|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
Text
. m, ------
y w
,.
..?".
- .- ... ,
i e g .' .
,
l U.S. NUCLEAR REGULATORY COMMISSION REGION I-
'
Report N /89-08 Docket N '
~
License N DPR65'
. .
Licensee: Northeast. Nuclear Energy Company P.O. Box 270 Hartford, CT 06101-0270 :
!
Facility Name: Millstone Nuclear Power Station, Unit 2
~
I i
Inspection.At:-Waterford,-Connecticut l
Dates: March 24.through-May 4, 1989 I
' Inspectors: J. Raymond, Millstone Senior Resident Inspector
'
' ,
P.'J. Habighorst, Resident Inspector, Millstone 2 1
' Approved by: NO bb. %
E. C. McCabe, Chief, Reai: tor Projects Section 18 6Itc h I Da e
' Inspection Summary: 3/24/89-5/4/89 (Report 50-336/89-08)
' Areas Inspected: Routine NRC' resident inspection (205 regular. hours, 35 back-shift hours, and 7 deep backshift hours), of plant operations, outage activi-ties, surveillance, maintenance, previously identified items, plant Incident
_
Reports (PIRs), allegations, committee activities, and Licensee Event Reports (LERs).
l Results: No unsafe. conditions, violations, or deviations were identifie I Three previously identified items and two NRC Temporary Instructions (tis) were-losed. An unresolved item was identified concerning licensee disposition of steam generator mechanical tube plugs from heat lot NX-4523. Good test direc-
' tion was noted on the engineered safety feature integrated surveillance tes j 8906280133 890620 PDR ADOCK 05000336 ,
o PDC
_ __ _ _ _ i
_ _ _ _ _ _ _
.
. .
. ,
.
l b'
TABLE OF' CONTENTS PAGE 1.0 Persons Contacted.................................................... I 2. 0 S umma ry o f Fa c i l i ty Act i v i t i e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 3.0 Previously Identi fied Items (92702/92701) . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 3.1 (Closed) UNR 88-24-02, Untimely Compensation of the Control Room Card Reader (SEP5019)......................................... 1 3.2 (Closed) Temporary Instruction (TI) 2515/93, " Inspection for Verification of Quality Assurance of Olesel Generator Fuel 011".......................................................... 2 3.3 (Closed) Temporary Instruction (TI) 2515/101, " Loss of Decay Heat Removal (Generic Letter 88-17)".......................... 3 3.4 (Closed) UNR 89-05-06, Potentially Defective Steam Generator Tube Plugs.................................................... 5 3.5 (Closed) UNR 89-05-03, Justification for Continued Operation (JCO) for Gamma-Mr.trics (GM) Wide Range Nuclear Instrumentation....................... .......... ............ 7 4 . 0 Fa c i l i ty To u r s ( 717 0 7 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 5.0 Plant Operational Status Reviews (71707/81700/93702/71711)........... 9 5.1 Review of Plant Incident Reports (PIRs) . . . . . . . . . . . . . . . . . . . . . . . 9 5.2 Safety System Operability............................. ......... 9 5.3 Unintended Safety Injection Actuation........................... 10 5.4 Low Power Physics and Power Ascension Testing Discrepancies.. . .. 11 5.5 10 CFR 21 - Rosemount Transmitter Oil Leaks........... ......... 12 6.0 Allegation RI-88-A-40 on Reactor Trip Breakers (92701/61726)......... 12 7.0 Committee Activities (40500)......................................... 17 8.0 Licensee Event Reports ( LERs) (92700) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 9.0 Maintenance (62703).......... ....... .... ...... ................... 17 10.0 Surveillance Testing (61726)............................ ............. 17 11.0 Periodic Reports (92700)......... .............. .................... 18 12.0 Management Meetings (30703/30702).................................... 19 l
I
{
t ___ __
_ - - _ _ - - - - -
,.
--.-
,
h r- ,
. .
L . ,
, ,
U I DETAILS
'1.0 Persons Contacted Inspection findings were discussed periodically with the supervisory and management personnel identified belo S. Scace, Millstone Station Superintendent J. Keenan, Unit 2 Superintendent J. Riley, Unit 2 Maintenance Supervisor F. Dacimo, Unit 2 Engineering Supervisor J. Becker, Acting Unit 2 Instrument and Controls Supervisor J. Smith, Unit 2 Operations Supervisor The inspector also contacted other members of the Operations, Radiation Protection, Chemistry, Instrument and Control, Maintenance, Reactor Engi-neering, and Security Department "
2.0 Summary of Facility Activities At the start of the inspection period, Millstone 2 was in an extended re-fueling' outage. The outage extension was primarily due to repair of the low pressure turbine rotor (Inspection Report 50-336/89-05) and steam generator (SG) mechanical tube plugs (See Detail 3.4).
The unit was'taken critical on April 23, at 8:38 Low power physics testing and power ascension testing began (See Detail 5.4). At the end of the inspection period, the unit was at 55% powe .0 Previously Identified Items (92702/92701)
3.1 (Closed) UNR 88-24-02, Untimely Security Compensation for the Loss of the Control Room Card Reader At about 7:20 a.m., October 25, 1988, the Unit 2 reactor trippe The inspector responded and attempted to enter the control room but was locked out. An officer was not posted at the control room door until approximately 20 to 25 minutes after the initial even The inspectors met with licensee management to discuss control room access. Licensee management stated that they had not taken action to j restore control room access sooner because they had concluded that
[ the onshift response was appropriate and adequate. This assessment was based on a short discussion over the phone with the Shift Super-visor by a manager outside the area. Other feedback after the event supported this position. The inspectors noted the licensee comments and emphasized the need for both licensee managers and NRC inspectors to have access to the control room. The licensee agreed to further
. .. ,
.. -. - - - - _ .
.-
.
... .
.. .,
.,
1 assess the event and consider corrective actions. The licensee'docu-E mented their review in a November 4,1988 memorandum (MP-SEC88-96) .
