|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000213/19990021999-08-20020 August 1999 Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted. Major Areas Inspected:Decommissioning Operations & Sf Safety Maint & Surveillance,Plant Support & Rediological Controls IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000213/19990011999-05-21021 May 1999 Insp Rept 50-213/99-01 on 980119-990419.No Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000213/19980061999-02-26026 February 1999 Insp Rept 50-213/98-06 on 981103-990118.Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility. Security Program Was Also Inspected IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19980051998-12-21021 December 1998 Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155F8511998-10-29029 October 1998 Insp Rept 50-213/98-04 on 980720-0911.Violations Noted. Major Areas Inspected:Aspects of Licensee Preparations, Planning & Implementation of RCS Chemical Decontamination, Operations,Engineering,Maint & Plant Support IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000213/19980031998-08-21021 August 1998 Insp Rept 50-213/98-03 on 980414-0803 & 13.Violations Noted. Major Areas Inspected:Operations,Maint,Sf Safety, Decommissioning Activities & Radiological Controls IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000213/19980011998-05-13013 May 1998 Insp Rept 50-213/98-01 on 980113-0413.Violations Noted.Major Areas Inspected:Decommissioning Support Activities,Spent Fuel Safety,Plant Support & Radiological Controls & Facility Mgt & Control IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000213/19980021998-05-0505 May 1998 Insp Rept 50-213/98-02 on 980316-20 & 25-27.No Violations Noted.Major Areas Inspected:Radiological Control Programs IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19970091998-02-17017 February 1998 Insp Rept 50-213/97-09 on 971012-980112.Violations Noted. Major Areas Inspected:Decommissioning Operations & Planning & Included Aspects of Engineering,Maint & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000213/19990021999-08-20020 August 1999 Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted. Major Areas Inspected:Decommissioning Operations & Sf Safety Maint & Surveillance,Plant Support & Rediological Controls IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000213/19990011999-05-21021 May 1999 Insp Rept 50-213/99-01 on 980119-990419.No Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000213/19980061999-02-26026 February 1999 Insp Rept 50-213/98-06 on 981103-990118.Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility. Security Program Was Also Inspected IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19980051998-12-21021 December 1998 Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155F8511998-10-29029 October 1998 Insp Rept 50-213/98-04 on 980720-0911.Violations Noted. Major Areas Inspected:Aspects of Licensee Preparations, Planning & Implementation of RCS Chemical Decontamination, Operations,Engineering,Maint & Plant Support IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000213/19980031998-08-21021 August 1998 Insp Rept 50-213/98-03 on 980414-0803 & 13.Violations Noted. Major Areas Inspected:Operations,Maint,Sf Safety, Decommissioning Activities & Radiological Controls IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000213/19980011998-05-13013 May 1998 Insp Rept 50-213/98-01 on 980113-0413.Violations Noted.Major Areas Inspected:Decommissioning Support Activities,Spent Fuel Safety,Plant Support & Radiological Controls & Facility Mgt & Control IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000213/19980021998-05-0505 May 1998 Insp Rept 50-213/98-02 on 980316-20 & 25-27.No Violations Noted.Major Areas Inspected:Radiological Control Programs IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19970091998-02-17017 February 1998 Insp Rept 50-213/97-09 on 971012-980112.Violations Noted. Major Areas Inspected:Decommissioning Operations & Planning & Included Aspects of Engineering,Maint & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000213/19990021999-08-20020 August 1999 Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted. Major Areas Inspected:Decommissioning Operations & Sf Safety Maint & Surveillance,Plant Support & Rediological Controls IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000213/19990011999-05-21021 May 1999 Insp Rept 50-213/99-01 on 980119-990419.No Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000213/19980061999-02-26026 February 1999 Insp Rept 50-213/98-06 on 981103-990118.Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility. Security Program Was Also Inspected IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19980051998-12-21021 December 1998 Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155F8511998-10-29029 October 1998 Insp Rept 50-213/98-04 on 980720-0911.Violations Noted. Major Areas Inspected:Aspects of Licensee Preparations, Planning & Implementation of RCS Chemical Decontamination, Operations,Engineering,Maint & Plant Support IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000213/19980031998-08-21021 August 1998 Insp Rept 50-213/98-03 on 980414-0803 & 13.Violations Noted. Major Areas Inspected:Operations,Maint,Sf Safety, Decommissioning Activities & Radiological Controls IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000213/19980011998-05-13013 May 1998 Insp Rept 50-213/98-01 on 980113-0413.Violations Noted.Major Areas Inspected:Decommissioning Support Activities,Spent Fuel Safety,Plant Support & Radiological Controls & Facility Mgt & Control IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000213/19980021998-05-0505 May 1998 Insp Rept 50-213/98-02 on 980316-20 & 25-27.No Violations Noted.Major Areas Inspected:Radiological Control Programs IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000213/19970091998-02-17017 February 1998 Insp Rept 50-213/97-09 on 971012-980112.Violations Noted. Major Areas Inspected:Decommissioning Operations & Planning & Included Aspects of Engineering,Maint & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000213/19900131990-10-19019 October 1990 Safety Insp Rept 50-213/90-13 on 900801-0911.Good Radiological Controls Performance Noted.Major Areas Inspected:Plant Startup Following 1989/1990 Refueling Outage,Reactor Trips on 900813 & 0903 & Safeguards Problems IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000213/19900181990-10-10010 October 1990 Insp Rept 50-213/90-18 on 900926.No Violations Noted IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000213/19900121990-08-22022 August 1990 Safety Insp Rept 50-213/90-12 on 900621-0731.Major Areas Inspected:Review of Final Refueling Outage Activities, Preparations for Reactor Startup,Exams of safety-related Equipment Readiness & Review of Operational Events IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000213/19900081990-07-11011 July 1990 Insp Rept 50-213/90-08 on 900509-0620.Weaknesses Noted.Major Areas Inspected:Plant Operations,Reactor Fuel Reload Activities,Radiological Controls,Loss of Power Testing, Cleaning & Insp of RCS & Insp of Pressurizer Clad Cracks IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 IR 05000213/19900071990-05-18018 May 1990 Insp Rept 50-213/90-07 on 900402-05.No Violations Noted. Major Areas Inspected:Changes to Emergency Plan & Implementing Procedures,Emergency Response Facilities, Equipment & Organization & Mgt Control ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000213/19890121989-09-29029 September 1989 Insp Rept 50-213/89-12 on 890726-0905.No Violations Noted. Major Areas Inspected:Plant Operations,Radiation Protection, Fire Protection,Security,Maint,Surveillance Testing,Licensee Events,Open Items & Opening of New Security Access Point IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000213/19890141989-09-21021 September 1989 Insp Rept 50-213/89-14 on 890911-15.