MONTHYEARML16299A2822016-11-10010 November 2016 Scoping and Screening Methodology Audit Report Regarding Waterford Steam Electric Station, Unit 3 License Renewal Application Review Project stage: Other ML16315A2352016-11-10010 November 2016 Responses to Request for Additional Information Set 2 Regarding the License Renewal Application Project stage: Response to RAI W3F1-2016-0075, Responses to Request for Additional Information Set 6 Regarding the License Renewal Application2016-12-0707 December 2016 Responses to Request for Additional Information Set 6 Regarding the License Renewal Application Project stage: Response to RAI ML16343A0722016-12-0808 December 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 10 Project stage: RAI W3F1-2016-0077, Responses to Request for Additional Information Set 7 Regarding the License Renewal Application2016-12-15015 December 2016 Responses to Request for Additional Information Set 7 Regarding the License Renewal Application Project stage: Response to RAI ML16351A0452016-12-19019 December 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 11 Project stage: RAI ML16341B0632016-12-21021 December 2016 November 30, 2016 Summary of Teleconference Held Between NRC and Entergy Operations, Inc. Concerning RAI Set 9 Pertaining to the Waterford Steam Electric Station, Unit 3, License Renewal Application Project stage: RAI ML16356A5822016-12-30030 December 2016 12/07/2016 Summary of Teleconference with Entergy Operations, Inc. Concerning Requests for Additional Information Set 10 Pertaining to the Waterford Steam Electric Station Unit 3 License Renewal Application Project stage: RAI ML17038A4362017-02-0707 February 2017 Responses to Request for Additional Information for the Environmental Review Project stage: Response to RAI ML17040A5382017-02-14014 February 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 13 Project stage: RAI ML17054D2392017-02-23023 February 2017 Responses to Request for Additional Information Set 12 Regarding the License Renewal Application Project stage: Response to RAI ML17272A3352017-03-0101 March 2017 Request for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 14 Project stage: RAI ML17072A0102017-03-14014 March 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set - 15 Project stage: RAI ML17086A5852017-03-28028 March 2017 Request for Additional Information for the Environmental Review of Waterford 3 Project stage: RAI ML17088A1852017-03-30030 March 2017 Summary of Telecon Held on March 28, 2017, Between NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) Project stage: RAI ML17090A0472017-03-31031 March 2017 Summary of Telecon Held on March 28, 2017, Between the NRC and Entergy Concerning RAI Pertaining to the Waterford Steam Electric Station License Renewal Application (Cac. No. MF7493) - Updated with ADAMS Accession Nos Project stage: RAI ML17101A4432017-04-17017 April 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 17 Project stage: RAI ML17054C5292017-05-0909 May 2017 Aging Management Programs Audit Report Regarding Waterford Steam Electric Station, Unit 3 License Renewal Application Review Project stage: Other ML17131A1942017-08-24024 August 2017 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application (CAC Nos. MF7492 and MF7493) Project stage: Approval W3F1-2017-0065, License Amendment Request for Use of RAPTOR-M3G Code for Neutron Fluence Calculations2017-11-28028 November 2017 License Amendment Request for Use of RAPTOR-M3G Code for Neutron Fluence Calculations Project stage: Request W3F1-2017-0083, License Renewal Application Supplement Clarification2017-12-0707 December 2017 License Renewal Application Supplement Clarification Project stage: Supplement ML17347A1272017-12-20020 December 2017 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application (CAC Nos. MF7492 and MF7493) Project stage: Approval ML18085A6942018-03-26026 March 2018 Ref: Waterford Steam Electric Station, Unit 3, License Renewal Application - RAI Set 18 Project stage: RAI ML18165A1402018-08-16016 August 2018 Notice of Availability of the Draft Plant-Specific Supplement 59 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford 3 Project stage: Draft Other ML18165A4242018-08-16016 August 2018 Notice of Availability