ML20245A678

From kanterella
Jump to navigation Jump to search
Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement
ML20245A678
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/07/1989
From: Chaudhary S, Mcbrearty R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20245A656 List:
References
50-245-89-11, GL-88-01, GL-88-1, NUDOCS 8906220116
Download: ML20245A678 (8)


See also: IR 05000245/1989011

Text

I

F ,3

-

.

p:

-

'

.

'U.'S.' NUCLEAR _ REGULATORY COMMISSION

REGION I-

Report No. 50-245/89-11

Docket No. 50-245'

License No. DPR-21

Category i

Licensee: Northeast Nuclear Energy Company ~

P. O. Box 270

Hartford, Connecticut 06141-0270

. Facility'Name: . Millstone Nuclear Power Station, Unit 1_

Inspection At: Waterford, Connecticut

Inspection Conducted: May 1-5, 1989

Inspectors: hh h*

/,// /E9

R. A. McBrearty, Reactd Engineer

date

C[da[te7 Sf

Approved by:

42&f

/

S. K. Chauanar,v, Cinef, Materials and

Processess Section, EB, DRS

Inspection ' Summa ry: Routine Unannounced Inspection on May 1-5, 1989

(Report No. 50-245/89-11)

Areas Inspected: The . inspection consisted of observations, review of data,

licensee.'s response to Generic Letter 88-01, NDE procedures, engineering

-support, QA involvement, and personnel qualification / certification records in

the area of _ inservice inspection.

Results: The inspector concluded that the licensee's activities complied with

applicable requirements. The licensee's response to GL 88-01 was timely, and

addressed the areas required by the Generic Letter.

g6220116 890609

eo=oso00243[

PNU

g

a

_ _ _ _ _ _ _ _ _ . _ . _ _ _ _ _ _ _ . _ _ _ _ _ . = . _ _ _ _ . _ _ . _ _ _ _ _

_ . _ _ . _ .

. . . _ . _ __

_ _ _ _ _ _ _ _ . _ _

__

_ - _ - - _ _ _ _ _ .

_

__

_ _ _ _ - _ - _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ . _ _ - _ _ _ _ -

_ _ _ _ _ _ _ _ - _ _ = _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ _ _ _

.

~

.

n

.

Details

1.0 Persons Contacted

Northeast Nuclear Energy Company

L

  • T. Davis, Inservice Inspection Technician
  • J. Leason, Inservice Inspection Coordinator

S. Sikorski, NDE Level III

  • J. Stetz, Unit i Superintendent
  • R. Voger, Engineering Supervisor
  • R. West, Inservice Inspection Coordinator

The'Hartfor'd Steam Boiler Inspection and Insurance Company

R. Zoner, ANI/ANII

U. S. Nuclear Regulatory Commission

  • L. Kolonauski, Resident Inspector
  • Denotes those present at the exit meeting.

2.0 Scope of Inspection

Section XI, Rules for Inservice Inspection of Nuclear Power Plant

Components, of the ASME Boiler and Pressure Vessel Code establishes rules

for the examination, testing and inspection of components and systems in

a nuclear power plant.Section XI mandates that the plant owner develop

,

a program which will demonstrate conformance to Code requirements, and

that the licensee perform inservice inspections (ISI) to comply with

those requirements and prop, ram.

Ultrasonic examination for the detection

of intergranular stress corrosion cracking (IGSCC) in stainless steel

piping systems in BWR plants is mandated by an augmented examination

progrcm based on NUREG-0313, Revision 2, and Generic Letter 88-01.

The following areas were selected for inspection:

Implementation of nondestructive examination (NDE) procedures

Observations of work in progress

i

Persor.nel . qualification /certificatica records

Licensee response to Generic Letter 88-01

NDE data

i

w

- - _ _ - -

_ _ - .

_

-

- _

_ _ _ _ _ _ _ _ - _ _ _ _ _

_ _ _ - - _ _ _ - _ _ - _ - - - . _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ _

Q

-

+

,

.

.

y

a;

.