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys, Transportation,Liquid & Gaseous Effluents Programs, Including Mgt Controls,Audits & QA IR 05000213/19890131989-09-15015 September 1989 Insp Rept 50-213/89-13 on 890814-18.No Violations Noted. Major Areas Inspected:Const Activities of New Switchgear Bldg Constructed to Comply W/App R Requirements & Review of Adequacy & Implementation of Fire Protection Program IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000213/19890111989-08-24024 August 1989 Safety Insp Rept 50-213/89-11 on 890731-0804.No Violations Noted.Major Areas Inspected:Changes to Emergency Preparedness Program,Emergency Facilities,Equipment, Instrumentation,Supplies & Organization & Mgt Control IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000213/19890101989-08-18018 August 1989 Safety Insp Rept 50-213/89-10 on 890614-0725.No Violations & No New Unresolved Items Noted.Major Areas Inspected:Plant Operations,Radiation Protection,Fire Protection,Security, Maint,Surveillance Testing,Open Items & Safety Sys Lineups IR 05000213/19890091989-08-0303 August 1989 Partially Withheld Physical Security Insp Rept 50-213/89-09 on 890626-30 (Ref 10CFR73.21 & 2.790(a)).No Violations Noted.Major Areas Inspected:Mgt Support,Program Plans, Audits & Protected & Vital Area Physical Barriers IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000213/19890071989-07-11011 July 1989 Insp Rept 50-213/89-07 on 890503-0613.Violations Noted. Major Areas Inspected:Plant Operations,Radiation Protection, Fire Protection,Security,Maint,Surveillance Testing,Licensee Events & Open Items from Previous Insps IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000213/19890081989-07-0707 July 1989 Insp Rept 50-213/89-08 on 890614-16.No Violations Noted. Major Areas Inspected:Radiological Controls Program on Site, Including Changes in Organization,Personnel,Procedures & Review of Preparations for Refueling Outage IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-I-99-039, on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting1999-09-0101 September 1999 PNO-I-99-039:on 990831,Haddam Neck Plant CR Was Notified by Transportation Contractor,Hittman Transportation Svcs,That Driver of Truck,Left Plant Earlier in Day Noticed Water Leakage from from sea-land Container He Was Transporting IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000213/19990021999-08-20020 August 1999 Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted. Major Areas Inspected:Decommissioning Operations & Sf Safety Maint & Surveillance,Plant Support & Rediological Controls IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage IR 05000213/19990011999-05-21021 May 1999 Insp Rept 50-213/99-01 on 980119-990419.No Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility ML20206R7141999-05-12012 May 1999 Notice of Violation from Investigation on 970314-0722. Violation Noted:M Thomas Engaged in Deliberate Misconduct on 970227,that But for Detection,Would Have Caused Licensee to Be in Violation of 10CFR20.1802 ML20206R7391999-05-12012 May 1999 Notice of Violation from Investigation on 970616-0718. Violations Noted:On 961209 & 10,J Foley Deliberately Caused Util to Be in Violation of 10CFR50.9 & TS 6.11 & in June 1997 Provided Inaccurate Info to NRC Inspector PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities ML20205J8031999-04-0505 April 1999 Notice of Violation from Insp on 961102-27.Violation Noted:Licensee Failed to Adequately Instruct Workers & Failed to Perform Adequate Radiological Surveys in Reactor Cavity & Fuel Transfer Cavity IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20206B3801999-03-29029 March 1999 EN-99-015:informs Commission That Staff Intends to Exercise Discretion Pursuant to Section VII.B.6 of Enforcement Policy & Not Propose Civil Penalty for Severity Level III Problem That Occurred in Nov 1996,prior to Licensee Decision ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000213/19980061999-02-26026 February 1999 Insp Rept 50-213/98-06 on 981103-990118.Violations Noted. Major Areas Inspected:Aspects of Licensee Activities in Preparation for Dismantlement & Decommissioning of Facility. Security Program Was Also Inspected ML20207B7041999-02-26026 February 1999 Notice of Violation from Insp on 981103-990118.Violations Noted:Two Different Locked High Radiation Area Doors in Containment Builiding Found Unlocked & Unattended PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power IR 05000213/19980051998-12-21021 December 1998 Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155F8511998-10-29029 October 1998 Insp Rept 50-213/98-04 on 980720-0911.Violations Noted. Major Areas Inspected:Aspects of Licensee Preparations, Planning & Implementation of RCS Chemical Decontamination, Operations,Engineering,Maint & Plant Support ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000213/19980031998-08-21021 August 1998 Insp Rept 50-213/98-03 on 980414-0803 & 13.Violations Noted. Major Areas Inspected:Operations,Maint,Sf Safety, Decommissioning Activities & Radiological Controls 1999-09-14
[Table view] |
Text
,
.
,
., ,
4 .
I V. S. NUCLEAR REGULATORY COMMISSION REGION I -
' Report Nos. _50-213/90-83, 50-245/90-82 50-336/90-82, 50-423/90-83
.Dockec No , 50-245 50-336, 50-423 License N DPR-61, DPR-21 l'
DPR-65, NPF-49
< Licensee: Northeast Nuclear Energy _ Company P.O. Box 270 Hartford, CT 06141-0270
..
Facility-Names: Connecticut Yankee Haddam Neck Nuclear Power Station and
' Millstone Nuclear Power Station Units 1, 2 and 3 Inspection At: Northeast Nuclear Energy Company, Corporate Office, Berlin, C ;
'
. Inspection Conducted: September 24-28, 1990 Inspectors: /LA> ~r // - 6 - 9 O R. P olino, Senior Reactor Engineer, Plant date '
'S tems Section, EB/0RS-ll (Mr h-4~L // - f ~ 9 O W. H/ ~ Baunack, ySentbr Reactor Engineer date Op rati nal Programs Section, OB/ ORS .
..)<t
'W. J.'Raymo @ ,- Sen16r Resident inspector Il- V O '
date
'M lls one Nuclear Power Station, DRP
-
A. 'Vegel, Re ctor Engineer, Reactor Projects ll- 7-90
.date Secti n 4' , O P Approved!by: / #
C. J/ Anderson, Chief, Plant Systems-Section, date Engineering Branch, DRS~
-Inspection Summary: Inspection on September 24-28_,1990 (Inspection
+ Report Nos. 50-213/90-83, 50-245/90-82, 50-336/90-82, a 50-423/90-83) ,
Areas-Inspected: Special, announced inspection ;o review the licensee's timeliness for reporting / operability determinatfon Results: Based upon the review conducted, the team determined that the
' licensee.has an adequate program to ensure that-issues are properly evaluated
.for operability'and reportabilit No violations'were. identifie l 9011200225 902109 PDR ADOCK 05000213:
G PNU .
