee is holding the test data approval pending NRC approval of the requested TS chai e. The test results, of the breaker test witnessed by the i inspecter were within the present TS tolerances and wert signed by licensee's surervisio I The celuulations and engineering analysis to justify that the pene- )
tration f ault current and the thermal rating of the penetration is j not degraded by the selected protective relaying is df: cussed in 4 Millstane 3 Electrical Penetration Protection report. A review of I tne above report and test witnessing by the inspector verified that the 15 change request to change the containment penetration over-l
1
!
_ _ ,
.,
.
current device surveillance testing for molded case breakers will not exceed the thermal limits of the penetration that the breakers protec The inspector'had no further questions in this are .2 Station Operating Procedures for Overcurrent Protective Devices Durin;; a review of the overcurrent protective system procedures, the inspector identified that procedures had over three changes attached to the procedures that were not incorporated into a pro-cedure revision. Quality Assurance procedure ACP-QA-3.02 requires that after three changes to a procedure, the procedure will have the changes incorporated into a new revision. During a review of the licensee audit / surveillance program on procedures, the inspector verified that this problem was identified in Quality Assurance Surveillance Report No.- 387-37, October 10, 1987. The licensee is reducing this backlog at a rate of 2% per week. The expected com-pletion date is the second quarter of 1988. The inspector verified that each procedure change is manually incorporated into the control room procedures which are used by the operations personnel. The licensee stated that upon completion of the Emergency Operating Procedure (EOP) upgrade program, they believe they should signifi-cantly reduce the present backlog. Their trending program, which started in May 21, 1987 to present, indicates that their procedure change and incorporation program is ahead of schedule at this tim After reviewing the licensee's method of updating changes into their operating procedures, their manpower associated with this task and management attention an.1 support of the program, the inspector had no further questions in this are No violations or deviations were identifie .0 Management Meetings The plant management was informed of the scope and purpose of this inspection at an entrance interview conducted on November 30, 1987. The findings of the inspection were periodically discussed with the licensee's cognizant representatives during the course of this inspection. The exit interview was conducted on December 4, 1987, at which time the findings of the inspection were presented (reference Paragraph 1 for attendees). The licensee did not indicate that any proprietary information was contained within the scope of this inspectio At no time during this inspection was written material provided to the licensee by the inspector . _ ._ __
! .i
-
s l
.
>
ATTACHMENT 1 I
,
ADMINISTRATIVE PROCEDURES (ACPs) (AOPs)
.
ACP-QA-2.02C, Work Orders, Rev. 15, September 21, 1987 !
'
ACP-QA-2.02A, Installation Inspections, Rev. 14, September 21, 1987-ACP-QA-1.00, Quality Assurance -~ Quality Control Program, Rev. 9,
- November 4, 1987
.
ACP-QA-4.01A, System and Component Housekeeping, Rev. 2, September 21, 1987 ACP-QA-4.01, Plant Housekeeping, Rev. 15, October 6, 1987 -
'
AOP 2560, Storms, High Winds or High Tides, Rev. 2, January 28, 1987
,
ACP-QA-9.02B, Master Test Control List, Rev.12 l
'
OPERATING PROCEDURES (ops)
1-OPS-10.09, Plant Equipment Check Log, Rev. 29, November 6, 1987
.
-
ONP 5148, Freezing Temperatures, Rev. 2, March 4, 1987 :
- OP2343, 4160 Volt Electrical System, Rev. 7, Change No. 6, July 31,1987 I t
OP3346A, Emergency Diesel, Rev. 2, Change No. 16, November 25, 1987 l
,
j OP3338A, Radioactive Solid Waste, Rev. O, Change No. 7 l OP3351E, Access to CO2 Protected Area, Rev. O, Change 11, May 1987 i OP3341, Fire Protection Carbon Dioxide System, Rev. 2, Change 5, March 13, 1987 CALIBRATION SURVEILLANCE PROCEDURES (SPs)
l SP 412H, Core Spray Header Differential Pressure Switch Functional and Calibration Test, Rev. 7, April 23, 1986
q SP 412J, Core Spray System Automatic Actuation, Rev. 7, May 13, 1987 i l
SP 419B, Feedwater Regulation Valve Logic Test J
SP 412K, LPCI/ Containment Cooling System Logic Test, Rev. 5, June 4, 1987
! IC 450, Unit 1, Instrument and Control Department Training, Rev. 8, March 12, 1986
!
