IR 05000306/2014010: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 74: Line 74:


====a. Inspection Scope====
====a. Inspection Scope====
(1) Review of Newly Identified Structures, Systems, and Components The inspectors discussed the identification of newly identified Structures, Systems, and Components (SSCs) under the purview of 10 CFR 54.37(b), with the licensee's license renewal staff. The licensee performed a review of engineering changes and the site component database to identify SSCs, which had not previously been screened for license renewal applicability. In their letter dated November 20, 2012 (ML12335A135), pursuant with 10 CR 54.37(b), the licensee stated 592 SSCs were found to be subject to aging management requirements and therefore were considered "newly identified" SSCs. The inspectors confirmed all newly identified components had been assigned to existing Agin g Management Programs (AMPs) and appropriate aging management strategies had been invoked to detect and manage the applicable aging effects throughout the period of extended operation. The inspectors verified the list of newly identified SSCs were included as an enclosure to the Updated Safety Analysis Reports (USAR) updates issued November 20, 2012 and June 27, 2014
: (1) Review of Newly Identified Structures, Systems, and Components The inspectors discussed the identification of newly identified Structures, Systems, and Components (SSCs) under the purview of 10 CFR 54.37(b), with the licensee's license renewal staff. The licensee performed a review of engineering changes and the site component database to identify SSCs, which had not previously been screened for license renewal applicability. In their letter dated November 20, 2012 (ML12335A135), pursuant with 10 CR 54.37(b), the licensee stated 592 SSCs were found to be subject to aging management requirements and therefore were considered "newly identified" SSCs. The inspectors confirmed all newly identified components had been assigned to existing Agin g Management Programs (AMPs) and appropriate aging management strategies had been invoked to detect and manage the applicable aging effects throughout the period of extended operation. The inspectors verified the list of newly identified SSCs were included as an enclosure to the Updated Safety Analysis Reports (USAR) updates issued November 20, 2012 and June 27, 2014
, (ML14203A383). The inspectors did not identify any deficiencies.
, (ML14203A383). The inspectors did not identify any deficiencies.
 
: (2) Review of Updated Safety Analysis Report and Commitment Change Process As part of reviewing the AMPs associated with the commitments, the inspectors reviewed the U SAR descriptions to confirm the implemented programs were consistent with the U SAR descriptions.
(2) Review of Updated Safety Analysis Report and Commitment Change Process As part of reviewing the AMPs associated with the commitments, the inspectors reviewed the U SAR descriptions to confirm the implemented programs were consistent with the U SAR descriptions.


The inspectors reviewed the licensee's procedures to ensure that commitment revisions would follow the guidance in NEI 99
The inspectors reviewed the licensee's procedures to ensure that commitment revisions would follow the guidance in NEI 99
Line 83: Line 82:


No disparities were identified with respect to implementation.
No disparities were identified with respect to implementation.
 
: (3) Review of Commitments The inspectors reviewed supporting documents including completed surveillance records and conducted interviews to veri fy the licensee completed the necessary actions to comply with the license conditions that are a part of the renewed operating license. The inspectors verified the licensee implemented the AMP s and time-limited aging analyses (TLAA) included in NUREG
(3) Review of Commitments The inspectors reviewed supporting documents including completed surveillance records and conducted interviews to veri fy the licensee completed the necessary actions to comply with the license conditions that are a part of the renewed operating license. The inspectors verified the licensee implemented the AMP s and time-limited aging analyses (TLAA) included in NUREG
-1 960, "Safety Evaluation Report (SER) Related to the License Renewal of the Prairie Island Nuclear Plant Units 1 and 2
-1 960, "Safety Evaluation Report (SER) Related to the License Renewal of the Prairie Island Nuclear Plant Units 1 and 2
," (ML 11235A622)
," (ML 11235A622)
Line 243: Line 241:
Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 14.
Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 14.


15. Commitment Item 15 , Fuel Oil Chemistry Program Commitment Item 15 specified the Fuel Oil Chemistry Program (FOCP) would be enhanced prior to the period of extended operation. Enhancements to the FOCP ensure: (1) particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in-scope of License Renewal will be performed, in accordance with American Society for Testing and Materials D6217, on an annual basis; and (2) One
15. Commitment Item 15 , Fuel Oil Chemistry Program Commitment Item 15 specified the Fuel Oil Chemistry Program (FOCP) would be enhanced prior to the period of extended operation. Enhancements to the FOCP ensure:
: (1) particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in-scope of License Renewal will be performed, in accordance with American Society for Testing and Materials D6217, on an annual basis; and
: (2) One
-Time ultrasonic thickness measurements will be performed at selected tank bottom and piping locations. The inspectors reviewed the licensing and program basis documents, procedures, work orders, and ARs associated with this program. The inspectors verified the program enhancements were complete through review of commitment implementing documents for:    particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in
-Time ultrasonic thickness measurements will be performed at selected tank bottom and piping locations. The inspectors reviewed the licensing and program basis documents, procedures, work orders, and ARs associated with this program. The inspectors verified the program enhancements were complete through review of commitment implementing documents for:    particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in
-scope of license renewal (recurring);
-scope of license renewal (recurring);
Line 411: Line 411:
Furthermore, the licensee committed the program will:
Furthermore, the licensee committed the program will:
be enhanced to include additional inspection parameters
be enhanced to include additional inspection parameters
;  require an inspection frequency of once every five (5) years for structures and structural components within the scope of the program. The frequency of inspections can be adjusted, if necessary, to allow for early detection and timely correction of negative trends; and  require periodic sampling of groundwater and river water chemistries to ensure they remain non
;  require an inspection frequency of once every five
: (5) years for structures and structural components within the scope of the program. The frequency of inspections can be adjusted, if necessary, to allow for early detection and timely correction of negative trends; and  require periodic sampling of groundwater and river water chemistries to ensure they remain non
-aggressive The inspectors reviewed the licensing and program basis documents. The licensee made enhancements to the applicable program basis documents and implementing procedures. These documents were applicable to both unit s and were reviewed during the Unit 1 inspection documented in IR 05000282/2013008; therefore, the inspectors did not perform further review. The inspectors reviewed a sample of corrective actions since the Unit 1 inspection and interviewed the plant personnel responsible for this program.
-aggressive The inspectors reviewed the licensing and program basis documents. The licensee made enhancements to the applicable program basis documents and implementing procedures. These documents were applicable to both unit s and were reviewed during the Unit 1 inspection documented in IR 05000282/2013008; therefore, the inspectors did not perform further review. The inspectors reviewed a sample of corrective actions since the Unit 1 inspection and interviewed the plant personnel responsible for this program.


Line 534: Line 535:
39. LR-TR-543, GALL Gap Analysis (LR
39. LR-TR-543, GALL Gap Analysis (LR
-TR-543/LRI-TR-001) At the time the licensee submitted their application for a renewed license, the NRC used Revision 1 of NUREG-1801, "Generic Aging Lessons Learned (GALL) Report
-TR-543/LRI-TR-001) At the time the licensee submitted their application for a renewed license, the NRC used Revision 1 of NUREG-1801, "Generic Aging Lessons Learned (GALL) Report
."  Since that time, the agency revised the NUREG incorporate (1) lessons learned from the reviews of previous license renewal applications, (2) operating experience obtained after the NRC issued Revision 1 to the GALL Report, and (3) other public input, including industry comments. On July 1, 2011, the NRC issued NRC Regulatory Issues Summary (RIS) 2011-05, "Information on Revision 2 to the Generic Aging Lessons Learned Report for License Renewal of Nuclear Power Plants," which describes the more noteworthy differences between the two revisions. Although the RIS does not require specific action or written response, this document highlights the value the NRC staff places on operating experience. It reminds licensees that the determination of the adequacy of AMPs is based, in part, on the applicant's consideration of, and its actions taken to address, both plant
."  Since that time, the agency revised the NUREG incorporate
: (1) lessons learned from the reviews of previous license renewal applications,
: (2) operating experience obtained after the NRC issued Revision 1 to the GALL Report, and
: (3) other public input, including industry comments. On July 1, 2011, the NRC issued NRC Regulatory Issues Summary (RIS) 2011-05, "Information on Revision 2 to the Generic Aging Lessons Learned Report for License Renewal of Nuclear Power Plants," which describes the more noteworthy differences between the two revisions. Although the RIS does not require specific action or written response, this document highlights the value the NRC staff places on operating experience. It reminds licensees that the determination of the adequacy of AMPs is based, in part, on the applicant's consideration of, and its actions taken to address, both plant
-specific and industry operating experience.
-specific and industry operating experience.



Revision as of 08:38, 17 September 2018

IR 05000306/2014010; on 07/14/14 - 08/1/14; Prairie Island Nuclear Generating Plant, Unit 2; Post-Approval Site Inspection for License Renewal
ML14258B212
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 09/12/2014
From: Stone A M
NRC/RGN-III/DRS/EB2
To: Davidson K
Northern States Power Co
Thomas Bilik
References
IR 2014010
Download: ML14258B212 (36)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532

-4352 September 12, 2014 Mr. Kevin Davidson Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2 NRC POST-APPROVAL LICENSE RENEWAL INSPECTION REPORT 05000 306/20 1 4 0 10

Dear Mr. Davidson:

On August 1, 201 4 , the U.S. Nuclear Regulatory Commission (NRC) completed a Post-Approval Site Inspection for License Renewal at your Prairie Island Nuclear Generating Plant, Unit 2. The enclosed report documents the results of this inspection, which have been discussed on August 1 , 201 4, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, performed walkdowns, and interviewed personnel.

Based on the sample selected for review, there were no findings of significance identified during this inspection. The team concluded commitments were properly identified, implemented, and completed.

Based on the sample selected for review and in consultation with the Division of License Renewal in the Office of Nuclear Reactor Regulation, the NRC concludes that the licensee has completed the necessary commitments for operation into the period of extended operation.

