U Harris Nuclear Plant Safety Focus I

Bob Duncan Director of Site Operations Harris Nuclear Plant I

I C Progress Energy Agenda

  • Key Safety Indicators I

Plant Performance Indicators

  • Risk Reduction Activities
  • Refueling Outage Risk Reduction Activities I

I

~*2 Progress Energy I

L Occupational Safety Industrial Safety: Lost Time Injuries Per 200,000 Hours Worked 1.6I 1

L.C C-I, I

0 1997 1998 1999 2000 2001 2002 2003 YTD I

C Progress Energy 2

Nuclear Safety Radiation Exposure (Person-Rem) 300 260 E 200 c

160 li 60 IL 0

1997 1998 1999 2000 2001 2002 2003 YrD

! Progress Energy 3

Plant Performance Forced Outage Hours GMi C

0 7i 400 300 200 1-C) t I

100 70 0

I 1997 1998 1999 2000 2001 1

2002 2003YrD e Progress Energy 4

5

  • Risk Reduction Activities
  • Plant Security I

Emergency Planning

  • Fire Protection S

self Evaluation

  • Foreign Material Discovery
  • Charging System Venting
  • Zero Tolerance For Equipment Failure
  • Secondary Chemistry Improvements I.

Employee Radiation Dose Reduction l

~Ci Progress Energy Harris Plant Security

  • Key Focus Area In 2002
  • NRC "Interim Compensatory Measures Order" (Feb. 25, 2002)
  • Facility modifications
  • Plant equipment upgrade
  • Process/Procedure changes
  • Security staffing & training i Plant access controls l
  • Coordination & Liaison With Federal, State & Local Agencies
  • Security-specific Drills And Program Evaluations I Progress Energy 6

l Emergency Preparedness

  • Successful NRC/FEMA Graded Exercise March 4, 2003
  • Continued Communications And Coordination With State And Counties P Siren replacements
  • Evacuation time estimates updated
  • Regular Communications To Residents Within The Plant Vicinity
  • Continued Outreach And Community Information I
  • Harris Plant Media Day i School/civic group presentations P Visitors Center - 7000+ studentsI Progress Energy Fire Protection
  • Significant Plant Modifications To Improve Safety
  • Additional barriers will be added in 2003 I

C Progress Energy 7

Fire Protection

  • 2003 Fire Protection Project I

Validate Safe Shutdown Analysis

  • implement modifications to enhance safety

C Progress Energy Foreign Material

  • Low To Moderate Safety Significance
  • Cause: Improper Work Practice In 1991
  • Corrective Actions
  • Removed material i Comprehensive search for additional material I
  • Improved procedures IC Progress Energy 8

, Refueling Outage 11 Risk Reduction Activities I

Reactor Vessel Head Bare Metal Inspection

  • Ongoing Testing of Plant Equipment I
  • Instrumentation Pressure Boundary Design Improvement l

A' Progress Energy

' Conclusion

  • Harris Plant Performing In A Safe Reliable Manner Producing Affordable Electricity For Our Customers
  • Safety Continues To Be The Top Priority
  • Ongoing Effort To Focus On Risk Reduction
  • Self Evaluation Cornerstone Of Continuous Improvement I

Progress Energy 9