ML18139B515

From kanterella
Jump to navigation Jump to search
Steam Generator Repair Program for Surry Power Station Unit 1:Final Rept (Radiological Progress Rept Number 5) for Period 800914-810630
ML18139B515
Person / Time
Site: Surry Dominion icon.png
Issue date: 06/30/1981
From:
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
Shared Package
ML18139B514 List:
References
PROC-810630, NUDOCS 8109090141
Download: ML18139B515 (42)


Text

-- --~-

'/ 8109090141 8108-31~

PDR ADOCK 05000280!

p PDR::

STEAM GENERATOR REPAIR PROGRAM FOR THE SURRY POWER STATION UNIT NO. 1 FINAL REPORT*

(RADIOLOGICAL PROGRESS REPORT -

NO. 5)

FOR THE PERIOD SEPTEMBER 14, 1980 THROUGH JUNE 30, 1981 DOCKET NO. 50-280 LICENSE NO. DPR-32 VIRGINIA ELECTRIC AND POWER COMPANY

,.1 1.0 2.0 TABLE OF CONTENTS INTRODUCTION OCCUPATIONAL RADIATION EXPOSURES 2.1 General 2.2 Evaluation of Exposure Data 2.3 Description and Format of Exposure Data 2.4 Conclusions and Observations 3.0 APPLICATION OF ALARA PRINCIPLES 3.1 General 3.2 Initial Containment Cleanup 3.3 Temporary Shielding

  • 3,4 Steam Generator Water Level 3.5 Plasma-Arc Cutting Equipment 3.6 Temporary Containments and Ventilation 3.7 Mock-Up Training 3.8 Videotape 3.9 Reactor Coolant Piping 3.10 General Techniques and Practices 4,0 RADIOACTIVE EFFLUENTS AND SOLID WASTE 4.1 General 4.2 Airborne Releases 4.3 Liquid Releases 4.4 Solid Radioactive Waste 5.0 STEAM GENERATOR STORAGE BUILDING SURVEILLANCE

6.0 CONCLUSION

S i

PAGE NO.

PRS-1 PRS-2 PRS-2 PRS-2 PRS-3 PRS-3 PRS-5 PRS-5 PRS-5 PRS-6 PRS-8 PRS-8 PRS-9 PRS-10 PRS-11 PRS-11 PRS-12 PRS-14 PRS-14 PRS-14 PRS-14 PRS-14 PRS-16 PRS-17

l. I TABLES Table 1 -

Personnel Radiation Exposure Summary Table 2 - Report of Radioactive Effluents*

Table 2A - Effluent Release and Solid Waste Comparison Summary Table 2B - Liquid Effluent Isotopic Distributions Table 2C -

Gaseous Effluent Isotopic Distributions ii

~I

1. 0 INTRODUCTION PRS-1 SSGP The Steam Generator Repair Program (SGRP) for Surry Power Station, Unit No.

1, commenced on September 14, 1980 and was completed on June 30, 1981.

This Final Progress Report contains information on the radiological effects of the SGRP, and on the measures taken to maintain these effects "as low as reasonably achievable" (ALARA).

Much of the information presented has been obtained from earlier radiological progress reports submitted periodically during the repair program.

The following report sections provide an assessment of the occupa-tional radiation exposure expended, the dose reduction techniques employed and their effectiveness, and the radioactive effluents and solid waste generated during the repair program.

An assessment of the surveillance activities associated with onsite storage of the old steam generator lower assemblies is also provided.

This final report has been prepared pursuant to the license condi-tions issued under Amendment No. 47 to the operating license for Surry, Unit No. 1 and, as such, completes and fully satisfies the requirements set forth in those conditions.

2.0 OCCUPATIONAL RADIATION EXPOSURES 2.1 General PRS-2 SSGP Occupational exposure to radiation is considered to be the major radiological effect of the SGRP.

As such, this aspect of the pro-ject underwent an extensive evaluation during the planning phase to provide realistic estimates of the amounts of personnel radiation exposure (manrem) which would be required to perform each of the tasks involved.

These estimates were based upon the anticipated labor requirements (manhours) and the average radiation dose rates in the work area, and were presented in summary form in_Table 5.3-1 of the report entitled "Steam Generator Repair Program", dated August 17, 1977 and amendments thereto, hereafter referred to as the SGRP Report *

. Prior to commencement of the project, a program was established to assess the actual exposures received by personnel during the repair effort.

This program was designed to provide data compatible with the detail and format of the exposure summary presented Table 5.3-1 of the SGRP Report, thereby permitting valid comparisons between estimated and actual expenditures.

This section discusses the implementation of that program and provides an evaluation of the occupational exposure information compiled during the repair effort.

2.2 Evaluation of Exposure Data The exposure assessment program referred to above was basically designed to utilize daily worker exposure data, as recorded by self-reading pocket dosimeters, in conjunction with contractor supplied, worker task data to determine task-related manrem expen-di tu res.

The worker task data was standardized to system of discrete work packages (called Engineering Task Assignments) which was developed during the project planning phase.

The use of this system to categorize exposure related work facilitated the process of compiling an accurate breakdown of the collective exposure ex-pended on the many tasks performed.

i '

2.3 Description and Fonnat of Exposure Data PRS-3 SSGP Table 1 presents a summary of the occupational radiation exposure expended during the repair effort, the exposure related labor ex-penditures, and the original estimated expenditures.

The following comments are provided for clarification and should be considered when reviewing the data presented.

(a)

Additional tasks perfonned during the repair program which were not listed in Table 5.3-1 of the SGRP Report have been included in Table 1.

Similarily, exposures received by personnel per-fonning functions not directly attributable to any specific, pre-defined task have been listed separately.

Expenditures reported for these "Additional Tasks" and "Unassigned Person-nel Categories" were allocated to a particular phase based upon the major activities being performed at the time they were incurred.

(b)

For each phase (except Phase V), separate subtotals are provided for:

(i) the "pre-defined tasks" and (ii) the "addi-tional

  • tasks and unassigned personnel categories".

Page 1 of Table 1 provides a summary of the "pre-defined tasks" subtotals for each phase and a summation of the "additional tasks and unassigned personnel categories" subtotals for all phases. The Project Totals are also shown on Page 1 of the table.

2.4 Conclusions and Observations (a)

The total occupational radiation exposure expended during the repair program for Unit No. 1 was approximately 15%, or 309 manrem, below the exposure estimate of 2,067 manrem.

