| issue date = 01/09/2009 | | issue date = 01/09/2009 | ||
| title = | | title = Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000382/2009006) and Request for Information | ||
| author name = O'Keefe N | | author name = O'Keefe N | ||
| author affiliation = NRC/RGN-IV/DRS/EB-2 | | author affiliation = NRC/RGN-IV/DRS/EB-2 | ||
| addressee name = Walsh K | | addressee name = Walsh K | ||
Line 14: | Line 14: | ||
| page count = 8 | | page count = 8 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000382/2009006]] | ||
=Text= | =Text= | ||
{{#Wiki_filter:January 9, 2009 | {{#Wiki_filter:UNITED STATES | ||
NUC LE AR RE G UL AT O RY C O M M I S S I O N | |||
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA | R E GI ON I V | ||
612 EAST LAMAR BLVD , SU I TE 400 | |||
AR LI N GTON , TEXAS 76011-4125 | |||
January 9, 2009 | |||
facility in April 2009. | Kevin Walsh, Vice President, Operations | ||
Entergy Operations, Inc. | |||
Waterford Steam Electric Station, Unit 3 | |||
17265 River Road | |||
Killona, LA 70057-3093 | |||
SUBJECT: WATERFORD 3 - NOTIFICATION OF AN NRC TRIENNIAL FIRE | |||
PROTECTION BASELINE INSPECTION (NRC INSPECTION | |||
REPORT 05000382/2009006) AND REQUEST FOR INFORMATION | |||
Dear Mr. Walsh: | |||
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC), | |||
Region IV staff will conduct a triennial fire protection baseline inspection at your Waterford 3 | |||
facility in April 2009. The inspection team will be comprised of reactor inspectors from the NRC | |||
Region IV office. The team will conduct the inspection in accordance with the baseline | |||
Inspection Procedure 71111.05TTP, "Fire Protection-NFPA 805 Transition Period (Triennial)." | |||
The schedule for the inspection is as follows: | |||
* Information gathering visit: March 24 - 26, 2009 | |||
* Onsite inspection: April 06 - 10, 2009 | |||
April 27 - May 1, 2009 | |||
Two individuals will participate in the information gathering visit, to select the fire areas for | |||
evaluation, identify additional documents needed to support the inspection, obtain unescorted | |||
access, meet with the key personnel who will support the inspection, and become familiar with | |||
your fire protection program. The enclosure to this letter provides an initial list of the documents | |||
the team will want to review. We request that your staff transmit copies of the documents listed | |||
in the enclosure to the NRC Region IV office for team use in preparation for the inspection. | |||
Please send this information so that it will arrive in our office in Arlington, Texas, by the dates | |||
listed in the enclosure. | |||
We request that during the onsite inspection weeks, you ensure that copies of analyses, | |||
evaluations, or documentation regarding the implementation and maintenance of the fire | |||
protection program, including post-fire safe shutdown capability, be readily accessible to the | |||
team for their review. Of specific interest are those documents that establish that your fire | |||
protection program satisfies the NRC regulatory requirements and conforms to applicable NRC | |||
and industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant | |||
systems required to achieve and maintain safe shutdown conditions from inside and outside the | |||
control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant | |||
fire protection systems, and (4) the fire protection program and its implementation should be | |||
available to support the team at the site during the inspection. | |||
Entergy Operations, Inc -2- | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRCs document system | |||
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
Your cooperation and support during this inspection will be appreciated. If you have questions | |||
concerning this inspection or the inspection team's information or logistical needs, please | |||
contact the lead inspector, Greg Pick, at 817-860-8270. | |||
Sincerely, | |||
/RA/ | |||
Neil OKeefe, Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket: 50-382 | |||
License: NPF-38 | |||
Enclosure: Triennial Fire Protection | |||
Inspection Supporting Documentation | |||
Entergy Operations, Inc -3- | |||
Senior Vice President | |||
Entergy Nuclear Operations | |||
