ML030980748

From kanterella
Revision as of 08:06, 23 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Summary of Annual Assessment Meeting for Shearon Harris Nuclear Power Plant
ML030980748
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 04/04/2003
From: Fredrickson P
NRC/RGN-II/DRP/RPB4
To: Scarola J
Carolina Power & Light Co
Shared Package
ML030980744 List:
References
Download: ML030980748 (5)


Text

April 4, 2003 Carolina Power & Light Company ATTN: Mr. James Scarola Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

MEETING

SUMMARY

- ANNUAL ASSESSMENT MEETING SHEARON HARRIS NUCLEAR POWER PLANT

Dear Mr. Scarola:

This refers to the open annual assessment category 1 public meeting that was conducted at our request at the Apex Community Center on March 25, 2003, to present the results of the 2002 annual assessment. The topics discussed included the reactor oversight process, the NRCs action matrix and the performance of the Harris Nuclear Plant. A list of attendees and a copy of the presentation handouts are enclosed.

It is our opinion that this meeting was beneficial.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact us.

Sincerely,

/RA/

Paul E. Fredrickson, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No. 50-400 License No. NPF-63

Enclosures:

1. List of Attendees
2. NRC Presentation Handout
3. Licensee Presentation Handout cc w/encls: (See page 2)

CP&L 2 cc w/encls:

James W. Holt, Manager Peggy Force Performance Evaluation and Assistant Attorney General Regulatory Affairs PEB7 State of North Carolina Carolina Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Public Service Commission Robert J. Duncan II State of South Carolina Director of Site Operations P. O. Box 11649 Carolina Power & Light Company Columbia, SC 29211 Shearon Harris Nuclear Power Plant Electronic Mail Distribution Chairman of the North Carolina Utilities Commission Benjamin C. Waldrep c/o Sam Watson, Staff Attorney Plant General Manager--Harris Plant Electronic Mail Distribution Carolina Power & Light Company Shearon Harris Nuclear Power Plant Robert P. Gruber Electronic Mail Distribution Executive Director Public Staff NCUC Terry C. Morton, Manager 4326 Mail Service Center Support Services Raleigh, NC 27699-4326 Carolina Power & Light Company Shearon Harris Nuclear Power Plant Herb Council, Chair Electronic Mail Distribution Board of County Commissioners of Wake County John R. Caves, Supervisor P. O. Box 550 Licensing/Regulatory Programs Raleigh, NC 27602 Carolina Power & Light Company Shearon Harris Nuclear Power Plant Tommy Emerson, Chair Electronic Mail Distribution Board of County Commissioners of Chatham County Steven R. Carr Electronic Mail Distribution Associate General Counsel - Legal Department Distribution w/encls: (See page 3)

Progress Energy Service Company, LLC Electronic Mail Distribution John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Acting Director Division of Radiation Protection N. C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution

CP&L 3 Distribution w/encl:

C. Patel, NRR L. Slack, RII EICS RIDSNRRDIPMLIPB PUBLIC OFFICE DRP/RII SIGNATURE GTM NAME GMacDonald:as DATE 04/04/2003 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO PUBLIC DOCUMENT YES NO OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML030980748.wpd

List of Attendees NRC Attendees C. Casto, Director Division of Reactor Safety, Region II (RII)

P. Fredrickson, Branch Chief, Division of Reactor Projects Branch 4, RII K. Clark, Public Affairs Officer, RII J. Brady, Senior Resident Inspector, Harris, DRP, RII R. Hagar, Resident Inspector, Harris, DRP, RII Licensee Attendees J. Scarola, Site Vice President, Harris Nuclear Plant (HNP)

R. Duncan, Director Site Operations, HNP B. Waldrep, Plant General Manager, HNP W. Gurganious, Manager Nuclear Assessment Section, HNP T. Morton, Manager Site Services, HNP J. Caves, Supervisor Licensing/Regulatory Programs, HNP D. Braund, Superintendent Nuclear Security, HNP T. Pilo, Supervisor, Emergency Planning, HNP H. Deja, Progress Energy Corporate Communications S. Hall, Progress Energy Corporate Communications T. Natale, Progress Energy, HNP P. Burns, Progress Energy, HNP M. Clayton, Progress Energy M. Roseum, Progress Energy Other Attendees A. Combs, WRAL-TV J. Creighton, Wake County Emergency Management J. Cress, Photographer News 14 Carolina K. Garnett, Public Staff to NC Utilities Commission K. Hawkins, Chatham County B. Horen, WPTF L. Inge, WUNC J. James, NCRPS - Radiological Emergency Coordinator B. McFeaters, Wake County Emergency Management G. Pope, Harnett County Emergency Management W. Rawlins, News and Observer J. Warren, NC WARN B. Williams, Harnett County Emergency Management Enclosure 1