(b)

During the repair effort, no worker assigned to the SGRP re-ceived radiation exposure in excess of the federal standards specified in 10CFR20.

\\,

PRS-4 SSGP (c)

The actual labor expenditures (manhours) reported in Table 1 exceed, in most cases, the estimates made during the project planning phase.

This is largely attributed to the fact that peripheral and support activities performed in conjunction with a specific task have been included in the assessment of actual expenditures.

The labor estimates developed prior to commencement of work were directed primarily toward providing a basis for evaluating the task exposure estimates and were not intended to consider or anticipate these additional activ-ities.

\\,

3.0 APPLICATION OF ALARA PRINCIPLES 3.1 General PRS-5 SSGP This section summarizes the specific techniques and practices which were employed during the repair effort in order to maintain occupa-tional exposures to radiation "as low as reasonably achievable" (ALARA).

Where the available data permits, the following evalua-tions include a quantitative assessment of the manrem savings which can be attributed to the technique used.

Additional information on these techniques and how they relate to the overall steam generator replacement activities can be found in the SGRP Report.

3.2 Initial Containment Cleanup After shutdown and the removal of all fuel from the reactor, a general cleaning of the containment interior was performed to re-move loose radioactive contamination in the work areas and thereby reduce the potential for airborne contamination during subsequent activities.

Additional cleaning and debris removal was performed after the biological shield walls and steam generator insulation were removed.

The exposure received by personnel involved in these initial cleaning activities totaled approximately 58 manrem.

The benefit, in terms of manrem savings, is difficult to quantify, how-ever, the following observations give some indication as to the favorable results obtained.

(a)

The use of respiratory protection devices, with their inherent degrading effect on worker efficiency, was rarely required, except as a localized precautionary measure for specific cut-ting and grinding activities.

(b)

An *extensive whole body counting program, to monitor workers for internal radioactivity, and the use of "Friskers" and portal monitors, to detect radiation on body surfaces, identi-fied no instances of significant internal or external personnel contamination during the repair program.

PRS-6 SSGP The worker's ability to perform tasks more efficiently, and thus complete them more quickly, undoubtedly resulted in a reduction of the time spent in radiation areas.

Considering the large number of workers involved even a small reduction in individual exposure times can produce significant savings in total manrem.

The initial cleanup effort and the maintenance of good radiological working conditions are thus considered successful ALARA techniques.

3.3 Temporary Shielding The use of temporary shielding can be attributed with significant reductions in personnel radiation exposure for the SGRP.

A separate work package was devoted to the design and installation of shielding and frequent evaluations were performed to identify improved methods and new applications.

The lower steam generator cubicles received the most extensive application of shielding during the repair effort and thus the work performed in these areas benefitted most directly from its use.

Piping and components located in the cubicles were shielded to achieve minimum exposure levels prior to the start of cutting and removal activities.

After cutting of the reactor coolant piping, shield plugs were installed in the steam generator and pipe openings to reduce radiation "streaming".

During the installation phase, additional shielding of the exposed reactor coolant pipe ends was performed, by placing specially fabricated bags containing lead beads inside the pipe and lead "blankets" on the outside surfaces.

The removal and installation of miscellaneous piping located within the cubicles also received a significant shielding effort utilizing lead blankets and sheet lead "curtains".

Detailed radiation surveys were performed frequently and have pro-vided a basis for evaluating the effectiveness of temporary shield-ing in achieving net reductions in personnel exposure.

Survey data obtained prior to and after shielding installation permits the cal-culation of average dose rate reduction factors for appropriate tasks, and thereby an assessment of manrem savings.

Three tasks

PR5-7 SSGP involving significant personnel exposure have been considered in this assessment.

(a)

Cutting and removal of reactor coolant piping is reported in Table 1 as requiring the expenditure of about 77 manrem.

Con-tact exposure rate measurements obtained during surveys has shown that an average dose rate reduction factor of 6 was achieved by shielding of this pipe.

Using this factor and the actual exposure value for the task, a postulated expenditure of about 462 manrem would have been required to complete the task without the benefit of shielding.

An assumed savings of 385 manrem can thus be credited.

(b)

The removal of miscellaneous piping located in the steam gene-rator cubicles accounted for the expenditure of approximately 14 manrem.

Shielding applied_to this pipe provide~ an average dose rate reduction factor of 5.

Thus, without shielding 70 manrem would have been required to complete the task.

A savings of 56 manrem is credited *

(c)

The installation of reactor coolant piping involved several major activities inside the generator cubicles.

Included were pipe end refurbishment and fit-up and welding of new coolant pipe sections.

In Table 1, the installation of reactor cool-ant piping is reported to have required a total expenditure of 234 manrem.

Survey data indicates that shielding performed for these*activities was effective in reducing dose rates by a factor of 6, and thus resulted in a savings of 1,170 manrern.

Totaling the exposure savings calculated for the above three tasks results in an overall savings of about 1,611 manrem attributable to the use of temporary shielding.

The exposure "cost" incurred during installation of shielding is listed in Table 1 as approximately 64 manrem.

A comparison of these "benefits" and "costs" provides a clear indication of the value of this technique in maintaining occu-pational exposures ALARA.

t, 3.4 Steam Generator Water Level PRS-8 SSGP In the early stages of the SGRP, the water in the secondary system was maintained at a level.covering the steam generator tube bundles in order to fully utilize its shielding quality.

The high water level was maintained until the lower portion of the steam generator was ready to be removed from the containment, at which time it was drained to remove the extra weight.

The shielding effect of this water has historically provided an approximate 10 to 1 dose rate reduction for the area of the steam generator above the tubesheet.

This reduction factor was substantiated by actual survey results obtained during the removal phase and can be used to assess the effectiveness of this technique for several appropriate tasks.

(1)

Removal of Insulation (upper shell, mainsteam and feedwater piping)

(2)

Cut and Remove Steam Generator Upper Shell (3)

Cutting of Mainsteam and Feedwater Piping (4)

Disassembly of Steam Generator Supports (5)

Removal of Steam Generator Level Instruments and Blowdown Piping.

All of these tasks were performed in areas where the shielding effect of the steam generator water was beneficial.

The total exposure received for these five tasks was approximately 23 manrem.

The observed dose reduction factor of 10 thus translates into a postulated exposure savings of 207 manrem.

Since practically no exposure "costs" were required to utilize this technique, its contribution to the ALARA program is obvious.

3.5 Plasma-Arc Cutting Equipment In order to remove the steam generator lower shells from the con-tainment, sections of the reactor coolant piping were cut and removed.