In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Ann Marie Stone

, Branch Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-306 License No. DPR-60

Enclosure:

Inspection Report 05000306/2 01 4 0 10

w/Attachment:

Supplemental Information cc w/encl: Distribution via LISTSERV

Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION III Docket No: 05000 306 License N o: DPR-60 Report No:

05000 2 82/2 01 4 0 10 Licensee: Northern States Power Company, Minnesota Facility: Prairie Island Nuclear Generating Plant, Unit 2 Location: Welch , MN Dates: July 14, 201 4 - August 1, 201 4 Inspectors:

T. Bilik, Senior Reactor Engineer (Lead) V. Meghani, Reactor Engineer G. O'Dwyer, Reactor Engineer A. Shaikh, Reactor Engineer S. Sheldon, Senior Reactor Engineer L. Smith, Observer Approved by: Ann Marie Stone

, Branch Chief Engineering Branch 2 Division of Reactor Safety 2

SUMMARY OF FINDINGS

Inspection

Report (IR)05000 306/20 1 4 0 10; 0 7/14/1 4 - 0 8/1/1 4; Prairie Island Nuclear Generating Plant, Unit 2; Post-Approval Site Inspection for License Renewal. The report covers a team inspection conducted by region-based engineering inspectors. The inspectors concluded that commitments, license conditions, and regulatory requirements associated with the issuance of the renewed operating license are being met. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process" Revision 5, dated February 2014.

A. NRC-Identified

and Self-Revealed Findings No findings were identified

.

B. Licensee-Identified Violations

No violations were identified

.

3

REPORT DETAILS

OTHER ACTIVITIES

4 OA 5 Other Activities

.1 Post-Approval Site Inspection for License Renewal

(Phase II) - Inspection Procedure 71003

a. Inspection Scope

(1) Review of Newly Identified Structures, Systems, and Components The inspectors discussed the identification of newly identified Structures, Systems, and Components (SSCs) under the purview of 10 CFR 54.37(b), with the licensee's license renewal staff. The licensee performed a review of engineering changes and the site component database to identify SSCs, which had not previously been screened for license renewal applicability. In their letter dated November 20, 2012 (ML12335A135), pursuant with 10 CR 54.37(b), the licensee stated 592 SSCs were found to be subject to aging management requirements and therefore were considered "newly identified" SSCs. The inspectors confirmed all newly identified components had been assigned to existing Agin g Management Programs (AMPs) and appropriate aging management strategies had been invoked to detect and manage the applicable aging effects throughout the period of extended operation. The inspectors verified the list of newly identified SSCs were included as an enclosure to the Updated Safety Analysis Reports (USAR) updates issued November 20, 2012 and June 27, 2014

, (ML14203A383). The inspectors did not identify any deficiencies.

(2) Review of Updated Safety Analysis Report and Commitment Change Process As part of reviewing the AMPs associated with the commitments, the inspectors reviewed the U SAR descriptions to confirm the implemented programs were consistent with the U SAR descriptions.

The inspectors reviewed the licensee's procedures to ensure that commitment revisions would follow the guidance in NEI 99

-04, Guidelines for Managing NRC Commitment Changes, including the elimination of commitments, and would properly evaluate, approve, and report changes to license renewal commitments listed in the U SAR , in accordance with 10 CFR 50.59. The inspectors reviewed each change associated with the commitment as noted in the next section.

No disparities were identified with respect to implementation.

(3) Review of Commitments The inspectors reviewed supporting documents including completed surveillance records and conducted interviews to veri fy the licensee completed the necessary actions to comply with the license conditions that are a part of the renewed operating license. The inspectors verified the licensee implemented the AMP s and time-limited aging analyses (TLAA) included in NUREG

-1 960, "Safety Evaluation Report (SER) Related to the License Renewal of the Prairie Island Nuclear Plant Units 1 and 2

," (ML 11235A622)

, i n accordance with Title 10 of the Code of Federal Regulations (CFR) Part 54, "Requirements for the Renewal of Operating Licenses for Nuclear Power Plants."

The inspectors verified the corrective actions taken to address issues identified during the Prairie Island Unit 1 License Renewal Phase II inspection , which was documented in IR 050002 82/20 1 3 00 9 (ML13205A429)

.

When changes to these commitments were identified, the inspectors reviewed the Commitment Change Evaluation (CCE) to verify the licensee followed the guidance in NEI 99-04 for the license renewal commitment change process, including the elimination of commitments, and properly evaluated, reported, and approved where necessary, changes to license renewal commitments listed in the U SAR , in accordance with 10 CFR 50.59.

The inspectors reviewed the commitments listed below which are referenced to Appendix A of the SER. All Commitment Item s were selected except Item 36, which was reported as complete in the SER

and therefore

, not reviewed.

Specific documents reviewed are listed in the

. 1. Commitment Item 1, Annual Prairie Island Nuclear Generating Plant Amendments to Prairie Island Nuclear Generating Plant Application Commitment Item 1 specified that each year, following the submittal of the License Renewal Application and at least three months before the scheduled completion of the NRC review, Nuclear Management Company (NMC) will submit amendments to the Prairie Island Nuclear Generating Plant application pursuant to 10 CFR 54.21(b). These revisions will identify any changes to the Current Licensing Basis that materially affect the contents of the License Renewal Application, including the USAR supplements.

The inspectors reviewed the license renewal application annual amendments submitted prior to completion of the NRC review.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 1.

2. Commitment Item 2, TLAA's, License Renewal Commitments, Incorporated into Prairie Island Nuclear Generating Plant USAR Commitment Item 2 specified that following the issuance of the renewed operating license, the summary descriptions of AMPs and TLAAs provided in Appendix A, and the final list of License Renewal commitments, will be incorporated into the USAR as part of a periodic USAR update, in accordance with 10 CFR 50.71(e).

Other changes to specific sections of the USAR necessary to reflect a renewed operating license will also be addressed at that time.

The inspectors verified that the summary descriptions of AMPs and TLAAs provided in Appendix A of the License Renewal Application, and the final list of License Renewal commitments were incorporated into the USAR.

Based on review of the timeliness and adequacy of the licensee

's actions, the inspectors determined the licensee met Commitment Item 2.

3. Commitment Item 3, Above Ground Steel Tanks

Commitment Item 3 states the Above Ground Steel Tanks Program perform s visual inspection of accessible external tank surfaces for corrosion. Inaccessible external surfaces (e.g., bottoms of tanks that sit directly on the ground or other support structures) will be inspected by ultrasonic inspection from inside the tank.

The inspectors reviewed the licensing and program basis documents, procedures, work orders, and Action Requests (ARs) associated with this program. This commitment requires that the licensee to ultrasonically examine the condensate storage tank (CST) bottoms to verify adequate thickness. The inspectors reviewed the ultrasonic test (UT) inspection results from the Unit 2 CST inspections. No concerns were identified during this inspection.

Based on the review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 3.

4. Commitment Items 4, Bolting Integrity Program Commitment Item 4 states, in part, the procedures for the conduct of inspections in the External Surfaces Monitoring Program, Structures Monitoring Program, Buried Piping and Tanks Inspection Program, and the RG 1.127 Inspection of Water

-Control Structures Associated with Nuclear Power Plants Program will be enhanced to include guidance for visual inspections of installed bolting.

The inspectors reviewed the licensing and program basis documents, implementing procedures, work orders, and ARs associated with this program. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 4.

5. Commitment Item 5, Buried Piping and Tanks Inspection Program Commitment Item 5 states the licensee will implement a Buried Piping and Tanks Inspection Program prior to the period of extended operation, as described in LRA, Section B2.1.8. The enhancements to the program are implemented to ensure:

The program performs visual inspections following excavation of external surfaces of buried piping and associated components (e.g., bolting) for evidence of coating damage and degradation of the underlying carbon steel and cast iron; A cathodic protection system is provided as an additional preventive measure, and is maintained at a minimum system availability of 90 percent. Cathodic protection system potential surveys are performed at least annually; Representative samples of buried piping, including a minimum of four inspection locations, are inspected every ten

-year period of the license renewal term; Initial inspections, conducted within the ten years prior to the period of extended operation, will include at least one buried piping segment in each system within the scope of the program. Each inspection will include a minimum of ten linear feet of piping; and A minimum of three tank inspections are performed once every ten years, with three tanks inspected in the ten years preceding the period of extended operation.

The program will ensure that all seven buried fuel oil tanks will be inspected over the

30-year period, starting ten years prior to the period of extended operation The inspectors reviewed the licensing and program basis documents, procedures, work orders, inspection documentation, and ARs associated with this program. The inspectors verified implementing documents have been established to implement inspections of the cathodic protection system.

Based on the review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 5.

6. Commitment Item 6, Closed Cycle Cooling Water System Program The Closed

-Cycle Cooling Water System Program is an existing program, consistent with, and includes an exception to, the program as described in GALL AMP XI.M21, "Closed-Cycle Cooling Water System."

Commitment Item 6 specified the program will be enhanced to include the attributes documented in LRA Section B2.1.9. The following enhancements will be implemented prior to the period of extended operation:

Periodic inspection of accessible surfaces of components serviced by closed

-cycle cooling water will be done when the systems or components are opened during scheduled maintenance or surveillance activities; Inspections are performed to identify the presence of aging effects and to confirm the effectiveness of the chemistry controls; Visual inspection of component internals will be used to detect loss of material and heat transfer degradation; and Enhanced visual or volumetric examination techniques will be used to detect cracking. The general program requirements for this commitment were previously inspected and determined to be complete as documented in Inspection Report 05000282/2013008. During this inspection, the inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection to verify the program remained effective for both units.

The inspectors also reviewed program basis documents, implementing procedures, and work orders. In addition to the commitment implementation review, the inspectors reviewed attributes of the Aging Management Program with IP 71002 to determine the adequacy of the program in detecting and monitoring aging effects. No concerns were identified during this inspection.

Based on the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 6.

7. Commitment Item 7, Compressed Air Monitoring Program The Compressed Air Monitoring Program as an existing program that is consistent with GALL AMP XI.M24, "Compressed Air Monitoring," with enhancements and an exception.

