o O                  POWER COMPANY                              ,
i 231 W. MICHIGMI, P.O. BOX 2046, MILWAUKEE; Wl 53201 f
February 11, 1983 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U. S. NUCLEAR REGULATORY COMMISSION Washington, D. C. 20555 Attention:            Mr. R. A. Clark, Chief Operating Reactors Branch 3 Gentlemen:
DOCKET NOS. 50-266 AND 50-301 AUXILIARY FEEDWATER SYSTEM MODIFICATIONS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 On December 15, 1982 we sent you a letter discussing the status of modifications we have undertaken to enhance the seismic resistance of the auxiliary feedwater (AFW) system at our Point Beach Nuclear Plant. That letter indicated certain modifi-cations would be completed by the end of January 1983. These modifications included additional supports for AFW system piping and components. This letter is to inform you that due to priority conflicts with other plant modifications, we have had to reschedule the installation of these supports to June 1983.
Another letter to you dated June 30, 1982 also discussed modifications to the AFW' system. These modifications were designed to provide a continuous indication in the control room of motor driven auxiliary feedwater-pump automatic initiation bypass and to change the AFW automatic actuation circuitry to allow periodic testing. We had anticipated completing installation of these modifications by December 31, 1982, however, upon more detailed engineering of these modifications we determined that the final installation on the unit control boards could not be readily accomplished while operating at power. Accordingly, we have delayed installation of these modifications until after the spring refueling for Unit 2, presently scheduled for June, and the fall refueling for Unit 1.
OL 8302150410 830211 DR ADOCK 050002gg
 
r' l
r                                                                        -
Mr. H. R. Denton                              February 11, 1983 As requested in your letter dated July 27, 1982, we shall notify you when these modifications have been completed so that the pending Technical Specification changes concerning these matters may be issued.
Very truly yours, (b
                                                                  /    -
hfil/    d2 Vice President - Nuclear Power C. W. Fay Copy to NRC Resident Inspector r
j
  \}}

Revision as of 12:37, 31 March 2020

Advises That Installation of Addl Supports for Auxiliary Feedwater Sys Piping & Components Rescheduled to June 1983, Due to Conflicts W/Other Plant Mods
ML20064L899
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 02/11/1983
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Clark R, Harold Denton
Office of Nuclear Reactor Regulation
References
TASK-2.E.1.1, TASK-2.E.1.2, TASK-TM TAC-43669, TAC-43670, TAC-53271, TAC-53272, NUDOCS 8302150410
Download: ML20064L899 (2)