IR 05000282/2020001

From kanterella
(Redirected from IR 05000306/2020001)
Jump to navigation Jump to search
Integrated Inspection Report 05000282/2020001 and 05000306/2020001
ML20119A899
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/28/2020
From: Hironori Peterson
Region 3 Branch 3
To: Sharp S
Northern States Power Co
References
IR 2020001
Download: ML20119A899 (13)


Text

April 28, 2020

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000282/2020001 AND 05000306/2020001

Dear Mr. Sharp:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant. On April 9, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000282 and 05000306

License Numbers:

DPR-42 and DPR-60

Report Numbers:

05000282/2020001 and 05000306/2020001

Enterprise Identifier: I-2020-001-0052

Licensee:

Northern States Power Company, Minnesota

Facility:

Prairie Island Nuclear Generating Plant

Location:

Welch, Minnesota

Inspection Dates:

January 01, 2020 to March 31, 2020

Inspectors:

E. Fernandez, Reactor Inspector

L. Haeg, Senior Resident Inspector

I. Hafeez, Reactor Inspector

K. Pusateri, Resident Inspector

L. Rodriguez, Reactor Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Units 1 and 2 operated at or near full power for the entirety of the inspection period, with the exception of brief power reductions to perform surveillance testing or flexible power operations.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather (heavy snow storm) on 01/15/2020

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on 03/09/2020

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)122 control room chiller on 01/15/2010

(2) D5 and Bus 25 during D6 maintenance window on 01/23/2020 (3)11 containment spray pump with 12 containment spray out of service for surveillance test on 02/20/2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the D1 and D2 emergency diesel generators on 01/30/2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire detection zone 89: guard house and emergency generator building on 01/10/2020
(2) Fire detection zone 87: unit 1 rod drive room on 01/13/2010
(3) Fire detection zone 75: Plant screenhouse safeguards traveling screens during hotwork on 02/05/2020
(4) Fire detection zone 11: Unit 1 safeguards Bus 15 room on 01/25/2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Auxiliary building and postulated internal flood analysis on 01/17/2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during during Unit 1 main feedwater leading-edge flowmeter troubleshooting on 03/02/2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator re-qualification training in the control room simulator on 03/13/2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Motor-operated valve program deferrals on 01/27/2020
(2) Maintenance effectiveness procedure use and adherence on 02/28/2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Maintenance risk during D6 maintenance window on 01/21/2020
(2) Bus 26 load sequencer unplanned LCO on 01/24/2020 (3)22 component cooling pump emergent outboard beaming maintenance on 02/24/2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) D1 air start issue Part 21 review on 01/21/2020
(2) Bus 26 breaker 26-16 incorrect breaker sizing past operability on 01/27/2020
(3) Steam generator vendor weld qualification issue (AR 501000036873) on 01/29/2020
(4) Cooling water through-wall leak (AR 501000036454) on 02/05/2020 (5)122 fuel oil storage tank pump motor cable low insulation resistance issue (AR 501000038846) on 3/20/2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) D5/D6 fuel oil day tank volume change (EC 601000000142) on 01/09/2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1)22 turbine driven auxiliary feed water pump following maintenance on 01/17/2020

(2) D6 following maintenance on 01/27/2020 (3)21 fan coil unit following breaker troubleshooting (WO 700070246) on 02/07/2020 (4)12 diesel driven cooling water pump following instrument calibrations on 03/04/2020 (5)22 diesel-driven cooling water pump following maintenance on 03/16/2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) SP 1093; D1 Diesel Generator Monthly Slow Start Test on 01/13/2020
(2) SP 1106B; 22 Diesel Cooling Water Pump Monthly Test on 01/30/2020
(3) SP 1295; D1 Diesel Generator 6-month Fast Start Test on 03/09/2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) SP 2089B; 21 RHR Pump and Suction Valve from the Reactor Water Storage Tank Quarterly Test on 03/30/2020

