IR 05000282/2020001

From kanterella
(Redirected from IR 05000306/2020001)
Jump to navigation Jump to search
Integrated Inspection Report 05000282/2020001 and 05000306/2020001
ML20119A899
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/28/2020
From: Hironori Peterson
Region 3 Branch 3
To: Sharp S
Northern States Power Co
References
IR 2020001
Download: ML20119A899 (13)


Text

April 28, 2020

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000282/2020001 AND 05000306/2020001

Dear Mr. Sharp:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant. On April 9, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000282 and 05000306 License Numbers: DPR-42 and DPR-60 Report Numbers: 05000282/2020001 and 05000306/2020001 Enterprise Identifier: I-2020-001-0052 Licensee: Northern States Power Company, Minnesota Facility: Prairie Island Nuclear Generating Plant Location: Welch, Minnesota Inspection Dates: January 01, 2020 to March 31, 2020 Inspectors: E. Fernandez, Reactor Inspector L. Haeg, Senior Resident Inspector I. Hafeez, Reactor Inspector K. Pusateri, Resident Inspector L. Rodriguez, Reactor Inspector Approved By: Hironori Peterson, Chief Branch 3 Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Units 1 and 2 operated at or near full power for the entirety of the inspection period, with the exception of brief power reductions to perform surveillance testing or flexible power operations.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather (heavy snow storm) on 01/15/2020

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on 03/09/2020

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) 122 control room chiller on 01/15/2010
(2) D5 and Bus 25 during D6 maintenance window on 01/23/2020
(3) 11 containment spray pump with 12 containment spray out of service for surveillance test on 02/20/2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the D1 and D2 emergency diesel generators on 01/30/2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire detection zone 89: guard house and emergency generator building on 01/10/2020
(2) Fire detection zone 87: unit 1 rod drive room on 01/13/2010
(3) Fire detection zone 75: Plant screenhouse safeguards traveling screens during hotwork on 02/05/2020
(4) Fire detection zone 11: Unit 1 safeguards Bus 15 room on 01/25/2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Auxiliary building and postulated internal flood analysis on 01/17/2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during during Unit 1 main feedwater leading-edge flowmeter troubleshooting on 03/02/2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator re-qualification training in the control room simulator on 03/13/2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Motor-operated valve program deferrals on 01/27/2020
(2) Maintenance effectiveness procedure use and adherence on 02/28/2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Maintenance risk during D6 maintenance window on 01/21/2020
(2) Bus 26 load sequencer unplanned LCO on 01/24/2020
(3) 22 component cooling pump emergent outboard beaming maintenance on 02/24/2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) D1 air start issue Part 21 review on 01/21/2020
(2) Bus 26 breaker 26-16 incorrect breaker sizing past operability on 01/27/2020
(3) Steam generator vendor weld qualification issue (AR 501000036873) on 01/29/2020
(4) Cooling water through-wall leak (AR 501000036454) on 02/05/2020
(5) 122 fuel oil storage tank pump motor cable low insulation resistance issue (AR 501000038846) on 3/20/2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) D5/D6 fuel oil day tank volume change (EC 601000000142) on 01/09/2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) 22 turbine driven auxiliary feed water pump following maintenance on 01/17/2020
(2) D6 following maintenance on 01/27/2020
(3) 21 fan coil unit following breaker troubleshooting (WO 700070246) on 02/07/2020
(4) 12 diesel driven cooling water pump following instrument calibrations on 03/04/2020
(5) 22 diesel-driven cooling water pump following maintenance on 03/16/2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) SP 1093; D1 Diesel Generator Monthly Slow Start Test on 01/13/2020
(2) SP 1106B; 22 Diesel Cooling Water Pump Monthly Test on 01/30/2020
(3) SP 1295; D1 Diesel Generator 6-month Fast Start Test on 03/09/2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) SP 2089B; 21 RHR Pump and Suction Valve from the Reactor Water Storage Tank Quarterly Test on 03/30/2020

