November 12, 2020
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT - SECURITY BASELINE INSPECTION REPORT 05000282/2020402 AND 05000306/2020402
Dear Mr. Domingos:
On October 23, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety
Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000282 and 05000306
License Numbers:
Report Numbers:
05000282/2020402 and 05000306/2020402
Enterprise Identifier: I-2020-402-0032
Licensee:
Northern States Power Company, Minnesota
Facility:
Prairie Island Nuclear Generating Plant
Location:
Welch, MN
Inspection Dates:
September 28, 2020 to October 23, 2020
Inspectors:
J. Kutlesa, Physical Security Inspector
M. Ziolkowski, Senior Physical Security Inspector
Approved By:
Steven K. Orth, Chief
Plant Support Branch
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Unless otherwise noted, baseline security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), regional inspectors were directed to begin telework. The inspection documented below was determined that the objectives and requirements stated in the IP could, in part, be performed remotely.
SAFEGUARDS
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
===inspection elements:
Access Control===
(1)
- Tier I: All Requirements
- Tier II: 02.06 a, b, c, d; 02.08 a, b, c, d, e, f, g
- Tier III: 02.09; 02.10 a
71130.04 - Equipment Performance, Testing, and Maintenance
The inspectors evaluated the security equipment testing and maintenance program through completion of the following inspection elements:
Equipment Performance, Testing, and Maintenance (1 Sample)
(1)
- Tier I: All
- Tier II: None
- Tier III: None
71130.08 - Fitness For Duty Program
The inspectors evaluated the fitness for duty program through completion of the following
inspection elements: Fitness For Duty Program
(1)
- Tier I: All Requirements
- Tier II: 02.05 a, b, c, d, e, f, h, j; 02.06 f, g; 02.07 a, c, d; 02.08 a, b
- Tier III: 02.11 a; 02.13 c; 02.14 c
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following procedure elements:
Review Security Plan Changes (IP Section 02.01) (1 Sample)
- (1) Since the last NRC inspection of this program area, Security Plan Revision 12 to 13 was implemented based on your determination, in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan, and that the revised security plan changed continues to meet the requirements of 10 CFR 73.55(b). The inspectors conducted a review of the security plan changes to evaluate for potential decrease in safeguards effectiveness of the security plan. However, this review does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety.
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)
=
(1)
(January 2019 - September 2020)
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 23, 2020, the inspectors presented the security baseline inspection results to Christopher Domingos and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
501000041035
Issue Involving Vehicle Keys
05/26/2020
501000044453
Issue Involving Visitor Escort
09/22/2020
Corrective Action
Documents
Resulting from
Inspection
0501000045810
Security NRC Inspection 2020
10/23/2020
501000045811
Security NRC Inspection 2020
10/23/2020
Procedures
FP-S-FSIP-06
Searches
FP-S-FSIP-07
Access Controls
FP-S-FSIP-10
Security Response to Emergency Events
Miscellaneous
LM-0616
Qualification
Lookup
Weapons Armorer - AR15/M4/AR10 Platform
10/22/2020
N/A
Weapons Accountability
10/22/2020
QF2704 -
601000001465
Design Change Package - Prairie Island Security Upgrade
Procedures
FP-S-FSIP-04
Equipment Inventory, Maintenance, Testing, and Calibration
Miscellaneous
NANTeL
Generic Fitness for Duty and Behavior Observation Training
06/08/2017
QF1772/1773/1774 Security Event Logs
November
2019 to
October
20
Procedures
FP-S-FFD-01
Monticello/Prairie Island Fitness for Duty Program
Self-Assessments A-SEC-FLT-2020-1 2020 Nuclear Oversight Audit of Fleet Security and Cyber
Security
07/31/2020
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
N/A
Prairie Island Physical Security Plan
N/A
Technical Basis for Physical Security Plan Rev. 13
08/24/2020
N/A
Prairie Island Physical Security Plan
Procedures
QF0501 -
601000001465
50.59 Screening - PINGP Security Upgrades
N/A
71151
Miscellaneous
QF0445
NRC/INPO/WANO Data Collection and Submittal Forms
January
2019 to
September
20