A plasma-arc cutting torch was chosen as the means for performing these cuts.

Plasma-arc has high cutting speed and pro-duces good cut quality for pipe reinstallation.

The high cutting rate was a primary factor in this choice since faster cutting means

PRS-9 SSGP reduced exposure times.

During the evaluation of this task, alter-nate methods such as mechanical cutting and other flame cutting techniques were considered.

These alternatives were estimated to require 1 to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per cut, as compared to 15 to 20 minutes for plasma-arc.

In actual use, most of the reactor coolant pipe cuts were performed in approximately 20 minutes with the plasma-arc torch.

Equipment set-up times were estimated to be about the same for all methods considered, since all would require special track mounting to maintain the close tolerances necessary for fit-up of new reactor coolant pipe.

The exposure savings attributable to the use of plasma-arc equipment could not be assessed, since the total manrem reported for the cut-ting of reactor coolant piping include significant contributions from equipment set-up and pipe removal. However, this technique has proven valuable in reducing exposure times and its use is consistent with the ALARA committment.

As a result of improvements made in the plasma arc cutting equip-ment prior to the Unit 1 outage, the cutting of the reactor coolant piping was accomplished with a total expenditure of 77 manrem. This compares to the Unit 2 outage in which 214 manrem was expended for this operation.

3.6 Temporary Containments and Ventilation To a large degree, the initial containment cleanup and decontamina-tion minimized the need for extensive use of temporary containments such as tents and glove boxes to control the spread of contamina-tion.

However, in areas where significant cutting and grinding work was performed on highly contaminated piping and components, temporary containments were constructed and effectively utilized.

The most significant application of this technique was made in the lower steam generator cubicles, where the removal of reactor cool-ant and miscellaneous piping was performed.

In Unit No.

1, the lower cubicle for each steam generator was totally enclosed to

L, PRS-10 SSGP transform the entire room into a single contairnnent.

Portable ventilation units. continuously withdrew air from these enclosures through appropriate filters whenever cutting or grinding operations were in progress.

Personnel working inside the cubicles were required to wear respiratory protection equipment during these operations, and until the ventilation flow effectively reduced the airborne radioactivity to acceptable levels.

Additional tent enclosures were constructed in various locations to provide controlled work areas for pipe cutting, component refur-bishment and equipment decontamination.

Portable, filtered venti-lation was provided to these enclosures as appropriate.

The benefits observed for these ALARA techniques were threefold.

(a)

The use of small glove boxes for individual pipe cuts was (b) eliminated, These devices required considerable time and exposure to ins tall and remove, and during the Unit 2 SGRP were found in many cases to be counter-productive to ALARA due to this fact.

The use of temporary containments, especially as applied to the lower steam generator cubicles, largely eliminated delays and interference with work being performed in adjacent areas while cutting and grinding of contaminated piping was in pro-gress.

(c)

The overall potential for airborne contamination and problems associated with contamination control was minimized by effec-tive use of temporary containments and portable ventilation.

3.7 Mock-up Training The installation of reactor coolant piping represented the most significant task performed during the repair effort with regard to occupational earlier were exposure.

While the shielding techniques described effective in reducing the radiation exposure rates

PRS-11 SSGP associated with this task, the use of mock-ups to train the workers involved can be credited with providing reductions in exposure times.

Welders, pipe-fitters, riggers and laborers all received extensive training in the activities to be perfonned by "dry runs" in full scale piping mock-ups.

Completion times were noticeably reduced as the simulated activities were repeated to maximize each worker's familiarity with the actual job situation. Quantifying the exposure savings which have been realized through the use of mock-up training has not been attempted here, however, the inherent benefits of reducing exposure times for this major task were of significant importance to the ALARA program.

3.8 Videotape As part of the Unit 2 outage a consultant was retained to videotape and take 35mm slides of the major activities during the project.

This documentation was then edited into a one hour videotape which was used as a training aid to familiarize workers with the steam generator replacement program.

The actual exposure savings which can be attributed to use of this videotape are difficult to quan-tify, however, the desired effect was to familiarize workers with the job and the environment in which it was to be performed, there-by eliminating a period of familiarization inside the contairnnent.

3.9 Reactor Coolant Piping For the Unit 2 SGRP, the old reactor coolant pipe sections were re-used.

In Unit 1, new reactor coolant pipe elbows were installed.

This eliminated the task of decontaminating reactor coolant pipe sections, which required the expenditure of approximately 42 man-rem during the Unit 2 repair effort.

Additionally, during the Unit 2 outage, three sections of reactor coolant piping were removed from each loop. Based on experience gained in Unit 2, it was deter-mined that removal of only two pieces of pipe would still allow an acceptable fitup to be achieved during reinstallation.

This fact, in addition to the acquired familiarity with reinstallation of reactor coolant piping, is estimated to account for an additional savings of 95 manrem.

PRS-12 SSGP 3.10 General Techniques and Practices In addition to the specific dose reduction techniques described thus far, it is important to note the more general procedures and practices which were implemented prior to and during the repair effort to assure adequate control of occupational radiation ex-posure and to maintain this exposure ALARA.

A brief description of each is given below.

(a)

A comprehensive Heal th Physics program was implemented to provide adequate control and surveillance of the radiation hazards associated with each task.

This program included the use of Radiation Work Permits (RWP' s) to familiarize workers with the specific radiological hazards involved and proper protective measures to be taken in the performance of their work.

The successful implementation of this program is evi-deuced by the excellent radiation protection record which was achieved.

(b)

An extensive training program was conducted to provide ade-quate instruction in the biological effects of radiation

exposure, radiation protection practices and applicable federal regulations to all personnel involved in the steam generator replacement activities.

Training for specific tasks, using mock-ups, photographs or "dry runs" was conducted where appropriate.

(c)

The use of discrete "Work Packages" provided a mechanism to assure adequate preplanning and review of specific tasks, with special emphasis on minimizing radiation exposures to the personnel involved.

(d)

Spec'ial tools and equipment, designed to minimize personnel exposure times by increasing worker efficiency and providing remote handling capability were utilized where practicable.

( e)

PRS-13 SSGP A consultant was retained to compile an extensive photographic and video-tape documentary of the entire steam generator re-placement project for Unit No. 2.

Components, equipment and work areas involved in the major tasks were photographed in detail to record significant events as the tasks progressed from start to completion.

Video-tapes were used to record actual operations where complex procedures or equipment was used, or where the activity was repetitive in nature.