. , . - _ _, . - _ _ _. . . ~
l f kt-l hkg
'
?
'
3. W
-
, 3
l' t
- w['s.; '
y; '
w.%- * _c m,,,-
3 s
-
r> n *
>;yy .. & 'n ' ,
,
!
,
y._ . .
')
'
Wgg eu[> TABLE-0F CONTENT ;f ! jn-m
+ --PAGE
- . i
- i3 , E1[0 i P e r s o n s C o n t a c t e d - . . . . . - . . . . . . . . . . . . . . . . . . . . . . . -. . . . . . . . . . . . - . . . . . . . . . 1
'
% <
L1'.1 Northea st' Nucl ea r- Ene rgy~ Company -... . . . . . . . . . . . . . .-. .-. .'. . . . . . . I
< ._
i 11.2 U.S. Nuclear Regulatory Commission ...................._.... 1-
-
% m . .
.
.
f,
""'
J2.0 1IntroductionL...... ............................-..............,,,. 1- .
M, :2.1: LScoper .........................-............................. 1-
+
j , ' 2 .~ 2 . B a c k g ro'u n d . : . - . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - . . . . . . . 2
- ql -
a 1
,
>
.J3.0( Inspection Details?............................................. 2
., "
2 3 .1 s P roc ed u re s . . c. . . -. . . . . . .: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . : - 2
.
' 3 . 2 c T r a i n i n g . . . .;- . . .._ -.,...3....._.................................,4
, 3 ; 3 f A u d i t s E . . . . . . . . . . . . . - . . . . . . . . . . . . .. . . . . . - . . . . . . . - . . . . . . . . . . . . . . . . .- 5 -
W W, . ..'
3.4 Review of, Reporting Evaluation Forms .......;.....,.......... 5 q:
, ,
'
s $ 3 . 4 . -l ' .Reportability Evaluations with:Significant_
DTimeliness Deficiencies ........,,-......... ,... 6L
- .. 1 -,
y
,,
~3; Technical,Adequ'acy of-Operability /Reportabilit ,i c, , , .
1 De t e rm i n a t i o n s . . . . .; . . . . :. . . . .' . . . . . . . . . . . . . . -. . .. . . . . 7 _
'
M
~
[; 4 . 0j Ex i t . M e e t i n g . , . . . : . . . . . . . . . . . . . . . . . . . . ; . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 o
_
.
.
%,MMig .LAttachmentul:" .;. ~ . . _ > 1 DocumentsiReviewed
.. .
_ .
'
.N
.u .;. -
p 3;\i i !'
, . < ,
<
m ; Attachment 2: TAnch,or , Bolt Def'i ciency -
m ~ -
, ; , .
% 5 d
1- ; ;j i ,
.~ o
..t i$
d
~
i
,( f ,
A
- '_h !
'
-
(
e
-- t
'g
'
4 4 g ..
..>
t\
4 ; ,
- lN p-. q) ; ,.-,
,
,
, .c
'
q
..
g-
<-
n
,i
.
- .;
_t,
=
, M:- , .'
,
' '
'
.. .
t # . ./ ' :p(? ' ^ : tJ,. '
?15 ~ '
A i ' l
. . . .f .4,- *
s'
? 7 '
>
(;y r t
- #
_. r ) .
cr w .
e I
, ,,f
.
lil.,. . j, w
<
g
- ,
.
.q
-
. ,
/,# , . ,
jfsJ - i (3 ) .
, , c.jl
[i_,\ ,Aj.J. j'
'
i
' I 5j
_ _ _ - . - . - _ ___
,
.
.!
[ \' t . }
L'
i DETAILS
.
1.0 Persons Contacted
.
1.1. Northeast Nuclear Energy Company
.
- E.-J. Mroczka, Senior Vice President, Nuclear Engineering and Operations !
- C._F. Sears,.Vice President, Nuclear and Environmentel Engineering l
- Wi 0. Romberg, Vice President, Nuclear Operations !
- E. A. DeBarba, Vice President, Generation Engineering and Construction j
- E. Scace, Director, Millstone Station !
- L. Johnson, Director, Generation Engineering
-
C. H. Clement, Unit' Director, Millstone 3 ;
- R. L. McGuinness,. Supervisor, Nuclear Licensing '
- G. P. VanNoordennen, Supervisor, Nuclear Licensing
- A, Blasioli, Supervisor, Nuclear Licensin M. Marino,. Unit Coordinating' Engineer, Nuclear Operations-
- T. B. Siiko, Licensing Engineer *
M.' V. Bonaca, System Manager, Reactor Engineering !
J.~A. Blaisdell, Nuclear Engineering Consultant !
- V. Papadopoli, Senior Engineer, Quality Services Millsto'ne M. S. Wadkins, Engineer, Generation Electrical Engineering
.B. A. Tuthill, Supervisor, Generation Electrical Engineering
-
e
=B. J. Smith, Technician, Generation Electrical ~ Engineering i;
-W.; J. Hayes, Jr., Senior Technician, Generation Electrical Engineering T. J. Mawson, Supervisor, Generation Mechanical Engineering
. .'L. Coleman,-Engineer, Generation Mechanical Engineering
'
J. Becker,' Instrument and Controls Manager, Millstone 2 !
- D._D. McCory, Manager, Procurement Quality _ Services
j A. R. Roby,. System Manager, Generation Electrical Engineering 1,2 U.S.~ Nuclear Regulatory Commission- I
- 0. Have.'kamp, Chief, Reactor Projects Section_4A,' Division of s Reactor Projects 1
- 0enotes personnel present at the exit meeting on SAptember 28, 1990 j 2.0 Introduction l i
2.1 Scope The scope of this inspection was to evaluate the timeliness of the' i licensee's-reportability and operability program and its implementatio 'The basis for determination included: reviews of. training programs, m applicable audits, procedures and verification of licensee conformance to the established operability /reportability determination procedur '
. ..
2.2 Background Safety and safety-support components, systems and. structures are '
designed to meet the requirements of the regulations, satisfy the
' licensing or design basis and conform to applicable codes and standard These requirements are explicitly stated for each licensed facilit For degraded-or non-conforming conditions of these systems and 3 structures; the licensee is guided by the Technical Specifications- '
and the provisions of 10 CFR Part 50, Appendix B, Criteria XVI, to promptly identify and correct . conditions . adverse to safety or qualit Reporting is required principally by Sections 50.72,50.73,-50.9(b)
and Part 21, Title ~10 of the Code of Federal.. Regulations (10 CFR) and the Technical Specifications. Each of these regulations requires documentation as well as a Section 50.71 report for an update of the final safety analysis report (FSAR). Collectively, these requirements constitute a process that forms the basis for the licensees to continue operations _or place the plant in a safe. condition, and to take prompt corrective action to return the plant to the licensing basi For the process to be complete, changes to the facility pursuant to 10 CFR 50.59 may be used as a partial fulfillment of the corrective action as required by Appendix .