P.O. Box 31995 | |||
Jackson, MS 39286-1995 | |||
Senior Vice President and | |||
Entergy Operations, Inc - | Chief Operating Officer | ||
Entergy Operations, Inc. | |||
P.O. Box 31995 | |||
Jackson, MS 39286-1995 | |||
Vice President, Operations Support | |||
Entergy Services, Inc. | |||
P.O. Box 31995 | |||
Jackson, MS 39286-1995 | |||
Senior Manager, Nuclear Safety | |||
and Licensing | |||
Entergy Services, Inc. | |||
P.O. Box 31995 | |||
Jackson, MS 39286-1995 | |||
Site Vice President | |||
Waterford Steam Electric Station, Unit 3 | |||
Entergy Operations, Inc. | |||
17265 River Road | |||
Killona, LA 70057-0751 | |||
Director | |||
Nuclear Safety Assurance | |||
Entergy Operations, Inc. | |||
17265 River Road | |||
Killona, LA 70057-0751 | |||
General Manager, Plant Operations | |||
Waterford 3 SES | |||
Entergy Operations, Inc. | |||
17265 River Road | |||
Killona, LA 70057-0751 | |||
Manager, Licensing | |||
Entergy Operations, Inc. | |||
17265 River Road | |||
Killona, LA 70057-3093 | |||
Chairman | |||
Louisiana Public Service Commission | |||
P.O. Box 91154 | |||
Baton Rouge, LA 70825-1697 | |||
Entergy Operations, Inc -4- | |||
Richard Penrod, Senior Environmental | |||
Scientist, State Liaison Officer | |||
Office of Environmental Services | |||
Northwestern State University | |||
Russsell Hall, Room 201 | |||
Entergy Operations, Inc - | Natchitoches, LA 71497 | ||
Parish President Council | |||
St. Charles Parish | |||
P.O. Box 302 | |||
Hahnville, LA 70057 | |||
Director, Nuclear Safety & Licensing | |||
Entergy, Operations, Inc. | |||
440 Hamilton Avenue | |||
White Plains, NY 10601 | |||
Louisiana Department of Environmental | |||
Quality Radiological Emergency Planning | |||
and Response Division | |||
P.O. Box 4312 | |||
Baton Rouge, LA 70821-4312 | |||
Louisiana Department of Environmental | |||
Quality | |||
Office of Environmental Compliance | |||
P.O. Box 4312 | |||
Baton Rouge, LA 70821-4312 | |||
Lisa R. Hammond, Chief | |||
Technological Hazards Branch | |||
National Preparedness Division | |||
FEMA Region VI | |||
800 N. Loop 288 | |||
Denton, TX 76209 | |||
Entergy Operations, Inc -5- | |||
Electronic distribution by RIV: | |||
Regional Administrator (Elmo.Collins@nrc.gov) | |||
Deputy Regional Administrator (Chuck.Casto@nrc.gov) | |||
DRP Director (Dwight.Chamberlain@nrc.gov) | |||
DRP Deputy Director (Anton.Vegel@nrc.gov) | |||
DRS Director (Roy.Caniano@nrc.gov) | |||
DRS Deputy Director (Troy.Pruett@nrc.gov) | |||
Senior Resident Inspector (Ray.Azua@nrc.gov) | |||
Resident Inspector (Dean.Overland@nrc.gov) | |||
Branch Chief, DRP/E (Jeff.Clark@nrc.gov) | |||
Senior Project Engineer, DRP/E (George.Replogle@nrc.gov) | |||
WAT Site Secretary (Vacant) | |||
Public Affairs Officer (Victor.Dricks@nrc.gov) | |||
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov) | |||
RITS Coordinator (Marisa.Herrera@nrc.gov) | |||
Only inspection reports to the following: | |||
DRS STA (Dale.Powers@nrc.gov) | |||
S. Williams, OEDO RIV Coordinator (Shawn.Williams@nrc.gov) | |||
ROPreports | |||
File located: | |||
SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials | |||
Publicly Avail Yes No Sensitive Yes No Sens. Type Initials | |||
EB2 C: EB 2 | |||
G.Pick N.OKeefe | |||
/RA/ RLatta for | |||
01/ 7 /09 01/9 /09 | |||
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax | |||
ENCLOSURE | |||
Triennial Fire Protection Inspection Documentation Requested | |||
Please provide the following documentation items 1 - 4 prior to the onsite information-gathering | |||
visit, preferably no later than March 6, 2009. Where practical, please provide copies | |||
electronically. | |||
1. The current version of your fire protection program and fire hazards analysis. | |||
2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate | |||
acceptable plant response. | |||
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports, | |||
pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters | |||
to/from the NRC regarding fire protection/fire safe shutdown, etc.). | |||
4. The Fire Probabilistic Risk Assessment or portions of the plants Individual Plant | |||
Examination for External Events report addressing fire events. | |||
5. Plant layout and equipment drawings for the selected fire areas (these areas will be | |||