of the Draft Plant-Specific Supplement 59 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford Project stage: Draft Other ML18165A1392018-08-16016 August 2018, 20 August 2018 Notice of Availability of the Draft Plant-Specific Supplement 59 to the Generic Environmental Imapct Statement for License Renewal of Nuclear Plants Regarding Waterford 3 Project stage: Request ML18228A6682018-08-17017 August 2018 Safety Evaluation Report Related to the License Renewal of Waterford Steam Electric Station, Unit 3 Project stage: Approval ML18221A1162018-08-17017 August 2018 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application (CAC Nos. MF7492 and MF7493) Project stage: Approval ML18165A3992018-08-20020 August 2018 FRN Draft SEIS Availability Project stage: Request ML18227A0282018-08-31031 August 2018 NUREG-1437, Dfc, Suppl. 59, Generic Environmental Impact Statement for License Renewal of Nuclear Plants - Supplement 59, - Regarding Waterford Steam Electric Station, Unit 3 Project stage: Acceptance Review ML18309A2242018-11-20020 November 2018 Federal Register Notice - Notice of Availability of the Final Plant-Specific Supplement 59 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford 3 Project stage: Other ML18309A2222018-11-20020 November 2018 Notice of Availability of Final SEIS NUREG-1437 Supplement 59 License Renewal Project stage: Request ML18309A2232018-11-20020 November 2018 Notice of Availability of the Final Plant-Specific Supplement 59 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford 3 Project stage: Other ML18155A5802018-11-28028 November 2018 Issuance of Scoping Summary Report Associated with License Renewal Application Environmental Review (CAC No. MF7493; EPID No. L-2016-LNE-0001) Project stage: Approval ML18309A1752018-12-0303 December 2018 Notice of Availability of the Final Plant-Specific Supplement 59 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford 3 and Response to Comments on the Environmental Impact Statement Project stage: Other ML18275A2152018-12-27027 December 2018 Issuance of Renewed Facility Operating License No. NPF-38 for Waterford Steam Electric Station, Unit 3 CAC Nos. MF7492 and MF7493) Project stage: Approval 2017-03-14
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23097A0412023-04-0606 April 2023 June 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23076A0552023-03-13013 March 2023 EP Program Inspection RFI Hjs 10132022 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23052A0882023-02-17017 February 2023 Inspection Request for Information ML22335A4802022-12-0101 December 2022 NRR E-mail Capture - NRC Update Completion Date for Waterford 3 LAR to Adopt TSTF-505 ML22336A0202022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request to Revise Technical Specification 3/4.3.2 ML22329A0152022-11-0202 November 2022 NRR E-mail Capture - NRC Update Completion Date for Waterford 3 LAR to Adopt TSTF-505 ML22290A0442022-10-13013 October 2022 December 2022 Emergency Preparedness Program Inspection - Request for Information ML22215A2062022-08-0303 August 2022 NRR E-mail Capture - Waterford 3 - LAR to Adopt Title 10 of the Code of Federal Regulations, Section 50.69: Loe and Completion Date Update ML22215A1492022-08-0303 August 2022 NRR E-mail Capture - Waterford 3 - LAR to Permit the Use of Risk-Informed Completion Times in Accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2 ML22206A0172022-07-22022 July 2022 NRR E-mail Capture - Request for Additional Information: Waterford 3 - License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22209A1082022-07-15015 July 2022 NRR E-mail Capture - Draft RAIs to License Amendment Request for Application to Adopt 10 CFR 50.69 and Revise Technical Specifications to Adopt TSTF-505, Revision 2 ML22144A1662022-05-24024 May 2022 PI&R Request for Information and Transmittal e-mail ML22108A1792022-04-14014 April 2022 WF3 Cpcs Installation Inspection Plan Email ML22209A1062022-01-20020 January 2022 NRR E-mail Capture - (External_Sender) Options Moving Forward Regarding Waterford TSTF-505 and 50.69 ML22209A1052022-01-0606 January 2022 NRR E-mail Capture - Estimate for Completion of 50.69-TSTF-505 Peer Review ML22012A1592022-01-0505 January 2022 WF3 2022 EP Exercise Inspection RFI