)'

-3

,

Engineering support of ISI

,

C

QA involvement in.ISI

3.0 Review of NDE Implementing Procedures (73052)

Inservice inspection at Millstone Unit 1 is routinely performed in

accordance_with the licensee's procedures. Vendor NDE technicians are

provided training on'each procedure which they will be required to

implement; and,.in' addition, each individual is required to pass a

practical examination administered by.the licensee prior to performing

examinations at the site.

.During the. current refueling outage the work _ load was divided among four.

vendors such that IGSCC examinations were performed by General-Electric

Company and EBASCO,. reactor vessel nozzle examinations were performed by

Southwest Research Institute, and reactor vessel welds (flange ligament

areas, shell to flange, circumferential and longitudinal welds) were

examined by TTI, a Swedish company, and Westinghouse /Dynacon using UDRPS.

The following vendor procedures were selected for inspection to ascertain

compliance with ASME Code and regulatory requirements and' technical

adequacy for their intended use:

SWRI-NDT-600-11, Revision 47, " Manual Ultrasonic Examination of

  • -

Vessel-to-Nozzle Inner Radius Section"

,

SWRI-NDT-706-6, Revision 33, " Mechanized Ultrasonic Outside Surface

Examination of Ferritic Vessels Greater Than 2.0 Inches In Thickness"

Westinghouse NSD/Dynacon Document #ITI-ISI-89-1/89-T-1040,

" Examination Plan For Millstone, Unit .1"

The above listed procedures were reviewed and approved by the licensee

and were incorporated into the licensee's program for use at Millstone.

No violations were identified.

Conclusion

The vendor procedures complied with applicable code and regulatory

requirements and were technically adeqtate for their intended use.

Additionally, licensee control of the program is maintained by its

requirement for Level III review and approval of the procedures.

i

-

-

--

__ __ ____ _ _

.. .

.

4

,

4.0 Observations of Work in Progress (73753)

The video tapes of the visual examination of the "A"

and "C" core spray

spargers and the "A" supply piping, and the ultrasonic examination of RPV

stud No. S-2-57 were observed by the inspector to ascertain compliance

with code and regulatory requirements.

The visual examinations were performed by CTS Company personnel using

remote, underwater video cameras.

Examination results were reco.*ded on

video tape and are intended to serve as a permanent record of the

examinations.

The licensee will install all new RPV studs during the current outage and

the ultrasonic examinations are intended to comply with the preservice

inspection requirements of the ASME Boiler and Pressure Vessel Code,

Section XI.

These examinations.are performed by EBASCO, the licensee's

ISI vendor.

No violations were identified.

Conclusion

The video tapes representing the visual examination results were of

excellent quality and provided for an intelligible evaluation and disposi-

tion of examination results. Code and regulai.ory requirements were complied-

with regarding the examination area and the examination resolution, which

was adequate to display a 0.001 inch diameter wire.

The ultrasonic examination of RPV stud S2-57 complied with Code,

regulatory, and procedural requirements.

Indications resulting from

geometric reflectors were recorded as required by code, and the the

technicians showed a good understanding of the examination requirements

and the examination equipment. Additionally, the examination personnel

were certified to the proper level of avalification in accordance with

SNT-TC-1A, the governing document.

-5.0

Personnel Qualification / Certification . Records (73753)

Qualification / certification records of vendor NDE personnel were selected

for inspection to ascertain that those personnel were qualified to perform

their assigned duties.

Records uf G.E., SWRI and EBASCO NDE technicians

were included in the inspection sample and were examined with regard to

applicable SNT-TC-1A requirements, and EPRI training and certification for

the detection and sizing of intergranular stress corrosion cracking

(IGSCC).

No violations were identified.

i

,

_

-

-

'

.

5

l

,

1

l

1

Conclusion

Vendor inspection personnel at Millstone Unit I were certified to the

appropriate level of qualification in accordance with their employer's

program for the qualification and certification of NDE personnel.

Personnel who performed examinations for the detection of IGSCC were

listed on the latest EPRI registry of personnel qualified for the detec-

tion and sizing of IGSCC. The licensee verified the qualification of

l

vendor personnel prior to their performing work at Millstone.