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 1Q19 through 4Q19 on 01/08/2020
(2) Unit 2 1Q19 through 4Q19 on 01/08/2020

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 1Q19 through 4Q19 on 01/10/2020
(2) Unit 2 1Q19 through 4Q19 on 01/10/2020

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 2 1Q19 through 4Q19 on 01/09/2020
(2) Unit 1 1Q19 through 4Q19 on 01/09/2020

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (2 Samples)

(1) Unit 1 1Q19 through 4Q19 on 01/13/2020
(2) Unit 2 1Q19 through 4Q19 on 01/13/2020

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) D5/D6 emergency diesel generator extreme cold performance reconstitution effort on 01/07/2020

INSPECTION RESULTS

Observation: D5/D6 emergency diesel generator extreme cold weather evaluation 71152 The inspectors reviewed the licensee's efforts to re-evaluate extreme cold weather performance and operability limits for the Unit 2 D5 and D6 emergency diesel generators.

This effort was in response to extreme cold weather that occurred in late-January of 2019; challenging operability of the D5 and D6 systems.

The inspector's review consisted of analyses and calculations performed by a vendor to demonstrate lower temperature limits from existing values. The inspectors also reviewed the method for incorporating information for plant operators if/when extreme cold weather was experienced in the future. Based on the inspector's review, no concerns were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 9, 2020, the inspectors presented the integrated inspection results to Mr. S. Sharp, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

AB-2

Severe Weather

AB-4

Flood

71111.04

Calculations

NL-40960-2A

D1 and D2 Emergency Generator Governor Full Load

Position Indicator Microswitch Mounting

11/27/1972

Corrective Action

Documents

AR

501000018362

D1 Governor Ready Lights Not Responding

10/12/2018

AR

501000019870

D1 Governor Ready Lights Not Lit

11/14/2018

AR

501000032206

21 CR Chiller Purge Unit Rusting

10/24/2019

AR

501000032206

21 CR Chiller Purge Unit Rusting

09/22/2019

AR

501000036567

21 Control Room Chiller Purge Unit

01/16/2020

AR

501000036690

Surface Rust on the Base Plate-Excessive Leakage During

TP 1687

01/17/2020

AR

501000037469

D1 Governor Ready Lights Not Lit

2/10/2020

Corrective Action

Documents

Resulting from

Inspection

AR

500001011327

NRC Identified Concerns With D1/D2 Operability

03/29/2006

AR

501000038509

Fuel Oil Leak on D2 FO Pump Discharge

03/09/2020

Drawings

NE-40006-1

4160V Switchgear Safeguard Unit 1 and 2 - Schematic

Diagram

08/18/1994

NF-39603-4

Flow Diagrams - Cooling and Chilled Water System and Fire

Protection for Vent Filters in Auxiliary and Containment

Buildings

NF-40325-1

Interlock Logic Diagram Diesel Generator System Units 1

and 2: D1 Diesel Generator Voltage Regulator Control Logic

71111.04

Procedures

C1.1.20.7-6

D2 Diesel Generator Auxiliaries and Room Cooling Local

Panels

C1.1.20.7-8

D2 Diesel Generator Circuit Breakers and Panel Switches

IC20.7

D1/D2 Diesel Generators

SP 1295

D1 Diesel Generator 6-Month Fast Start Test

SP 1305

D2 Diesel Generator Monthly Slow Start Test

71111.05

Fire Plans

Fire Detection

Zone 11-F5

Appendix A

Fire Detection Zone 11 - Fire Areas 20 and 81;

Cables/Miscellaneous

Fire Detection

Zone 75-F5

Appendix A

Fire Detection Zone 75 - Fire Areas 41 and 41A - Open

Areas From Elevation 670'