selected during the information gathering trip) that identify: (a) the physical plant | |||
locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or | |||
fire zone delineation; and (c) the locations of fire protection equipment, such as | |||
detection, suppression, and post-fire emergency lighting units; and (d) fire area | |||
boundaries. | |||
Please provide the following documentation items 5 - 34 during the information-gathering visit or | |||
by March 27, 2009, in order to support inspection preparation. Whenever practical, please | |||
provide copies electronically. However, drawings should be provided as paper copies of | |||
sufficient size that all details are legible. | |||
6. Fire protection program implementing procedures (e.g., administrative controls, operator | |||
response procedures for fires, fire fighting procedures, etc.). | |||
7. Operating procedures used for achieving and maintaining hot and cold shutdown | |||
conditions from the control room in the event of a fire outside the control room (III.G.2 | |||
areas). | |||
8. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas) | |||
capability with or without control room evacuation. | |||
9. Pre-fire plans for the selected fire areas (areas to be selected by the team during the | |||
information-gathering trip). | |||
10. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the | |||
event of a fire (safe shutdown equipment lists). | |||
-1- Enclosure | |||
11. Piping and instrumentation (flow) diagrams showing the components used to achieve | |||
and maintain hot standby and cold shutdown for normal and alternate shutdown. Please | |||
provide one copy of the piping and instrumentation (flow) diagrams for these systems of | |||
a size sufficient to read all details. These should include the systems used for RCS | |||
makeup, RCS pressure control, decay heat removal, and reactivity control, including the | |||
essential support systems. | |||
12. A listing of design change packages which were determined to impact fire protection and | |||
post-fire safe shutdowns, performed in the last 3 years. | |||
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years. | |||
14. A listing of open and closed corrective action documents initiated in the last 3 years, | |||
which relate to the fire protection program or equipment. Include corrective action | |||
document number, date, and subject. | |||
15. A listing of the applicable codes and standards (with the versions) related to the design | |||
of plant fire protection features and evaluations of any code deviations. | |||
16. Drawings of the portions of the emergency lighting system which support fire response. | |||
17. Procedures used to remove smoke from safety-related areas and the engineering | |||
studies or calculations which support the design basis. | |||
18. Drawings of communication systems credited in the license basis for firefighting and | |||
plant operations during fires where control room is occupied and/or evacuated. | |||
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems. | |||
20. A listing of maintenance and surveillance testing procedures for alternative shutdown | |||
capability and fire barriers, detectors, pumps and suppression systems. | |||
21. Maintenance Rule performance criteria and a summary of the last 3 years performance | |||
history for fire protection program systems or functions monitored within the | |||
Maintenance Rule program. | |||
22. A copy of fire protection program requirements (e.g. limiting conditions for operation, | |||
surveillance test requirements) covered by Technical Specifications, Technical | |||
Requirements Manual, Updated Final Safety Analysis Report, or similar documents. | |||
23. Copies of internal and external self-assessments, audits, peer-assessments or similar | |||
reviews related to post-fire safe shutdown capability or the fire protection program | |||
completed since August 1, 2006. | |||
24. A list of manual actions taken outside the control room which are credited to mitigate the | |||
consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should | |||
group actions by the initiating fire area or zone and indicate where the action must take | |||
place. | |||