- .
from the Security. Supervisor ':o the Station Services Superintenden The licensee . stated that enhancements will be made to ensure rapid .
access to the control room when the card reader is inoperable. Modi--
'
fications were also planned and partially completed to increase the reliability of the security computers. . Modifications to. card readers at the entrances to the control room complex were completed.and should preclude a recurrence of the problem encountered on October 2 Inspector review found these licensee actions responsive. This item is close .2 (Closed) Temporary Instruction (TI) 2515/93, "Inspectisn for Verification of Quality Assurance of Diesel Generator Fuel Oil" TI 2515/93 addresses whether the licensee has included diesel gener-
.
'
ator fuel in their quality assurance progra Revision II to the licensee's Quality Assurance Topical Report (NUCAP), Appendix A, ,
. states: '
l-The following. systems, structures and components of a nuclear power plant, including their foundations-and supports, are de-signated as Category I. 'The pertinent quality assurance require-ments of Appendix B to 10 CFR Part 50, should be applied, as a minimum, to all quality activities affecting.the safety function of these systems, structures, and components as listed below and to other items and services specifically identified by NU in the FSAR as addressing Section 3.2.1 of NRC Regulatory Guide 1.7 Emergency diesel generator fuel oil is subsequently listed in Appen-dix A under the heading "Consumables." The inspector concluded that the licensee has fulfilled Multiplant Action Item A15 for Millstone Unit 2 regarding inclusion of emergency diesel generator fuel in the quality assurance program. This TI is close .3 (Closed) Temporary Instruction (TI) 2515/101, " Loss of Decay Heat Removal (Generic Letter 88-17)
The objective of TI 2515/101 was to assess licensee preparations for and controls over actions during reduced inventory operation in ac-cordance with NRC Generic Letter 88-17 dated October 17, 1988. TI 2515/101 addresses the short-term licensee program entitled "expe-ditious actions" per Generic Letter 88-17.
, The inspector had previously reviewed the licensee response and im-l plementation actions for NRC Generic Letter 88-17 as documented in h routine Inspection Reports 50-336/88-28 and 50-336/89-03. During the l
current inspection, the inspector further reviewed TI 2515/101 and
__-- - _ _ _ _ - .
-_ . __ .
4 ,
cc , ,
- .
- .; i
- .
- licensee actions in. response to GL 88-17. .The follow-upiitems iden-tified were: (i) the licensee's emergency containment closure pro-cedure;.(ii) required time to initiate addition of water'to the reac - ,
. tor.' coolant system to prevent uncovering.the core during;a loss of shutdown cooling; (iii) injection flowrate needed to prevent uncover- .i
]
ing the core; (iv) licensee procedures.to address. items (ii) and
~
j (iii); and (v) licensee analyses to assess whether the RCS vent path .{
ensures pressurization will be less than 1 psi if cold leg openings
.
I exist,.and less than nozzle dam design pressure capability with a 25%. 1 safety facto Procedure MP 270451, " Containment Equipment Hatch Emergency Closure,"
was effective on February 6,198 The procedure was implemented
, 1 prior to reduced inventory operation for the current refueling'out-ag Reduced inventory conditions were established between Febru-ary 7-9 and in mid-April', ICS? The purpose of the procedure is emergency closing of the containment equipment hatch within two hours. (The licensee's basis for two hours was documented in routine Inspection Report 50-336/88-28.)
MP 270451 makes the licensee's shift engineer responsible for tagging control of all lines (air, hose, electrical cables, etc) penetrating
'the equipment hatch. The tools, equipment, and materials required to close the equipment hatch are identified in the procedure, and were verified periodically by t,he inspector during the outage. The in-spector also verified periodically that the shift engineer maintained an accurate accountability log. No inadequacies were noted. The
- inspector had no further questions on MP 270451 and its imp?ementa-l~
tio The. inspector reviewed the licensee's response to NRC generic Letter 87-12,. " Loss of Shutdown Cooling While the RCS is Partially Filled,"
dated September 18, 1987. That response documents licensee calcula-tions to indicate core uncovery in 122 minutes based on loss of shut-down cooling, no alternate cooling, and guidance in NUREG-1269. Lic-ensee calculation W2-517-889-RE, Revision 2, concludes the RCS hot ;
leg pressure required to depress RCS hot leg level and raise cold leg
'
level is 3.00 psi. The calculation further concludes that, for the decay heat available at 5 days, 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after shutdown, the press-urizer manway provides an adequate vent path for a loss of SDC, such j that the hot leg pressure rise would be limited to 3 psi. The in-spector verified the licensee removed the pressurizer manway and in-stalled the SG nozzle dam after 5 days, 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from subcritice .ty of the reactor. Licensee procedure MP 2705G Revision 2, SG Nozzle Dam Installation and Removal, prerequisite step 3.13 requires opera-tors to verify pressurizer manway removal prior to installing the final hot leg nozzle dam. The procedure was effective on January 25, 198 i
_ _ _ . . _ _ _ _ _ . _ _ _ _ _ . . _ _ _
i
- _ _ . - _ _ _ _ _ _ -
, .
c,J ,
.