Previous 1NRC inspections at the Mil _1 stone Nuclear Power Station have noted instances where-the timeliness for~reportability and-operability
-
determinations could be improved. (Millstone-1 FWCI Operability-IR
, 50-245/89-25, Millstone 2. Service Water Check Valve-IR 50-336/89-24 and Millstone 3. Fast Bus' Transfer - IR 50-423/89-23). The issues of timeliness and Northeast Utilities (NU) reporting policies were _
C3 cussed with.the NRC on March 13, 199 The licensee responded to-the-NRC. concerns, by letter dated April.9, 1990, recognizing.that prompt identification, investigation and resolution of. safety questions is a matter.of high priority.__ In the April 9, 1990 response, the licensee acknowledg'ed that in the examples sited above, the reporting determinations (conducted under procedure NE0~2.25) could have been 1
. initiated at an earlier time and that ' procedural improvements.and
,
heightened attention -in' this area-would help avoid future delays in
. reporting determination In the. NRC mid-SALP inspection-(Report No. 50-245/90-80; 50-336/90-80i 50-423/90-81) dated July 5, 1990,.the NRC staff noted.that further
. review was needed~to completely evaluate the effectiveness of licensee initiative The purpose of this inspection was to perform this review of licensee initiatives in order to complete the NRC's evaluation'of-their reporting progra .0 Inspection Details
. Procedures A' review was cmducted to determine if procedures have been -i established to assure that incidents or events which occur at the NU
'
facilities are adequately reviewed for reportability to the NR ..
- . . .
>
,
!. .
< ,
'
.
'
-
4
,
Procedures which are intended to assure that incidents or events are reviewed for reportability are ACP-QA-10.01, Plant Incide;it Report .mi (For Millstone), ACP 1.2-16.1 Plant Information Report (for Connecticut Yankee) and NE0 2.25, Operability and Reportabilitv Determination (10.CFR-50.72, 10 CFR 50.73, and 10 CFR 50 9).
.
.
Procedure ACP 1.2-16.1, Plant Information' Report (PIR) and ACP-QA-10.01, .
Plant Incident Report (PIR) both require that any situation or problem ,
which is' processed'under these procedures is evaluated for reportabilit l Both of these procedures require that.the shift superintendent as well as.the unit director perform reportability determinations. These two procedures are generally implemented at the= site and have a ver low threshold for events which are required to have a PIR prepare Procedure ACP 1.2-16.1 is more specific in identifying when a report-ability evaluation is to be performed for issues where reportability !
is uncertain. However, both procedures have provisions for the initiation.of reportability evaluation Issues for which reportability is uncertain in PIR's or identified during design. basis reviews, staf f work, or. other means are evaluated'
.by Nuclear Engineering and Operations. Procedure NE0 2.25. This-procedure provides instructions for the timely evaluation of-potentially reportable. items. Procedure _NEO 2-25 is implemented-
.
-through the use of a Reportability Evaluation Form (REF). ;
During"the review of NE0 2.25, it was noted that for several steps in l the body of the procedure where completion times were specified as .i
"shalls," the implementing form had the same_ steps identified as
-
"should." Also, he body of the' procedure: requires that if an evalua-
. tion -cannot be cenpleted within 20 days a preliminary reportability '
recommendation'st all. be provided. This procedural requirement is not reflected on.the implementing form. The preliminary reportability
. recommendation n)t being specified on the form, may be the reason it has on occasion oeen provided late or notiat all. The licensee; indicated that these aspects of the' procedure-will be' reviewed for
.
-incorporation into the next. revision of the procedur '
' Procedure NE0 2.25 was initially issued as:a method of evaluating-
.potentially reportable items in June 1987. To improve its effective-
. ness, it was revised in October 1988. .In JuneJ1990, the procedure was again revised-to reference NEC 2.29 for JCO's .(Justification for
' Continued Operation) and to clarify the time constraints for completing evaluations. Major changes incorporated in this. latest . revision
-
include: Operability Determination Instructions; Clarification of responsibilities of individuals to promptly initiate an evaluation when warranted; clarifications of the need for reduced transit time between parties, places time constraints upon the NUp0C Director for 1 final determinations of the operability /reportability issue and strengthens requirements for timely evaluation i
l s; u
, ..
.
i-l The team concluded that procedures have been provided to assure that potentially reportable conditions identified both at the sites or by other means_.are evaluated and reported as required. The.reportability determination procedure has been revised several tires to' improve its effectiveness particularly in the area of timely completion of evaluations. Further improvements to the procedure are being considered to revise the implementing forms to reflect procedural requirement i 3.2 Training The-training provided to NU personnel describing their role in the reporting process was reviewed to verify that training has been provided describing company policies and more specifically the irplementation of Nuclear Engineering and Operations Procedure NE0 2.25, Operability and Reportability Determinations (10 CFR 50.72, 10 CFR 50.73, and 10 CFR 50.9).
The licensee has provided a Nuclear Engineering and Operations ;
Procedure NE0 2.26, Departmental Training, which establishes the T
training requirements for. Nuclear Engineering and Operations Group 1 personnel. This procedure requires that supervisors of personnel who i perform quality activities are responsible for ensuring that these ;
personnel are properly qualified. Among the training specified is-procedural training. The training records for two groups.were
..
!
'
-selected by the NRC inspector at random to-determine if these groups ;
Lhad received training in procedure NEO 2.25. The groups selected . j were the' Safety Analysis Group in the Engineering Department. and the Generation Electrical Engineering Group in the Generation Engineering j
and Design Department. The training records required-by procedure NEO 2.26, were provided and showed that both groups had received ^ !
training in' procedure NE0 2.25, i
<
y .
_
.. Additional instructions are provided to licensee personnel-in the !
Technical Staff and-Management Continuing Training Program This !
was verified to include training'in reportability requirements. The l lesson plan associated with reportability requirements training was; a reviewed and found to describe: why the training was provided, what- !
,
the reportability requirements are, the NU reportability philosophy, !
the process for determining reportability and operability, and the policies and procedures which have-been established to implement reporting. The lesson plan clearly identified the companies policy -I
' for timeliness, conservatism and consistency in reporting. The procedures associated with determining reportability, particularly U
NE0 2.25 were emphasized in the training. "Further formal training is .
anticipated to be conducted when a new reporting guidance document is '
approve <
.
