Forwards Steam Generator Repair Program for Surry Power Station Unit 1:Final Rept Radiological Progress Rept-Number 5 for Period 800914-810630. Final Rept Satisfies Requirements of License Conditions Issued Under Amend 47
ML18139B513
Person / Time
Site: Surry Dominion icon.png
Issue date: 08/31/1981
From: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
Shared Package
ML18139B514 List:
References
051D, 51D, NUDOCS 8109090137
Download: ML18139B513 (1)


Text

R. lJ. LEASBURG VxoB PRESIDENT NUCLEAR 0PERA'f1'.0NS e August 31, 1981 Mr. Harold R:r-Denton, Director Office of Nuclear Reactor Regulation Attn: Mr. Steven A. Varga Operating Reactors Branch No. 1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Denton:

  • Serial No. 051D NOCHP/WWC:cba Docket No. 50-280 License No. DPR-32 Enclosed herein is the Final Radiological Report (Progress Report No. 5) for the Surry Power Station, Unit No. 1 Steam Generator Repair Program. This final report completes and fully satisfies the requirements of the license conditions issued under Amendment No. 47 to the operating license for Surry, Unit No. 1. The report describes the occupational radiation exposure expended, the dose reduction techniques employed and their effectiveness, and the radioactive effluents and solid waste generated during the repair program, which commenced on September 14, 1980 and was completed on June 30, 1981. If you have any questions on this matter, do not hesitate to contact us. Enclosure cc: Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II Very truly yours, \\ (-) ~-.. ~. 0 (>J \-" __,,-C>A\,\.4-,_,\

\ R.H. Leasburg