This documentation was of significant benefit in training and retraining of personnel for the Unit No. 1 Steam Generator Replacement Project.

(f)

General work area cleanup and debris removal was performed periodically to avoid buildups and maintain good radiological working conditions.

Decontamination of tools, equipment and components was also performed when necessary to facilitate handling and transfer.

These efforts resulted in cleaner and safer work areas and minimized the potential for radioactive airborne contamination throughout the repair effort.

(g)

Early in the project, "rest areas" were designated inside the containment to accommodate workers during idle periods.

The rest areas were located where exposure levels were minimum (less than 5 mR/hour) and were well posted for identification.

Effective utilization of rest areas was continually emphasized to workers in order to minimize unnecessary exposure.

Although quantitative assessments could not be performed for these "general" techniques, all have been of significant value in contri-buting to the overall ALARA program for the steam generator replace-ment project.

4. 0 RADIOACTIVE EFFLUENTS AND SOLID WASTE 4.1 General PRS-14 SSGP Radioactive liquid and gaseous effluents, and radioactively con-taminated solid wastes generated during the SGRP for Unit No. 1 are summarized in Table 2.

given below.

4.2 Airborne Releases A description of each category is Airborne releases during the repair effort originated primarily from the initial purging of containment following shutdown, and continuous ventilation thereafter.

This was necessary to maintain a negative pressure while the equipment hatch was open.

These re-leases were processed through appropriate filter banks to minimize the concentration of airborne particulates released to the environ-ment.

The relative isotopic distributions observed for airborne releases is presented in Table 2C.

4.3 Liquid Releases The major contributor to liquid effluent releases attributed to the SGRP was the disposal of laundry waste water.

The activities and relative distributions of the major isotopes released in liquid effluents is presented in Table 2B.

4.4 Solid Radioactive Waste The solid radioactive waste generated during the repair effort consisted of:

(i) contaminated insulation, structural materials, and components not intended for reuse, (ii) solidified liquids used for decontamination, and (iii) contaminated paper waste, disposable protective clothing and contamination control materials.

5.0 STEAM GENERATOR STORAGE BUILDING SURVEILLANCE PRS-15 SSGP The Steam Generator Storage Building was reopened in November of 1980 to receive the steam generator lower assemblies removed from Unit No. 1.

The building was subsequently closed and resealed, and a periodic surveillance program was resumed.

Average contact expo-sure rates measured on the outside of the building are less than 0.1 mR/hr, as anticipated, and the building HEPA filters continue to show no detectable radioactivity.

It is apparent, however, that some pathway for water intrusion into the building still exists; as shown by periodic checks of the collection sump level.

Additional sealing work is planned to correct this condition.

6.0 CONCLUSION

S PRS-16 SSGP The following general conclusions have been made based on the information contained within this report.

(a)

The total exposure (manrem) expended during the repair effort on Unit 1 was significantly less than the original estimate established prior to the project, and represents a consider-able exposure savings when compared to the Unit No. 2 total.

The ALARA techniques described in Section 3, and the benefit of prior experience gained during the Unit No.

2 SGRP are attributable as the major factors in this success.

b)

Radioactive liquid effluents were below the total release estimate presented on page 9.A.5-5 of the SGRP Report and, as expected, were less than 1% of that normally encountered dur-.

ing station operation.

(c)

Radioactive gaseous effluents released during the repair pro-gram were comparable to, but less than the estimates esta-blished in the SGRP Report on page 9.A.8-7. The reported noble gas releases occurred as a normal result of the defueling operation.

Radioiodine releases were comparable to the esti-mated value and gradually decreased to undetectable quantities due to their short half-lives.

Radioactive particulate and tritium releases were lower than but comparable to the esti-mated quantities.

(d)

Solid radioactive waste generation for the Unit No. 1 repair program exceeded the volume and activity estimates set forth on page 9.A.9-2 of the SGRP Report, as was the case for Unit No. 2.

(e)

Surveillance data obtained thus_ far indicates the following with respect to onsite storage of the old steam generator lower assemblies.

PRS-17 SSGP (i)

Radiation levels measured at the outside wall of the storage building are less than 0.1 mR/hr on contact.

This is less than the estimated level presented on page 9.A. 16-3 of the SGRP Report.

Therefore, the resulting radiation level at the site boundary will be less than 0.0001 mR/hr, as anticipated.

(ii)

Samples of the building HEPA filters have contained no detectable radioactive particulates; an indication that cleari and stable airborne conditions exist within the building.

(iii)

Water intrusion into the building is still occurring and additional sealing is necessary to correct this situation.

PHASE DESCRIPTION I

Shutdown and Preparatory Activities II Removal Activities III Installation Activities IV Post Installation and Startup Activities V Steam Generator Storage Activities SUBTOTAL Additional Tasks and Unassigned Personnel Categories PROJECT TOTALS TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

STEAM GENERATOR REPLACEMENT ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE (MANHOURS)

(MANHOURS)

(MAN-REM) 39,021 45,424 596.27 57,422 142,783 559.6 74,195 402,013 448.23 62,650 91,518 427.54 300 937 35.0 233,588 682,675 2,066.64 109,452 233,588 792,127 2,066.64 Page 1 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 194.786 396.511 811.531 150.589 8.079 1,561.496 197.319 1,758.815

TASK DESCRIPTION Erect Equipment Hatch*

Temporary Exposure Prepare and Load Test Polar Crane Open Equipment Hatch**

Defueling and Fuel Storage Install Reactor Vessel Cavity Cover Installation of Jib Cranes TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE I-SHUTDOWN AND PREPARATORY ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE (MANHOURS)

(MANHOURS)

(MAN-REM) 264 0.4 210 463 1.05 156 o*. 23 585 2,863

11. 7 130 753
1. 3 1,838 3,492 9.19 Disassemble Manipulato; Crane 58 629
1. 74 Install Steam Generator 572 3,948 2.86 Transport System Removal of Biological 1,296 916 19.44 Shield Wall Disassemble Shroud Cooling 150 601 3.0 System e

Page 2 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 1.285 23.503

1. 915 5.479 1.533 6.953 2.298
1. 228

TASK DESCRIPTION Cutting of Crane Wall at Hatch Opening Installation of Temporary Ventilation System Temporary Scaffolding Temporary Lighting and Power Cleanup and Decon Polar Crane Operator Shielding H.P., Q.A.