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01) ===

(1) Unit 1 1Q19 through 4Q19 on 01/08/2020
(2) Unit 2 1Q19 through 4Q19 on 01/08/2020 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02)

(2 Samples)

(1) Unit 1 1Q19 through 4Q19 on 01/10/2020
(2) Unit 2 1Q19 through 4Q19 on 01/10/2020

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 2 1Q19 through 4Q19 on 01/09/2020
(2) Unit 1 1Q19 through 4Q19 on 01/09/2020

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (2 Samples)

(1) Unit 1 1Q19 through 4Q19 on 01/13/2020
(2) Unit 2 1Q19 through 4Q19 on 01/13/2020

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) D5/D6 emergency diesel generator extreme cold performance reconstitution effort on 01/07/2020

INSPECTION RESULTS

Observation: D5/D6 emergency diesel generator extreme cold weather 71152 evaluation The inspectors reviewed the licensee's efforts to re-evaluate extreme cold weather performance and operability limits for the Unit 2 D5 and D6 emergency diesel generators.

This effort was in response to extreme cold weather that occurred in late-January of 2019; challenging operability of the D5 and D6 systems.

The inspector's review consisted of analyses and calculations performed by a vendor to demonstrate lower temperature limits from existing values. The inspectors also reviewed the method for incorporating information for plant operators if/when extreme cold weather was experienced in the future. Based on the inspector's review, no concerns were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 9, 2020, the inspectors presented the integrated inspection results to Mr. S. Sharp, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Procedures AB-2 Severe Weather 46

AB-4 Flood 57

71111.04 Calculations NL-40960-2A D1 and D2 Emergency Generator Governor Full Load 11/27/1972

Position Indicator Microswitch Mounting

Corrective Action AR D1 Governor Ready Lights Not Responding 10/12/2018

Documents 501000018362

AR D1 Governor Ready Lights Not Lit 11/14/2018

501000019870

AR 121 CR Chiller Purge Unit Rusting 10/24/2019

501000032206

AR 121 CR Chiller Purge Unit Rusting 09/22/2019

501000032206

AR 121 Control Room Chiller Purge Unit 01/16/2020

501000036567

AR Surface Rust on the Base Plate-Excessive Leakage During 01/17/2020

501000036690 TP 1687

AR D1 Governor Ready Lights Not Lit 02/10/2020

501000037469

Corrective Action AR NRC Identified Concerns With D1/D2 Operability 03/29/2006

Documents 500001011327

Resulting from AR Fuel Oil Leak on D2 FO Pump Discharge 03/09/2020

Inspection 501000038509

Drawings NE-40006-1 4160V Switchgear Safeguard Unit 1 and 2 - Schematic 08/18/1994

Diagram

NF-39603-4 Flow Diagrams - Cooling and Chilled Water System and Fire 12

Protection for Vent Filters in Auxiliary and Containment

Buildings

NF-40325-1 Interlock Logic Diagram Diesel Generator System Units 1 77

and 2: D1 Diesel Generator Voltage Regulator Control Logic

71111.04 Procedures C1.1.20.7-6 D2 Diesel Generator Auxiliaries and Room Cooling Local 13

Panels

C1.1.20.7-8 D2 Diesel Generator Circuit Breakers and Panel Switches 18

IC20.7 D1/D2 Diesel Generators 54

SP 1295 D1 Diesel Generator 6-Month Fast Start Test 67

SP 1305 D2 Diesel Generator Monthly Slow Start Test 62

71111.05 Fire Plans Fire Detection Fire Detection Zone 11 - Fire Areas 20 and 81; 41

Zone 11-F5 Cables/Miscellaneous

Appendix A

Fire Detection Fire Detection Zone 75 - Fire Areas 41 and 41A - Open 44

Zone 75- F5 Areas From Elevation 670'