The enhancements ensure the Station and Instrument Air System air quality will be monitored and maintained, in accordance with the instrument air quality guidance provided in ISA S7.0.01. Particulate testing will be revised to use a particle size methodology as in ISA S7.0.01. The commitment also specifies the program will be enhanced to incorporate on

-line dew point monitoring.

The general program requirements for this commitment were previously inspected and determined to be complete as documented in Inspection Report 05000282/2013008

. During this inspection, the inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection to verify the program remained effective for both units.

The inspectors interviewed the program owner and reviewed the implementing procedures, completed work orders, scheduled recurring tasks for the program, and available trending data for applicable components. No concerns were identified during this inspection. In addition to the commitment implementation review, the inspectors reviewed attributes of the aging management program in accordance with IP 71002 to determine adequacy of the program in detecting and monitoring aging effects.

Based on the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 7.

8. Commitment Item 8, Electrical Cable Connections Not Subject to 10 CFR 50.49 Environmental Requirements Program Commitment Item 8 states the licensee will develop a new program that is consistent, with exceptions, to NUREG

-1801, Aging Management Program (AMP) XI.E6 for electrical cable connections not subject to 10 CFR 50.49 environmental qualification (EQ) requirements.

The licensee developed a one

-time inspection program, which conducts a test of a representative sample of electrical connections to confirm the absence of aging effects. The inspectors reviewed licensing and program basis documentation.

The licensee credited of all electrical thermography inspections conducted in 2012 to meet this one time inspection requirement. These results were previously reviewed during the Unit 1 inspection as documented in Inspection Report 05000282/2013008 and were not further reviewed.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 8.

9. Commitment Item 9, Electrical Cables

and Connections Not Subject to 10 CFR 50.49 Environmental Qualification (EQ) Requirements Program Commitment Item 9 states the licensee will develop a program that is consistent with NUREG-1801, AMP XI.E1 for electrical cables and connections installed in adverse localized environments not subject to 10 CFR 50.49 EQ requirements.

The licensee developed a program to visually inspect a representative sample of accessible electrical cables and connections installed in adverse localized environments to confirm insulation integrity. The program will also help to ensure the applicable electrical components will perform their intended functions.

The inspectors interviewed the program owner, reviewed licensing and program basis documentation, ARs, procedures, work orders, and records of walk downs for determining adverse localized environments, and visual inspections for cables. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 9.

10. Commitment Item 10, Electrical Cables and Connections Not Subject to 10 CFR 50.49 EQ Requirements Used in Instrumentation Circuits Commitment Item 10 states the licensee will develop a program that is consistent with NUREG-1801, AMP XI.E2 for electrical cables and connections used in instrumentation circuits exposed to adverse localized environments, not subject to

10 CFR 50.49 EQ requirements. The program includes periodic testing and review of surveillance data to manage the aging effect of reduced insulation resistance on non-EQ sensitive instrumentation circuit cables and connections.

The inspectors reviewed the licensing and program basis documents, procedures, work orders, and related corrective actions.

No concerns were identified during this inspection.

Based on the review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 10.

11. Commitment Item 1 1, External Surfaces Monitoring Program Commitment Item 11 states the licensee will implement an enhanced External Surfaces Monitoring Program prior to the period of extended operation. The inspectors reviewed the enhancements to verify:

the scope of the program was expanded as necessary to include all metallic and non-metallic components within the scope of License Renewal that require aging management, in accordance with this program; the program ensures surfaces that are inaccessible or not readily visible during plant operations will be inspected during refueling outages; the program will ensure surfaces that are inaccessible, or not readily visible during both plant operations and refueling outages will be inspected at intervals to provide reasonable assurance aging effects are managed such that the applicable components will perform their intended function during the period of extended operation; the program will apply physical manipulation techniques, in addition to visual inspection, to detect aging effects in elastomers and plastics; the program includes acceptance criteria (e.g., threshold values for identified aging effects) to ensure the need for corrective actions will be identified before a loss of intended function; and the program ensures program documentation, such as walkdown records, inspection results; and other records of monitoring and trending activities are auditable and retrievable.

The inspectors reviewed the licensing and program basis documents, procedures, work orders, and ARs associated with this program. The inspectors verified the program enhancements and program commitments to ensure all have been incorporated into implementing plant procedures.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 11.

12. Commitment Item 12, Fire Protection Program Commitment Item 12 specified the licensee has an existing Fire Protection Program, with enhancements, that is consistent with NUREG

-1801, AMP XI.M26. The Fire Protection Program was enhanced to require periodic visual inspection of the fire barrier walls, ceilings, and floors to be performed during walkdowns at least once every refueling cycle.

The general program requirements for this commitment were previously inspected and determined to be complete as documented in Inspection Report 05000282/2013008

. During this inspection, the inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection to verify the program remained effective for both units.

The inspectors also reviewed program basis documents, implementing procedures, and work orders. No concerns were identified during this inspection.

During the Unit 1 licensing renewal inspection, the inspectors reviewed the scheduled frequency of the enhanced inspections and identified the licensee scheduled the fire barriers inspections for every 18 months with a 25 percent grace period attached to it. The inspectors were concerned the inspection frequency did not meet the committed frequency of at least once per fuel cycle. The licensee initiated AR 01386211 t o address this issue. During this inspection

, the inspectors reviewed the corrective actions of AR 01386211 and found that the frequency of the inspection was changed to at least once per fuel cycle

, which met the commitment. The inspectors reviewed program basis documents, implementing procedures, and work orders. In addition to the commitment implementation review, the inspectors reviewed attributes of the Aging Management Program in accordance with Inspection Procedure (IP) 71002 to determine the adequacy of the program in detecting and monitoring aging effects.

No additional concerns were identified during this inspection.

Based on the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 12.

13. Commitment Item 13, Fire Water System Program Commitment Item 13 is an existing Fire Water System Program, with enhancements, that is consistent with NUREG

-1801, AMP XI.M27. The Fire Protection Program has been enhanced to add additional areas to the scope of the annual visual inspection and flushing activities, and to replace sprinkler heads that have been in service for 50 years. The general program requirements for this commitment were previously inspected and determined to be complete as documented in Inspection Report 05000282/2013008

. During this inspection, the inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection to verify the program remained effective for both units.

The inspectors interviewed the program owner, reviewed the licensing and program basis documents, procedures, work orders, and corrective actions. No concerns were identified during this inspection.

Based on the review of the timeliness and adequacy of the licensee's actions, the inspectors determined that the licensee met Commitment Item 13.

14. Commitment Item 14, Flux Thimble Tube Inspection Program The Prairie Island Nuclear Generating Plant Flux Thimble Tube Inspection Program manages the loss of material due to wear on the in

-core instrument thimble tubes. The flux thimble tubes provide a path for the in

-core flux monitoring detectors and form part of the reactor coolant pressure boundary. The program conducts periodic inspections to monitor thinning of the flux thimble tube wall through eddy current testing. The program provides evaluation and trending of inspection results and appropriate corrective actions.

Commitment Item 14 states the Flux Thimble Tube Inspection Program will be enhanced as follows:

The program will require the interval between inspections are established such that no flux thimble tube is predicted to incur wear that exceeds the established acceptance criteria before the next inspection; The program will require that re

-baselining the examination frequency be justified, using plant

-specific wear rate data unless prior plant

-specific NRC acceptance for re

-baselining have been received. If design changes are made to use more wear

-resistant thimble tube materials, sufficient inspections will be conducted at an adequate inspection frequency for the new materials; and The program will require that flux thimble tubes that cannot be inspected must be removed from service.

The inspectors reviewed the program basis document, procedures, work orders, and ARs associated with this program. The inspectors verified the program and program enhancements were in place.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 14.

15. Commitment Item 15 , Fuel Oil Chemistry Program Commitment Item 15 specified the Fuel Oil Chemistry Program (FOCP) would be enhanced prior to the period of extended operation. Enhancements to the FOCP ensure:

(1) particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in-scope of License Renewal will be performed, in accordance with American Society for Testing and Materials D6217, on an annual basis; and
(2) One

-Time ultrasonic thickness measurements will be performed at selected tank bottom and piping locations. The inspectors reviewed the licensing and program basis documents, procedures, work orders, and ARs associated with this program. The inspectors verified the program enhancements were complete through review of commitment implementing documents for: particulate contamination testing of fuel oil in the 11 fuel oil storage tanks in

-scope of license renewal (recurring);

external UT on select tank bottom locations on one of the vaulted fuel oil storage tanks for the Unit 2 emergency diesel generators; internal tank cleaning, visual inspection and internal UT on select bottom locations on one of the Unit 1 emergency diesel generator underground storage tanks; internal tank cleaning, visual inspection, and internal UT on select bottom locations of the diesel driven cooling water pump fuel oil storage tank. Comparable areas of the tank will be inspected to provide a basis for trend evaluation; external UT on select bottom locations on four of the seven diesel fuel oil day tanks; external UT on select bottom locations of one of the two D1/D2 clean fuel oil storage tanks; and external UT on select piping locations typically considered low flow/stagnant areas.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 15.

16. Commitment Item 16, Fuse Holders Program Commitment Item 16 states the licensee will develop a program that is consistent with NUREG-1801, AMP XI.E5.

The licensee developed a Condition Monitoring Program, which implements periodic visual inspections and test on fuse holders, in scope of license renewal, which are located in passive enclosures and assemblies, and exposed to environments that could potentially lead to electrical failures if left unmanaged. The licensee chose thermography as a proven test method.

The inspectors reviewed licensing and program basis documentation, procedures, work orders, and thermography inspections and results.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 16.

17. Commitment Item 17, Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Commitment Item 17 states the licensee will develop a program consistent with NUREG-1801, AMP XI.E3 for inaccessible medium and low voltage cables not subject to 10 CFR 50.49, Environmental Qualification.

The licensee developed a program, that performs periodic tests to provide an indication of the condition of the conductor insulation for inaccessible low and medium voltage power cables in scope of License Renewal and exposed to long periods of high moisture (greater than a few days at a time).

