Advises of Delay of Commitment in LER 85-003 to Reroute Instrument Impulse Lines & to Heat Trace & Insulate by Dec 1985,due to Design & Matl Lead Times.Implementation of Mods Delayed Until 1986 Outage
ML20137E183
Person / Time
Site: McGuire Duke energy icon.png
Issue date: 08/20/1985
From: Tucker H
DUKE POWER CO.
To: Adensam E, Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8508230158
Download: ML20137E183 (1)


LER-2085-003, Advises of Delay of Commitment in LER 85-003 to Reroute Instrument Impulse Lines & to Heat Trace & Insulate by Dec 1985,due to Design & Matl Lead Times.Implementation of Mods Delayed Until 1986 Outage
Event date:
Report date:
3692085003R00 - NRC Website

text

DUKE POWER GOMPANY

.O. Box 33180 CitARLOTTE, N.C. 28242

_ .. _ (7 o73-4 G31 August 20, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Ms. E. G. Adensam, Chief Licensing Branch No. 4

Subject:

McGuire Nuclear Station ~

Docket Nos. 50-369 and 50-370 '

' Commitment to Reroute Instrument Lines

Dear Mr. Denton:

In Licensee Event Report 369/85-03 dated February 20, 1985, Duke Power Company 1 committed to reroute instrument impulse lines and to heat trace and insulate j by next winter (December, 1985). Due to design and material lead times, and that the implementation of these modifications during an outage is preferred, the modifications vill be delayed until an outage.in 1986.

Very truly yours, I

  • y Hal B. Tucker

{

JBD/hrp  !

l cc: Dr. J. Nelson Grace, Regional Administrator l

U. S. Nuclear Regulatory Commission '

Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Mr. W. T. Orders Senior Resident Inspector McGuire Nuclear Station