Licensee engineering calculation W2-517-889-RE',' Revision 2 identifies the required alternate cooling injection source to prevent core-uncovery due to boil-off on a loss of SD The following lists the injection sources and time after shutdown at which the listed sources are sufficient to make up for boil-off:
--
One Charging. Pump - 16 days after shutdow Two Chargirg Pumps - 2 days, 21 hours2.430556e-4 days <br />0.00583 hours <br />3.472222e-5 weeks <br />7.9905e-6 months <br /> after shutdow Three Charging Pumps - 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> after shutdow Licensee procedure OP 2301E, " Draining the RCS," prerequisite step 3.12 and 3.13 require one high pressure safety injection (HPSI) pump and 2 charging pumps to be available during reduced inventory condi-tions. The inspector verified this pump availability as described in Inspection Report 50-336/89-0 No inadequacies were note Licensee' calculation W2-517-889-RE further concluded, based on ele-vation head, pressure drop through the pressuria r surge line, and maximum injection flow, that there would be a total of 24.6 psig at the center-line of the cold leg with the pressurizer floode CE-NPSD421, Revision 1, " Loss of RHR Scenarios - Detailed Qualitative Assessment - CE0G Task 555," concluded that the Steam Generator Nozzle Dams may leak at between 25-50 psig RCS pressure. That is below the nozzle dam design pressure rating. Based on time after shutdown limitations on installing the last SG nozzle dam and on pressurizer manway availability for venting, the pressur'zation of the RCS would be limited to 3 psig (18 psia).
The inspector had no further questions concerning TI 2515/10 .4 (Closed) UNR 89-05-06, Potentially Defective Steam Generator Tube Plugs This item concerned potentially defective steam generator (SG) mech- ;
anical tube plugs supplied by Westinghouse. Inspector follow-up in- ,
cluded the vendor's basis for limiting the suspect tube plugs to heat j lots NX-3513, NX-3279, and NX-3962, the licensee's basis for select- )
ing the plugs to be addressed, the engineering design and installa- l tion procedure, the basis for excluding plugs installed in 1985, and licensee actions to keep radiation exposures for the repair as low as reasonably achievabl The vendor's (Westinghouse) basis for identifying heat lots NX-3513, NX-3279 and NX-3962 as suspect was a lack of material grain boundary carbides. That condition, first found in heat lots NX-3513 and NX-3962, makes mechanical plugs susceptible to primary water stress cor-rosion cracking (PWSCC). The service limit for these plugs was not determined by the vendor by the end of the inspection. On May 2,
,
j l
f
._- _ .. _ . _ _ - _ _ _ _ _ _ _ _ _
. .
-
,
.
. Westinghouse informed the licensee that heat lot NX-4523 also may be susceptible to PWSCC, based on pulled in-service mechanical plugs at the Salem and Farley nuclear plant Licensee repair of the mechanical plugs was based on the vendor's recommendation and on licensee design input #6 to Plant Design Change Request (PDCR) 2-088-8 Design input #6 is licensee calculation 88-008-1073GP, " Millstone 2 Steam Generator Tube Plug-Cracking An-alysis." ~The objective of this calculation was to determine the re-lationship between service temperature and the time required to in-itiate cracks in the steam generator plugs. The two assumptions utilized in this engineering calculation were: (1) the Arrhenius re-lationship can be used to describe stress corrosion cracking in In-conel alloy 600 SG tubing in a Pressurized Water Reactor (PWR); and (2) once a tube slug crack forms, it will propagate through wal The calculation showed that it takes nine times longer to initiate cracking in a steam generator cola leg than in a hot leg, based on an average activation energy. Conservatively, for the lowest activation energy, the difference between cold and hot leg time to failure is a ,
factor'of The licensee repaired all heat lot NX-3513 plugs in- l stalled from 1986-198 Heat lots NX-3279 and NX-3962 are not in-stalled at Millstone The licensee concluded that no immediate action is required on susceptible cold leg plugs based on the engi-neering calculation showing acceptable plug performance until the end of cycle 13. The licensee will document this conclusion in their Preventive Maintenance Management System (PMMS) data base and will track the service life of the plugs on PMMS as well. The inspector had no further questions in this are The inspector reviewed PDCR 2-008-89, " Steam Generator Tube Plug Re-pair Fixtures." Factors considered in the Plag-in-Plug (PIP) fixture design included: 1) NRC Regulatory Guide 1.121 design criteria; ii) If all susceptible plugs begin leaking into the secondary, the total primary to secondary leakage would not exceed 1 gallon per minute (gpm); iii) reduction in ballistic energy, if a tube plug fails, to less than is required to pierce the tube wall at the U-bend; and iv) reduced probability of a PIP loose part due to tack welding and American Society of Mechanical Engineers (ASME) preload
,
stress limits. The licensee installation procedures were ACP 2.18, l "ASME Section XI Repair Program," and MP 2701S, " Instructions for ASME Section XI Repairs." The inspector reviewed the licensee's sup-porting calculations and reference material and had no further ques-tion The inspector reviewed the licensee's actions to maintain personnel
! radiation exposure as-low-as reasonably achievable (ALARA). The PIP modification was divided into seven specific activities: (i) template installation / removal; ii) mechanical plug brushing; iii) installation and torquing the PIPS; iv) welding the PIPS; v) verification and re-work; and vi) general support. The ALARA estimate in PDCR 2-008-89
1
l l
L __. . - _ - _ __ .__- . ._ _ _ _ - - . _ _ _ - _ _ . . ._ __. _. . _ _ _ _ _ _ _ ..
_,
,
. .
'
..
.
P
'
.;
was 107 man-rem total. .The basis for this estimate was mock-up !
L training for all SG channel head workers, face-to-face turnover be-L . tween workers, maintaining. distance from the primary SG manway open-ing, and maintaining spare tools on the SG platfor The actual. exposure for the PIP installation was 145.08 man-rem, ac-cording to a tabulation by the llcensee's ALARA coordinator. Accord - -l ing to the licensee's ALARA coordinator.and health physics . super- l visor, the installation was stopped for one shift due to excessive- j exposure during. PIP welding (255 PIPS were welded with a cumulative exposure of approximately 55 man-rem). .The estimated exposure to weld all 446 PIPS was 66 man-rem. The licensee identified the major problem as worker orientation in the channel plenum before and after l turnover activities. To address this item, the licensee removed the l
'
PIP. templates, provided bigger template openings, numbered the tem-plate sections, and identified the plugs by number. The remaining
<191 PIPS were welded with approximately 7 man-rem of personnel ex-posur The primary difference between actual and estimated exposure' results ;
was verification / rework and general support of PIP installatio !