The program also includes actions to limit the exposure of in

-scope inaccessible low and medium voltage power cables to long term significant moisture, through periodic manhole and pull box inspections, for water accumulation, and draining of water, as needed.

The inspectors reviewed the licensing and program basis documents, work orders, and corrective actions. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 17.

18. Commitment Item 18, Inspection of Internal Surfaces of Miscellaneous Piping and Ducting Components Aging Management Program The Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Components Program is a new condition monitoring program consistent with GALL AMP XI.M38, "Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Components." This program performs visual inspections of the internal surfaces of mechanical components within the scope of License Renewal not covered by other aging management programs. The internal inspections are performed during scheduled preventive and corrective maintenance activities, or during other routinely scheduled tasks such as surveillance procedures, when internal surfaces are made accessible for inspections. The program inspections are performed to provide assurance that existing environmental conditions are not resulting in degradation that could result in a loss of component intended functions.

Commitment Item 18 states, an inspection of internal surfaces of miscellaneous piping and ducting components AMP will be implemented. The program features will be as described in LRA Section B2.1.22. Inspections for stress corrosion cracking will be performed by visual examination with a magnified resolution, as described in 10 CFR 50.55a(b)(2)(xxi)(A), or with ultrasonic methods.

General program requirements for this commitment were determined to be complete in Prairie Island Unit 1 IR 05000282/2013008. The inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection and ensured that the program remained effective for both units.

The inspectors reviewed the license renewal application, program basis documents, implementing documents, and interviewed the plant personnel responsible for this program.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 18.

19. Commitment Item 19, Inspection of Overhead Heavy Load and Light Load (Related to Refueling) Handling Systems Program Commitment Item 19 states that the program will be enhanced as follows:

Program implementing procedures will be revised to ensure the components and structures subject to inspection are clearly identified; and Program inspection procedures will be enhanced to include the parameters corrosion and wear, where omitte d. The inspectors reviewed the licensing and program basis documents. The licensee made enhancements to the applicable program basis documents and implementing procedures. These documents were applicable to both units, and since they were reviewed during the Unit 1 inspection documented in IR 05000282/2013008, the inspectors did not perform further review. The inspectors reviewed a sample of work orders performed since the Unit 1 inspection and interviewed the plant personnel responsible for this program

. Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 19.

20. Commitment Item 20, Metal

-Enclosed Bus Program Commitment Item 20 states the licensee will develop a program that is consistent with NUREG-1801, AMP XI.E4 for the interiors of the non

-segregated 4160V phase bus between station offsite source auxiliary transformers and plant bus.

The licensee developed a condition

-monitoring program that inspects the interiors of non-segregated 4160V phase bus between station offsite source auxiliary transformers and plant buses. The program manages the aging effect of reduction of installation resistance in insulation components, loose connections, and corrosion from moisture or debris intrusion in non

-segregated bus ducts.

The inspectors reviewed licensing and program basis documentation, corrective actions, implementing procedures, work orders, and inspections results.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 20.

21. Commitment Item 21, Nickel

-Alloy Nozzles and Penetrations Program Commitment Item 21 has been withdrawn according to Revision Letter dated March 27, 2009 (ML090900222)

. 22. Commitment Item 22, Nickel

-Alloy Penetration Nozzles Welded to the Upper Reactor Vessel Closure Head of Pressurized Water Reactors (PWRs) Program Commitment Item 22 was withdrawn by the licensee in the Annual Update of the Application for Renewed Operating License (L

-PI-09-043), dated April 13, 2009 (ML091140020). The withdrawal of the commitment was a result of the replacement of the Unit 1 reactor head, which incorporated Nickel

-Alloy 690 for each of the penetration nozzles instead of the Nickel

-Alloy 600 utilized in the previous heads. Inspections for the upper reactor vessel head surface and each nickel alloy reactor head penetration nozzle are being implemented, in accordance with the requirements of the American Society of Mechanical Engineers (ASME) Code Case N

1. 23. Commitment Item 23, One

-Time Inspection Program Commitment Item 23 states a One

-Time Inspection Program will be completed and the program features will be as described in LRA Section B2.1.29. The program developed a one

-time inspection program to verify unacceptable material degradation is not occurring in areas exposed to oil, steam, treated water, or other environments where significant degradation is not expected to occur. The one

-time inspection program addressed potentially long incubation periods for certain aging effects and has verified these aging effects are either, not occurring or are progressing so slowly as to have negligible effect on the intended function of the structure or component.

The inspectors reviewed the licensing and program basis documents. The inspectors previously reviewed the results of the one

-time inspections during the Unit 1 inspection as documented in IR 05000282/2013008. The inspectors reviewed results of an additional inspection performed since the Unit 1 inspection. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined that the licensee met Commitment Item 23.

24. Commitment Item 24, One

-Time Inspection of American Society of Mechanical Engineers Code Class 1 Small Bore

-Piping Program Commitment Item 24 states:

Part A: A one

-time inspection of ASME Code Class 1, Small-Bore Piping Program will be completed prior to the period of extended operation except as noted in Part B of this commitment. The program features will be as described in LRA Section B2.1.30. The following examinations of ASME Code Class 1 small-bore piping socket welds will be performed prior to the period of extended operation: Volumetric examinations of two socket welds on Unit 1 and three socket welds on Unit 2; or Destructive Examination of two socket welds per Unit; and Part B: Socket weld examinations required by the one

-time inspection of ASME Code Class 1, Small

-Bore Piping Program, not performed prior to the period of extended operation, will be performed within three years of each Unit entering the period of extended operation.

The licensee developed a one

-time inspection program for inspection of the small

-bore piping.

The inspectors reviewed licensing and program basis documentation.

The licensee completed inspections of a sample of welds as required by the program. Results of the inspections, with the exception of the volumetric examination of socket welds in Unit 2, were reviewed previously during the Unit 1 inspection documented in IR 05000282/2013008

. The inspectors reviewed results of a sample of the Unit 2 socket weld examinations and identified no issues

.

During review of the licensee's License Renewal Proof Notebook, the inspectors identified the sample size of Unit 1 socket welds did not meet the minimum 3 percent required by the program. According to the commitment, the licensee was required to perform two examinations prior to the period of extended operations and the remaining examinations as required to meet the minimum 3 percent sample size, were to be completed within three years after entering the period of extended operation.

For Unit 1, this inspection is expected to be complete by August 9, 2016.

Based on a population of 76 socket welds on Unit 1, the licensee needed to perform a minimum of three (2.28 rounded up) examinations. The licensee performed two examinations prior to the period of extended operations for Unit 1 per the commitment, but had not planned to perform the third examination. The licensee personnel rounded down the 2.28 value to two and believed that they had met the 3 percent sample size. In response to inspectors' concern, the licensee initiated AR 1439207 and AR 1441222 to capture the concern and to track completion of the required examination within the period specified in the commitment. As stated above, since the third inspection is required to be complete by August 9, 2016, no violation or deviation from this commitment was identified at this time.

Based on the review of the timeliness and adequacy of the licensee's actions, the inspectors determined that the licensee met Commitment Item 24.

25. Commitment Item 25, PWR Vessel Internals Program Commitment Item 25 originally state d the licensee committed to the following activities for managing the aging of reactor vessel internal components:

Participate in the industry programs for investigating and managing aging effects on reactor internals; Evaluate and implement the results of industry programs, as applicable to the reactor internals; and Upon completion of these programs, but not less than 24 months before entering; and t he period of extended operation, submit an inspection plan for reactor internals to the NRC for review and approval. The licensee will implement an enhanced Reactor Vessel Internals Program prior to the period of extended operation.

By letter to the NRC, dated May 12, 2009 (ML091620163), the licensee amended the LRA and revised the commitment to read as follows:

A PWR Vessel Internals Program will be implemented. The program features will be described in LRA Section B2.1.32. The program will be implemented prior to the period of extended operation; and An inspection plan for reactor internals will be submitted for NRC review and approval at least 24 months prior to the period of extended operation.

Then, by letter to the NRC, dated June 24, 2009

, (ML09190003 7), as a response to follow up request for additional information (RAI) B2.1.38, the commitment was revised to read as follows:

A PWR Vessel Internals Program will be implemented. Program features will be described in LRA Section B2.1.32 and will be implemented prior to the period of extended operation.

An inspection plan for reactor internals will be submitted for NRC review and approval at least 24 months prior to the period of extended operation. In addition, the submittal will include any necessary revisions to the scoping, screening , and aging management review results for reactor internals, to conform to the NRC

-approved Inspections and Evaluation Guidelines.

Lastly, by letter to the NRC, dated August 8, 2011

, (ML112210299), Part B of the commitment has been revised by a commitment change to read as follows:

An inspection plan for reactor internals will be submitted for NRC review and approval no later than October 1, 2012. In addition, the submittal will include any necessary revisions to the PWR Vessel Internals Program, as well as any related changes to the scoping, screening, and aging management, review results for reactor internals, to conform to NRC

-approved Inspection and Evaluation Guidelines.

The inspectors reviewed procedures, program basis documents, commitment change evaluation, and ARs associated with this program. In a letter dated October 1, 2012 , (ML12276A041), the licensee provided the inspection plan; therefore, the inspectors determined the licensee met Commitment Item 25.

26. Commitment Item 26, Reactor Head Closure Studs Program Commitment Item 26 specified the implementation of inservice inspection of the reactor vessel head closure studs. The program incorporates controls which ensure procurement of reactor head closure studs will be, in accordance with the material and inspection guidance provided in NRC Regulatory Guide (RG) 1.65. The inspectors reviewed the licensing and program basis documents, implementing procedures, work orders and ARs associated with this program.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 26.

27. Commitment Item 27, Reactor Vessel Surveillance Program The Reactor Vessel Surveillance Program is an existing program that manages the reduction of fracture toughness of the reactor vessel due to neutron embrittlement using monitoring methods, in accordance with 10 CFR Part 50, Appendix H, "Reactor Vessel Material Surveillance Program Requirements." This program ensures the reactor vessel materials meet fracture toughness requirements and have adequate margin against brittle fracture caused by pressurized thermal shock. Commitment Item 27 specified the licensee save and store all withdrawn and tested surveillance capsules and withdrawn, untested spare capsules.

