MONTHYEARIR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20220062023-03-0101 March 2023 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report, Units 1 and 2 (Report 05000282/2022006 and 05000306/2022006) ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 IR 05000282/20220052022-08-29029 August 2022 Updated Inspection Plan for Prairie Island Nuclear Generating Plant (Report 05000282/2022005; 05000306/2022005) ML22007A1542022-01-0707 January 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000282/2022010 and 05000306/2022010 ML21363A0542021-12-29029 December 2021 Prairie Nuclear Generating Plant - Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information; Inspection Report 05000282/2022002 05000306/2022002 IR 05000282/20210052021-09-0101 September 2021 Updated Inspection Plan for Prairie Island Nuclear Generating Plant Units 1 and 2 (Report 05000282/2021005 and 05000306/2021005) IR 05000282/20200062021-03-0404 March 2021 Annual Assessment Letter for the Prairie Island Nuclear Generating Plant (Report 05000282/2020006 and 05000306/2020006) ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant IR 05000282/20200052020-09-0101 September 2020 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2020005 and 05000306/2020005) ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 IR 05000282/20190062020-03-0303 March 2020 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019006 and 05000306/2019006) IR 05000282/20190052019-08-28028 August 2019 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019005; 05000306/2019005) ML19136A1562019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19071A3532019-03-12012 March 2019 Ltr. 03/12/19 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000282/2019012; 05000306/2019012 (DRS-A.Dahbur) IR 05000282/20180062019-03-0404 March 2019 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018006 and 05000306/2018006) ML18324A6122018-11-20020 November 2018 Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn IR 05000282/20180052018-08-28028 August 2018 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018005 and 05000286/2018005) ML18156A5532018-06-0505 June 2018 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg) IR 05000282/20170062018-03-0202 March 2018 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2017006; 05000306/2017006) IR 05000282/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000282/2017005 and 05000306/2017005) IR 05000282/20160062017-03-0101 March 2017 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016006) ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) IR 05000282/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016005; 05000306/2016005) ML16222A7022016-08-0909 August 2016 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000282/20150062016-03-0202 March 2016 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Inspection Report 05000282/2015006 and 05000306/2015006) ML15261A7182015-09-15015 September 2015 Ltr. 09/15/2015 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000282/2016008; 05000306/2016008. (Dxs) IR 05000282/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2015005; 05000306/2015005) IR 05000282/20140012015-03-0404 March 2015 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2, (Report 05000282/2014001 and 05000306/2014001) ML14245A2012014-09-0202 September 2014 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 ML14209A9342014-07-28028 July 2014 Notification of NRC Inspection and Request for Information IR 05000282/20130012014-03-0404 March 2014 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2(Report 05000282/2013001; 05000306/2013001) ML13246A2392013-09-0303 September 2013 2013 Prairie Island MOC Letter Combined ML13203A2862013-07-22022 July 2013 Notification of Baseline Inspection and Information Request ML13077A4742013-03-18018 March 2013 Information Request for a Post-approval Site Inspection for License Renewal IR 05000282/20120012013-03-0404 March 2013 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2012001 and 05000306/2012001) ML12249A4252012-09-0404 September 2012 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 IR 05000282/20110072012-03-0505 March 2012 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2011007 and 05000306/2011007) IR 05000282/20110062011-09-0101 September 2011 Mid-Cycle Letter for Prairie Island Nuclear Plant, Units 1 and 2, 05000282-11-006; 05000306-11-006 ML1106203132011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan ML1024400922010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Prairie Island Nuclear Power Plant IR 05000282/20100012010-03-0303 March 2010 Prairie Island Power Plant EOC Assessment Letter (05000282-10-001; 05000306-10-001) ML0924403672009-09-0101 September 2009 Prairie Island - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20090012009-03-0404 March 2009 Annual Assessment Letter - Prairie Island Nuclear Generating Plant, Units 1 and 2 (05000282-09-001 and 050000306-09-001) ML0824603142008-09-0202 September 2008 Prairie Island, Units 1 & 2 - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20080012008-03-0303 March 2008 Prairie Island, EOC Annual Assessment Letter (Inspection Report 05000282-08-001 and 05000306-08-001) ML0735402802007-12-19019 December 2007 Change to the Inspection Plan 1/1/08 - 12/31/08 ML0724302372007-08-31031 August 2007 8/31/07 Prairie Island - Mid-Cycle Performance Review and Inspection Plan 2024-08-28
[Table view] Category:Letter