~
~
,
j
-
.
In addition to formal. training dealing with reportability requirements, !
several memo's-have been issued by management to stress the importance of timeliness in the completion of reportability determination Discussions with various personnel that received this training confirmed-the increased emphasis which has been placed on reportability/cperability determinations, l
i The team concluded adequate reportability training is being provided and also that management has stressed the importance of timeliness Lin the completion of reportability determination .3 Audits _ -
In November of 1989, licensee management requested from Quality
. Services.that a special audit on NE0 2.25, Identification and Imple- l
. mentation of NRC Reporting Requirements, be . performed to determine i timeliness of evaluations performed compared with the timeliness ,
specified in the procedure. The request for this audit reflected- 1 managements increased interest in timely reporting of issues to:the . '
.NR The' audit reviewed eleven Reportability Evaluated Forms (REF's) ,
generated.during early 1989. Four of the eleven REF's audited were '
. .
'found not to be completed within the time constraints of the procedur "
Overall the audit findings indicated that.some time limits had been
' '
Lexceeded and that the. procedure needed to be clarified to prevent i this from-happening in the future, . This Inspection Team's review of i REF's generated during essentially the same time frame agreed with ;
the audit findings. The audits findings could have been more specific 1
. in identifying: procedural weaknesses, such as the, Shall vs. Should ;j differences which existed between the body of the procedure u d the '
REF form which-implements the procedure. -Likewise the number of- !
'
Linstances in which procedural non-adherence was identified, particularly .i in the preparation of required preliminary recommendations, was not !
clearly identified in the audit report. .The results of the NRC team's !
review was discussed in detail ~with the lead auditor who indicated ;
that although the. specific procedural weaknesses and examples of !
procedural non adherence identified by the NRC team were not clearly- !
identified in the audit report, they were discussed in detail during the exit;for the audi ,
The team felt that the audit was a good initiative on the part of 1 management, that it was thorough and comprehensive, and that existing . !
problems were noted. .However, the audit would have been more beneficia tif the findings which were stated to have been presented at the: audit exit were identified in the audit report'to management. Nevertheless, ;
E procedural changes were made as a result of the.- audit and significant i improvements were noted in the REF's completed more recentl <
Q +- .
, .
. .
8'
.
s 3.4 Review of-Reporting Evaluation Forms b The team reviewed 65 reporting evaluations, as lined in Attachment A, including' supporting documentation, PIR's, LER's and licensee
- correspondence. Specifically, reportability evaluation forms were reviewed for completeness and timeliness, verifying that the guidelines provided in the Operability and Reportability Determinations Procedure, NE0 2.25 were being followe Emphasis was placed on the timeliness of managerial reviews and the use of preliminary reportability/ - ,
k operability recommendations when the time limits could not be met.
P 'The; inspectors also evaluated the reportability/coerability determina- .
tions made to ensure that they conformed with cucrent NRC guidanc [
s
" In. reviewing the reportability evaluations, the Inspectors compared !
the tirieliness ar.J quality of the evaluations initiated in 1989 with those initiated in 1990 to determine if increased management attention :
and an improved _ procedure have had an impact on the evaluation progra The inspectors noted that the evaluations performed in 1990, especially under revision two of NE0 2.25, were more thorough and usually met 4 y the time requirements with a few exceptions, in comparison to the evaluations performed in 1989'- Withstanding the evaluations discussed-
.
beiow,-the inspectors noted that implementation of Revision 2:of NE0 2.25 and the-increased management awareness in regards to timely reporting, has had a positive impact on the timeliness and quality of
..
the evaluation . Reportability Evaluations with Significant
"
Timeliness Deficiencies
~REF 89-37 Millstone Unit 1 CU-2A Failure Due to Full Instrument Air Pressure This evaluation was initiated on February 7,1989, and reviewed by the~ originators supervisor on February 13, 1989. Six months J
later, on August 21, 1989, the Generation Facilities Licensing .,"
Manager received this evaluation for-revie Eventually, in October, 1989, this issue was evaluated as not reportable and the file was closed. The inspectors were concerned with'the six month gap (February-August,1989). During this period, the-evaluation was apparently'not being reviewed. .No action was:
being taken to' track down the evaluation to expedite the revie The licensee investigated this breakdown in the review and-- .
'
tracking process and determined.that the reportability evaluation
'
.
was lost in the in-basket of an employee who had left the compan .
The licensee recognized that the reportability evaluation program !
-was. deficient in tracking this issue and that further emphasis on - tracking reportability evaluations' was needed. To prevent
"
such a problem from reoccurring, the licensee'has conducted training,to educate personnel on their responsibilities in i processing reportability evaluations to ensure that the evalua-tions are properly turned-over to different entities involved in
,
i I .
.
. -
, .
- .
9 !
>
,
<
+ the review process. . Based on the team's review of reportability
_
evaluation's initiated in 1Y90, fewer timeliness deficiencies
-
y were.noted, indicating that the enhanced training on the
~
l reportability evaluation p'.ocess-has had a positive impact on (
the timeliness of evaluation l REF-90-43 Haddam Neck - Reactor Coolant System Hot and Cold Leg Isolation Valve Operability:
This issue was first documented and dispositioned for further repo'rtability. evaluation in a Plant Incident Report (PIR), dated June 7, 1990. The reportability evaluation was not initiated until JulyJ 10,1990, more than a month later. The team questioned why a reportability evaluation was not initiated when the deter-mination was made in the _ PIR that further . evaluation was necessar The licensee noted this deficiency, surmising-that further i guidance should be provided in the PIR to ensure that entry into .
. procedure NEO 2.25 is initiated promptly after its been identified '
.that further evaluation is necessary.
'
3.412 Technical Adequacy of Operability /Reportability Determinations REF-90-45 Millstone Unit 2 Reactor Building Closed Cooling Water Heat Erchanger Anchor Bolting Failure
.-
Reportability evaluation form (REF) 90-45'was -initiated on July 18, 1990,.to initiate further review of a deficiency previously identified with the anchor bolts-on the reactor building closed cooling water (RBCCW) heat exchanger The
. anchor' bolt deficiency was identified by the plant staff'during inspections completed during the 1989 refueling o~utage and was dispositioned .in plant-incident report- (PIR) 89-17, dated _ _ _ !
February 22,'1990. Inspections.during the'1989 outage' identified corrosion on anchor boltsifor the "C" RBCCW heat exchangers, and ,
repairs were completed for all three RBCCW heat exchangers during
.the 1989 outag The REF addresses two issues that apparently were not completely evaluated at the time'the-PIR was dispositioned: -(1) effects of seismic loads; and, (ii) other examples of supports with corrosion similar-to that on RBCCW heat _exchangers. These issues.are discussed in detail in Attachment 2 of-this repor Reportability Determination
-
The inspector reviewed the bases for the licensee's determination-
that the RBCCW anchorage problem was not repe 'able. The reportability determination was made on February 24, 1989, based l on the observation that the "C" heat exchanger had remained l functional in spite of the anchorage proble l
q j
'.j . s c .