Licensee

)

oversight of vendor performance was enhanced by its system which requires

i

its Level III to verify, by re-examination, reported indications.

This

was an additional evidence of licensee control of the ISI program.

6.0 Nondestructive Examination Data Review (73755)

Inservice inspection NDE data were selected for inspection to ascertain

that ASME Code and regulatory requirements were complied with regarding

recording of results, evaluation and disposition of findings, and

completeness of the data.

Data representing ultrasonic examination of

the following welds were selected for inspection.

CUAJ-5, RWCU system 8" diameter pipe to valve weld

CUAJ-1, RWCU system 8" diameter weldolet to pipe weld

CUAJ-4, RWCU system 8" diameter elbow to pipe weld

CUBJ-18, RWCU system 8" diameter pipe to penetration weld

CRDF-1-NZ, CRD system nozzle to cap weld

- CSAF-1-NZ/SE core spray system safe end to nozzle weld

CSAC-1-SE, core spray system safe end to nozzle weld

The above sample included welds in the IGSCC augmented program and welds

which were part of the Mechanical Stress Improvement Program (MSIP).

The

strrss improved welds were ultrasonically examined before and af ter applica-

tion of the trestment.

No significant changes were noted.

Indications

wh'ch were detected prior to the treatment were found to be unchanged after

th. applied treattent.

Si ,nificant indications which were detected in the reactor water cleanup

t

system were properly i ecorded. Unresolved indication and nonconformance

reports (UIR/NCR) were issued as appropriate.

______

h., . .

'

.

3-

.

, .,

.

s

The evaluation of' examination results obtained from weld CUAJ-5-

-identified a rejectable. condition indicative of IGSCC and the engineering

disposition required repair. The licensee chose to perform the repair

!

. using the weld overlay method, and the work was'in progress at the time

'l

the inspector. left the site.

Engineering' support was requested via the VIR and NCR. The evaluation,.

disposition and: corrective action provided by.the. Responsible Engineer

was, in each instance, appropriate to the reported condition, and was

technically adequate to return the component to an acceptable condition.

No_ violations were identified.

Conclusion

Inservice-inspection data confirm that associated examinations complied

with ISI program requirements.

Examination results were properly

recorded and the disposition'of those results was based on reexaminations,

data plots, and technically correct engineering evaluations.

s

The in progress weld' overlay repair complied with regulatory requirements

regarding-liquid penetrant examination and determination of.the ferrite

number to' assure the acceptability of the completed overlay.

The documentation associated with each weld contained the appropriate

information to assess the quality and acceptability of the weld, and

complied with' applicable code and regulatory requirements.

'7.0

Licensee Response to Generic' Letter (GL) 88-01

Intergranular stress corrosion cracking near weldments in BWR piping has

been occurring for almost 20 years.

Early cases were in relatively small-

diameter piping.

In early 1982, cracking was identified in large

diameter piping in a recirculation system of an operating BWR plant in.

this country.

Since then,. extensive inspection programs have been

-conducted in BWR piping. systems which have resulted in the detection.of

significant numbers of cracked weldments in almost all operating BWRs.

Substantia 1' efforts in resaarch and development by the BWR Owners Group

for IGSCC, related' work by vendors and consulting firms, and confirmatory

research sponsored by the NRC have permitted the development of revised

staff positions regarding the IGSCC problems.

The technical bases for these positions are detailed in NUREG-0313,

Revision 2, " Technical Report on Material Selection and Guidelines for

BWR Coolant Pressure Boundary Piping." NUREG-0313, Revision 2 describes

the technical ~ bases for the staff positions on materials, processes, and

primary coolant chemistry to minimize and control IGSCC problems.

Inspection schedules and inspection sample sizes are based on the

!

susceptibility of weldme.nts to initiation and propagation of IGSCC.

'

- = ____ _ __ -_ _ _-

$

-

,

L

-

j

s.*-

, , , ,

57

-

_.

Inspection schedules are' comparable to those specified in Section XI of

the ASME Boiler and Pressure vessel code in cases where the piping

material.is IGSCC resistant.