-2- Enclosure | |||
25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design | |||
basis documents that describe the purpose/function/operating characteristics of the safe | |||
shutdown systems (reactor coolant system (RCS) makeup, RCS pressure control, decay | |||
heat removal, and reactivity control, including the essential support systems). | |||
26. Two copies of one-line diagrams of the electrical distribution system. These should | |||
depict how power gets from the switchyard to the engineered safety feature loads (480V | |||
and 4160V). Also, include the vital DC distribution system one-line diagrams. | |||
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant, | |||
giving location and the key equipment being protected. | |||
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or | |||
maintain hot shutdown and b) reach and/or maintain cold shutdown. | |||
29. A list of high to low pressure interface valves. | |||
30. A copy of procedures governing the training and operation of the fire brigade. | |||
31. Organization charts of site personnel down to the level of fire protection staff personnel. | |||
32. A contact list of key site personnel who will be supporting this inspection, giving location | |||
of their office and phone number onsite. | |||
33. The team would like to observe an unannounced fire brigade drill in the plant, if possible, | |||
during the week of April 27, 2009. Please put us in contact with the appropriate | |||
personnel for planning drills during the onsite information gathering trip. | |||
34. The team would like to perform a walkthrough of the procedure for control room | |||
evacuation due to fire with qualified operators in the plant during the week of | |||
April 6, 2009. Please put us in contact with the appropriate personnel for planning the | |||
walkthrough during the onsite information gathering trip. | |||
-3- Enclosure | |||
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant, giving location and the key equipment being protected. | |||
32. A contact list of key site personnel who will be supporting this inspection, giving location of their office and phone number onsite. | |||
personnel for planning drills during the onsite information gathering trip. | |||
walkthrough during the onsite information gathering trip. | |||
}} | }} |
Latest revision as of 09:58, 14 November 2019
ML090090644 | |
Person / Time | |
---|---|
Site: | Waterford |
Issue date: | 01/09/2009 |
From: | O'Keefe N NRC/RGN-IV/DRS/EB-2 |
To: | Walsh K Entergy Operations |
References | |
IR-09-006 | |
Download: ML090090644 (8) | |
See also: IR 05000382/2009006
Text
UNITED STATES
NUC LE AR RE G UL AT O RY C O M M I S S I O N
R E GI ON I V
612 EAST LAMAR BLVD , SU I TE 400
AR LI N GTON , TEXAS 76011-4125
January 9, 2009
Kevin Walsh, Vice President, Operations
Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3
17265 River Road
Killona, LA 70057-3093
SUBJECT: WATERFORD 3 - NOTIFICATION OF AN NRC TRIENNIAL FIRE
PROTECTION BASELINE INSPECTION (NRC INSPECTION
REPORT 05000382/2009006) AND REQUEST FOR INFORMATION
Dear Mr. Walsh:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),
Region IV staff will conduct a triennial fire protection baseline inspection at your Waterford 3
facility in April 2009. The inspection team will be comprised of reactor inspectors from the NRC
Region IV office. The team will conduct the inspection in accordance with the baseline
Inspection Procedure 71111.05TTP, "Fire Protection-NFPA 805 Transition Period (Triennial)."
The schedule for the inspection is as follows:
- Information gathering visit: March 24 - 26, 2009
- Onsite inspection: April 06 - 10, 2009
April 27 - May 1, 2009
Two individuals will participate in the information gathering visit, to select the fire areas for
evaluation, identify additional documents needed to support the inspection, obtain unescorted
access, meet with the key personnel who will support the inspection, and become familiar with
your fire protection program. The enclosure to this letter provides an initial list of the documents
the team will want to review. We request that your staff transmit copies of the documents listed
in the enclosure to the NRC Region IV office for team use in preparation for the inspection.