Sdh 010522 ML21356A5872021-12-22022 December 2021 NRR E-mail Capture - Acceptance for Review: Waterford 3 - Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML21349A2242021-12-14014 December 2021 NRR E-mail Capture - (External_Sender) Waterford 3 - Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial EP Exercise ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21280A0812021-10-0505 October 2021 Email 10-5-21 - Request for Information_ Waterford EP Inspection (71114.04 & 71151) - Nov-Dec 2021 ML21285A0242021-10-0505 October 2021 Digital Instrumentation and Control Modification Inspection Request for Information ML22112A1512021-08-0606 August 2021 NRR E-mail Capture - for Review: Draft RAIs to LAR to Relocate Chemical Detection Systems Technical Specifications (TS) to Technical Requirements Manual (TRM) ML21216A4562021-08-0404 August 2021 WF3 2021 EP Exercise Inspection Request for Information (RFI) ML21218A0402021-07-26026 July 2021 NRR E-mail Capture - Final RAIs to Entergy Operations, Waterford Steam Electric Station, Unit 3 LAR to Adopt 10 CFR 50.69 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21173A1082021-06-22022 June 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request to Adopt TSTF-563 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21160A0852021-06-0404 June 2021 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Louisiana Regarding a Waterford Steam Electric Station, Unit 3 Amendment - Digital Upgrade I&C ML21145A0062021-05-24024 May 2021 NRR E-mail Capture - Supplement Received - Waterford Unit 3 - License Amendment Request for Boration Systems Tech Specs ML21120A1192021-04-30030 April 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - LAR to Relocate Chemical Detection TSs to TRM ML21105A0512021-04-14014 April 2021 4-14-21 Email - RFI for In-Office Inspection of Recent WF3 Submission of EAL Procedure Revision ML21104A0382021-04-13013 April 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request for TSTF-505 ML21084A2552021-03-22022 March 2021 NRR E-mail Capture - Supplement to Audit Plan Dated October 1, 2020 (Waterford 3, L-2020-LLA-0164) ML21088A1512021-03-15015 March 2021 NRR E-mail Capture - Draft Waterford Acceptance Review Letter for TSTF-505 LAR ML21069A1842021-03-0202 March 2021 NRR E-mail Capture - Announcement of QA Inspection ML21040A3892021-02-0808 February 2021 NRR E-mail Capture - Announcement of QA Inspection ML21039A6412021-01-28028 January 2021 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford 3 50.69 LAR ML21022A1692021-01-22022 January 2021 NRR E-mail Capture - Entergy Fleet (ANO, Grand Gulf, River Bend, and Waterford) - Acceptance Review for RR EN-20-RR-003, Proposed Alternative to Use ASME Code Case N-711-2 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20288A2082020-10-0808 October 2020 8Oct2020 Email - Request for Information (RFI) to Support and Prepare for the Emergency Preparedness (EP) Program Inspection at the Waterford 3 Station Scheduled to Occur the Week of December 7, 2020 ML20289A3502020-10-0505 October 2020 NRR E-mail Capture - NRC Request for Additional Information - WF3 EAL Scheme Change - L-2020-LLA-0122 ML20239B0552020-08-26026 August 2020 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford U3 Digital Upgrade LAR ML20197A3122020-07-14014 July 2020 NRR E-mail Capture - NRC Notification of State of Louisiana Re. Waterford Steam Electric Station License Amendments - Changes to Technical Specifications ML20191A0172020-06-26026 June 2020 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford U3 EAL Scheme Change LAR ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) 2023-04-06
[Table view] Category:Letter