'Th'is. Generic Letter applies to all 'BWR piping made of austenitic

'

stainless steel that is four inches or larger in nominal diameter and

'contains reactor cnolant at a temperature above 200 F during power

. operation,:regardless of Code classification.

It.also applies to reactor vessel attachments and appurtenances such

as jet pump instrumentation penetration assemblies and head spray and

vent components.

Licensees are requested to respond to the GL within 180

. days of the receipt of the letter. The GL provides a list of specific

items which should'be included by licensees to constitute an acceptable

response to the GL.

The licensee's response to the GL dated July 27, 1988, was reviewed by

the inspector to ascertain that applicable systems were identified, welds

were categorized and inspection schedules were established in accordance

with Table-1:of NUREG-0313, Revision 2.

The licensee. responded to the GL within the allotted time, and the

response addressed the five areas listed by the Generic Letter.

The-licensee has applied the Mechanical Stress Improvement Process (MSIP)

to 22 nozzle safe-end welds with Inconel 182 weld butter. Those welds

that_were not ultrasonically examined to the upgraded 1985 EPRI NDE

'

Center Qualification Program were examined prior to the application of

MSIP. All 22 welds also were examined subsequent to the application of

MSIP.

In addition to the above, the licensee has installed an acoustic local

leak detection system on the X-168 Core Spray piping penetration (an

IGSCC Category G weld as defined by NUREG-0313, Revision.2). The system

will be used to collect. background noise level data during Cycle 13.

The decision for further use of the system will-be based on licensee

evaluation.of those data.

The licensee has completed a preimplementation test of hydrogen water

chemistry (HWC) and the results are being evaluated to determine whether

HWC will be implemented at Millstone Unit 1.

No violations were identified.

Conclusion

The licensee has responded to the GL within the allotted time and has

committed to meet the staff's position on IGSCC as defined by NUREG-0313,

Revision 2.

The installation on the X-16B Core Spray piping penetration

fulfills the licensee's commitment as stated ire their response to the GL,

and is a positive step to assure the integrity of the associated

-- . _ - - _

y:

..

+

E

E~

8

,.

l

Category G weld. The application of MSIP to 22 welds fulfills a second

licensee commitment stated in their response, and the post-MSIP ultrasonic

examination further assures the integrity of those welds.

8.0 Quality Assurance Involvement in ISI Activities (73051)

The licensee contracted Southwest Research Institute (SWRI) to perform

NDE during the 1989 refueling outage at Millstone Unit 1.

That vendor-

has not participated in activities at Millstone since the preservice

examinations were performed prior to the facility going operational.

Licensee Quality Assurance Audit No. A04040 was conducted on

November 1-3, 1988 at the SWRI facility at San Antonio, Texas to assess

the SWRI capability to perform NDE at Millstone, and to place SWRI on the

licensee's Approved Suppliers list.

The report of QA Audit No. A04040 was selected for inspection to

ascertain that SWRI was considered an approved supplier, and that the

audit was performed in accordance with the licensee's program.

The audit at San Antonio was performed by a qualified licensee auditor,

who examined the vendor's implementation of its QA Manual with respect to

10 CFR 50, Appendix B and ANSI N45.2. Audit Report No. A04040 documented

the audit results and the audit plan verified that the areas audited were

appropriate to make the determination regarding the SWRI capability as a

vendor of ISI services.

Surveillance of SWRI onsite activities was performed by a member of the

licensee's Nuclear Engineering and Operations staff, and it was verified

that NDE procedures were complied with, vendor personnel were qualified to

perform their assigned duties, and examination results were properly

documented.

No violations were identified.

Conclusion

Audit A04040 was performed in accordance with the licensee's program, and

the areas audited confirmed that SWRI was qualified as a vendor of ISI

services.

Licensee onsite surveillance further confirmed compliance with

applicable licensee, Code and regulatory requirements.

9,0 Exit Meeting

The inspector met with licensee representatives (denoted in paragraph 1)

at the conclusion of the inspection on May 5, 1989. The inspector

summarized the scope and findings of the inspection.

At no time during the inspection was written material provided by

the inspector to the licensee.

The licensee did not indicate that

proprietary information was involved within the scope of this inspection.

___

_