-
l l
- ' The conclusion was supported by the calculation results completed by March 1, 1989, and summarized in the March 29, 1989, mem ..d Although not documented at that time, the engineering personnel interviewed stated an operability assessment, including seismic considerations, was used for a reportability determination in 1989. The operability assessment was documented in the ",
September 11, 1990 memorandum in response.to REF 90-4 i The operability assessment concluded that the RBCCW heat exchangers )
r and-associated piping would have remained operable during a design 1 h
'
basis earthquake (DBE), although design allowable. load restrictions i x would not necessarily be satisfie This conclusion was based ,j on engineering ' judgement and included .the following considerations:
piping systems are flexible under seismic loadings; the degraded bolts still' had some load carrying capability; and 'a preliminary !
analysis with degraded anchorage showed heat exchanger stability with_ margins ten to twenty percent below the design allowable limit '
The-licensee concluded that a. detailed coupled-model analysis would demonstrate.that allowable loads'would be exceeded, but *
- the system pressure boundary would remain intact and operabl ,
'The licensee-decided not to expend the resources to perform the more complex analysis since the modifications had been completed to correct: the deficiencie ,
-
These sections _ of the-rules require the reporting of events that !
result in'the plant being seriously degraded or in an unanalyzed t co.ndition that significantly compromises plant safety,'or 3 conditions ~where'a single cause results in multiple trains to be "
inoperable. The reporting guidance of.NUREG 1022 allows the use-of engineering judgement to determine whether_an unanalyzed .
'l'
condition exists. The' licensee concluded, based on analyses and engineering judgement,_that the RBCCW' system in the as-found ,
condition was operable for normal operational loads'and would a remain functional for design basis conditions such that plant safety was -not significantly compromised. Thus,-the condition was not' reportable. - The inspector did not identify any inadequacies in the licensee's conclusions.-
4.0. Exit Meeting The inspectors met with licensee corporate personnel at the conclusion of the inspection on September 28,.1990 the corporate office. The inspectors summarized the scope of the inspection and the inspection findings at that' tim During this inspection, no written material was provided to the licensee, ,
>
l w ,n .
T y, '. l a
./ i _11* +
.t g[f( 1 li! ;' < -
]
e
,
-
,
j f:
o
,-
W> ,
,
- ATTACHMENT 1
1
[ ,
_'D0CUMENTS REVIEWED .
W ie ,
-REF# PLANT SUBJECT [
>
~ +
b?' ~ 88-121 MP1 Possible Inadequate NPSH for LPCI Pumps h dueLto a Low Value (5 psig)_ of Containment '
> -
Spray Interlock 4
j
'
89 )9i2
.MP3" - Undetectable Failures of Rosemount Transmitters'
u , .
~
C l89-30 C PIR89-99: Fire'DamperDesign/ Inst $11ationProblems- 3
%> .
.. 'i l89-33; MP Nonconforming Stud Material
,
89-36 MP1 CRD System Leakage During LOCA j h ';-89 L37 MP CV-2A Solenoid Valve Failure Due To' Full Instr.
(l3 s
<
- Air Pressure-
'-
+
->
a
.. . .. .
!
,189-38 ,MP3i SBO Containment Responses-
'
--;
d
>
, -- . . - . .. . .
J
, < 989-391 <
-MP2- : SB0_ Containment-Responses; 'j m,.
- . .
u-89-40A MPSi C&D Model ARRJBattery Char'gers
<89-41;
. >
.CY :: Molded Case' CB'S; Type i"FB'F d
. . > . . .
Mi 8'
.
"
"89-42: '
- C Y- .-
Motor Cooler sCheck Valve Problems'
n~
'
, .. . .. .. .
.. .A-y (89-43- .MP21 2-SW-3;2Af(SW;To TBCCW Header, Isolation) Instr. Air; 1 V SupplyJcheck Valve'
-
,
'
or
,
(89-44? , LCY 480V. Load-Center-125V-DCcControl-. Power': Problems
,+ . . .m ,
'
-I' -
V59-I45 MP , NUSCO QSD' Audit:.A60496Lof:PDCR 2-30-8 ,
4 , 789-461 : CY? Cicle<15 Failed Fuel
-
-
h CY' Non-Detectable Failure of Thermal-0verload-~
s 189247? Li V Re 1 ays lfo r., MOV ' s '
n%;
, ,
.
M 1,' (9'-01 0 ,MPSL Limitorque.Part-21 on?DC Motors l;i M < :CY;
'
i
?dt" ..
.
.
,. ,
Ai -
. .
. .
.
- 90-02-
.
. MPS .- -Limitorque.Part 21 on SMB 00/000 Torque ~
i C Switches !
'
190-03 i MP3_ MCC/RCA A/C Units Inoperable following LNP y
<
J l
r q ,
I
f ; L i h, ,, ' 1
,
'
J 4' p ;;
,
.. .
, -
+w-. .s- .,
^ 'Attachmentil',
. . ..
2 4 cp
-
-
'
s
+
n
'
1 f i.- y;W -DOCUMENTS REVIEWED .
,
..
.-;
f,, . ..REF#:- PLANT- SUBJECT 4 S90-04' 'CYl Service Water FlowlThrough Ad'ms Filter
a
,
H 90-0 . C Y.- "B" EDG Service Water Flow Deficiency
'
I <
- 90-06 C ' Service Water Seismic Qualfication-Spray and. Flooding -
<
,; L; i';;g #
l90-08- CY- Feedwater Regulation Bypass Check Valve ~ Leakage'
q l
W ;90-10: CY' ' Bus-Failure Results In Loss Of 2 SW Pumps During Normal;0peration j
.. .
. . .
a 7 190-13 MP EEQ-RCS. Narrow Range ~RTD's .[
m 90-14 MP1 GE Auxiliary Contact Adder Blocks ..
- .90-16: MP2- Pressurizer Cooldown, Rate o
'
@ >
>
,
l', .90-30' .CY ;AFW Pumps - NPSH Requirements j
, . .
,
,
'.90-31 ; . ICY.- , Containment Penetrations P-23A and.72A -
,
w M Design Deficiencies- ,i
..