This difference was 34.2 man-rem. The primary cause for added ex- I posure was initial orientation problems in the SG channel head I Mock-up training for the manual PIP installation minimized man-rem i exposure in the SG primary plenum The licemee's basis for excluding repair of mechanical plugs in- i stalled it. 1985 was that those plugs were from.unaft-cted heat lot l NX-2387. The inspector verified the licensee conclusion by review of :
the vendors NSID Primary Services Field Service Report for 198 .I Item 89-05-06 (UNR) is close l
!
3.5 (Closed) UNR 89-05-03, Justification for Continued Operation (JCO)
for Gamma-Metrics (GM) Wide Range Nuclear Instrumentation This item concerned the licensee's operability justification for GM l
-
wide range nuclear instrumentation (WRNI) cables. The environmental j qualification of the cables was questioned based on failure of the 1 vendor recommended pressure drop test performed by the licensee on j 1 February 14, as documented in Inspection Report 50-336/89-05. All ;
four wide range nuclear instrumentation cable assemblies failed the !
pressure drop test. The failure mode for the GM WRNI cables is mois- :
ture intrusion during a LOCA or main steam line break (MSLB). !
- 1 NRC Generic Letter 86-15, Information Relating to Compliance with 10 CFR 50.49, Environmental Qualification of Electric Equipment Import-ant to Safety for Nuclear Power Plants, provides information to lic-ensees concerning the use of a JC0 as it relates to environmental'
qualification. The inspector reviewed GL 86-15 and the licensee's operability evaluation. That operability evaluation described the
_--_ - -_ _ - 1
__ __ _ _ _ _ _ _ _ . . _ . ___ ___ _ _ _ _ _ _ _ _ _ _ _ ._ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _
. .
-
,
.
'
9 wide range nuclear instrumentation (WRNI) system function, technical specification requirements, accident operation, availability of al-ternate instrumentation, operator awareness, and duration of the evaluation's validity. The inspector concluded that the WRNI system functions are maintained during normal plant operation, and that no credit for WRNI operation is taken in the licensee's safety evala-ation during or following a design basis accident. Also, the licen-see is not required by the Technical Specifications (TSs) to have the WRNI operable for post-accident instrumentation. The duration of validity of this operability evaluation is one fuel cycle because qualified repairs or fully qualified detectors and cables are com-mitted by the licensee to be installed at the end of that tim :
The inspector discussed the licensee's operability statement with NRC ;
regional specialists. A concern was operator awareness of the condi- l tion of the WRNI. The licensee provided that information to the operators via a night order. The inspector discussed WRNI operation with the control room operators, who were aware of the conditio This item is close l
'
4.0 Facility Tours (71707)
The inspector observed plant operations during regular and backshift tours of the following areas:
Control Room Containment Vital Switchgear Room Diesel Generator Room l
'
Turbine Building Intake Structure )
Enclosure Building ;
Control room instruments were observed for correlation between channels, f proper functioning, and conformance with Technical Specification. Alarm conditions in effect and alarms received in the control room were dis-cussed with operators. The inspector periodically reviewed the night or-der log, tagout log, Plant Incident Report (PIR) log, 'av log, and bypass jumper log. Each of the respective logs was discusst with the operations department staf No inadequacies were note During plant tours, logs and records were reviewed to ensure compliance with station procedures, to determine if entries were correctly made, and to verify correct communication and equipment status. No inadequacies were note The inspector verified proper control room manning and discussed alarm i
conditions in effect and alarms received with the or.rators, who were found to be cognizant of plant conditions ano indications. The inspector observed prompt and appropriate operator response to changing plant condi-tions. Shift turnovers were found to be thorough and in conformance with ACP 6.12, " Shift Relief Procedure." Operating logs and Plant Incident l
l
!
I
_ - _ _ _-
_ -_ _ - - -_ _ _ . .
.
, .
.
,
.4
Reports (PIRs) were reviewed for accuracy and adherence to station pro-cedure During plant tours, posting, control, and the use of personnel monitoring devices for radiation, contamination, and high radiation areas were inspected. Plant housekeeping controls were observed, including con-trol of flammable and other hazardous materials. No inadequacies were identifie The inspectors conducted backshift inspections of the control room and found all shift personnel to be alert and attentive to their duties. No
,
unacceptable conditions were identifie Selected aspects of site security were verified to be proper during in-spection tours, including site access controls, personnel searches, per-sonnel monitoring, placement of physical barriers, compensatory measures, guard force staffing, and response to alarms and degraded condition .0 Plant Operational Status Reviews (71707/81700/93702/71711)
5.1 Review of Plant Incident Reports (PIRs)
The plant incident reports (PIRs) listed below were reviewed during the inspection period to (1) determine the significance of the events; (ii) review the licensee's evaluation of the events; (iii) verify the licensee's response and corrective actions were pro-per; and, (iv) verify that the licensee reported the events in ac-cordance with applicable requirements. PIRs 89-23 thru 89-29 were reviewed. The following PIRs warranted inspector followup:
-- PIR 89-29 " Mechanical Tube Plug Failure" - see Inspection Report 50-336/89-05 5.2 Safety System Operability (71710)
On April 10, two engineering safety feature (ESF) systems were re-viewed to verify system operability. The systems reviewed were Facility I Service Water and Auxiliary Ferdwater. The review in-cluded proper positioning of major flowpath valves, proper operation of indication and controls, and visual inspection for proper lubri-cation, cooling, and other condition References used were:
--
The Final Safety Analysis Report (FSAR);
--
Plant Instrument and Piping Diagrams (P& ids) 25203-26008 and 25203-26005;
--
Operating Procedures (ops) 2612C1 and 2610C-2;
--
Tag-out log #2-1422-89; and
--
Authorized Work Order ( AWO) M2-88-510 Minor deficiencies noted during the system walkdov:n were: valve posi-tion indicator bent on valve 2-SW3.28, "A" Service Water Header to Turbine Building Component Cooling Water (TBCCW) Heat Exchangers, and
,
m_.______.__ _ . - - - - . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _
.