Please send this information so that it will arrive in our office in Arlington, Texas, by the dates
listed in the enclosure.
We request that during the onsite inspection weeks, you ensure that copies of analyses,
evaluations, or documentation regarding the implementation and maintenance of the fire
protection program, including post-fire safe shutdown capability, be readily accessible to the
team for their review. Of specific interest are those documents that establish that your fire
protection program satisfies the NRC regulatory requirements and conforms to applicable NRC
and industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant
systems required to achieve and maintain safe shutdown conditions from inside and outside the
control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant
fire protection systems, and (4) the fire protection program and its implementation should be
available to support the team at the site during the inspection.
Entergy Operations, Inc -2-
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Your cooperation and support during this inspection will be appreciated. If you have questions
concerning this inspection or the inspection team's information or logistical needs, please
contact the lead inspector, Greg Pick, at 817-860-8270.
Sincerely,
/RA/
Neil OKeefe, Chief
Engineering Branch 2
Division of Reactor Safety
Docket: 50-382
License: NPF-38
Enclosure: Triennial Fire Protection
Inspection Supporting Documentation
Entergy Operations, Inc -3-
Senior Vice President
Entergy Nuclear Operations
P.O. Box 31995
Jackson, MS 39286-1995
Senior Vice President and
Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Vice President, Operations Support
Entergy Services, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Senior Manager, Nuclear Safety
and Licensing
Entergy Services, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Site Vice President
Waterford Steam Electric Station, Unit 3
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057-0751
Director
Nuclear Safety Assurance
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057-0751
General Manager, Plant Operations
Waterford 3 SES
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057-0751
Manager, Licensing
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057-3093
Chairman
Louisiana Public Service Commission
P.O. Box 91154
Baton Rouge, LA 70825-1697
Entergy Operations, Inc -4-
Richard Penrod, Senior Environmental
Scientist, State Liaison Officer
Office of Environmental Services
Northwestern State University
Russsell Hall, Room 201
Natchitoches, LA 71497
Parish President Council
St. Charles Parish
P.O. Box 302
Hahnville, LA 70057
Director, Nuclear Safety & Licensing
Entergy, Operations, Inc.
440 Hamilton Avenue
White Plains, NY 10601
Louisiana Department of Environmental
Quality Radiological Emergency Planning
and Response Division
P.O. Box 4312
Baton Rouge, LA 70821-4312
Louisiana Department of Environmental
Quality
Office of Environmental Compliance
P.O. Box 4312
Baton Rouge, LA 70821-4312
Lisa R. Hammond, Chief
Technological Hazards Branch
National Preparedness Division
FEMA Region VI
800 N. Loop 288
Denton, TX 76209
Entergy Operations, Inc -5-
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (Ray.Azua@nrc.gov)
Resident Inspector (Dean.Overland@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)
WAT Site Secretary (Vacant)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Only inspection reports to the following:
S. Williams, OEDO RIV Coordinator (Shawn.Williams@nrc.gov)
ROPreports
File located:
SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials
Publicly Avail Yes No Sensitive Yes No Sens. Type Initials
EB2 C: EB 2
G.Pick N.OKeefe
/RA/ RLatta for
01/ 7 /09 01/9 /09
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
ENCLOSURE
Triennial Fire Protection Inspection Documentation Requested
Please provide the following documentation items 1 - 4 prior to the onsite information-gathering
visit, preferably no later than March 6, 2009. Where practical, please provide copies
electronically.
1. The current version of your fire protection program and fire hazards analysis.
2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate
acceptable plant response.
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports,
pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters
to/from the NRC regarding fire protection/fire safe shutdown, etc.).
4. The Fire Probabilistic Risk Assessment or portions of the plants Individual Plant
Examination for External Events report addressing fire events.