'
< '
90-32 : MP1- Wide 1 Range' Level Indication not EQ ;;
l
-90-33- .CY _ Charging Pump. Suction Vent SOV- j
$ 90-34: ~CY- -PIR-90-106'Fuseblocks Not_Seismicly-Qual.ified'
Y > 90-35 MP3 Deficiencies in. Task Lighting _&: Equipment-
- Accessibility inisupport.of/ Safe-Shutdown:
[
t . >
>4 B %. ; Following'aiFire '
_. .
.
' .
o :'90-36i ,
, CYf ~ CAR Fan-Damper Solenoid Air. Supply: Pressure Regulators ,
.
a
. , T90-37i ' CY- Teledyne MOV's - ' Incorrect 0-Ring. Material _
-
yx- ,
y y? 990138' :CY Teledyne.. Valve Actuator..(MOV)l Motor Wire Insulation n
90-39 MR1: Nitrogen Compressor' System' ,
Mi U '
- '9051
- LCYT MCC 5.0versized Feeder Breaker'
'
,,
.
.90-42: MPS/CY_ _EQ of KS-500 Silicone Rubber Insulated Cable ~l
'
O ci h
1 90-43; CY RCS Hot & Cold Leg Isolation Valve Operability j
,
a l q
'i e
'
4 2
.. -
,
tj. y ,
.:q +,
...-_
'
-Attachment 1:' , 3'
. .
-
DOCUMENTS ~ REVIEWED N REF#J -PLANT- SUBJE_CT 90-44; :MP1 Seismic Mounting of Diesel Control Panel L'90-45- MP2' RBCCW: Heat Exchanger Anchor Bolting Failure E90-d6 MP3 H2 Monitors and Recombiner Building Ventilation
- -
-
.
.
'. 90-47 L .MP3 ECCS Evaluation ~Model
_,.
. - . . - -
f
- i ' ' ' '90-48 ^MP3 . Fuel _Bui_1 ding Exhaust Filter System
-
!
190-49 MP3 Service Water. System _- Required Number'of
,M : Operating Pumps
~
u 190-50s .. MP3 -Seismic-Qualification of Equipment 3 ,
CCE*EIA,B &-3 CCI*EIA, ' '
,
,, , -
e -]
'
c90-51h ,
MP2'- Swing Battery Charger Power Supply 90-52 MP2' Incorrect Load Center Tap 4 Positions- 9
' .
.
.
.'
- 90-53l CY~ , ANSI B16.34 Pressure & Temperature
,
Ratings.for Valves :1
~
J j
'
90-54- .CY - Operability ofrSW-MOV-3&4- During LOCA-Recirculation- ,
~90-55 ;CY 1FW-MOV-13 Contractor Coil; Operability H Li
,
, 290-56: C AFW:0perability-Loss of Control: Air L90-57; ?
CY- ~AFW Operability-Operator' Action-
-90-59 MP LPCI! Heat Exchanger Flow' Rate -
t
,
-_1
'90-60- MP 'LPCI Flow Rate Instrumentation Accuracy ~
y ,
l 90-61 MP1- LPCI Flow Through Heat Exchanger
>
>
d
.c
"
j90-62i
.
,9 ,
.
,
MP1- -'LPCI Heat Exchanger, Flow' Rate o
.q y<0 :90-63 MP1; lECCS: Pump NPSH Concerns Flow-R' ate
'
Sl
.90-64' 'MP1' ECCSLPump~NPSH Concerns - Containment Spray Interlock I
- 90-65~- MP1 Make-up Water Cross-tie to LPCI
11 ,
'$ ,
. . . . . . . . . _ .
_
.:
.-,-- ,,
.
' Attachment 1 4
_
DOCUMENTS REVIEWED
'~
REF# PLANT SUBJECT 90-66' MP1 ECCS Pump NPSH Concerns-Supression Pool Temperature h 90-67 MP1 Loss of Feedwater Flow Analysis 90-68 MP1- CRD Pump Seal Cross Connection
{
-
_
90-69 MP1 Control Rod Drive Accumulator Pressure Alarm
__
-.
h
-
E
-
-
-
-
_
T
_
- . . . , .
b .l
- - ,
.
.
'
,
ATTACHMENT 2-ANCHOR BOLT DEFICIENCY (REF-90-45)
PIR 89-17 Deficiency and Resolution '
The deficiency was originally identified during the 1989 refueling outage when workers noted a loose anchor bolt on a base plate for the "C" RBCCW heat >
-exchanger.-_The deficiency was documented in PIR 89-1 Each RBCCW heat-
. exchanger has.four anchor bolts, two of the four anchor bolts on the "C" heat exchanger were found to be corroded to the point of failure, The two bolt ' failed at.the joint between the base plate and concrete pad with the nut separated'from_.the lower half of the anchor, Actions were taken during the--
outage under -plant design change evaluation-(PDCE) MP2-89-023 to repair the anchor bolts on all three heat exchangers, Nonconformance report 289-056 was issued to document the "C" heat exchanger anchor problem and to address the-question of corrosion of anchor bolts generically,
~
Event Cause Analysis Licensee'inve:tigation under PIR 89-17 determined that the anchor bolt corrosion was caus~ed by salt water that infiltrated the ~ joint between the base ;
plate and the-concrete pad. _The anchor-bolts were found to be severely- '
'
corroded-(necked down) from the original 1 inch nominal diameter to about 1/16 inch diameter, or less. The corrosion occurred over about 1 inch or so of the length of the anchor and only at the interface between the base plate and the-concrete (grout) anchor pad,
'
,
LThe corrosion occurred slowly over the fifteen years that the heat exchangers
~had been.-in service. . ~ The base plates were wetted 'by, either leaks in service water piping or during periodic maintenance on the' heat exchangers, such as when the end bells are opened to clean or repair tubes, The corrosion-occurs due-to'the' base plate design configuration which ham ~pers quick'or complete drying of the anchor once the base plate was submerged'or sprayed with sea water,
.
-PDCE MP2-89-023 The action taken during the.1989 outage to resolvethe RBCCW anchor bolt
. deficiency was to repair the anchors for all three heat-exchangers under PDC MP2-89-02 ,'
The spare anchors on'the RBCCW HX base plates, located just outboard of the '!
' failed ones, were also subjected to..the same wetting' conditions as the in' '
'
service anchors, Licensee inspection of_the spaie anchor bolts'for each heat .
exchanger showed no corrosion. ~ Modifications to v heat exchanger base !
plates were performed and the base plates were re-anchored using the spare i anchor bolts. Also, the base plates were welded to-the underlying embedment plate 'c ;
_
O J, p . p.x,
.
Attachment'2 2
-An epoxy sealant was installed around the base plates (in the joint between .