The inspectors reviewed the licensing and program basis documents, procedures, work orders and related ARs associated with this program.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 27.

28. Commitment Item 28, Regulatory Guide 1.127, Inspection of Water

-Control Structures Associated with Nuclear Power Plants Program Commitment Item 28 states the program will be enhanced as follows:

Include inspections of concrete and steel components that are below the water line at the Screenhouse and Intake Canal. The scope will also require inspections of the Approach Canal, Intake Canal, Emergency Cooling Water Intake, and Screenhouse immediately following extreme environmental conditions or natural phenomena including an earthquake, flood, or tornado.

Include an inspection of water

-control concrete components that are below the water line for cavitation and erosion degradation.

Visually inspect for damage such as cracking, settlement, movement, broken bolted and welded connections, buckling, and other degraded conditions following extreme environmental conditions or natural phenomena.

The inspectors reviewed the licensing and program basis documents. The licensee made enhancements to the applicable program basis documents and implementing procedures. These documents were applicable to both units, and since the se were reviewed during the Unit 1 inspection as documented in IR 05000282/2013008, the inspectors did not perform further review. The inspectors reviewed a sample of work orders and corrective actions since the Unit 1 inspection.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined that the licensee met Commitment Item 28.

29. Commitment Item 29, Selective Leaching of Materials Program Commitment Item 29 states the implementation of an one

-time Selective Leaching of Materials Program. However, when examinations indicated that the selective leaching aging mechanism was present, the licensee implemented a continuing Selective Leaching of Materials Program (USAR change 01372330).

The inspectors reviewed the licensing and program basis documents, implementing procedures, work orders and ARs associated with this program.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 29.

30. Commitment Item 30, Structures Monitoring Program Commitment Item 30 states the Structures Monitoring Program will be enhanced prior to the period of extended operation to add the following structures, components, and component supports to the scope of the inspections:

Approach Canal; Fuel Oil Transfer House; Old Administration Building and Administration Building Addition; Component supports for cable tray, conduit, cable, tubing tray, tubing, non

-ASME vessels, exchangers, pumps, valves, piping, mirror insulation, non

-ASME valves, cabinets, panels, racks, equipment enclosures, junction boxes, bus ducts, breakers, transformers, instruments, diesel equipment, housings for heating, ventilation, and air conditioning (HVAC) fans, louvers, and dampers, HVAC ducts, vibration isolation elements for diesel equipment, and miscellaneous electrical and mechanical equipment items; Miscellaneous electrical equipment and instrumentation enclosures including cable tray, conduit, wire

-way, tube tray, cabinets, panels, racks, equipment enclosures, junction boxes, breaker housings, transformer housings, lighting fixtures, and metal bus enclosure assemblies; Miscellaneous mechanical equipment enclosures including housings for HVAC fans, louvers, and dampers; Station Black out (SBO) yard structures and components including SBO cable vault and bus duct enclosures; Fire Protection System hydrant houses; Caulking, sealant and elastomer materials; and Non-safety-related masonry walls that support equipment relied upon to perform a function that demonstrates compliance with a regulated event(s).

Furthermore, the licensee committed the program will:

be enhanced to include additional inspection parameters

require an inspection frequency of once every five
(5) years for structures and structural components within the scope of the program. The frequency of inspections can be adjusted, if necessary, to allow for early detection and timely correction of negative trends; and require periodic sampling of groundwater and river water chemistries to ensure they remain non

-aggressive The inspectors reviewed the licensing and program basis documents. The licensee made enhancements to the applicable program basis documents and implementing procedures. These documents were applicable to both unit s and were reviewed during the Unit 1 inspection documented in IR 05000282/2013008; therefore, the inspectors did not perform further review. The inspectors reviewed a sample of corrective actions since the Unit 1 inspection and interviewed the plant personnel responsible for this program.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 30.

31. Commitment Item 31, Thermal Aging Embrittlement of Cast Austenitic Stainless Steel Program Commitment Item 31 states a Cast Austenitic Stainless Steel (CASS) Program be implemented with features as described in LRA Section B2.1.39. The CASS Program manages the loss of fracture toughness due to thermal aging embrittlement of components, other than pump casings and valve bodies. The program determines the susceptibility of CASS components to loss of fracture toughness due to thermal aging embrittlement based upon the casting method, molybdenum content, and percent ferrite. For components determined to be potentially susceptible to thermal aging embrittlement, component

-specific flaw tolerance evaluations are being prepared.

The inspectors reviewed the licensing and program basis documents, procedures, work orders and related ARs associated with this program.

No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 31.

32. Commitment Item 32, Water Chemistry Program Commitment Item 32 is an existing Water Chemistry Program, with enhancements, that is consistent with NUREG

-1801, AMP XI.M27. Commitment Item 32 states the licensee will implement an enhanced Water Chemistry Program prior to the period of extended operation. The enhancements to the Water Chemistry Program require an increased sampling as needed, per revised fleet procedure, FP

-CY-CHEM-01, to confirm the effectiveness of corrective actions taken to address abnormal chemistry conditions. The program will also require Reactor Coolant System dissolved oxygen action level limits to be consistent with the limits established in the Electric Power Research Institute (EPRI) PWR Primary Water Chemistry Guidelines.

The general program requirements for this commitment were previously inspected and determined to be complete as documented in Inspection Report 05000282/2013008. During this inspection, the inspectors reviewed changes to the program that occurred after the Unit 1 licensing renewal inspection to verify the program remained effective for both units.

The inspectors also reviewed program basis documents, implementing procedures, and work orders. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 32.

33. Commitment Items 33, 34, 35, and 47, Metal Fatigue of Reactor Coolant Pressure Boundary Program Commitment Item 33 states that the program will be enhanced as follows:

The program will monitor the 6

-component locations identified in NUREG/CR

-6260 for older vintage Westinghouse plants, either by tracking the cumulative number of imposed stress cycles using cycle counting, or by tracking the cumulative fatigue usage, including the effects of coolant environment. The following locations will be monitored:

(a). Reactor Vessel Inlet and Outlet Nozzles

(b). Reactor Pressure Vessel Shell to Lower Head
(c). Reactor Coolant System (RCS) Hot Leg Surge Line Nozzle
(d). RCS Cold Leg Charging Nozzle
(e). RCS Cold Leg Safety Injection Accumulator Nozzle; and (f). Residual Heat Removal

-to-Accumulator Piping Tee Program acceptance criteria wi l l be clarified to require corrective action is taken before a cumulative fatigue usage factor exceeds 1.0 or a design basis transient cycle limit is exceeded.

Commitment Item 34 states the reactor internals baffle bolt fatigue transient limits of 1,835 cycles of plant loading at 5 percent per minute and 1,835 cycles of plant unloading at 5 percent per minute will be incorporated into the Metal Fatigue of Reactor Coolant Pressure Boundary Program and USAR Table 4.1

-8. Commitment Item 35 states the licensee will perform an ASME Section III fatigue evaluation of the lower head of the pressurizer to account for effects of insurge/outsurge transients. The evaluation will determine the cumulative fatigue usage of limiting pressurizer component(s) through the period of extended operation.

The analyses will account for periods of both "Water Solid" and "Standard Steam Bubble" operating strategies. Analysis results will be incorporated, as applicable, into the Metal Fatigue of Reactor Coolant Pressure Boundary Program.

Commitment Item 47 states the licensee will perform a review of the design basis ASME Class 1 fatigue evaluations to determine whether the NUREG/CR6260 components that have been previously evaluated for the effects of reactor coolant environment on fatigue life are the limiting components.

If a more limiting component(s) is identified, the most limiting component will be evaluated for the effects of the reactor coolant environment on fatigue usage; and If the limiting component identified consists of nickel alloy, the methodology used to perform the Environmentally Assisted Fatigue (EAF) calculation for nickel alloy will be consistent with NUREG/CR

-6909, or otherwise justified.

The inspectors reviewed the licensing and program basis documents. Commitment Items 34, 35, and 36 were completed prior to the Unit 1 inspection as documented in inspection report 05000282/2013008

and therefore

, the inspectors did not perform further review. Program documents and procedures associated with commitment Item 33 were also reviewed during the Unit 1 inspection. The inspectors reviewed a sample of work orders associated with Commitment Item 33 and the Unit 2 calculations associated with Commitment Item 47. The inspectors also interviewed the plant personnel responsible for this program. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Items 33, 34, 35, and 47.

34. Commitment Items 36, Metal Fatigue of Pressurizer Surge Line Hot Leg nd the Charging Nozzles Commitment Item 36 states the licensee will complete fatigue calculations for the pressurizer surge line hot leg nozzle and the charging nozzle using the methodology of the ASME Code (Subsection NB) and will report the revised Cumulative Usage Factor (CUF) and CUFs adjusted for environmental effects at these locations as an amendment to the application. Conforming changes to LRA Section 4.3.3, "PINGP EAF results," will also be included in that amendment to reflect analysis results and remove references to stress

-based fatigue monitoring.

Commitment 36 was completed per Attachment A of the SER.

35. Commitment Items 37, 38, 39, and 40, Cultural Resources Management Plan The Cultural Resources Management Plan (CRMP) was developed by the licensee in cooperation with the Prairie Island Indian Community and the U.S. Department of the Interior, Bureau of Indian Affairs. The CRM P was developed as a tool to licensee employees responsible for planning, reviewing, approving, overseeing, and/or participating in construction and excavation activities or other undertakings on the plant property. The CRM P seeks to: prevent disturbances of known and unknown archaeological, cultural, and historical (AC&H) resources by presenting the history of Prairie Island, its inhabitants, and the location and significance of its known AC&H resources; establish specific review and notification procedures for those who manage and conduct construction or excavation projects at the facility; and present guidance for proper identification of previously unidentified AC&H resources so the appropriate actions can be made.