PHASE I SUBTOTAL TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE I-SHUTDOWN AND PREPARATORY ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMA,TED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE (MANHOURS)

(MANHOURS)

(MAN-REM) 432 586 2.16 so 106 0.05 7,500 4,846 75 5,200 2,174 26.25 9,000 14,920 135 1,500 198 4.5 3,600 2,045 270 6,480 6,884 32.4 39,021 45,424 596. 27 Page 3 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM)

1. 208 0.053 14.786 2.162 57.975 0.137 64.315 9.956 194.786

TASK DESCRIPTION ADDITIONAL TASKS Installation of Service Air System Work Platform Modification Protection of Containment Components TABLE l PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE I-SHUTDOWN AND PREPARATORY ACTIVITIES SURRY POWER STATION - UNIT NO. l ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE (MANHOURS)

(MANHOURS)

(MAN-REM) 627 1,939 1,289 UNASSIGNED PERSONNEL CATEGORIES Project Supervision Not Reported and Administration SUBTOTAL (ADDITIONAL 3,855 TASKS & PERSONNEL CAT.)

PHASE I PROJECT TOTAL 39,021 49,279 596.27 Page 4 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 2.198 0.752 6.158 8.471 17.579 212.365

TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE II -

REMOVAL ACTIVITIES SURRY POWER STATION - UNIT NO. 1 TASK DESCRIPTION Removal of Insulation (lower shell, RC Piping)

ESTIMATED LABOR (MANHOURS) 720 Removal of Insulation (upper shell, 864 mainsteam and feedwater piping)

Removal of Miscellaneous 72 Piping Set Up Steam Generator 1,152 Girth Cut Equipment Cut and Remove Steam 330 Generator Upper Shell Cut ting of Reactor 2,982 Coolant Piping Cutting of Mainsteam and 1,428 Feedwater Piping Disassembly of Steam 792 Generator Supports Removal of Moisture 396 Separation Equipment Refurbish Steam Generator Upper Shell 9,246 ACTUAL LABOR EXPENDED (MANHOURS) 1,647 959 1,288 90 5,529 7,181 1,399 6,988 5,333 12,990 ESTIMATED EXPOSURE (MAN-REM) 28.8 12.96 1.8 28.8 8.25 149.1 7.14 15.84

1. 98 46.23 Page 5 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 14.000 5.354
13. 896 0.208 9.173 76.682 2.391 55.120 9.402 10.884

TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE II -

REMOVAL ACTIVITIES SURRY POWER STATION -

UNIT NO. 1 ESTIMATED LABOR TASK DESCRIPTION (MANHOURS)

ACTUAL LABOR EXPENDED (MANHOURS)

Removal of Steam Generator Level 135 Instruments and Blowdown Piping Removal of Steam Generator Lower Shell Temporary Scaffolding Temporary Lighting and Power Cleanup and Decou Polar Crane Operator H.P., q;A.

PHASE II SUBTOTAL ADDITIONAL TASKS Material Handling, Equipment Maintenance, and Miscellaneous Construction Activities 1,575 7,500 5,250 17,000 1,500 6,480 57,422 1,472 4,341 13,611 5,356 44,732 2,365 27,502 142,783 24,484 ESTIMATED EXPOSURE (MAN-REM) 4.05

31. 5 75.0 26.25 85.0 4.5 32.4 559.6 Page 6 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 6.389 22.870 40.919 4.451 88.604 2.428 33.740 396.511 35.868

TASK DESCRIPTION TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE II -

REMOVAL ACTIV,ITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR LABOR EXPENDED (MANHOURS)

(MANHOURS)

UNASSIGNED PERSONNEL CATEGORIES Project Supervision Not Reported and Administration SUBTOTAL (ADDITIONAL 24,484 TASKS & PERSONNEL CAT.)

PHASE II PROJECT TOTAL 57,422 167,267 Page 7 of 13 ESTIMATED ACTUAL EXPOSURE EXPOSURE EXPENDED (MAN-REM)

(MAN-REM) 19.379 55.247 559.6 451. 758

\\ TASK DESCRIPTION Steam Generator Lower Shell Installation Installation of Reactor Coolant Piping Steam Generator Girth Weld Installation of Main Steam Piping Installation of Feedwater Piping Installation of Blowdown and Miscellaneous Piping Install Steam Generator I*

Level Instruments Installation of Insulation Temporary Scaffolding Temporary Lighting and Power TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE III -

INSTALLATION ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR LABOR EXPENDED (MANHOURS)

(MANHOURS) 1,926 12,250 6,768 31,365 5,400 15,791 3,735 7,036 2,700 6,418 1,782 16,051 2,592 8,297 11,562 1,024 7,500 28,757 5,250 11,805 Page 8 of 13 ESTIMATED ACTUAL EXPOSURE EXPOSURE EXPENDED (MAN-REM)

(MAN-REM) 9.63 25.888 67.68 233. 771 27.0 12.341 18.68 3.335 13.5 2.997 17.82 93.686 12.96 10.525 5 7. 81 6.531 75.0 91.674 26.25 6.477

TASK DESCRIPTION Cleanup and Decou Polar Crane Operator H.P., Q.A.

PHASE III SUBTOTAL ADDITIONAL TASKS Material Handling, Equipment Maintenance, and Miscellaneous Construction Activities TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE III -

INSTALLATION ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR LABOR EXPENDED (MANHOURS)

(MANHOURS) 17,000 172,542 1,500 9,225 6,480 81,452 74,195 402,013 67,539 UNASSIGNED PERSONNEL CATEGORIES Project Supervision Not Reported and Administration SUBTOTAL (ADDITIONAL 67,539 TASKS & PERSONNEL CAT.)

PHASE III PROJECT TOTAL 74,195 469,552 Page 9 of 13 ESTIMATED ACTUAL EXPOSURE EXPOSURE EXPENDED (MAN-REM)

(MAN-REM) 85.0 221. 466 4.5 4.863 32.4 97.977 448.23 811.531 70.694 33.876 104.570 448.23 916.101

TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE IV -

POST INSTALLATION AND STARTUP ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE TASK DESCRIPTION (MANHOURS)

(MANHOURS)

(MAN-REM)

Install Biological 3,240 2,772 16.2 Shield Wall Repair Crane Wall 473 95 2.37

.Opening Install Steam Generator 9,000 12,771 90.0 Recirculation and Transfer System Remove Reactor Cavity 130 161 0.65 Cover Install Reactor Cavity 240 1,665

1. 2 Coaming Reassemble Manipulator 1,176 1,572 23.25 Crane Remove Steam Generator 425 47 2.12 Transport System Reassemble Shroud 576 2,610
11. 52 Cooling System Hydrostatic Tests 75 2,923
0. 38 Refueling 585 600
11. 7 Page 10 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 4.822 0.080 33.756 0.375
2. 692
1. 783 0.014 3.055 7.447 2.158

TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE IV -

POST INSTALLATION AND STARTUP ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE TASK DESCRIPTION (MANHOURS)

(MANHOURS)

(MAN-REM)

Temporary Scaffolding

- 7,500 5,937 75.0 Temporary Lighting 5,250 2,379 26.25 and Power Cleanup and Decon 17,000 36,104 85.0 Polar Crane Operator 1,500 1,845 4.5 Painting 9,000 3,478 45.0 H.P., Q.A.