MONTHYEARIR 05000382/20230102024-01-31031 January 2024 Comprehensive Engineering Team Inspection Report 05000382/2023010 IR 05000382/20230032024-01-23023 January 2024 Acknowledgment of Reply to a Notice of Violation NRC Inspection Report 05000382/2023003 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23340A2292023-12-28028 December 2023 Withdrawal of an Amendment Request to Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability (EPID L-2022-LLA-0169)-LTR ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1442023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23312A1832023-11-14014 November 2023 Integrated Inspection Report 05000382/2023003 and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000382/20234012023-10-0404 October 2023 Cyber Security Inspection Report 05000382/2023401 (Cover Letter Only) IR 05000382/20230052023-08-21021 August 2023 Updated Inspection Plan for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2023005) IR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 IR 05000382/20230022023-08-0808 August 2023 Integrated Inspection Report 05000382/2023002 IR 05000382/20234022023-08-0707 August 2023 NRC Security Inspection Report 05000382/2023402 (Full Report) IR 05000382/20230402023-07-12012 July 2023 Revised 95001 Supplemental Inspection Report 05000382/2023040, Exercise of Enforcement Discretion, and Follow-Up Assessment Letter ML23191A4562023-07-10010 July 2023 Notification of Comprehensive Engineering Team Inspection (050003822023010) and Request for Information ML23158A1042023-06-0808 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000382/2023401 ML23145A2272023-06-0202 June 2023 95001 Supplemental Inspection Report 05000382/2023040, and Exercise of Enforcement Discretion ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment IR 05000382/20230012023-04-24024 April 2023 Integrated Inspection Report 05000382/2023001, Independent Spent Fuel Storage Installation Report 07200075/2023001, and Exercise of Enforcement Discretion ML23111A2132023-04-21021 April 2023 Responses to RAI Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML23108A2542023-04-18018 April 2023 WCGS Information Request, Security IR 2023401 IR 05000382/20234032023-04-17017 April 2023 Security Baseline Inspection Report 05000382/2023403 ML23093A2122023-04-0303 April 2023 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2022 ML23089A0602023-03-30030 March 2023 Entergy Operations, Inc. - Fleet Project Manager Assignment ML23088A3922023-03-29029 March 2023 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML23080A2882023-03-21021 March 2023 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) Entergy Operations, Inc ML23059A2592023-03-0707 March 2023 Correction to Issuance to Amendment No. 270 Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23065A2002023-03-0303 March 2023 EN 56252 Update - Flow Serve - Final Notification of Potential Part 21 on Peerless 56 Frame DC Motors ML23060A1092023-03-0101 March 2023 Proof of Financial Protection (10 CFR 140.15) IR 05000382/20220062023-03-0101 March 2023 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3, (Report 05000382/2022006) ML22322A1092023-02-17017 February 2023 Issuance of Amendment No. 270 Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000382/20230902023-02-0101 February 2023 Final Significance Determination of a White Finding, NOV, and Follow-Up Assessment Letter; NRC Inspection Report 05000382/2023090 ML23032A5062023-02-0101 February 2023 Technical Specification Index and Bases Update to the NRC for the Period November 11, 2021 Through July 25, 2022 ML23030A6642023-01-27027 January 2023 Flowserve, Part 21 Second Interim Notification Report Re Peerless 56 Frame DC Motors IR 05000382/20220042023-01-26026 January 2023 Integrated Inspection Report 05000382/2022004 and Independent Fuel Storage Installation Inspection Report 07200075/2022001 ML23024A0822023-01-20020 January 2023 Stephens Insurance, Entergy - 2023 Nuclear Energy Liability Evidence of Financial Protection ML23018A2202023-01-18018 January 2023 Quality Assurance Program Manual Reduction in Commitment IR 05000382/20220912023-01-12012 January 2023 Emergency Preparedness Inspection Report 05000382/2022091 and Preliminary White Finding and Apparent Violation IR 05000382/20220032023-01-0505 January 2023 Revised Integrated Inspection Report 05000382/2022003 ML22342B1402022-12-0202 December 2022 56252-EN 56252 - Flowserve - Limitorque - Interim Report Potential Part 21 on Peerless 56 Frame DC Motors ML22300A2082022-11-30030 November 2022 Issuance of Amendment No. 269 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22332A5292022-11-29029 November 2022 Notification of NRC Initial Operator Licensing Examination 05000382/2023301 IR 05000382/20220132022-11-28028 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000382/2022013 IR 05000382/20220022022-11-0101 November 2022 Revised Integrated Inspection Report 05000382/2022002 2024-01-31