Appendix A

Fire Detection Unit 1 Rod Drive Room 7

Zone 87

Fire Detection Guard House and Emergency Generating Building 44

Zone 89

71111.06 Calculations ENG-ME-448 Auxiliary Building Flooding Analysis 2

71111.11Q Miscellaneous Simulator Cycle 20C Simulator Session #2 0

Exercise Guide

PI-LOR-20C-

2S

Procedures AR LEFM Behavior During Flex Ops 03/01/2020

501000038248

71111.12 Corrective Action AR Algae in Sightglass to 2CL-128-6 12/03/2019

Documents 501000035269

AR MOV Program Health Color Change 01/22/2020

501000036851

AR 22 CC Pump Outboard Bearing Oil Leak 02/22/2020

501000037993

AR Corporate Elevation: VM WO Preps / Exec 02/27/2020

501000038128

AR Elevation / Escalation Letter Template 02/27/2020

501000038128

AR Potential Trend in Procedure Use and ADH 02/27/2020

501000038129

Drawings NF-39216-1 Flow Diagram Cooling Water Screenhouse Units 1 and 2 04/11/2007

XH-1048-5 #10096 "CPK" Heat Exchanger 5-046-10-096-005 3

Miscellaneous X-HIAW-48-34 Lubrication System and Piping Detail for 200L-26 D

Procedures ICPM 2-063-22 22 DD Clg Water Pump Bearing Water Pressure Switch 5

Calibration

Work Orders WO 700028834- Replace DDCLP Heat Exchanger O-Rings 11/08/2018

0010

WO 700028834- 22 Olg Water Pump Diesel Jacket Heat Exchanger 11/17/2018

20

71111.13 Corrective Action AR Unsatisfactory SP 2095, Bus 26 Sequencer, Error 11 01/24/2020

Documents 501000036964

AR Breaker 29-16 Charging Motor Wire Issue 01/26/2020

501000036976

AR D6 Lessons Learned-SP 2095 Schedule 01/27/2020

501000037073

AR D6 Lessons Learned-PMT Sequence 01/27/2020

501000037074

AR D6 Lessons Learned PMT & RTS Work Plans 01/28/2020

501000037078

AR D6 Lessons Learned-PMT Quality Issue 01/28/2020

501000037079

AR 22 CC Pump Outboard Bearing Oil Leak 02/22/2020

501000037993

AR 22 CC Pump Vibes Step Change 02/25/2020

501000038027

Drawings XH-105-1 Component Cooling Water Pump Section Drawing 2

Procedures 2C20.7 AOP3 Bus 26 Load Sequencer Out of Service 15

SP 2155B CC System Quarterly Test Train B - 22 CC Pump and Motor 31

Vibration Data

Work Orders WO 700070775- Replace 22 CC Pump Outboard Seal and Bearings 2

0010

71111.15 Corrective Action AR Clg Water Thru Well Drip 3-CL-88 01/10/2020

Documents 501000036454

AR Framatome Additional SG Welding Issues 01/23/2020

501000036873

AR Breaker 26-16 Found Wrong Frame Size 01/24/2020

501000036932

AR Low Megger: 122 FOST PMP MTR PE4826 03/17/2020

501000038846

Drawings NE-40006 Sheet 12 MDAFWP-Auxiliary Feedwater Pump Bus 16 Cub 3 80

71111.18 Corrective Action AR D6 Cracked Flame Arrestor Relocation 01/23/2020

Documents 501000036878

AR D6 Day TK Flame Arrestor Flange Cracked 01/23/2020

501000036884

Procedures DC D5/D6 Fuel Oil Day Tank Volume Change 0

601000000142

71111.19 Procedures ICPM 1-012A 12 Diesel Cooling Water Pump Instrument Calibration - Part 21

A

SP 2307 D6 Diesel Generator 6-Month Fast Start Test 46

Work Orders WO 700070246- Perform PE MCC-G7 on Breaker 212J-2 02/06/2020

0010

71111.22 Procedures SP 1106B 22 Diesel Cooling Water Pump Monthly Test 98

11