6,480 16,559 32.4 PHASE IV SUBTOTAL 62,650 91,518 427.54 ADDITIONAL TASKS Material Handling, Equipment 13,574 Maintenance, and Miscellaneous Construction Activities Page 11 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 17.956 1.302

41. 078 0.918 14.869 18.284 150.589 13.007

TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE IV -

POST INSTALLATION AND STARTUP ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE TASK DESCRIPTION (MANHOURS)

(MANHOURS)

(MAN-REM)

UNASSIGNED PERSONNEL CATEGORIES Project Supervision Not Reported and Administration SUBTOTAL (ADDITIONAL 13,574 TASKS & PERSONNEL CAT.)

PHASE IV PROJECT TOTAL 62,650 105,092 427. 54 Page 12 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 6.916 19.923 170.512

TASK DESCRIPTION Steam Generator Storage Activities TABLE 1 PERSONNEL RADIATION EXPOSURE

SUMMARY

PHASE V -

STEAM GENERATOR STORAGE ACTIVITIES SURRY POWER STATION - UNIT NO. 1 ESTIMATED ACTUAL LABOR ESTIMATED LABOR EXPENDED EXPOSURE (MANHOURS)

(MANHOURS)

(MAN-REM) 300 937 35.0 TABLE NOTATION Page 13 of 13 ACTUAL EXPOSURE EXPENDED (MAN-REM) 8.079 The Equipment Hatch Temporary Enclosure used for the Unit No. 1 SGRP was the same structure used for Unit No. 2 previously.

Thus, no fabrication was involved and erection required only lifting and placement.

Insignificant labor and exposure were expended for this task.

    • Labor and Exposure expenditures for this task were included in other task totals.

(Primarily "Defueling and Fuel Storage").

Labor and Exposure estimates are included in the Subtotal Values.

LIQUID RELEASES

~. UNt°TS I.

Curies Isotooe: Released MPC uci/ml I-131 3 X 10-1 I-132 8 X lQ-6 I-133 1 X 10-6 I-134 2 X 10-*

I-135 4 X 10-6 Cs-134 9 X 10- 0 Cs-137 2 X 10-*

Co-57 4 X 10-q Co.-5!1 g X 10-*

Co-bU 3 X 10-0 Mn-54 1 X 10-*

Na-24 3 X 10-0 Cr-51 2 X 10- 3 Fe-59 5 X lQ-5_

Nb-95 l

V 10-"

Sb-124 2 X ]Q-,

Sb-125 l

V 10-"

Zn-bS l x l 0-"

Zr-95 6 X 10-,

Mo-99

/,. X 10- 5 Ru-103 8 X 10- 5 Xe-133 3 X 10-b Xe-135 3 X 10-*

Xe-133m 3 X 10-6 Ar-41 3 X 10-6 Ag-HOm 3 X 10- 5 Ni-b3 3 X 10- 5 Fe-55 8 X 10-*

Ce-144 1 X 10-6 Tc-99m 3 X 10-'

Ce-141 9 X 10- 0 Volume of Liquid to Discharge Canal IT~~---

  • Not Detected
  • TABLE 2 SURRY POWER STATION
  • STEAM GENERATOR REPLACEMENT PROJECT REPORT OF RADIOACTIVE EFFLUENTS September October Novemher

"----',pr S.96E-5

/,.

Q *:ii;*.

~

?

?~R-"l

1. 73E-6 1.32E-5 3.47E-7 3.0lE-4 8.32E-4 2.48E-2

-2.'.:ltlE-4 1.04E-3 2.38E-3 3 35E-2 8.0BE-4 1.89E-6 3.57E-7 S.73E-4

':\\ /llR. ':\\

1.36E-2

!J.b0~-4 1.lOE-3

'i 72F-3 1.BlE-2 3.48E-3 3.36E-5 1 llE-4 2,78E-3 4.45E-5 1.17E-3 6.29E-3 1.99E-4 4.87E-4 1.14E-4 1.llE-5 S.68E-S 3.66E-5 1 21R.<;

1.20E-6 3.86E-5 7.SOE-7 1.44E-6 2.60E-6 1.89E-6 8.66E-5 4.74E-4 1.BSE-2 3.68E-6 7.48E-5 2.41E-3 1.lSE-5 8.38E-7

~

4.0lE-5 l.41E-3 1..lSE-3 1:ooE-3 1.16E-4 1.12E-2

1. 77E-7 9.0BE-7 6.70E+4 S.89E+S 1.16E+6 4.76E+5 PAGE 1

of 6

YEAR: 1980

II.

AIRBORNE RELEASES u--..-s.

Released:

Isotopes (a)

Particulates Cs-134 Cs-137 Cr-51 Co-58 Co-60

-~.:.54 I

Fe-59 Cs-138 Rb-88

~b) Halogens 1-1,31 1-I-132 I-133 I

I-lJ{!

T-11'i

(!;;) !,a1,e1, Xe-133 Xe-133m Xe-135 I

Kr-85m Kr-85 Kr-87 Kr-88

\\

Ar-41 Xe-131m H-3 I*

I I

I

" r--

  • Nut Detected TABT.E 2 SURRY POWER STATTON STEAM GEN°ERJ\\TOR REPJ.ACEMENT PRO.JECT REPORT OF RADIOACTIVE IWFLlfENTS

~.--=-~- - - - --**=-= =~~-,-~ --~--:*-~-

UNITS September October November

-~~---,-*--**-**.:!.-.. - ciia~~= -=-:-~--..-..==-~-=-=*-

    • ---.. *----~

3.12E-6 1 22E-6 9.07E-6

1. 76E-5_

j,66E-5 4.42E-5 1.65E-5 2.63E-5 5,02E-5 1.65E-5 3.49E-5

- 5.97E-5

<;. Q'iF-~

1.()lE-4

'i ?l.F-'i l.78E-3 -- l6....12E::..l.