. .
-
..
.
e
no valve identification . tag on 2-FW9C, " Turbine Auxiliary Feed Pump Discharge Isolation. These discrepancies did not affect safety sys--
tem operability. The items were discussed with the licensee and were subsequently corrected. The inspector had no further question .3 Inadvertent Safety Injection (SI)
On April 30 at approximately 3:40 a.m., with the unit in hot standby, a partial safety injection actuation occurred. The equipment started were.the 'A' and 'B' Boric Acid pumps, and the 'B' and 'D' contain-ment air recirculation fans (in slow speed). Valve 2-CH514 (Boric Acid Emergency Feed Stop Isolation) opened and emergency air chiller 1698 started. No actual injection into the reactor coolant system
.
occurred. The licensee secured the affected equipment, . reset the safety injection actuation modules, and reported the event to the NRC as required by 10 CFR 50.72(b)(2)(11).
The cause of the partial SI actuation was reinstallation of the auto-matic test inserter (ATI). The ATI generates dual, 2-millisecond pulses to each Engineering Safety Actuation System (ESAS) channe The dual pulses simulate a monentary trip for continual testing of the ESAS logic over a total test interval of 27 seconds. At the time, the licensee was troubleshooting a control room "ATI Fault" alarm. The licensee determined the cause of the alarm was the IC-U2 electronic NAND gate whose output is the alarm function. No spare IC-U2 NAND gate was availabl During reinstallation of the ATI module, the partial SI actuation occurred. The licensee concluded that the cause was that the mcmentary trip signals generated then were of long enough duration (i.e., 30 milliseconds) to result in the actuation.
l At the end of the inspection period, the licensee prepared procedure
'
I/C 2430F, "ATI Installation / Removal." The two principal methods described in the procedure are de-energizing the ESAS actuation cabi-nets and entering TS action statements, or removing 24 volt fuses to the ATI module. The inspector had no further question .4 Low Power Physics and Power Ascension Testing Discrepancies During the week of April 22, the licensee was conducting low power physics testing per in-service test T89-11, " Initial Criticality / Low
,
Power Physics Testing" l
l The licensee's low power physics testing measures actual reactor para-meters and compares the values to the fuel vendor's predicted value The parameters measured were: all rods out (ARO) Critical Boron Con-centration, ARO isothermal co-efficient of reactivity, AR0 moderator temperature co-efficient, and control rod worth Licensee review of completed data found individual control element assembly (CEA) group 4 rod worth outside the acceptance criteri The licensee acceptance
)
_ .-
,
.
. .
e
10 criteria, per ANSI 19.6.1-1985, were within +/- 15% or +/-0.1% delta rho (whichever is greater) from the predicted rod worth. Group 4 rod worth was +19.77% and +0.1022% delta rho greater than predicted, out-side the acceptance criteria. All other rod worth and reactor physics parameters met the acceptance criteria. The inspector inde-pendently verified the licensen's conclusio The licensee contacted the fuel vendor on April 24 to determine if the safety analysis for cycle 10 had been invalidated based on CEA group 4 rod worth. On April 26 the fuel vendor reported that the conclusions of the Cycle 10 safety analysis remain valid, and recom-mended no additional low power physics testing based on acceptable ARO boron concentration and moderator temperature co-efficien !
The licensee concurred with the fuel vendor's analysis and recommen-dations. The inspector reviewed assumptions in the licensee's ac-cident analysis, the fuel vendor's response letter to the licensee, i discussions with licensee reactor engineering, results of in-service test T89-11, and Plant Operation Review Committee close out of T89-11, and had no further question On May 1, the licensee found that the Incore Analysis (INCA) program ,
was producing unexplained results during power ascension testin Licensee investigation revealed that the peak pin to box power fit- !
ting coefficients were incorrect for several selected nodes at the j top and bottom of the fuel assemblies. The fuel vendor had not pro- '
vided the correct peak pin to box power coefficients as a function of '
fuel burn-up. (The peak pin to box power coefficients link one fuel node to another.) The result was a calculated negative linear heat rate at the periphery of the reactor core. The total error in the calculation of linear heat rate and total integral radial peaking factor (FrT) was approximately 2%. The licensee concluded the co-efficient error did not affect the INCA monitoring capability for Azmuthal Power Tilt or correlation of incore nuclear instrumentation to excore nuclear instruments. The inspector concurre The coefficient error resulted in the INCA program being unable to measure linear heat generation rate (LHGR) accurately over the full length of the core or to calculate the total integral radial peaking factor (FrT). The maximum error for LHGR determinations occurred at the top and bottom axial nodes. The error was minimal for the cen-tral nodes where linear heat rates are the highest, such that INCA LHGR values in the core central regions were relatively accurat The inspector reviewed the applicable requirements for LHGR and Fr TS 3.2.1 requires the LHGR to be calculated by either incore detec-tion monitoring system or the excore detector monitoring syste Based on co-efficient errors, the licensee decided to use the excore detector monitoring system to satisfy the T The inspector verified licensee calculation of LHG No inadequacies were note _
.
vs
,
.'}_-4 . 1 .
> _o w;"y 11~
The vendor provided augmentation' factors'for the peak pin to box' '
power coefficients. The coefficients were the conservative differ-ence between predicted. values and calculated values. The licensee-L 'implemented'the augmentation factors'until the vendor.provided cor-f rected coefficients on May 5. - The INCA system was declared operable by the licensee on-May 6. Between May.2.and May 6, the licersee cal-culated FrT using the augmentation factors. The.inspectorireviewed
~,'
. calculated FrT values on a: sampling basis to verify results wer within required TS limit's when the augmentation' factors were use Satisfactory- core performance based: on INCA measurements .was . verified after. revision of the INCA calculations on May 6. No inadequacies were note .5 10 CFR 21 - Rosemount Transmitter Oil' Leaks Background in' formation concerning Rosemount. transmitter Models 1153 and 1154 failures due to loss of sensor fluid is documented in In-spection' Reptrt. 50-423/89-02, dated March 13, 1989. The licensee wrote a letter to the NRC on April 13, 1989 to provide additional
.information on activities involving Rosemount 1153 and 1154 trans-
,
. mi tte rr. .
