|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
Text
..
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report N /87-18 Docket N I License N DPR-21 Licensee: Northeast Nuclear Energy C P. O. Box 270 Hartford, Connecticut 06141-0270
Facility Name: Millstone Nuclear Power Plant, Unit 1
Inspection At: Waterford, Connecticut Inspection Conducted: July _ 31_, 1987 - August 7,_1987
.
i i
Inspectors: _ _dn/_ . fee.L/
_
/0/ *>f--f0/
i r. Jin W. hung date enior Reactor E ineer Approved by: ,'.. J. Anderson, Chidf __ .. f!2- h7
'date
'
i it Systems Section
,
l Insp_ection Summary: Inspection on July 31, 1987_- August 7, 1987 (Inspection No. 50-245/87-18).
Areas Inspected: Routine unannounced inspection of test witnessing and preliminary results evaluation of Containment Integrated Leak Rate Test (CILRT), and tours of the facilit Results: No violations or deviations were identifie PDR ADOCK 05000245 O PDR l
l l
L______________._________-__-._-
{ -
i
.
l-DETAILS l 1.0 Persons Contacted-M. Bigiarelli, Assistant Test Director, ILRT'
i
- G. J. Closure, Plant Quality Services Supervisor
- E. J. Georgian, ILRT Test Director
'
D, Johnson, IDC B. Loweth, Test Director, ILRT J. Nowell, Shift Supervisor R. Palmieri, Operations Supervisor
- S. E. Scace, Millstone Station Superintendent J. Selvidio, QA
- J. Stetz, Millstone Unit 1 Superintendent R. Thompson, QA NNECO Test Personnel
.
J. T. Dimarzo, Sr. Engineer W. English, Sr. Engineering Technician N. Herzig, Engineer R. J. Schmidt; Supervisor - Special program's Stone & Webster B. I. Parry The inspector also held discussions with other licensee employees during the inspection, including operations, technical support, and other craft personne * Indicates those present at the exit meeting held August 7, 1987 1.1 Attendees at August 5, 1987 Meeting G. E. Cornelius, NUSCO-GME J. W. Calderone, CY-Engineering E. J. Georgian, NNECO, Millstone 1 Engineering M. D. Hess, NNECO, Millstone 3 M. S. Ledermen, NUSCO - Licensing S. L. Stadnick, NNECO, Millstone ? Engineering J. W. Chung, USNRC, Region I 2.0 Administrative Control of Integrated Leak Rate Test (ILRT)
Several pretest meetings were held with the licensee representatives to discuss the progress of test preparations, the scope of test, and the testing methodolog The following observations were made: j l
];
q J
-
.
Continuous 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> QA coverage was planned
- Scheduling and scope of the containment walkdown were evaluated and discusse * ILRT valve lineups were in progres *
Test personnel, including operations, were briefed on " Punch List" items, critical to the ILR *
A total of 20 RTDs and 6 Dewcell sensors were placed for the test; 8 RTDs and 2 Dewcells in the Torus, and the rest of the sensors in the i Drywell . l l
- In-situ calibration checks were performed prior to the ILR i
Control Roorn Halon test (Appendix R test) was performed on August 2, 1987, prior to the ILRT performanc *
General housekeeping and final instrument visual inspections were conducted by I&C, QA, and test personne *
Equipment hatch was tested for Local Leak Rate Testing (LLRT) Type * Torus manway was tested for LLR *
Due to alignment problem of the Drywell header, the ILRT was delaye ]
The inspector interviewed selected licensee personnel and reviewed administrative documents, procedural sign-offs, data collection and the official Type A test-log of event The test activities were observed to verify that: Prerequisites were met; the tast was conducted in ,
accordance with the procedure; test directors were designated and their l responsibilities were defined; and required plant parameters were being recorded during the test. The inspector noted that the licensee maintained good control of containment and penetration area access before and during the ILRT.
i 2.1 Documents Reviewed l
l *
Control Room Log and Shift Supervisor Lo !
Calibration Records: 2 pressure gauges, 2 data acquisition units, Dewcells, RTDs, and 2 Flow meters for verification tes * Technical Specification *
Selected containment penetration valve lineup diagram !