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23191A4562023-07-10010 July 2023 Notification of Comprehensive Engineering Team Inspection (050003822023010) and Request for Information ML23097A0412023-04-0606 April 2023 June 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23076A0552023-03-13013 March 2023 EP Program Inspection RFI Hjs 10132022 ML23052A0882023-02-17017 February 2023 Inspection Request for Information ML22290A0442022-10-13013 October 2022 December 2022 Emergency Preparedness Program Inspection - Request for Information ML22206A0172022-07-22022 July 2022 NRR E-mail Capture - Request for Additional Information: Waterford 3 - License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 ML22209A1082022-07-15015 July 2022 NRR E-mail Capture - Draft RAIs to License Amendment Request for Application to Adopt 10 CFR 50.69 and Revise Technical Specifications to Adopt TSTF-505, Revision 2 ML22103A1712022-04-13013 April 2022 LAR to Revise TS to Adopt TSTF-505_NRC Request for Additional Information ML22012A1592022-01-0505 January 2022 WF3 2022 EP Exercise Inspection RFI Sdh 010522 ML21280A0812021-10-0505 October 2021 Email 10-5-21 - Request for Information_ Waterford EP Inspection (71114.04 & 71151) - Nov-Dec 2021 ML21285A0242021-10-0505 October 2021 Digital Instrumentation and Control Modification Inspection Request for Information ML22112A1512021-08-0606 August 2021 NRR E-mail Capture - for Review: Draft RAIs to LAR to Relocate Chemical Detection Systems Technical Specifications (TS) to Technical Requirements Manual (TRM) ML21216A4562021-08-0404 August 2021 WF3 2021 EP Exercise Inspection Request for Information (RFI) ML21218A0402021-07-26026 July 2021 NRR E-mail Capture - Final RAIs to Entergy Operations, Waterford Steam Electric Station, Unit 3 LAR to Adopt 10 CFR 50.69 ML21196A5302021-07-19019 July 2021 Wat 2021010 RFI Letter 21N_05 Gap ML21195A0692021-07-13013 July 2021 Staton, Unit 3 - Notification of Digital Instrumentation and Control Modification Inspection and Request for Information ML21125A6522021-05-0606 May 2021 Wat 2021003 Brq RFI- Md, Waterford Steam Electric Station, Unit 3, Notification of Inspection (NRC Inspection Report 05000382/2021003) and Request for Information ML21112A2542021-04-29029 April 2021 Request for Additional Information Digital Upgrade to the Core Protection and Control Element Assembly Calculator System (EPID L 2020 Lla 0164) - Redacted Version ML20288A2082020-10-0808 October 2020 8Oct2020 Email - Request for Information (RFI) to Support and Prepare for the Emergency Preparedness (EP) Program Inspection at the Waterford 3 Station Scheduled to Occur the Week of December 7, 2020 ML20289A3502020-10-0505 October 2020 NRR E-mail Capture - NRC Request for Additional Information - WF3 EAL Scheme Change - L-2020-LLA-0122 ML20125A3212020-05-0404 May 2020 WAT2020410 Inspection Document Request ML20086M3852020-04-0101 April 2020 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3/4 8.1, A.C. Sources Operating W3F1-2020-0014, Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding Application for Technical Specification Change to Control Room Air Conditioning System2020-03-20020 March 2020 Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding Application for Technical Specification Change to Control Room Air Conditioning System ML20049A4102020-02-20020 February 2020 Request for Additional Information Regarding License Amendment Request to Revise Surveillance Requirement 4.7.6.1.d, Control Room Air Filtration System ML19262H0362019-09-0404 September 2019 Ti 2515/194 Request for Information and Email ML19274D4932019-07-24024 July 2019 Request for Information IR 05000382 2019-003 Occupational Radiation Safety Inspection ML19203A0062019-07-19019 July 2019 NRR E-mail Capture - Waterford 3 - Final Request for Additional Information (Rais) Re Relief Request WF3-RR-19-2: Alternate Repair of Degraded Drain Line of Chemical and Volume Control System ML19151A6102019-06-0404 June 2019 Non-Proprietary Second Round RAI Regarding License Amendment Request for Use of the Tranflow Code for Determining Pressure Drops Across the Steam Generator