.The inspector followed-up licensee actions surrounding Rosemount-transmitters at Millstone 2. The following documentation was re--
viewed:
--
. Licensee-letter to NRC, dated April 13, 1989;
---
Mp2-I1351, "Rosemount Transmitters at Millstone 2," memo dated February 28, 1989;
--
Licensee Deportability Evaluation 89-09, March 8,1989;.
- --
Rosemount letter, " Notification under 10 CFR 21," February 8, 1989;-
--
Licensee report of Substantial Safety Hazard, Millstone 3, dated March 25, 1989;
--
Nonconformance Report 289-565, "Rosemount Level Transmitters for Pressurizer level;"
--
SP'2402E, " Pressurizer Level Calibration Data Sheet" for February 8,1989;
--
NRC Information Notice 89-42, " Failure of Rosemount Models 1153 and 1154 Transmitters."
The licensee identified eleven installed Rosemount transmitters at Millstone 2. Eight of these are Model 1151 and measure reactor cool-ant pump and reactor core differential pressure. Two are Model 1154 and measure pressurizer level. One is a Model 1153 used for low-range. pressurizer pressure. These three transmitters are not on the listing of suspect Model 1153/1154 transmitters.
. - - _ - _ _ - _ _ _ _ _ _ _ _ _ - _ _ - _ - - _ _ _ _ _ - . _ .
mt .
'< <
,
. . . , .:
,
y ,
c;
'12 w
.
g W -
'
'
According to the licensee's letter to the NRC, dated April 13, 1989,.
.
'
.three suspect 1153/1154 transmitters from Rosemount's.10 CFR 21 noti-
-fication.. letter were supplied to the licensee. One of these, LT-110Y,.is currently installe LT-110Y provides pressurizer level-indication signals. These' signals are used for control and-indi-cation, and provide no reactor protection or engineered safety fea-
.
'
- ture actuations. The level signals are compared to a setpoint from the licensee's reactor regulating system. Deviations between the setpoint and. indicated level generate high/ low. level alarms, and -
change letdown' flow'and the number of charging pumps' operating. Two transmitters (LT-110Y and LT-110X) are provided for controlling chan-nels. Manual selection of one channel'is provided in the control roo The inspector- reviewed the operability requirements for pressurizer level transmitter LT-110Y. Two technical specifications (3.3.3 5, e
'" Remote Shutdown Instrumentation," and 3.3.3.8, " Accident Monitoring Instrumentation") apply. Both TSs require one out of two channels to be operable in modes 1, 2 and 3. The licensee can fulfill these TS with LT-110Y inoperabl <
The' licensee reported that the remaining two affected' transmitters:
are uninstalled spares. The inspector reviewed the lic.ensee's dispo-sition of these spares by NCR 289-565. That disposition returns the transmitters to Rosemot.nt for repair / replacement to meet the' criteria in the original purchase order. At the'end of the inspection, the licensee had returned one transmitter to Rosemount; the other was red tagged on hold and not to be installed without evaluatio In addition to the transmitters listed by Rosaniount as being of con-cern, the licensee reviewed all other safety-related Rosemount trans-mitters. The review considered whether further testing was require On' April 13, the licensee concluded that no other transmitters have exhibited- symptoms of loss of sensor flui The inspector reviewed the February 1989 response testing and cali-bration of transmitter LT-110Y. All surveillance met the acceptance criteri Licensee evaluation of potentially defective Rosemount transmitters was assessed as thoroug The inspector reviewed the LT-110Y Rosemount transmitter problem with the control room operators. The operators were cognizant of poten-o tial transmitter problems and the action required if the transmitter
! was to fail. The inspector had no further question .0 Allegation RI-88-A-40 on Reactor Trip Breakers (RTBs)
The inspector received an inter-office memo dated April 14, 1989 from an alleger with the following concerns:
l l_'--_-___-_____-
.
_ - _ - _
.3c
-
- .
L-> *
-
3 .,,
! :.
'
I 13 L
?> --
During the week of April 14, according to the. alleger, seven out of nine RTBs failed high risk testing. The alleger was informed of the-results. based on discussions between an electrician and the electri-cian's foreman. LThe alleger expressed concern that the electrical-foreman elected to address the failures with one' authorized work order (AWO) for one 'RTB (RTB2).
p On' April:17 and 18, the senior resid'ent inspector received an allegation about RTB performance from a second alleger with the following additional concerns:
r
--
- The alleger repeated a concern, recently documented in news articles,
- involving reactor protection system trip circuit breaters. The al -
L leger suggested the NRC talk to maintenance department electricians about recurrent problems with trip circuit breakers resetting re-motely from the control room during periodic testing. The problem reportedly occurred on RTBs 1, 2, 4, and 7. (RTB 7 was replaced dur-ing the current outage.) The alleger's concern was that the problem keeping the breakers from resetting on demand (e.g. from looseness)
might also keep the breaker from tripping. The alleger suggested that the NRC review test procedures 2401A and 24010, which have a prerequisite-that a maintenance electrician be present for the RPS logic matrix testing. The alleger stated this proves a known long-standing. problem exists with the breakers because the only reason for
. the maintenance departmer.t to be involved is to assist in reclosing-the breakers manually when it cannot be done from the control roo The inspector reviewed the licensee's surveillance program for RTB That program includes the following:
Department Periodicity Surveillance Purpose Instrument & Monthly Matrix testing per SP 2401 Control Melntenance Quarterly Preventive Maintenance (PM) to measure trip shaft torque requirements to open RT Maintenance Refueling Preventive Maintenance (PM) to inspect vital dimensions for breaker gap, con-tact overlap, arc quenchers, lubrica-tion, et Production Refueling PT21429 inspection and test of under-Test voltage trip device, RTB response time, and inspection and test of shunt tri ;
________ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ - - _ _ _ - _ _ _ - - _
_ _ _ _ _ _ _ _ -
.