Sensor location diagrams.
l'
__- ---__ J
p
.
i
Surveillance Procedure (SP) 623.14, local Leak Rate Tes *
Inservice Test Procedure Change Form, T87-1-6, Change No. *
Quality Activity Observation Report Response Form, No.187-44, ILRT Procedure Revie l l
'
- Internal Memo, MP-1-3163, Restricted Access to Unit 1 Reactor Building during Test, July 31, 1987
Nuclear Engineering and Operations Procedure, NE0 2.20, )
Containment Leakage Rate Testing Progra i
At 10:00 a.m., August 5,1987, the final drywell closecut inspection was ,
conducted as required by 10 CFR 50, Appendix The walkdown team !
included the ILRT Test director, I&C, Operations, QA monitor, and the USNRC inspector. The following items were observe l l
The necessary tanks and systems were vented per procedures, including MSIV accumulator *
Containment housekeeping was good: wood scaffolding, and flammable j materials were removed. Unvented containers had been vente i
A sample of ILRT Instrumentation was inspected at locatio *
The data acquisition center was inspected. The data center included computer harWare and equipment associated with the instrument verification bypass flow tes *
The containment pressurization system was inspecte This consisted of compressors and chiller *
The containment fans were secured in order to maintain a stable ai The rationale for such actions was discusse *
The reactor vessel water level was maintained approximately 30" above the reactor cor *
The CRD system was tripped, and the reactor water level was controlled with the shutdown cooling system, as needed.
- - - - - _ - _ _ _ - _ _ _ _ _ _ _ _ - _ _ -
_
. .
'
=
During the closecut inspection, the licensee's inspection team discovered that the personnel airlock seal gaskets were damaged. The l seals were replaced. The LLRT was to be performed after the Type A i tes *
Prior to final pressurization of the Drywell and Torus, A QA inspector checked the air quality from the compressors. The air quality was acceptabl l At 4:55 pm, August 5, 1987, the containment pressurization was commenced at a rate of 8#/hr. The licensee secured the compressors at a containment pressure of 10 psig. In accordance with the test procedure, the penetrations )
and system lineups were inspected to verify potential leak pathway j No unacceptable conditions were identifie ;
4.0 Containment Integrated Leak Rate Test (CILRT)
~
4.1 CILRT Procedure Review
!
The inspector reviewed the CILRT test procedure, T 87-1-6, and I associated procedure changes (Change Nos. I through 8) for adequacy and correctness of the procedure to perform the test. Procedure, T 87-106, " Primary Containment Integrated Leak Rate Test", included many options and test methodologies, including an 8_ hour reduced duration test, the Total Time Calculational method, and the Mass
,
point method of ANSI N56.8-198 l The licensee selected an 8-hour reduced duration test, employing the Total Time calculational option. This was consistent with the Bechtel i Topical Report, BN-TOP-1, Revision 1, " Testing Criteria for Integrated ;
Leakage Rate Testing of Primary Containment Structures for Nuclear '
Power Plants." The specified acceptance criteria were consistent with those specified in BN-TOP-1. The "As Found" penalty of 7 Standard Cubic Feet per Hour (SCFH) would be subtracted from the normal acceptance value of 375 SCFH (0.75 L,). The "As Found" penalty j was based on the Local Leak Rate Test (LLRT) results. The penalty h would reduce the acceptance criteri !
The procedure was revised to include provisions which allowed the .
licensee to control the reactor vessel water level using the shutdown '
cooling system should water level adjustment be needed during the tes c i
4.2 Test Instrumentation l The inspector reviewed the calibration records for the ILRT instrumen-tatio These records indicated that the standards used were traceable ,
to the National Bureau of Standards (NBS). The in-situ calibration i data and the automatic data acquisition / analysis system were also l inspecte i l
l
-
a + .
I
6 1 Under BN-TOP-1 recommendations, the ILRT should employ a' minimum of l 12 temperature sensors, at least 6 Dewpoint sensors, and one precision pressure gage. The following shows a summary of the. sensors used for-the test:
BN-TOP-1 Recommended Sensors Minimum Actual
'
RTD 12 20 Dewcell 6 6
.'
Flowmeter 1 1 Verification Test l Pressure Guage 1 2 The latest industrial standard, ANSI N56.8-1981, specifies a minimum of 3 Dew point sensors, and no Drybulb temperature sensor are allowed to represent a volume fraction greater than J0% during the CILR The actual instrumentation for the CILRT exceeded the above ANSI standard specificatio .3 Failure of "As Found" CILRT The containment pressurization was continued after a 10 psig holding-inspection pause. Containment pressurization was terminated at 7:24 am, August 6,-1987. The containment pressure reached the accident pressure of 58.6 psia at an average containment temperature of 87.4 F. The containment stabilization period was commenced immediately, and a 4-hour stabilization period was completed by 11:24 am, meeting the stabilization acceptance criteria as follows:
Criterion -Actual Acceptance Criterion (BN-TOP-1) Value Result The rate of change of average temperature averaged over the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, F/h . < .11 The rate of change of temperature changes averaged over the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, F/hr/h <0,5 0.0445 l The actual results presented in the above table were calculated values by the inspector based on the actuel data points analyzed by the data acquisition system. Individual data points were monitored every 15. minutes. The raw data points were calculated for the CILRT by the compute The official CILRT was commenced immediately following the 4-hours stabilization perio At 3:29 pm, August 6, 1987, a Service Air penetration was suspected as a leak pathway, and'the leak through
,
_ . _ - - - - - . _ - - - _ . _ - _ _ - - _ - - - - - - _ - _ _ . - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
m
.