Secondary Side Internal Components ML19172A0852019-05-24024 May 2019 NRR E-mail Capture - Waterford 3 - Final Request for Additional Information (Rais) Re Relief Request W3-ISI-032: Volumetric Examination Requirements ML19035A0412019-02-0101 February 2019 NRR E-mail Capture - Waterford 3 - Final Request for Information Regarding Relief Request WF3-RR-19-001 for Application of Dissimilar Metal Weld Full Structural Weld Overlay ML19018A0102019-01-28028 January 2019 Request for Additional Information Regarding License Amendment Request for Revision of Technical Specification 3/4.7.4,Ultimate Heat Sink ML18320A0902018-11-26026 November 2018 Request for Additional Information Regarding License Amendment Request for Use of the Transflow Code for Determining Pressure Drops Across the Steam Generator Secondary Side Internal Components ML18318A4352018-11-14014 November 2018 NRR E-mail Capture - Waterford 3 - Final Request for Additional Information Regarding Request for Alternative to ASME Code Case N-770-2 ML18299A0862018-11-0707 November 2018 Draft Request for Additional Information License Amendment Request Regarding the Revision of UFSAR Section 3.9 ML18262A0412018-09-25025 September 2018 Request for Additional Information Regarding License Amendment Request to Revise Section 15.4.3.1 of the Waterford 3 Updated Final Safety Analysis Report to Account for Fuel Misload ML18145A2652018-06-0101 June 2018 Supplemental Information Needed for Acceptance of Request for Licensing Action Use of Tranflow Code for Determining Pressure Drops Across Steam Generator Secondary Side Components ML18085A6942018-03-26026 March 2018 Ref: Waterford Steam Electric Station, Unit 3, License Renewal Application - RAI Set 18 ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update) ML18039A9722018-02-0808 February 2018 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000382/2018002) and Request for Information ML17233A2402017-08-14014 August 2017 NRR E-mail Capture - Draft RAI for Waterford Unit 3 Regarding License Amendment Request to Adopt TSTF-501 Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML17170A3012017-06-16016 June 2017 Notification of Inspection (NRC Integrated Inspection Report 05000382/2017003) and Request for Information ML17101A4432017-04-17017 April 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 17 ML17086A5852017-03-28028 March 2017 Request for Additional Information for the Environmental Review of Waterford 3 ML17072A0102017-03-14014 March 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set - 15 ML17272A3352017-03-0101 March 2017 Request for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 14 ML17040A5382017-02-14014 February 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 13 ML17018A3592017-01-26026 January 2017 Requests For Additional Information For The Review Of The Waterford Steam Electric Station, Unit 3, License Renewal Application Set 12 (CAC MF7492.) ML16354A1052016-12-27027 December 2016 RAI License Amendment Request to Revise TS 3/4.3.2 to Relocate Surveillance Frequency Requirements for Engineered Safety Feature Actuation System (ESFAS) Subgroup Relays to the Surveillance Frequency Control Program ML16356A5942016-12-19019 December 2016 NRR E-mail Capture - MF8325 Draft RAIs Regarding the License Amendment Request to Revise the Table Notation for Table 4.3-2, ESFAS Surveillance Requirements 2023-07-10
[Table view] |
Text
From: Keegan, Elaine To: "mchisum@entergy.com" Cc: "lpott90@entergy.com"; Dozier, Jerry; "erschmidt36@comcast.net"; William.Ivans@pnnl.gov; steve.short@pnnl.gov; "HARRIS, ALAN J"; Milster, Leia Elizabeth; Ramirez, Frances; Speer, Chris; Rikhoff, Jeffrey; "gyoung4@entergy.com"; "rbuckley@entergy.com"; Clark, Phyllis; Dricks, Victor; Maier, Bill; McIntyre, David; RidsNrrDlr Resource; RidsNrrDlrRarb Resource; RidsNrrDlrRasb Resource; RidsNrrDlrRerb Resource; RidsNrrPMWaterford Resource
Subject:
REQUEST FOR ADDITIONAL INFORMATION FOR THE ENVIRONMENTAL REVIEW OF WATERFORD STEAM ELECTRIC STATION, UNIT 3 Date: Tuesday, March 28, 2017 4:11:00 PM Attachments: image001.png Final WF3 SAMA Second Round RAI - 3_28_2017.pdf image002.png UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Michael R. Chisum Site Vice President Entergy Operations, Inc.