Commitment Item 37 states the licensee will revise procedures for excavation and trenching controls and archaeological, cultural and historic resource protection to identify sensitive areas and provide guidance for ground

-disturbing activities.

The procedures will be revised to include drawings and illustrations to assist users in identifying culturally sensitive areas, and pictures of artifacts that are prevalent in the area of the site.

The revised procedures will also require training of the Site Environmental Coordinator and other personnel responsible for proper execution of excavation or other ground

-disturbing activities.

Commitment Item 38 states the licensee will conduct a Phase I Reconnaissance Field Survey of the disturbed areas within the site's boundaries.

In addition, the licensee will conduct Phase I field surveys of areas of known archaeological sites to precisely determine their boundaries.

The licensee will use the results of these surveys to designate areas for archaeological protection.

Commitment Item 39 states the licensee will prepare, maintain and implement a CRMP to protect significant historical, archaeological, and cultural resources that may currently exist on the plant site.

In connection with the preparation of the CRMP, the licensee will conduct botanical surveys to identify culturally and medicinally important species on the plant site, and incorporate provisions to protect such plants into the CRMP. Commitment Item 40 states the licensee will consult with a qualified archaeologist prior to conducting any ground

-disturbing activity in any area designated as undisturbed and in any disturbed are that is described as potentially containing archaeological resources (as determined by the Phase I Reconnaissance Field Survey discussed in Commitment Number 38). These commitments were reviewed during the Unit 1 inspection as documented in IR 05000282/2013008, and were not further reviewed.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 37, 38, 39, and 40.

36. Commitment Items 41, 42, and 4 4, Reactor Cavity Leakage Commitment Item 41 states that during the first outage after refueling cavity repairs

, the site will excavate the concrete in Sump C (containment low point) to perform examination of the containment vessel, concrete and rebar. This commitment was met for Units 1 and 2 prior to the Unit 1 inspection as documented in IR 05000282/2013008

and therefore

, the inspectors did not perform further review.

Commitment Item 42 states that for two consecutive outages after refueling cavity repairs , the site will inspect areas with a history of leakage. If leakage is identified

, it will be entered into the corrective action program and evaluated for additional actions. The licensee performed the required inspections during refueling outages 2R27 and 2R28 and identified the leakage had not been totally eliminated. The licensee entered the identified leakage into their corrective action program and created actions for continued investigations and identification of leakage reduction opportunities.

Commitment Item 44 states that during the first refueling outage following refueling cavity leak repairs in each Unit (repairs performed in refueling outages 1R26 and 2R26), a concrete sample will be obtained from a location known to have been wetted by borated water leakage from the refueling cavity. These concrete samples will be tested for compression strength and will be subjected to petrographic examination to assess the degradation. This commitment item was met for both units as documented in IR 05000282/2013008

and therefore

, the inspectors did not perform further review.

The inspectors reviewed the licensing and program basis documents, ARs, and work orders documenting the inspection results and additional actions. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Items 41, 42, and 44.

37. Commitment Item 43, Diesel Generator Hose Replacement Commitment Item 43 states the licensee would implement a Diesel Generator Hose Replacement Program prior to the period of extended operation.

License Renewal (LR) Commitment 43, "Replace DG Rubber Hoses," was created to ensure procedures are in place to require the periodic replacement of rubber hoses in contact with fuel oil and lube oil environments. During a previous inspection as documented in Inspection Report 05000306/2012005

-03 (ML13038A671), the inspectors identified a non

-cited violation of 10 CFR Part 50, Appendix B, Criterion III for the licensee's failure to establish measures for the review for suitability the use of rubber hoses beyond the vendor recommended service life. Specifically, several hoses in the D5 and D6 emergency diesel generators and in the diesel driven fire pump had been installed beyond the vendor recommended service life of 10

-years without further evaluation of acceptability. The licensee entered this issue into their CAP as CAP 1361849, evaluated the installed hoses condition, and replaced or scheduled the replacement of hoses installed longer than the recommended service interval.

During this inspection effort, the inspectors reviewed program basis documents, periodic replacement procedures, vendor manuals, work orders, and associated ARs and interviewed plant personnel responsible for this program. The inspectors verified the program requirements for this commitment were complete. The inspectors also verified the licensee implemented actions to periodically replace rubber flexible hoses exposed to fuel oil or lubricating oil internal environments in the emergency diesel generators, their support systems, and in the 122 diesel driven fire pump.

No additional concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Item 43.

38. Commitment Items 45 and 46, Steam Generator Tube Integrity Program The Steam Generator Tube Integrity Program is an existing program that manages the aging effects of steam generator tubes, tube repairs, and accessible steam generator secondary side internal components. Incorporating the guidance of NEI 97-06, the program manages aging effects through a balance of mitigation, inspection, evaluation, repair, and leakage monitoring measures.

Commitment Item 45 states the performance of an inspection of each original Unit 2 steam generator to assess the condition of the divider plates and associated welds if they are not replaced prior to entry into the period of extended operation

. Commitment Item 46 states the performance of a one

-time inspection sample of tube

-to-tube-sheet welds in each Unit 1 steam generator to determine if primary water stress corrosion cracking is present. The inspections are to be performed during the first Unit 1 refueling outage after the steam generators have reached 20 years of service. The inspectors reviewed the program basis document, implementing procedures, completed work orders and ARs associated with this program.

With respect to Commitment Item 45, the licensee did replace the Unit 2 steam generators; therefore, no additional action is required for this commitment. No concerns were identified during this inspection.

Based on review of the timeliness and adequacy of the licensee's actions, the inspectors determined the licensee met Commitment Items 45 and 46.

39. LR-TR-543, GALL Gap Analysis (LR

-TR-543/LRI-TR-001) At the time the licensee submitted their application for a renewed license, the NRC used Revision 1 of NUREG-1801, "Generic Aging Lessons Learned (GALL) Report

." Since that time, the agency revised the NUREG incorporate

(1) lessons learned from the reviews of previous license renewal applications,
(2) operating experience obtained after the NRC issued Revision 1 to the GALL Report, and
(3) other public input, including industry comments. On July 1, 2011, the NRC issued NRC Regulatory Issues Summary (RIS) 2011-05, "Information on Revision 2 to the Generic Aging Lessons Learned Report for License Renewal of Nuclear Power Plants," which describes the more noteworthy differences between the two revisions. Although the RIS does not require specific action or written response, this document highlights the value the NRC staff places on operating experience. It reminds licensees that the determination of the adequacy of AMPs is based, in part, on the applicant's consideration of, and its actions taken to address, both plant

-specific and industry operating experience.

The licensee entered the RIS into their corrective action program as LRI-TR-001 to evaluate the impact on the current AMPs. The inspectors noted the licensee only addressed the issues specifically identified in the RIS but did not perform a review of other differences between the revisions. After further discussion, the licensee initiated AR 01438469, "Some Aging Management Programs Not Considering GALL Revision 2," to evaluate any inconsistencies or gaps that could warrant changes to the AMPs based on this operating experience.

b. Findings and Observations

The inspectors identified two observations of minor significance as documented above. 4 OA 6 Management Meetings

.1 Exit Meeting Summary

On August 1, 201 4, the inspectors presented the inspection results to the Site Vice

-President, Mr. K. Davison and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION KEY POINTS OF CONTAC

T Licensee

K. Davison, Site Vice President
C. Younie, Plant Manager
B. Hammargren, Regulatory Affairs

Engineer

J. Whitfield, Programs Engineer
L. Farrell, Senior Programs Engineer
K. Davison, Director , Site Operations
A. Mitchell, Site Engineering Director
S. Sharp, Plant Manager
T. Allen, Assistant Plant Manager
J. Anderson, Regulatory Affairs Manager

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened, Closed, and Discussed

None

LIST OF DOCUMENTS REVIEWED The following is a list of documents reviewed during the inspection. Inclusion on this list does not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that selected sections of portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report.

4OA5.1 Other Activities

Action Requests Generated as a

Result of the Inspection

AR 01441228; Lacking Procedure Adherence

During License Renewal Inspection; July 31, 2014

AR 01441222; 2014 U2 LR Inspection

- Additional Inspection Required; July 31, 2014

AR 01441161; NRC

-Identified

No License R

enewal Inspection

Results Form 1766 in WO 482732

-01 as required; July 31, 2014

AR 01439649; Typographical

Error in H29 Metal Fatigue Mgmt Prgm

Procedure; July 23, 2014

AR 01439473; Incorrect

Sharepoint

Version of H29; July 22, 2014

AR 01439207; 2014 LR Inspection

- Non-Conservative Sample Size; July 21, 2014

AR 01438869; During U2 Phase II LR Insp., WO 475341

Not Printed in PNB; July 18, 2014

AR 01438834; Untimely Storage of Field Service Report

into Records Mgmt.; July 17, 2014

AR 01438469; Some Aging Management Programs not Considering GALL Rev. 2; July 15, 2014

Commitment Item 1

Xcel Energy Letter L

-PI-09-043; Annual Update of the Application for Renewed Operating Licenses; April 13, 2009

Xcel Energy Letter L

-PI-11-034; Annual Update of the Application for Renewed Operating Licenses; May 11, 2011

Commitment Item 2

Prairie Island Updated Safety Analysis Report; Appendix L, Section L.2:

Summary Description of Programs that Manage the Effects of Aging; Revision

33P Commitment Item 3

LR-AMP-437; License Renewal Proof Notebook, Aboveground Steel Tanks Program; Revision 2

AR 01399914; Corrosion Points Identified on the Floor of the 21 CST; February 14, 2014

AR 01395632; D5 and D6 Fuel Oil Storage Tanks Inspection 2013; September 4, 2013

Commitment Item

LR-AMP-408; License Renewal Proof Notebook, Bolting Integrity Program; Revision 0

H65.2.6; Bolting Integrity Aging Management Program; Revision 0

Commitment Item

LR-AMP-420; License Renewal Proof Notebook, Buried Piping and Tanks Inspection Program; Revision 0