7 ;
1-SA-516 was quantified as 6.78 SCFH. At 1715 hour0.0198 days <br />0.476 hours <br />0.00284 weeks <br />6.525575e-4 months <br />, another leak was-located in the vent.line from the Isolation Condenser (IC) vent line to the Main Steam (MS) piping, downstream of the MSIV' Leaks .
through the IC A0Vs 6 and 7 were identified and quantified as 11.5' !
SCFM (690 SCFH). This exceeded the CILRT acceptance criteria of 0.75L L, is 500 SCFH and 0.75L, is 375 SCF The licensee, subsequently, declared the "As Found" CILRT as a failure. In accordance with.the' requirements specified in III.A.6(2)
of 10CFR50, Appendix J, the above "As Found" failure of the type "A" ,
test requires the licensee to submit the next type "A" test schedul I to the commission for an approva .4 "As left" CILRT Result The CILRT was conducted in accordance with BN-TOP-1 requirements, employing an 8-hour duration test and the Total Time calculational metho The inspector reviewed the preliminary test results, as shown on the attached figure. The measured leak rates and 95% upper confidence limit (UCL) values are plotted as a function of time and compared to the acceptance criteria. In this figure, the measured and the t-statistical points approach asymptotically. The initial data fluctuation represents the inherent perturbation of the points due to the statistical method employe !
A final evaluation of the test results will be performed by the NRC l on receipt of the licensee's summary technical report on the tes The following summarizes the test results:
Stabilization Period: 1844 hour0.0213 days <br />0.512 hours <br />0.00305 weeks <br />7.01642e-4 months <br /> - 2244' hour, August 7, 1987 f Actual : 0.003 F/hr/hr j Acceptance Criteria: 0.5 F/hr/hr a
\
CILRT: 2244 hour0.026 days <br />0.623 hours <br />0.00371 weeks <br />8.53842e-4 months <br />, August 7, 1987 - 0659 hour0.00763 days <br />0.183 hours <br />0.00109 weeks <br />2.507495e-4 months <br />, August 8, 1987 l l
Total Time Measured: 0.3395 weight %/ Day l Total Time 95% UCL : 0.400 weight %/ Day I Acceptance Criteria: 0.900 weight s/ Day l 4.5 ILRT CHRONOLOGY l
l August 2, 1987 j 10:30 - 12:00 * General tours inside Drywell and Torus. 8 RTDs and 2 Dewcells were installed in the Toru :18 17:44 * Control Room Halon test: Appeared to meet the acceptance criteria
._. _ . . . _
.
,
,
> August 3, 1987
.
-
09:00 All 20 RTDs' and' 6 Dewcells are installe In- !
situ Calibration. Faile :20 * Pre-closeout containment. inspection performe General penetratio'n inspection performe l 20:00 Equipment Hatch closed 22:20 I&C and QA made Drywe'll entry for final In-situ Calibration of the ILRT instrumentatio August 4, 1987 ILRT delayed due to Drywell vessel header alignment proble ,
20:30 Torus manway hatch close Equipment Hatch LLRT l completed ,
21:00 Torus Manway Hatch LLRT complete August 5, 1987 j 10:00 Drywell header was successfully place L 10:00 - 11:20 * Final pre closecut inspection was performed: l I&C, Operations, QA, ILRT Test' Director, and NR Found Personnel Airlock Gasket damage :30 Final ILRT Briefing held by Assistant Test I
Directo :55 * Air Compressor output air quality checked by Q Containment pressurization commenced at a l rate of 10 psia per hour: 300 cfpm 21:00 * Control Room Narrow Range Reactor Vessel Water level Indicator A shows 54" Water. level, a loss of more than 3" in less than 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> at a j containment pressure of 10 psi l 21:35 Containment pressurization commenced agai :55 Drywell Air Pressure,12.5 psi 'A' Narrow Range Level Indicator 53" l
l
, ,
.