)
the base plate and the concrete pad) to prevent infiltration of standing or ,-!
sprayed sea water and thereby precluding further corrosion. A program to-inspect the base plates periodically was initie.ted to ensure the coating
.
i remains intact.-
Engineering Evaluation i The licensee provided the following memoranda to document. engineering evaluations of the failed RBCCW anchors; Calculation 86-007-1074GP, dated March 1, 1989; engineering memorandum'PSE-SA-89-72, dated March 29, 1989; and engineering-memorandum PSE-SA-90-177,. dated September 11, 1990. The inspector interviewed members of the NUSCO-engineering group responsible for the calculations ;
regarding RBCCW anchor integrity and the _ operability assessments completed for !
PIR 89-17 and REF 90-4 I
!
Calculation 86-007-1074GP provided a structural evaluation of the RBCCW heat exchangers in the-as-found conditions. The heat exchangers function as an analytical; anchor for the RBCCW and service water piping. .The evaluation j determined whether the-loss of. anchorage affected the ability of the heat i exchangers .to function as an anchor- for the piping (i.e. , rigidity), or if the - !
loss of_ anchorage would invalidate the stability assumptions against overturning used in the original desig ,
The "C" RBCCW heat exchanger had two of four anchor bolts completely corrodeci through.' Site engineers stated that when the anchors for the "A" and "B" heat exchangers were replaced under PDCR MP2-89-023, one other bolt on each was found to be corroded through also, The calculation assumed a total loss of :
anchorage on-all three heat exchangers to conservatively bound the field condition j
1-A simple hand calculation was used employing conservative _ methods to apply
- RBCCW and service water piping nozzle reactions statically to the heat i
.
exchanger nozzles. The heat exchangers are ~QA,; seismic category I equipment j
j-and'are designed for thermal, deadweight, pressure and seismic SSE loads. The j calculation did not consider seismic. loadings for the rigidity' and stability ;
T evaluations, since the: plant had not experienced an operational basis i earthquake even '
.
The calculation showed that, even with a complete . loss of anchorage, the heat exchangers~will function as designed for pressure, deadweight-'and thermal hydraulic load- The RBCCW and service water-piping;Lloads' remained restrained
.
by the heat.exchangers, by. the frictional' shear of thelheat exchanger base -
plates and by the rotational resistance provided by the large _ moment of
.
inertia provided by-the-heat exchangers. .The factors of-safety against
. overturning and sliding were 3.63 and 3.57, respectively. ~Thus, the loss'of-anchorage did not affect the ability o.f the heat exchangers to function as an
~
anchor-for the piping systems. The inspector's review of the calculation-identified no inadequacies in the methods, input assumptions and result ;
i
[4, ~
( >
u
!
Attachment 2- 3
.
i
' '
program to Evaluate Seismic Category I Supports '
During interviews with site engineering personnel, the inspector noted the licensee _had previously identified the potential for anchor bolt corrosion and the need t3 address the concern generically, particularly in light of the experience.with the RBCCW heat exchangers. The corrosion mechanism and the location of bolt wastage allowed significant loss of n.aterial with attendant
,
- ' ;
, loss of margin to the' bolt design strength, with few obvious external
.
-
indications of corrosion or degradation. Indirect evidence of underlying 1
. corrosion included cracked grout or rust weapage on or around the support base
. plate '
<
Surface visual inspections and bolt torquing techniques w$e deemed inadequate for detecting:significant hidden corrosion. Thus, a program to systematically !
d1sassemble.and inspect the areas under the support base plates was considered _ [
n_ecessary to assure corrosion was identified and corrected. Site engineering- !
began to_ develop an_ inspection program following the 1989 outage and inspections were in? progress during the 1990 refueling outage'to address the issu The-licensee presented for NRC review a copy of draft procedure EN.21216, ;
'
Inspection /of Supports-Exposed'to Water Intrusion. The procedure and i Inspections were being .'mplemented during the present. outage to identify and :
correct support-anchor _ deficiencies of the type noted on the RBCCW heat !
exchangers. JThe licensee plans to inspect hangers in phases over-the course-
-
of:several outage Thelinspector.' reviewed the draft procedure:and noted it containedcinstructions-for the inspection, protection and. replacement _of seismic hangers and anchor -$
bolts exposed to' sea water. ' The' procedure contained a list of supports that .;
would be' evaluated.: including hangers on the RBCCW heat exchanger drain and ;
relief ~ valve lines, and_those;in the' service witer pipe-tunnel, the intake i structure, and the diesel generator. areas. The list was developed based 1on a' <
review by plantiengineering--personnel of areas most susceptible to the type of ;
corrosion found on the RBCCW heat exchangers. The' licensee' stated.that the :
evaluation would be. done_ by physically disassethbling the supports -and .lif ting
- the'b'as_e plates to allow direct visualLinspectionz of the underlying anchor 'The' procedure a~1so' contained instructions to use ultrasonic (UT) inspection
-
techniques as_necessary to evaluate.the condition--of the anchor bolts, and to
- develop criteriaLfor further use of the UT inspections for futurezsupport: .
N ' evaluation i
= Work was 1n progress during the week of September 28 to; inspect an initial l
,y ? list ofz7-supports, including 405561, 491023, 427714, 60027, 49108-2,'527045-A' ,
y land 527063. The initial supports 5 were chosen to obtain an estimate of the'
'
extent of anchor bolt-degradation. The selection criteria used included-hangers.on seismic Category 1-components _known to be subject to periodic l wetting; hangers in'the service water pipe tunnel; hangers with rust on or . ,
around theibase plates; and, one hanger in the. susceptible area'(for wetting)
which showed no external signs of degradatio .
i
{
94 ;;i'
,
s .
.
, ;g::
D E Attachment'2- 4-n 1
'Th'e hangers (inspected aslof: October 1 showed :' varying degrees of '.orrosion,
-which were documented using;nonconformance. reports.and will be dispositioned ._
by;NUSC0' engineerin Preliminary findings were that' base piate operability
'
-
,
E would not be compromis'ed and design. margins would be maintained, in spite of
'O :some obvious' corrosion.and degradatio This_ itenilis open pending further ' review of: documentation available at the-
, ,
site'regarding the 1989 RBCCW bolt deficiencies; documentation-of the seismic
>,
- considerations.-used-in the engineering evaluation for the-RBCCW'operabilityr I?
'
. assessment.in?l989,:and .the actions taken since the 1989 outage and:i ,
, progress during' the present-' outage to. address the potential' support ._
-!
,
' degradations. This item will 'be.followed as'part of-the routine resident
.
inspections: documented _in report 50-336/90-22, 1
a l~
]. s y
l
.-
$ f
'
[ ', d .,
.,
,
1 + ,
ll '
l l
l 15 s .
~ >: 4 ,
,
.,
-
, i h
J~,
a
,,
i c