7.90E-4 4.73E-6 2.12E-6 2.31E-5 4.03E-5 4.44E+2 5.26E+l 5.22EO 7.89EO 3.21E-1 1<

7.OBE-1 2,lSE-1 6.97E-2


*--- --- *----~

I

. ___. __.,... - -. -.. - - _, *- -*- *.. _- *-. -* ***- -- ~

==-=--;-. ~ ~~,.- -.. - - -.-. -. -

PAGE 2

of_6 __

YEAR:

1980

~--

'December 2.73E-6 2.21E-5 1.94E-5 6.27E-5 l.74E-5 l.31E-6 5.62E-2

III SOLID RADIOAeTIVE WASTE DISPOSAL

=*

Released:

Isotopes (a)

Total Amount of Solid Hantc Packaged (b)

Estimated Total Activity (c)

Date of Shipment and Disposition

~----=--=-==-=-===-=-=-=-=--==--=:*;-=- *-- ---*=-==---

I

  • TABLF. 2 SURRY POWER STATION STEAM GENERATOR REPLACEMENT PROJECT REPORT OF RADIOACTIVE EFFLUENTS

! Units Sen_tem~~ ~!kt!ili.eL-....

Curies FT 3 0

3.94E+3

  • 6.30E+3 Curies 0

1.451HO 1.82E+l frll to

!11 to

{lrnwell, I c::a~nwell, 0.....

s-r 10-15-80 11-3-80 110-21-80 11-4-80 10-23-80 11-6-80 10-28-80 11-7-'80 (2) 10-30-80

. 11-10-80 11-12-80 11-13-80

!11-14-80 11-18-80(2) ll-lQ-80 PAGE 3

of 6 YEAR: 1980 na~omb:J 1.64E+4 8.54E+O

~H to rnwell c:: r 12-1-80 (2) 12-2-80 (2) 12.-3-80 (2) 12-4-80 (2) 12-5-80 (2) 12.-8-80 12-11..:!!Qffi 12.-12-80 15..:80 12-16-80 12-17-80 12-18-80 12-19-80 12-22-80*

12-30-80(2)

UNt°TS I.

LIQUID RELEASES Curies Isoto(!e: Released MPC ~Ci/ml I-131 3 X 10-1 I-132 8 X 10-6 I-133 1 X 10-6 I-1Jl1 2 X 10-b I-135 4 X Io-G Ca-1Jl1 9 X 10-6 Cs-137 2 X 10-*

Co-57 4 X 10-*

Co,-50 9'x 10-*

    • r:;;=rio J X 10-*

!In-St, 1 X 10-*

. ii~-2/1

] X 10.*

- Cr-51 2 X 10-,

Fc-59 5 :g JO-'

.. Hb-95 1 X )0-lj

  • sii-121, 2

10-

~

g
  • sb-lis 1 X 10-4

-zn-b5 LLJ.!l-4

-*~r-95 6 x 10-b

--Mo-99 1 X lQ-5 nu-103 8 X 10-s X!!-133 3 X 10- b

-xe-135 3 X 10-*

xi;=1:iJn, 3 X 10-6

    • Ar=-ff 3 x 10-6 I i\\i;~:11om 3

10-*

X I* 11t=r,1 3 ll 10- 5 If<>_,,

8 x 10-*

. i:~-J.l,(,

1 X JO-*

  • rc-9<Jm 3 X m-,
  • ce-17il

!I X HJ-5

  • volume of L19uiil to ulscl1arge Canal l.i t.......
  • Not netl'cted TARl,E 2 SUllR'rPOIIEif STATION

. -REPORT OP RADIOACTIVE EPFLU~

. JANUARY

  • 1 llf.BRUARY MARCH APRIL

~~

~

1. 32E-6 l~

fr 11 t,,OlE-4 6,00E-4 2.lO!l-4 9.41E-4 1.49E-]

1,60!(-3 9.02E-l1 1.83E-3 8,28E-7 l.27E-5 1.52E-7 9.09E-7 l.69E-3 6.SOf.-4 2.28E-4 l.94E-3 7,64E-3 4,30Ii-3 2,{iSJ;-J 7.08E-3 1.BlE-4 5,00E-5 z 28E-6 9.02E-5 2.00E-4 2.21E-5 l~

~.

3.07E-5 4,DOE-6

],61E-6 S.86E-6

  • ~-

)~

~.13E-6*

2.JOE-4 3,63E-5 l.OJg-4 l.25E-6 k

5 9lE-6 l OOE-3

-1..1l!lE-li-

  • l OOIHi 1.0QE-6 4 lOE-7

.!.03E-4

1. 77E-3 1.31E-5 t,

)~

7.40E+S 8,00E+5 9.02E+S

.8.4SE+S r

PAm*:

4 of 6

YEAR: 1981 MAY JUNE

~--*

t::::t.

    • -*-:1::.*

5.21E-4 3.BSE-3 l.28E-3 6.14E-3 1.37E-6 2.32E-6 2.27E-3 1.96E-3 6,88E-3

1. 20E-2 1.BlE-4 l.84E-4 2.89E-5 l.91E-5 9.JBE-6 1.13E-5 2.JSE-5

~.5liE-b 5,39E-6 2.12E-5

--r--

R 7 ~F.-l.

4*, 87E-4

-ii 2°,34E-2

~

7.29E+5 6.16E+S

II. AIRBORNE RELEASES fu:*"isotopes Released:

(a}

Particulates Cs-134 Cs-137 Cr-51 Co-58 Co-60 Mn-:iti Fe-.59 Cs.'..I'.ln Rb-88 Nh-95 M

Halogens I-1:ll 1-132 I-lJJ I-lJ/1

.

  • I-lJS (c)

Gases Xe-lJ3 I

Xe-l.33m Xe-135 Kr-85m Kr-85 Kr-87 Kr-88 Ar-ltl Xe-lJlm 11-3

!1 ----

I' **--*

!!.. ~ -* *-.....