I I
_ - - - - - - - -
. . _ .
-_. - . . . _ _ .. _
J
>
L
.
Attachment 1 -2 !
!
CALIBRATION SURVEILLANCE PROCEDURES (SPs) (Continued) ,
IC 450A, Instrument and Control Contractor / IMP Training, Rev. 1, t September 25, 1985
'
'
IC 460A, Biennial Review of Instrumentation and Control Procedures,.
Rev. 1, September 25, 1985 -
,
IC 490A, Training, Certification and Qualifications of Instrument and -
,
Controls Personnel, Rev. O, September 25, 1987- '
IC 493A, Preparation, Review and Approval of Unit 1 I&C Procedures, Rev. 3, November 20, 1987 ,
!
'
SP 1061, ISI Power Operated Valve and Check Valve Operability Program, Rev. 4, October 26, 1983 SP 412A, Reactor Low Pressure Valve Permissive Functional and Calibration '
Test, Rev 7, December 5, 1985 l
r SP 412C, Reactor Low-Low Water Level Functional and Calibration Test, Rev. 11, May 6, 1986 SP 4120, High Drywell Pressure Functional and Calibration Test, Rev. 6, '
December 30, 1986 SP 412G, Break Detection Valve Permissive Functional and Calibration Test, Rev. 8, March 12, 1986 SP 412GA, LPCI Break Detection Pressure Switch Calibration Test, Rev.1, June 18, 1986 i SP 621.10, Core Spray System Operability Test, Rev. 8, July 7, 1987
]
SP 621.11, Core Sprcy Remote Valve Indication Check (ISI), Re January 25, 1984 l SP 622.7, LPCI System Operability Test, Rev. 12, September 22, 1986 ,
SP 622.8, LPCI System Remote Valve Indication Check (ISI), Rev. 1, January 25, 1984 SP 1060, l ISI Program Pump Vibration and Hydraulic Test, Rev. 8, i June 5, 1987 j
SP 2613C, Engineered Safety Features System (ESF) Integrated Test, Rev. 10, October 14, 1987 SP 3712T, Containment Penetration Overcurrent Device Surveillance Testing for Load Center Breakers, MCC, and Molded Case Breakers, Rev. 2, November 6, 1987
.
. Attachment 1 3 CALIBRATION SURVEILLANCE PROCEDURES (SPs) (Continued)
SP 3712T-4, Containment Penetration Load and Current Test Tables, Rev. O, Change 2, January 4,1986 SP 2401E, Calibration of Excore Nuclear Instruments to Incores, Rev. 8, December 1, 1987 SP 24011, Local Power Density Test, Rev. 7, December 1, 1987 SP 4060, Main Steam Line Radiation Monitor Detector Calibration, Rev. 5 SP 2401K, High Power Trip Calibration, Rev 3, January 5, 1987 SP 2402B, Pressurizer Pressure Calibration, Rev. 5, December 7, 1986 SP 2402D, Steam Generator Level Calibration, Rev. 4, December 12, 1986 SP 2403B, ESAS Undervoltage Bistable Calibration, Rev. 4, December 8, 1986 SP 2403D, Containment Pressure Calibration, Rev. 5, October 16, 1986 SP 408C, Reactor Vessel Low Water Level Scram and Low-Low Level Isolation Functional and Calibration Test, Rev. 5 IC 400A-11, Condensate Storage Tank Level Calibration, Rev. 7, March 5, 1987 IC 400A-17, Reactor Vessel Wide Range Level Calibration, Rev. 6, August 3, 1987 IC 400A-27, "A" Steam Line Pressure Calibration, Rev. 4, July 6,1987 IC 400A-33, Reactor Core Pressure Drop Calibration, Rev, 3, May 29, 1987 IC 400A-48, Reactor Feed Pump Discharge Pressure Calibration (ISI), Rev. 2, July 23,1987 IC 400A-63, LPCI Minimum Flow Line Pressure Calibration (ISI), Rev. 3, April 11, 1987 IC 400A-83, LPCI Pumps Flow Calibration (ISI), Rev. 3, January 15, 1987
IC 400A-95, Reactor Pressure / Level Instrument Calibration, Rev. 2, !