MONTHYEARIR 05000282/20240032024-11-13013 November 2024 Integrated Inspection Report 05000282/2024003, 05000306/2024003 & 07200010/2024001 ML24310A1682024-11-0505 November 2024 Core Operating Limits Report (COLR) for Cycle 34, Revision 0 ML24298A0552024-10-30030 October 2024 Response to Alternative RR-10, Auxiliary Feedwater Valve Testing IR 05000282/20244032024-10-25025 October 2024 – Security Baseline Inspection Report 05000282/2024403 and 05000306/2024403 05000282/LER-2024-001-01, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-10-22022 October 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies L-PI-24-044, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-10-21021 October 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software ML24221A3622024-09-27027 September 2024 Issuance of Amendment Nos. 245 and 233 Revise Technical Specification 3.8.1, AC Sources-Operating, Surveillance Requirement 3.8.1.2, Note 3 ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections 05000306/LER-2024-001-01, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump2024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 ML24130A2362024-05-0909 May 2024 Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Monitoring Program Report ML24130A2392024-05-0909 May 2024 2023 Annual Radioactive Effluent Report ML24071A1162024-05-0101 May 2024 Issuance of Amendment Nos. 244 and 232 Revise TS 3.7.8, Cooling Water (Cl) System ML24128A0882024-04-30030 April 2024 Submittal of Updated Safety Analysis Report (Usar), Revision 38 05000306/LER-2024-001, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump2024-04-29029 April 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 ML24100A8042024-04-24024 April 2024 – Alternative Request RR-09 for Safety Injection and Volume Control System Category C Check Valve Inservice Testing ML24114A0882024-04-23023 April 2024 Annual Report of Individual Monitoring for the Prairie Island Nuclear Generating Plant (PINGP) ML24113A1182024-04-12012 April 2024 NRC Letter Re NRC Office of Investigations Report No. 3-2023-004 ML24100A1212024-04-0909 April 2024 Submittal of Revised Pressure and Temperature Limits Report ML24093A2832024-04-0202 April 2024 Nuclear Material Transaction Report L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) ML24089A2402024-03-29029 March 2024 Guarantee of Payment of Deferred Premiums ML24060A1232024-03-27027 March 2024 To Request 1-RR-5-10 and 2-RR-5-10 Regarding Reactor Pressure Vessel Welds and Nozzle Welds 05000282/LER-2023-001-01, Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables2024-03-21021 March 2024 Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables ML24262A1512024-03-15015 March 2024 L-PI-24-011 150 Day Letter 2024 PINGP ILT NRC Exam ML24010A0582024-03-0505 March 2024 Amendment No. 12 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 2024-09-27
[Table view] |
Text
UNITED STATES rch 4, 2015
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (REPORT 05000282/2014001 AND 05000306/2014001)
Dear Mr. Davison:
On February 11, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Prairie Island Nuclear Generating Plant Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Prairie Island Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Prairie Island Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections for Unit 1 at your facility.
The NRC determined the performance at Prairie Island Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix because of one low-to-moderate safety significant (White) PI for Emergency Alternating Current Power Systems in the Mitigating Systems Performance Index. As described in Inspection Report 05000306/2014009 (ML14323A020), the NRC completed the required supplemental inspection and Prairie Island Unit 2 transitioned back to the Licensee Response Column of the ROP Action Matrix on November 18, 2014. With the closure of this White PI, all inspection findings having very low safety significance and all other PIs within the nominal expected range, the NRC will conduct ROP baseline inspections for Unit 2 at your facility.
In the mid-cycle assessment letter dated September 2, 2014 (ML14245A201), the NRC opened a substantive cross-cutting issue (SCCI) associated with the aspect of Documentation (H.7).
This assessment letter stated that the SCCI will remain open until the number of findings with a cross-cutting aspect of H.7 is reduced, the corrective actions taken to mitigate the cross-cutting theme prove effective, and sustained performance improvement is observed in the human performance area. During the current assessment period, the number of findings with H.7 assigned as the cross-cutting aspect has been reduced and no longer meets the definition of cross-cutting theme as described in IMC 0305, Operating Reactor Assessment Program, dated November 20, 2014. Specifically, a cross-cutting theme exists if there are four or more findings having the same cross-cutting aspect. To address the SCCI, your staff performed a root cause evaluation and developed corrective actions. However, as of the end of the assessment period, not all of the proposed corrective actions were completed and no effectiveness review of those completed corrective actions has been performed. Therefore, the SCCI will remain open until the corrective actions taken to mitigate the cross-cutting theme prove effective and sustained performance improvement is observed in the human performance area. This is the second consecutive assessment letter documenting this SCCI. The NRC will continue to monitor your staffs effort and progress in addressing the SCCI by evaluating your corrective action program, the root cause evaluation for the SCCI, and performance improvement initiatives to adequately assess if positive results are obtained.
The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
As stated in the inspection plan, from August 3, to September 4, 2015, the NRC plans to perform the Component Design Basis Inspection.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" is ongoing for various sites. The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee submittals, and to receive and review information relative to associated open items. This onsite audit will occur prior to the first unit at the site achieving compliance with the Orders and the audit will aid NRC staff in developing a final Safety Evaluation for the site. The audit at your site has been scheduled for the week of May 11, 2015. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Kenneth Riemer at 630-829-9628 with any questions you have regarding this letter.
Sincerely,
/RA/
Anne T. Boland, Director Division of Reactor Projects Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60 Enclosure:
Prairie Island Nuclear Generating Plant Inspection/Activity Plan cc w/encl: Distribution via LISTSERV