' ,
,
The licensee stated that no RTB failures to open had occurred during monthly matrix te. ting. This testing verifies that individual RTBs will open on signal but does not measure response time. The inspector reviewed monthly RTB test records from May 1988 through April 1989. All tests met acceptance criteria except that an indicating light was faulty in August 1988 and the indicating light contacts required maintenanc There was no affect on the trip functio The inspector reviewed the results of quarterly and refueling'PMs per pro-cedure MP2701J1 between January 1,1987 through April 19, 1989. The re-suits of the review are as follows for the nine RTBs:
--
RTB-1: All quarterly and refueling PMs met acceptance criteri RTB-2: All quarterly and 1988 refueling PMs met acceptance criteri On 4/18/89, corrective maintenance was conducted per AWO M2-89-04940 because the breaker would not close electrically. Licensee actions included replacement of the trip shaft return spring ano satisfac-torly retest per MP2720C-1 Step 5. RTB-3: All quarterly PMs were completed satisfactorily. Oc 4/19/89, AWO M2-89-05153 was generated to address a wire bundle catching on the side of the breaker bucket The bundle was on the top right side, and interfered with proper and safe rack-out for testing. The bundle was relocated and the RTB was tested satisfactoril RTB-4: All quarterly PMs and the two refueling PMs checked met ac-ceptance criteri RTB-5: All quarterly and refueling PMs met acceptance criteria.
.
--
RTB-6: All quarterly and refueling PMs met acceptance criteria.
!
l
--
RTB-7: All quarterly PMs were completed satisfactoril There was
!
a trouble report for the breaker's failure to reset electrically dur-ing most of the previous cycle. On 2/10/89 corrective maintenance was completed. According to the work order, the licensee identified the following problems with RTB-7: broken arc quencher, upper holes on side plate elongated, shaft ru..ation in latch / link assembly, and a rivet on the bottom right side of the closing solenoid armature was coming cat. On 4/21/89, per AWO M2-88-09236, the licensee completed an overnaul and retested RTB-7. The breaker was replaced during this outag RTB-8: All quarterly and refueling PMs until 3/9/89 were completed satisfactorily. On 3/9/89, per corrective maintenance AWO M2-89-02029, the secondary disconnects were found bent and were correcte On 4/19/89, the roller indication tape for test position indication was off track, preventing indication of whether the breaker was in test. This was also correcte ,
_ _ _ _ _ . - . _ _ _
_ _ - _ _ - _ _ _ _ _ _ -
-
o ,
. .
, ..
-
a m
15
--
RTB-9:.On 2/15/88, the breaker would'not close by push button. Per AWD M2-88-02360,_the licensee found the trip shaft bearing bad and the' closing. linkage not latching. A new bearing was installed. 0n 2/09/89, the refueling PM was' completed satisfactorily. This breake does'not have a safety function. It parallels the Motor-Generator sets and does not open. on a Limiting Safety System Setpoint (LSSS)
'being reache On.4/25/89 and 4/26/89, the senior resident inspector and resident inspec-tors discussed RTB performance with the Unit 2-maintenance foreman, main-tenance engineer, production test supervisor, and production test elec-trician. .The discussion was coupled with a demonstration of the pre-viously installed RTB-7 (GE AK-2-25 breaker).
The licensee acknowledged the electrical reset function for the RTB has been a proble The inspectors reviewed the corrective maintenance completed during the 1989 refueling outage coupled with a demonstration on what the problem was with each breaker. The' inspectors also reviewed the items checked during a ' refueling PM dry-run with a licensee maintenance electrician. .The in-spector also interviewed a General Electric (GE) representative who was on site during the refueling outage for RTB preventive maintenanc Based on the discussions and demonstrations, four potential causes exist for an RTB not resetting electrically from the control room. These are:
The licensee's production test department measures the undervoltage (UV)
coil reset function pick-up voltage during refueling. .The specification is 104 to.110 VDC,1at a temperature of 20-25C (68-77F). The RTBs at Mill-stone 2 are in the DC switchgear room in the auxiliary building. The am-
~
bient temperature of that room is above 77F. The licensee explained that, with the. coil continuously energized between monthly matrix tests, its temperature may prevent there being enough electro-magnetic force to pull down the reset bar.after the breaker opens. Based on discussions with the General Electric (GE) representative, the vendor has not yet addressed this issu The latch / link assembly spring attached to the trip shaft may be oriented in the wrong position. The wrong position is under the attachment to the trip bar, instead of over it. Such disorientation could lead to increased spring force, pre;*;enting electrical rese In February 1989, this was identified in R;8-7. According to the licensee, this information was made available by the GE representative during refueling PMs. All breakers
-
were checked for proper spring orientation during the 1989 outag Movement of the upper pin for the latch connect 4 m could result in inabil-ity to reset. A slight movement of the pin resul.: in misalignment of the latch that. holds the breaker shut. Excessive movement, according to the
__ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ - - _ - _ . -
, _ _ _ _
.
. .