Fire Detection

Zone 87

Unit 1 Rod Drive Room

Fire Detection

Zone 89

Guard House and Emergency Generating Building

71111.06

Calculations

ENG-ME-448

Auxiliary Building Flooding Analysis

71111.11Q Miscellaneous

Simulator

Exercise Guide

PI-LOR-20C-

2S

Cycle 20C Simulator Session #2

Procedures

AR

501000038248

LEFM Behavior During Flex Ops

03/01/2020

71111.12

Corrective Action

Documents

AR

501000035269

Algae in Sightglass to 2CL-128-6

2/03/2019

AR

501000036851

MOV Program Health Color Change

01/22/2020

AR

501000037993

CC Pump Outboard Bearing Oil Leak

2/22/2020

AR

501000038128

Corporate Elevation: VM WO Preps / Exec

2/27/2020

AR

501000038128

Elevation / Escalation Letter Template

2/27/2020

AR

501000038129

Potential Trend in Procedure Use and ADH

2/27/2020

Drawings

NF-39216-1

Flow Diagram Cooling Water Screenhouse Units 1 and 2

04/11/2007

XH-1048-5

  1. 10096 "CPK" Heat Exchanger 5-046-10-096-005

Miscellaneous

X-HIAW-48-34

Lubrication System and Piping Detail for 200L-26

D

Procedures

ICPM 2-063-22

DD Clg Water Pump Bearing Water Pressure Switch

Calibration

Work Orders

WO 700028834-

0010

Replace DDCLP Heat Exchanger O-Rings

11/08/2018

WO 700028834-

20

Olg Water Pump Diesel Jacket Heat Exchanger

11/17/2018

71111.13

Corrective Action

Documents

AR

501000036964

Unsatisfactory SP 2095, Bus 26 Sequencer, Error 11

01/24/2020

AR

501000036976

Breaker 29-16 Charging Motor Wire Issue

01/26/2020

AR

501000037073

D6 Lessons Learned-SP 2095 Schedule

01/27/2020

AR

501000037074

D6 Lessons Learned-PMT Sequence

01/27/2020

AR

501000037078

D6 Lessons Learned PMT & RTS Work Plans

01/28/2020

AR

501000037079

D6 Lessons Learned-PMT Quality Issue

01/28/2020

AR

501000037993

CC Pump Outboard Bearing Oil Leak

2/22/2020

AR

501000038027

CC Pump Vibes Step Change

2/25/2020

Drawings

XH-105-1

Component Cooling Water Pump Section Drawing

Procedures

2C20.7 AOP3

Bus 26 Load Sequencer Out of Service

SP 2155B

CC System Quarterly Test Train B - 22 CC Pump and Motor

Vibration Data

Work Orders

WO 700070775-

0010

Replace 22 CC Pump Outboard Seal and Bearings

71111.15

Corrective Action

Documents

AR

501000036454

Clg Water Thru Well Drip 3-CL-88

01/10/2020

AR

501000036873

Framatome Additional SG Welding Issues

01/23/2020

AR

501000036932

Breaker 26-16 Found Wrong Frame Size

01/24/2020

AR

501000038846

Low Megger: 122 FOST PMP MTR PE4826

03/17/2020

Drawings

NE-40006 Sheet

MDAFWP-Auxiliary Feedwater Pump Bus 16 Cub 3

71111.18

Corrective Action

Documents

AR

501000036878

D6 Cracked Flame Arrestor Relocation

01/23/2020

AR

501000036884

D6 Day TK Flame Arrestor Flange Cracked

01/23/2020

Procedures

DC

601000000142

D5/D6 Fuel Oil Day Tank Volume Change

71111.19

Procedures

ICPM 1-012A

Diesel Cooling Water Pump Instrument Calibration - Part

A

SP 2307

D6 Diesel Generator 6-Month Fast Start Test

Work Orders

WO 700070246-

0010

Perform PE MCC-G7 on Breaker 212J-2

2/06/2020

71111.22

Procedures

SP 1106B

Diesel Cooling Water Pump Monthly Test

98