{{#Wiki_filter:___ _ _ _ _ _ _ _ _ _ _
{{#Wiki_filter:}}
D' SMBROM STATION Engineering Office:
IPUBLIC Companyof NewSERVICE Hampshre 1671 Worcester Road Framinoham, Massachusetts 01701 (617) - 872 - 8100 August 26, 1982 S BN- 313 T.F. B7.1.2 United States Nuclear Regulatory Commission Washington, D. C. 20555 Attention:          Mr. Frank J. Miraglia, Chief Licensing Branch No. 3 Division of Licensing Re fe re nces:      (a) Construction Permits CPPR-135 and CPPR-136, Docket Numbers 50-443 and 50-444 (b) USNRC Letter, dated February 12,1982, " Request for Aiditional Information", F. J. Miraglia to W. C. Tallman (c)              PSNH Letter, dated March 12, 1982, " Response to 410 Series RAIs; ( Auxiliary Systems Branch)", J. DeVincentis to F. J. Miraglia (d)              PSNH Letter, dated February 12,1982, " Implementation of TMI Action Plan Requirements of NUREG-0737",
J. DeVincentis to F. J. Miraglia i
 
==Subject:==
Reliability Analysts of the Emergency Feedwater System
 
==Dear Sir:==
 
In Reference (d), we committed to developing a reliability analysis of the Emergency Feedwater System pursuant to the requirements of NUREG-0737, It em II.E.1.1.
In response to your request for Additional Information (RAI 410.45(2)],
which you forwarded in Reference (b), we reiterated the above commitment in Re ference (c) .
I In fulfillment of this commitment, we have enclosed a report entitled
        " Reliability Analysts of the Emergency Feedwater System at the Seabrook Nuclear Power Station" which was prepared by our consultant, Wood-Imaver and As soc iate s , Incorporated.
A draf t copy of this report was presented to the Staf f at a meeting conducted at your offices on June 23 and 24,1982 and was further discussed at a meeting with Instrumentation and Control Systems Branch and Auxiliary Systems Branch (July 15 and 16,1982 at Seabrook Station).
Very truly yours, YANKEE ATOMIC ELECTRIC COMPANY 8209080103 820826
                                                                    ' /dw<
J. DeVincentis                        005 PDR ADOCK 05000443 A                                                                Project Manager                  i PDR ALL: kip a}}

Revision as of 10:10, 31 March 2020

Forwards Reliability Analysis of Emergency Feedwater Sys, Per NUREG-0737,Item II.E.1.1
ML20064M791
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 08/26/1982
From: Devincentis J
PUBLIC SERVICE CO. OF NEW HAMPSHIRE, YANKEE ATOMIC ELECTRIC CO.
To: Miraglia F
Office of Nuclear Reactor Regulation
Shared Package
ML20064M794 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.E.1.1, TASK-TM SBN-313, NUDOCS 8209080103
Download: ML20064M791 (1)


Text