8.1; PINGP Buried Pipe Inspection Program; Revision 0

AR 01405916; 12 MO Average Availability at 88.5

Percent for GC System Rectifiers; November

16, 2013

Commitment Item 6

H70; PINGP Closed

-Cycle Cooling Water Aging Management

Program; Revision 1

H65.2, Closed

-Cycle Cooling Water Aging Management Program

Revision 0

PINGP 1766; Closed Cycle Cooling Water System Internal Inspection Form

Revision 0

WO 456150; 245

-121 21 CC Pump Seal Replacement

October 17, 2013 PINGP 1766; 21 CC Pump CCCW System Internal Inspection; October 21, 2013 WO 490369; Clean 22 SGB Primary Sample Cooler; November 13, 2013 PINGP 1766; 22 SGB Primary Sample Cooler CCCW System Internal Inspection; November 28, 2013 Commitment Item 7

LR-PN-AMP413; Compressed Air Monitoring Program License Renewal Proof Notebook; Revision 2 H65.2.10; Compressed Air Monitoring Aging Management Program; Revision 1

PINGP 196, Turbine Bldg Data

- Unit 2, Air System

Enhancements

Revision 121 WM-0462 PMRQ Detail Info Report, April 25, 2013 WO 00437783, MECH
013

-011 GMP INGE

-003 - 121 Inst Air Compr 4000 HR PM

November 29, 2012 WO 00449050, GMP SULL

-001 - 124 Station Air Compressor 1000 HR PM No

Leaks Observed; May 14, 2012 WO 00451437; TP 1461 Instrument Air Compressor Supply Flush; February 16, 2013 Commitment Item 8

LR-PN-AMP440; Electrical Cable Connections Not Subject

to 10 CFR 50.49 Program; Revision 0 Addended Commitment Item 9

H65.2.12; Electrical Cables and Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Aging Management Program; Revision 0

AR 1350176; 2C

-687, Cable

from TB 2346 to SV33347 (CV

-31067); August 31, 2012 WO 406155; U2 Containment Walkdown for Degraded Electrical Cable Insulation; March 4, 2012

WO 434527; Low Voltage Cable Walkdown; August 16, 2012

Commitment Item 10

H65.2.13; Electrical Cables

and Connections Not Subjected to 10 CFR 50.49 Environmental Qualification Requirements Used in Instrumentation Circuits Program; Revision 1

AR 1327440; 2N32

-NM106 Isolation AMP Found O.

O.T During SP 2318.1; March 02, 2012

AR 1324419; SP 2318.3 Out of Tolerance Equipment; February 09, 2012

WO 477534; Review Instrument Cables for License Renewal; May 08, 2013

WO 409654; SP 2318.3

- NIS Power Range Channel Calibration; February 10, 2012

Commitment Item 11

LR-AMP-422; License Renewal Proof Notebook, External Surfaces Monitoring Program; Revision 2 PINGP 1516, "Walkdown Checklist Mechanical Systems/Components"

Revision 3

Commitment Item 12

LR-PN-AMP414; Fire Protection Program License Renewal Proof Notebook; Revision 2

AR 01386211; 2013 LR P2

- PMRQ freq 18 Months Plus 25 Percent Grace Current Status

/29/2014 WO 00448357, Unit 0 SP 1053 Fire Protection Pumps Monthly Test

Completed 12/22/2012

WM-0462 PMRQ Detail Info Report, April 25 , 2013 WO 00448983; Unit 0 SP 1664 Monthly Fire Fighting Equipment Check; January 4, 2013

Commitment Item 13

WO 00357618, Inspect Pendent Sprinklers On WPS

-l0 and Clean; July 27, 2012 WO 00425901; SP 1189A Safety-Related Fire Det Check Unit 1 Cntmt; November 15, 2012 WO 00448358; Unit 0 SP 1183.1 Monthly Fire Ext, Hose Hse/Sta; December 27, 2012 WO 00448357; Unit 0 SP 1053 Fire Protection Pumps Monthly Test; December 22, 2012 Commitment Item 14

LR-PN-AMP-423; License Renewal Proof Notebook, Flux Thimble Tube Inspection Aging Management Program; Revision

H65.2.18; Flux Thimble Tube Inspection Aging Management Program; Revision 0

D67; Incore Instrumentation Refueling/Maintenance Outage Operations; Revision 34

WO 00411501; Unit 2 Incore Thimble Eddy Current; February 20, 2012

Commitment Item 15

LR-PN-AMP-416; License Renewal Proof Notebook, Fuel Oil Chemistry Aging Management Program; Revision

H65.2.19; Fuel Oil Chemistry Aging Management Program; Revision 0

Commitment Item 16

H65.2.20; Fuse Holders Aging Management Program; Revision 0

H32.3; Thermography Program; Revision 3

WO 315018; Thermography of Components in U2 CNTMNT for License Renewal; October 9, 2008

WO 374391; ELEC: SYS 0ED, Perform Electrical Inspection (SCRNHSE); September 2, 2010

Commitment Item 17

H65.2.21; Inaccessible Medium and Low Voltage Cables not Subject to 10 CFR 50.49 Environmental Qualification Requirements Aging Management Program; Revision 0

AB-4, Revision 43; Flood; Revision 43

WO 460235; CELE: Perform Inspection of JB 2045 (License Renewal); July 16, 2012

WO 460236; CELE: Perform Inspection of PB 2181 (License Renewal); July 16, 2012

WO 433043; Test 2RXCS1 Cables Per PE 4825; January 18, 2013

AR 01344831; PB 2181 Cover Gasket Degraded

Commitment Item 18

LR-PN-AMP438; Inspection of Internal Surfaces of Miscellaneous Piping and Ducting Components Program License Renewal Proof Notebook; Revision 1

WO 469313; Unit 0 PMRQ 7145

-01 122 Sample Room Hood and OSC Vent Filter Change; July 27, 2013 WM-0462 PMRQ Detail Info Report, PMID

-RQ 00026319

-03 - SP 1738 - Unit 0 TSC HVAC Clea

n Up Filter Removal Effcy Test April 25, 2013 WM-0462 PMRQ Detail Info Report, PMID

-RQ 00019757

-01- Unit 2 New Procedure CD

-34085 Internal Inspection (23 FCU DISCH TO GAP); April 25, 2013 Commitment Item 19

LR-PN-AMP-412; License Renewal Proof Notebook: Inspection of Overhead Heavy Load and Light Load (Related to Refueling) Handling Systems Program; Revision 1

WO 456283-01; PM3160

-1-21: Reactor Building Polar Crane Mechanical; September 22, 2013

WO 456280-01; PM3160

-6-2: Unit 2 Manipulator Crane Mechanical Ins; September 23, 2013

Commitment Item 20

H65.2.26; Metal

-Enclosed Bus Aging Management Program; Revision 0

PE 0005-TC; 4.16 KV Bus and Duct Inspection; Revision 6

WO 419810; 2RY

-S Bus Duct Perform PE 0005

-TC and Resistance Checking; April 11, 2012

WO 434385; U2, 2R

-X/3000BD PE 0005

-TC (XFMR to DISC Section); May 3, 2012

AR 01374532; LR WO Completions; March 14, 2013

WO 434469; Inspect/Repair 2RY Bus Duct; August 2, 2011

WO 444741; 2RY

-N Bus Duct Perform PE 0005

-TC; December 17, 2011

WO 474490; Perform

PE 0005-TC 1R-YN/3000 Bus Duct; April 18, 2013

AR 1410000; High

as Left Resistance Bus

Bolted Connection in 2RXBD; December 9, 2013

Commitment Item 21

No documents reviewed

Commitment Item 2

No documents reviewed

Commitment Item 23

LR-PN-AMP-418; License Renewal Proof Notebook:

One-Time Inspection Program; Revision 1

FP-PE-NDE-510; Visual Exam VT

-1, Report No BOP

-VT-13-264; October 7, 2013

Commitment Item 24

LR-PN-AMP-421; License Renewal Proof Notebook: Inspection of ASME Code Class 1 Small Bore Piping Aging Management Program; Revision 2

WO 00473171

-01; UT on Socket Weld on 2SI

-16-4 for OTISMBORE 2R28; October 16, 2013

WO 00473172

-01; UT on Socket Weld on CV

-31421 for OTISMBORE 2R28; October 17, 2013

WO 00473173

-01; UT on Socket Weld on 2RC-1-4 for OTISMBORE 2R28; October 22, 2013

AR 1439207; 2014 LR Inspection

- Non-Conservative

Sample Size; July 21, 2014

AR 1441222; 2014 U2 LR Inspection

- Additional Inspection

Required; July 31, 2014

Commitment Item 25

LR-PN-AMP-442; License Renewal Proof Notebook, PWR Vessel Internals Program; Revision 0

EPRI Report 1022863; Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines (MRP

-227-A); December 2011

L-PI-09-044; Supplemental Information Regarding Application for Renewed Operating Licenses; May 12, 2009

L-PI-09-082; Response to NRC Request for Additional Information Regarding Application for Renewed Operating Licenses; June 24, 2009

L-PI-09-097; Supplemental Information Regarding Application for Renewed Operating Licenses; August 21, 2009

H65.2.32; PWR Vessel Internals Aging Management Program; Revision 0

H44; Reactor Vessel Integrity Program; Revision 16

WO 00398643; Perform Reactor Vessel Baffle Former Bolt Inspection; August 29, 2013

AR 01408630; Preliminary Indications in Baffle

-to-Former Bolting November 29, 2013

Commitment Item 26

LR-PN-AMP434; Reactor Head Closure Studs Program; Revision 0

H65.2.33; Reactor Head Closure Studs Program Basis Document; Revision 0

H44; Reactor Vessel Integrity Program; Revision 14

H10.5; 4th Interval Inservice Inspection Program; Revision 14

M491; Reactor Vessel Closure Stud Addendum to E Spec 676413; Revision 00

USAR Section L; Reactor Head Closure Studs Program; Revision 33P

WO 393473; Unit 2

- Conduct ISI Exams in Containment in 2R26; April 6, 2010

Commitment Item 27

LR-PN-AMP417; Reactor Vessel Surveillance Program; Revision 0

H44; Reactor Vessel Integrity Program; Revision 14

Commitment Item 28

LR-PN-AMP-428W; License Renewal Proof Notebook:

