Responds to Re Review of NUREG-0737,Item I.C.6, Guidance in Ansi/Ansd 3.2-1982. Plan Developed to Modify Policy Considering Alara.Corrective Action Will Be Submitted by 830513.Delay Due Impact of Changes
ML20071A808
Person / Time
Site: Pilgrim
Issue date: 02/15/1983
From: Harrington W
BOSTON EDISON CO.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-1.C.6, TASK-TM 83-52, NUDOCS 8302250058
Download: ML20071A808 (1)


Text

-

BOSTON EDISON COMPANY B00 BOYLSTON STRary BOSTON, MASSACHUBETTS O2199 WILLIAM D. HARRINGTON s3xeon viss paseissut x ..

February 15, 1983 BECo Ltr. #83-52 Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D. C. 20555 License No. DPR-35 Docket No. 50-293 Response to NRC Letter Dated Dec. 20, 1982 Titled NUREG 0737 Item I.C.6

Dear Sir:

Boston Edison has reviewad the subject letter and has developed a plan which will modify our station policy regarding Item I.C.6. Our re-evaluation in-cludes a review of NUREG 0737 I.C.6 guidance and ANSI /ANS 3.2 - 1982. Sec. 5.2.6.

Accordingly, the policy should conform to the guidelines of I.C.6 considering ALARA and personnel resource requirements. In cases where the guidelines of I.C.6 are not adopted by station policy, justification will be provided.~

Based on this plan, our scheduled date for a Station Policy is March 21, 1983.

Our plan for corrective action to the station procedures will be submitted by May 13, 1983. This delay is based on our inability to determine the impact of changes to the procedures at this time.

If you have any questions, please contact us.