  • Nol llelectetl

'l'ABT.E 2 SURRY~WE!lSTATION STEAM GENF.Rl\\TOR REPLACEMENT PROJEC'l' REPORT 0\\1 RADIOACTIVE EFFLUENT:;

JANUARY FEIIRUARY MARCIi UNITS i~

Curies l.69E-5 1 f\\1'R-1'

1. lSE-4 7.13E-6 l

1~R-~

2.82E-4 5.44E-4 1.24E-4 J,ME-5 l.92E-5 1 1/iF.-li 2.lSE-,-6

  • /;,

f, 5.BOE-2

,3,33E-2

  • i.2rn-2

-~

---....a.~,=~~-

l'AGE __

S __ of __ 6 YEAR: 1981 _

APRIL MAY JUNE 5 09E-6 4 RliF.-6 4.92E-6

? 1QR~5 204E-5 2.43E-5 s*saE-s 3.31E-5

1. 46E-6

? i;oi,_4 4.00E-4 5,63E-5 4.97E-7 1.0SE-6

'ii 2 20E I 1.57E+O 7.07E-l 1*

~-----,,-

. ~~--~--~.

Ill, SOLID RADIOACTIVE WASTE DISPOSAL Unite TA.UJ.J~.£.

SURRY POWER S'l'ATION STEAM GENERATOR REl'i.ACEMENT PROJECT REPORT OF RADIOACTIVE EFFLUENTS JANUARY FEilRUARY MARCIi l'A(:l*:..., 6 -___ or_--~...

YEAR:

1981 APRIL MAY JUNE 0=======================11====11-------*- -------------*-* * *-*----*--* *** *------ * **** * ** *------**** ** *

  • __ 1,s.o_t_o=pe_s--::R_e-:l_ea_e_e_d_:--=-=-~,.,....=---------llt-.CU_r_i_ee--l I-----' _, __________ _

(a)

Total Amount of Solid Waste


1<-------11-- -*---------- ' -------

Packaged FT 3 7.48JW3

].01E+l1


'-'--'-""------------------11-----11--.c..;----- ~-------

(\\,)

Estimated Total Activity Curies 6, 32E+O 9 * )liE-1 1.07E+4 4.27E+3 4.29E+3 4.10E+3

2. 21E+0 ___,, __

1_. -12_E_* +-o--*ll-~5-. 3~0~E-+~o--* 9

Date of Shipment and

Barnwell, Barnwell,
Barnwell, Barnwell,
Barnwell, Barnwell,

___ __.cD_i_e.._p-'--oec...ic..t_i_o0110 _____________ ---l,-------ll--S-._c_. ___

11 __

s

  • C
  • S, C, S. C.

S. C,

__ S~. C_. ___

11 1-6-81 2-3-8]

3-2-81 4-2-81 5-5-81

  • 6.:.:5-81

ll----4 --1.dldll___.---2=..4=131 3-3-81 4-4-8]-.--*ll--5---7--8-1--*H-6--~9::-::8=1~_-_-_-_:"

1-()-8)

--2=5dll 3-6-81 4-9-81 5-13-81 6--::t1=~-

l-l 3-81.____ ---2=n=£)______

~3 __

-J=0~-~8=] ___

11_~4--2~1,_-_08~1 __ 5-14-81 6-16-81 J-14 81

...L:.1.0 Bl 3-11-81 4-~4-81

  • s=i9-°8_1 __ 6-2~-1--

1-15-81.____

2-12 81 3-16-81 4-28-Hl 5-21-81 1-?0 -Rl 2-11-8]___ 3-1 7-81 5-26-81 1-?1-Rl

?-lr.-Rl 3-19-8]

5-27-81 1-?fi-ftL_

'.J-lA-111 3-20-81


11-----11------11--?--~-?~0.dJJ___ 1-,;3-::..2<...3i:-;.,.8uJ ___,,_ ______,f.. ------fl------ll

?_?0-111 1-~~-~-?......._h-~.llu:1 ___ 1r------~1-------p------11


H*----11------11------11------*ll-------11------, -----

'-'=================::ll===-:c7:C:-*:l-1---,------11------1-1------11----- ----- *- *** * -

Volume (gal.)

Activity (Ci)

TABLE 2A EFFLUENT RELEASE AND SOLID WASTE COMPARISON

SUMMARY

STEAM GENERATOR REPLACEMENT PROJECT SURRY POWER STATION -

UNIT NO. 1 LIQUID EFFLUENTS Total Estimated Releases 6

2.3 X 10 0.344 Total Actual Releases 6

1.8 X 10 0.259 GASEOUS EFFLUENTS Estimated Release/Unit Actual Release During Isotope Noble Gases Iodines Particulates Tritium 3

Volume (ft )

Activity (Ci)

During SGRP (Ci)

Negligible 4.53 X 10-3 3.12 X 10-3 8.49 Unit No. 1 SGRP (Ci) 510 3.27 X

2. 70 X SOLID WASTE Estimated Quantities 26,236 18.9 4.18 10-3 10-3 Total 1977 Liquid Releases
1. 4 X 10 8 67.67 Average Six Month 1977 Release/Unit (Ci) 7400 0.24 1.4 X 10 120 Actual Quantities 67,580 45.0

-4

~.

Isotope Co-60 Cs-137 Fe-55 Cs-134 Co-58 Xe-133 Na-24 Ni-63 Mn-54 Xe-135 I-131 All Others Total TABLE 2B EFFLUENT RELEASE ISOTOPIC DISTRIBUTIONS STEAM GENERATOR REPLACEMENT PROJECT SURRY POWER STATION - UNIT NO. 1 LIQUID EFFLUENTS Total Activity Released (Ci) 6.88 X 10-2 5.10 X 10-2 3.65 X 10-2 3.27 X 10-2 2.68 X 10-2 2.01 X 10-2 7.66 X 10-3 5,17 X 10-3 3.66 X 10-3 2,59 X 10-3 2.36 X 10-3 1.59 X 10-3 2.59 X 10-1 Percent of Total Activity 27 20 14 13 10 8

3 2

1 1

< 1

< 1 100

1 Isotope Noble Gases Xe-133 Others Total Iodines I-131 Others Total Particulates Co-60 Co-58 Cs-137 Cs-138 Cr-51 Others Total TABLE 2C EFFLUENT RELEASE ISOTOPIC DISTRIBUTIONS STEAM GENERATOR REPLACEMENT PROJECT SURRY POWER STATION - UNIT NO. 1 GASEOUS EFFLUENTS Total Activity Released (Ci) 496. 6 13.4 510.0 3.20 X 10-3 7.16 X 10-5 3.27 X 10-3 1.65 X 10-3 4.85 X 10-4 2.90 X 10-4 1.01 X 10-4 6.07 X 10-5 1.16 X 10-4

2. 70 X 10-3 Percent of Total Activity 97 3

100 98 2

100 61 18 11 4

2 4

100