RG 1.127, Inspection of Water Control Structures Associated with Nuclear Power Plants Program; Revision 2

WO 462504-01; SP 1690 Approach, Intake, and Discharge Canal Hydrographic Survey; July 18, 2013 WO 457876-01; PM 3512

-08-2 SCRN House Under Water Inspect; June 16, 2014 AR 1428986; 5YR Screenhouse Underwater Inspect did not Identify PRA Unavail; April 30, 2014

AR 1432295; QF2007 Completion/Planning not Adequate for High Risk Work; May 27, 2014

Commitment Item 29

LR-PN-AMP-419; Selective Leaching of Materials Program; Revision 0

H65.2.36; Selective Leaching of Materials Aging Management Program; Revision 0

FP-PE-NDE-510; Visual Examination, VT

-1; Revision 5

H71; Selective Leaching of Materials Aging Management Program Procedure; Revision0

PINGP 1770; Selective Leaching of Materials Inspection Form; Revision 0

WO 406102; Perform VT

-1 Inspection of Existing Valve 2CL

-14-3; January 3, 2012

WO 405857; Perform VT

-1 Inspection of Removed Valve 2CL

-14-1; December 30, 2011

WO 414262; Perform VT

-1 Inspection of Existing Valve SV

-33141; August 1, 2012

Commitment Item 30

LR-PN-AMP-428; License Renewal Proof Notebook: Structural Monitoring Program; Revision 0

WO 462504-01; SP 1690 Approach, Intake, and Discharge Canal Hydrographic Survey; July 18, 2013 WO 467594-01; Winterization of HYDR and Roof Hose Station; November 8, 2013

AR 1363845; Lack of Resources to Implement License Renewal Programs; December 19, 2012

AR 1426609; MRule (a)(3):

(a)(1) Determination for Structures; April 14, 2014

AR 1433726; 2014 LR FSA AFI

- Structural Monitoring Reports Not Complete; June 6, 2014

Commitment Item 31

LR-PN-AMP-435; Thermal Aging Embrittlement of CASS Program; Revision 2

H65.2.39; Thermal Aging Embrittlement of CASS Aging Management Program; Revision

H44; Reactor Vessel Integrity Program; Revision 17

Commitment Item 32

LR-PN-AMP404; Water Chemistry Program License Renewal Proof Notebook; Revision 0

AR 1325454; Unit 2 Secondary System Chemistry Action Level One; February 17, 2013 AR 1313536; Unit 2 Secondary System Chemistry Action Level One; November17, 2011 Unit 1 and 2; Tech Spec Weekly Chemistry Analyses Report Week 25; June 22 - June 28, 2014 Unit 1 and 2; Tech Spec Weekly Chemistry Analyses Report Week 12; March 23 - March 29 , 2014 PINGP Unit 1 and 2 Cooling Water Systems Chemistry Report; 1st QTR

- 2014 PINGP Unit 1 and 2 TS Weekly Chemistry Analyses Report 12

March 23 - March 29, 2014 PINGP Unit 1 and 2 TS Weekly Chemistry Analyses Report 25; June 22

- June 28, 2014 Commitment Items 3

3, 34, 35, and 47

LR-PN-AMP-401; License Renewal Proof Notebook: Metal Fatigue of RCPB Program; Revision

Calculation 1301183.305; Selection of Bounding Locations; Revision 0

Calculation 1301183.306; Environmentally Assisted Fatigue Analysis, 6" Cold Leg Safety Injection Nozzle; Revision 0

Calculation 09000634.333; Hot Leg Surge Nozzle Loads; Revision 4

WO 00482074 01; SP 1173 Stress Cycle Record; February 24, 2014

WO 00487091 01; SP 1173 Stress Cycle Record; May 8, 2014 WO 00487117 01; SP 2173

Stress Cycle Record; June 20, 2014

WO 00470207 01; SP 2173 Stress Cycle Record; September 4, 2013 AR 01439473; Incorrect Sharepoint Version of H29; July 22, 2014

AR 01439649; Typographical Error in H29; July 23, 2014

Commitment Items 37, 38, 39, and 40

Documents Were Reviewed during the Unit 1 Phase II Inspection and are Documented in Inspection Report 05000282/2013008

Commitment Items 41, 42, and 44

License Renewal Proof Notebook; Reactor Cavity Commitments; Revision 1

AR 01160372

-14; Monitor and Document

Leakage, 1st Unit 2 Outage

after Repair; June 14, 2012

AR 01160372

-15; Monitor and Document Leakage, 2nd Unit 2 Outage

after Repair; December 9, 2013 AR 01329109; U2 Rflg Cavity Leaking Thru the Cement

AR 01409828; 2R28 Refueling Cavity Leakage; December 8, 2013 WO 00493788; Outage, Investigate and Repair Remaining Reactor CAV Leak; PLAN Status

Commitment Item 43

LR-PN-DGHOSE; Diesel Generator Hose Replacement License Renewal Proof Notebook; Revision 0

WO 469485; ICPM 1

-014A-D1 Replace EDG Instrument Flexible Lines; December 28, 2012 WO 416461; Unit 0 PMRQ 7161

-01: 122 DD Fire Pmp (045

-022) PM 3122

-1; June 29, 2011 WO 300466; Unit 2 D6

Replace Hoses Missed on 5 Yr PMs; June 4, 2004 AR 01361849; Rubber Hose Replacements not performed per Tech Man Req including Unit 2;

December 4, 2012 AR 01329042; LR Implementation Tasks

Overdue from Long Term Programs

Iincluding Unit 2; March 13, 2012 Commitment Items 45 and 46

LR-PN-AMP-409; Steam Generator Tube Integrity Program; Revision 1

H65.2.37; Steam Generator Tube Integrity Program Basis Document; Revision 0

H25; Steam Generator Program; Revision 17

SP 2391; Unit 2 Steam Generator Tube Surveillance; Revision 8

SP 2534; Unit 2 Steam Generator Internals Inspection; Revision 7

Other Documents

PMCR 01383617; 7041

-26 Adjust Schedule to Accommodate Grace Period; May 20, 2013

PMCR 01385224; PMRQ 7097

-09, Scrnhouse Under

-Water Inspect

June 3, 2013

PMCR 01385227; PMRQ 6035

-02, Cooling Water Emerg

Intake Structure; June 3, 2013

PMCR 01428600; Activate Compliance Params for License Renewal Cmtmnt. PMRQs

April 28 , 201 4 AR 01233306; D5 and D6 FOST Vault Oil and Water Sensors; May 15 2010

AR 01433731; 2014 LR FSA AFI

- Could Not Confirm CAP AR Issues Resolved; June 6, 2014

AR01384035; PM 3586

-10 Revision No. 8; May 23, 2013

PCR 01395520; FP

-R-LIC-24, NRC Commitment Management; September 4, 2013

PCR 01384081; H65.2.13, Revision 1 Electrical Cables

and Connections not Subject; May 23, 2013 PCR 01388678; Create

New PMs for CT11 and CT12 Bus

Ducts; July 2, 2013

PCR 01400095; SP 1192, Revision 18; October 4, 2013

PCR 01400115; F5 App K, Revision 18; October 4, 2013

PCMR 01400

21; PM Revision:

SP 1192 Frequency Change from 18M to 1R; October 4, 2013 PCR 01386286; H44 Revision 16; June 12, 2013

PCR 014033

48; New PM for PMID 715

D 1 Generator

- Aging Management LR; October 24, 2013

PCR 01403360; New PM for PMID 7153 D2 Generator

- Aging Management LR; October 24, 2013

PCR 01391655; PM 3505-05 Revision 13; July 26, 2013

LIST OF ACRONYMS USE

D AC&H Archaeological, Cultural and Historical

ADAMS Agencywide Document Access Management System

AMP Aging Management Program

AR Action Request

ASME American Society of Mechanical Engineers

CASS Cast Austenitic Stainless Steel

CFR Code of Federal Regulations

CRMP Cultural Resources Management Plan

CST Condensate Storage Tank

CUF Cumulative Usage Factor

EAF Environmentally Assisted Fatigue

EPRI Electric Power Research Institute

EQ Environmental Qualification FOCP Fuel Oil Chemistry Program

GALL Generic Aging Lessons Learned

HVAC Heating, Ventilation, and Air Conditioning

IP Inspection Procedure

IR Inspection Report

LRA License Renewal Application

NEI Nuclear Energy Institute

NMC Nuclear Management Compa

ny NRC U.S. Nuclear Regulatory Commission

PARS Publicly Available Records System

PINGP Prairie Island Nuclear Generating Plant

PWR Pressurized Water Reactor

RAI Request for Additional Information

RCS Reactor Coolant System

RG Regulatory Guide

RIS Regulatory Issue Summary

SBO Station Blackout

SER Safety Evaluation Report

SSC Structures, Systems and Components

TLAA Time-Limited Aging Analysis

USAR Updated Safety Analysis Report

UT Ultrasonic Test

V Volt WO Work Order

K. Davidson

-2- component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html

(the Public Electronic Reading Room).

Sincerely, /RA/ Ann Marie Stone, Branch Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50

-306 License No. DPR

-60 Enclosure:

Inspection Report 05000306/2014010

w/Attachment: Supplemental Information

cc w/encl: Distribution via LISTSERV

DISTRIBUTION w/encl

John Jandovitz

RidsNrrPMPrairieIsland Resource

RidsNrrDorlLpl3

-1 Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Steven Orth

Allan Barker

Carole Ariano

Linda Linn

DRPIII DRSIII Patricia Buckley

Carmen Olteanu

ROPreports.Resource@nrc.gov DOCUMENT NAME:

G:\DRSIII\DRS\Work in Progress

\PRA 2014010 Phase II LR TXB.docx

-Publicly Available

-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII NAME TBilik:ls A MStone DATE 9/12/1 4 9/12/1 4 OFFICIAL RECORD COPY