C
'
,
,
GE representative, coeld result in opening of the breaker during opera-tio The licensee was asked by the field representative to investigate movement of the pin connection during the 1989 outage. All RTBs were in-vestigated and none currently installed were found to have this proble The fourth potential problem identified is the trip bar connection to the outer frame of the breaker. A flapper assembly rotates downward when the trip shaft rotates during electrical rese If the breaker was racked-in improperly, flapper movement would not hold the trip shaft in position, and the RTB would not rese The licensee concluded that none of the problems affecting the remote re-set feature would prevent RTB opening to perform its safety functio Detailed inspecto" review of the breaker mechanical linkage also concluded that the electrical reset function has no affect on the safety function since failure to reset electrically would prevent shutting the breaker onl The UV coil drops out (de-energizes) to effect a trip, as compared to being energized to electrically close the breake There was no
" looseness" that could affect proper operation of the trip functio Local shutting of the breaker is sufficient for resuming operatio The inspector reviewed GE service letter 175 (CPDD) concerning the recom-mended pick-up voltage for the UV coil on the RTBs. That pick-up voltage is in accordance with ANSI C37.13-1981 The licensee has incorporated the vendor's information into the RTB surveillance progra Licensee procedure SP 24010, Revision 8, prerequisite step 4.7 requires electrical maintenance presence prior to cycling RTBs per this procedur This confirmed the alleger's input, but no safety inadequacy was identi-fied as being associated with this practic SP24010 Step 6.43.3 requires verification that the armature is in contact with the adjusting screw, assuring correct adjustment. The licensee's reported program during surveillance testing is to reset the breaker twice electrically / manually once opened. If unsuccessful, then a corrective maintenance authorized work order (AW0) is generate The safety significance of failure of an RTB to reset and close remotely is minimal based on: no identified failures of an RTB to open when re-quired; redundancy in the licensee's trip scheme; and no direct relation-ship between reset and failure to ope This allegation, though true in regard to the resetting problems and the presence of maintenance personnel being required for planned breaker cyc-ling, is unsubstantiated in regard to representing a safety concer _ _ _ _ _ _ _ _ _ _ - _
r _. - _ - _ -
. .
, ..
,
- 7.0 Committee Activities (40500)
The inspector attended Plant Operations Review Committee (PORC) meetings 2-89-65, 2-89-67, 2-89-69, 2-89-76, 2-89-77, 2-89-78, 2-89-79, 2-89-96, and 2-89-99 of the March 29, March 31, April 3, April 11, April 12, April 13, April 14, May 1, and May 3 respectively. The inspector noted
-
that committee administrative requirements were met for the meetings, and that the committee discharged its functions in accordance with regulatory requirements. The inspector observed a thorough discussion of matters before the PORC and a good regard for safety in the issues under consider-ation. No inadequacies were identifie .0 Licensee Event Report (LER) Review (92700)
Licensee event reports submitted during the period were reviewed to assess LER accuracy, the adequacy of corrective actions and compliance with 10 CFR 73 reporting requirements, and to determine if there were any generic implications or if further information was require The LERs reviewed we re .-
l --
LER 89-004-00
--
LER 88-011-01
--
LER 88-006-01
'No inadequacies were note .0 Maintenance (62703J The inspector observed and reviewed selected portions of preventive and corrective maintenance to verify compliance with regulations, use of ad-ministrative and maintenance procedures, compliance with codes and stand-ards, proper QA/QC involvement, use of bypass jumpers and safety tags, personnel protection, and equipment alignment and retest. The following activities were included: ,
--
No.1 SG Hot Leg Plug-in-Plug Template Verification, March 30, 198 MP-2701J, RTB Refueling PMs Demonstratio No inadequacies were identifie .0 Surveillance Testing (61726)
The inspector observed portions of surveillance tests to assess perform-ance in accordance with approved procedures and Limiting Conditions of Operation, removal and restoration of equipment, and deficiency review and resolution. The following tests were observed:
.
L___.___ ______
_ _. _ - -_
.
j-
'
' 4. 4 l 18'
,
--
. 0P 2613C, Integrated Loss of Normal Power (LNP) Test, on 4/13/8 ' -T89-47, ATWS Pre-Operational Test, on 3/29/8 T-89-11, Initial Criticality, Low Power Physics Testing, on May 1, 198 During inspector observation of OP 2613C on April-13, two non-intent pro-
, 'i cedural' changes, the pre-test briefing, and independent status checklist-verification.of Facility I and Facility II. engineered safety feature (ESF)
equipment were specifically reviewe '
'
Licensee data review concluded the following ESF equipment was outside:the acceptable start times. The inspector verified the licensee conclusion b independent data review. The eqeipment and time delay in starting is listed below:
Facility I Time Delay
'A Chill Water Pump 2.278 seconds Facility II Time Delay
'B' Containment Air' O.081 seconds Recirculation Fan-
'C' Charging Pump 0.228 seconos
'B' Chill.' Water Pump 2.28. seconds The licensee changed the acceptance criteria for the charging pumps to less than 9. seconds from emergency diesel generator breaker closure,.and also confirmed that the exact time of autostart of the ' A' and 'B ' chill water pumps was not significant, as long as they started. The procedural changes were approved during PORC meeting 2-89-80 on April 14. The new l
sequence times are based on: the as-left start times are within the safety analysis; and the difference in load sequencing did not effect diesel engine performanc .
The inspectors assessed the ESF integrated test as exhibiting good test I direction, with good communication and coordination. Also, personnel demonstrated good knowledge of system design and operating requirement .0 Periodic Reports (92700)
i Upon receipt, periodic reports submitted pursuant to Technical Specifi-l cations were reviewed. This review verified that the reported information was valid and included the NRC required data, and that the test results and supporting information were consistent with design predictions and performance specifications. The inspector also ascertained whether any reported inforn'ation should be classified as an abnormal occurrence. The following reports were reviewed:
l i ..
w:: - ._
,.
.
. . , . . ..
,,~.
,
--
Monthly Operating Report 89-03, March, 198 Monthly Operating Report 89-04, April, 198 No unacceptable conditions were identifie .0 Management Meetings (30703/30702)
Periodic meetings were held with station management to discuss inspection j findings. Also, a summary of findings was discussed at the conclusion of the inspection. No proprietary information was covere No written mate-rial was given to the license '
i I
L___ - -