5. Plant layout and equipment drawings for the selected fire areas (these areas will be
selected during the information gathering trip) that identify: (a) the physical plant
locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or
fire zone delineation; and (c) the locations of fire protection equipment, such as
detection, suppression, and post-fire emergency lighting units; and (d) fire area
boundaries.
Please provide the following documentation items 5 - 34 during the information-gathering visit or
by March 27, 2009, in order to support inspection preparation. Whenever practical, please
provide copies electronically. However, drawings should be provided as paper copies of
sufficient size that all details are legible.
6. Fire protection program implementing procedures (e.g., administrative controls, operator
response procedures for fires, fire fighting procedures, etc.).
7. Operating procedures used for achieving and maintaining hot and cold shutdown
conditions from the control room in the event of a fire outside the control room (III.G.2
areas).
8. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)
capability with or without control room evacuation.
9. Pre-fire plans for the selected fire areas (areas to be selected by the team during the
information-gathering trip).
10. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the
event of a fire (safe shutdown equipment lists).
-1- Enclosure
11. Piping and instrumentation (flow) diagrams showing the components used to achieve
and maintain hot standby and cold shutdown for normal and alternate shutdown. Please
provide one copy of the piping and instrumentation (flow) diagrams for these systems of
a size sufficient to read all details. These should include the systems used for RCS
makeup, RCS pressure control, decay heat removal, and reactivity control, including the
essential support systems.
12. A listing of design change packages which were determined to impact fire protection and
post-fire safe shutdowns, performed in the last 3 years.
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.
14. A listing of open and closed corrective action documents initiated in the last 3 years,
which relate to the fire protection program or equipment. Include corrective action
document number, date, and subject.
15. A listing of the applicable codes and standards (with the versions) related to the design
of plant fire protection features and evaluations of any code deviations.
16. Drawings of the portions of the emergency lighting system which support fire response.
17. Procedures used to remove smoke from safety-related areas and the engineering
studies or calculations which support the design basis.
18. Drawings of communication systems credited in the license basis for firefighting and
plant operations during fires where control room is occupied and/or evacuated.
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
20. A listing of maintenance and surveillance testing procedures for alternative shutdown
capability and fire barriers, detectors, pumps and suppression systems.
21. Maintenance Rule performance criteria and a summary of the last 3 years performance
history for fire protection program systems or functions monitored within the
22. A copy of fire protection program requirements (e.g. limiting conditions for operation,
surveillance test requirements) covered by Technical Specifications, Technical
Requirements Manual, Updated Final Safety Analysis Report, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar
reviews related to post-fire safe shutdown capability or the fire protection program
completed since August 1, 2006.
24. A list of manual actions taken outside the control room which are credited to mitigate the
consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should
group actions by the initiating fire area or zone and indicate where the action must take
place.
-2- Enclosure
25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design
basis documents that describe the purpose/function/operating characteristics of the safe
shutdown systems (reactor coolant system (RCS) makeup, RCS pressure control, decay
heat removal, and reactivity control, including the essential support systems).
26. Two copies of one-line diagrams of the electrical distribution system. These should
depict how power gets from the switchyard to the engineered safety feature loads (480V
and 4160V). Also, include the vital DC distribution system one-line diagrams.
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant,
giving location and the key equipment being protected.
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or
maintain hot shutdown and b) reach and/or maintain cold shutdown.
29. A list of high to low pressure interface valves.
30. A copy of procedures governing the training and operation of the fire brigade.
31. Organization charts of site personnel down to the level of fire protection staff personnel.
32. A contact list of key site personnel who will be supporting this inspection, giving location
of their office and phone number onsite.
33. The team would like to observe an unannounced fire brigade drill in the plant, if possible,
during the week of April 27, 2009. Please put us in contact with the appropriate
personnel for planning drills during the onsite information gathering trip.
34. The team would like to perform a walkthrough of the procedure for control room
evacuation due to fire with qualified operators in the plant during the week of
April 6, 2009. Please put us in contact with the appropriate personnel for planning the
walkthrough during the onsite information gathering trip.
-3- Enclosure