August 3, 1987 l l
l l
.
.
.
Attachment 1 4
$URVEILLANCE WORK ORDERS M3-86-07414, Panel 3RCP*PNL3A, Breaker F4K, 18 Month Surveillance Requirement M3-86-07418, Panel 3RCP*PNL3A, Breaker F3M, 18 Month Surveillance Requirement M3-86-07421, Panel 3RCP*PNL3B, Breaker R2M, 18 Month Surveillance Requirement M3-86-07469, Pressurizer Heater Backup, Heaters 36, 65 and 66 and Associated Breakers
. PLANT DESIGN CHANGE REQUEST (PDCR)
PDCR No. 1-98-86, Millstone Units 1/2, Appendix R, Backfeed Outage Work, November 1986 PDCR No. 2-87-86, EDG Auto. Start-Sequence Change, December 20, 1986 QUALITY ACTIVITY OBSERVATION REPORTS (QAOR, i.e., 0VALITY ASSURANCE SURVEILLANCE)
Unit 1 QAOR 187-14, May 19, 1987, Rod Block Monitor Functional Testing QAOR 187-21, June 23, 1987, Local Leak Rate Testing QAOR 187-26, July 9, 1987, Bolt Replacement on Motor Operators QAOR 187-44, July 30,1987, Revien of ILRT Procedure QAOR 187-52, December 2, 1987, Local Leak Rate Testing QAOR 187-54, September 16, 1987, ILRT Unit 2 QAOR 287-05, February 13, 1987, Review of Sealing and Seal Repair Electrical Cable and Piping Penetrations Procedure QAOR 287-06, February 26, 1987, Fire Penetration Seals
_
"
,
.
Attachment 1 5 QUALITY ACTIVITY OBSERVATION REPORTS (QA0R, i.e., QUALITY ASSURANCE SURVEILLANCE) (Continued)
Unit 3 QA0R 387-07, March 6, 1987, Onsite Vendor Inspections of Snubbers QA0R 387-29, July 6,1987, Onsite Vendor Air Flow Measurement Testing QAOR 387-31, August 10, 1987, Receipt Inspection of Measuring and Test Equipment QA0R 387-37, October 22, 1987, Operations Procedures and Change Incorporation QAOR 387-42, November 10, 1987, 8 Diesel Generator Maintenance QAOR 387-49, November 21, 1987, Local Leak Rate Test Instrumentation Calibration Records OTHER DOCUMENTATION P&ID 25202-26008, SH 1, Core Spray, Low Pressure Coolant Injection, and Emergency Service Water System Composite, Re July 22, 1986 P&ID 25202-26008, SH 6, Core Spray System, Rev.1, July 22,1986 P&ID 25202-26008, SH 7, Core Spray System, Rev.1, July 22,1986 Licensee Letter B12750, November 19, 1987, Millstone Unit No. 3, Containment Penetration Conductor Overcurrent Protective Devices Licensee Letter B12754, November 24, 1987, Millstone Unit No. 3, Supplement Information - Containment Penetration Conductor Overcurrent Protective ,
Devices ll National Electrical Manufacturers Association (NEMA) Publications No. AB3, Molded Case Circuit Breakers and Their Application Stone and Webster Engineering Corporation, NERM-71, Rev. O, November 9, 1985, i Electrical Penetration Protection, Millstone Unit No. 3 Licensee Letter GEE-85-1737, October 1, 1985, MP-1/2 Appendix R Backfeed Connecticut Valley Electric Exchange (CONVEX) Operating Instruction No. 8601, Millstone 345KV Substation Salt Decontamination General Electric Molded Case Circuit Breaker Maintenance Manual, GET 279G EPRI Research Project Report RP2472-3, December 1986