'
August 6 1_1987 07:24 Terminated pressurization. Added water via Shutdown Cooling System; ' A' Level Indicator 59"; Air Pressure, 58.6 psia; Average Temperature, 8 F. Official Stabilization period commence :24 Stabilization Criteria was satisfied: 0.1982 F/last 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />; 0.1053 F/hr/last hou ,i r 13:50 * Identified a leak through 2" Service Air Syste :30 Terminated ILRT to quantify the_ leak through IC l valves 6 and 7: Leakage rate was greater than i
10.00 SCFM. (Declared "as-found" Test a failure *)
August 7, 1987 -
18:44 Reinitiated Stabilization Perio :44 Completed 4 HR stabilization: 0T =
22:45 Commenced ILRT test !
August 8, 1987 06:59 Completed ILRT:
Total Time ILRT = 0.40 %/ Day 95% UC Least Square Feet ILRT = 0.3395%/ Day Acceptance = 0.90 %/ Day
- Inspector witnessed this activit .0 Local Leak Rate Test (LLRT)
At 1300 hour0.015 days <br />0.361 hours <br />0.00215 weeks <br />4.9465e-4 months <br />, August 5, 1987, the inspector held a meeting with the representatives of Millstone units 1, 2, 3, and Haddam Neck, and NUSCO i licensing engineer to discuss the Local Leak Rate Testing (LLRT) of some selected containment isolation valves. Attendees of the meeting were listed in section Under the provisions of Appendix J, Type C testing requirements, a reverse direction LLRT was permitted, provided that such reverse direction testing would provide more conservative test results. However,
~
some valves, such as Atmospheric Control valves, could yield less conservative results under the reverse direction test: the reverse direction test might be more conservative for the valve seat leakage However, the valve packing might not be exposed to the pressure under the reverse direction pressurization.
l l
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .
__ - - - -
,
.
The inspector determined that this situation had been recognized by the license The acceptability of such reverse direction test would be further investigate The licensee representative stated that final course of their actions would be conveyed to the NRC by September 1, 198 This is an unresolved item, pending final disposition of this item or submittal of an exemption, for the reverse direction test (50-245/87-18-01).
6.0 QA/QC Test Coverage The inspector discussed QA/QC activities during the CILRT and observed various QA activities related to the test preparation, initiation, equipment surveillance, air quality check, and test performance. Based on the above observation, the inspector determined that the QA surveillance were adequate, and 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> continuous monitoring of the CILRT activities was goo :
The inspector also determined that the QA Observation Report was adequate to document the QA activities during the CILRT performance. No unacceptable conditions, devitiations or violations were observe .0 Plant Tours The inspector made several tours of the plant facilities, including reactor building penetration areas, Drywell, Torus, Control Room, and 1 plant exterior (compressors, etc.). The objective of such tours included {
testing activity monitoring, general housekeeping, and administrative controls of the CILRT activities. The following findings were identified !
during the facility tours: .
-
The station superintendent entered the Drywell with anti-c, protective clothing. This is an indication of station management ;
attentio i
The interior or the Torus and Drywell were clean and general housekeeping was goo '
=
The administrative controls and access controls during the testing were adequat .
'
General housekeeping near the mechanical and electrical penetration areas were adequat No unacceptable conditions were identifie _ _ _ _ _ _ - _ _ -- _ _ _ - , - - - . _ _ - . - - - - . - - - - - - - -
_ - - - _ . - _ _ -_ . - _ _ - - - - - - - - - - - _ _ _ -_ _ _ - -
- - - - - ,
..
.
8.0 Exit Meeting Licensee management was informed of the purpose.and scope of the inspection at the entrance intervie The findings of the inspection were periodically discussed and were summarized at the exit meeting on August 17, 198 l L Attendees at the exit. meeting are listed in section 1.0 of this repor j At no time during the inspection was written material provided to the 1 licensee by the inspector l The licensee representatives indicated that no proprietary information was involved within the scope of this inspection.
I
i
'I
-
.
-
_
e
.
_
.
.
_
_
_
_
_ _
.
_
6 -
_
_
- _
_ 0 5 .
-
-
_
_
_
E Cl
_
_
k A
T P _-
e _ c 0
.
_
_
-
c 3
_
A _
_
E
-
d 0 M
-
c _- ga
_ I u -
o 2 T
% .- s A
e 5~
9 - s _
s
" '
\
l i'
\
h r s l , .-
,
l1'
81f !l, ( f f/ .
4
-
-
0 .
5 0 1_ 1
~
.
0 _
_ ~ . 2 2 _
_
n [C\Nv dLt J_[H F
-
.
.
-
_
.
-