Waterford 3 17265 River Road Killona, LA 70057-3093
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE ENVIRONMENTAL REVIEW OF WATERFORD STEAM ELECTRIC STATION, UNIT 3 (CAC NO. MF7493)
Dear Mr. Chisum:
The U.S. Nuclear Regulatory Commission (NRC) is conducting an environmental review of Entergy Operations, Inc. (Entergy) application for renewal of the operating license for Waterford Steam Electric Station, Unit 3 (WF3). On November 22, 2016, the NRC staff sent a request for additional information (RAI) (ADAMS Accession No. ML16309A580) based on the staffs review of the severe accident mitigation analysis (SAMA) in Entergys environmental report. After reviewing Entergys RAI response (ADAMS Accession No. ML17038A436, dated February 7, 2017), the NRC staff has identified several areas where further clarification is needed to complete the environmental review. The enclosure lists the SAMA request for additional information (RAI).
The enclosed requests for additional information were discussed with Mr. Alan Harris. A mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.
Sincerely, Elaine M. Keegan Elaine M. Keegan, Sr. Project Manager Environmental Review and Projects Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosure:
As stated cc: Listserv ADAMS Accession no.: ML17086A585 OFFICE PM:RERP:DLR BC:RERP:DLR PM:RERP:DLR NAME EKeegan JRikhoff EKeegan DATE 03/24/2017 03/28/2017 03/28/2017 Elaine M Keegan Sr. Project Manager Division of License Renewal, NRR U.S. Nuclear Regulatory Commission 301-415-8517
OFFICE OF NUCLEAR REACTOR REGULATION REQUEST FOR ADDITIONAL INFORMATION FOR A REQUEST TO RENEW THE OPERATING LICENSE ENTERGY OPERATIONS, INC WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NUMBER 50-382 TAC NUMBER MF7493 Entergy Louisiana, LLC and Entergy Operations, Inc. (Entergy or the applicant) submitted an assessment of severe accident mitigation alternatives (SAMAs) for Waterford Steam Electric Station (WF3), in Section 4.15 and Attachment D of the Applicants License Renewal Environmental Report (ER) (ADAMS Accession No. ML16088A324). Based on its review of the submittal, the NRC staff issued a Request for Additional Information (RAI) dated November 22, 2016 (ADAMS Accession No. ML16309A580). Entergy's responses to the RAIs was submitted by letter dated February 7, 2017 (ADAMS Accession No. ML17038A436).
General Regulatory Basis for all 3 RAIs Applicants for license renewal are required by 10 CFR 51.53(c)(3)(ii)(L) to consider SAMAs if not previously considered in an environmental impact assessment, related supplement, or environmental assessment for the plant. Guidance for the SAMA analysis submittal is provided in NEI 05-01 (Rev. A), Severe Accident Mitigation Alternatives (SAMA) Guidance Document which is endorsed in Regulatory Guide 4.2, supplement 1.
Regulatory Basis for RAI 1 NEI 05-01 provides the following guidance on the Level 2 model information to be provided in the SAMA submittal:
Provide a table or matrix describing the mapping of Level 1 accident sequences into Level 2 release categories and a description of the representative release sequences.
The ER did not provide a table or matrix describing the mapping of specific Level 1 accident sequences into the Level 2 release categories or a description of the representative release sequences. Entergy was therefore asked in RAI 2.e to provide a description of the sequences used to characterize the source terms for each of the significant release categories, the basis for this selection and its appropriateness for use in determining the benefit for the Phase II SAMAs evaluated. While the Entergy RAI response 2.e provided an expanded general discussion of the reviews made to select the representative sequence, no specific sequences were provided or a description of the representative release sequences provided.
RAI 1
Provide a description of the specific Level 1 and Level 2 accident sequences used to characterize the significant release categories (H-E, H-I and M-I) and why the particular Level 1 and Level 2 accident sequences were chosen to be representative for those release categories used in determining the benefit of the Phase II SAMAs.
Regulatory Basis for RAI 2 NEI 05-01 provides the following guidance for the identification of SAMAs:
SAMAs may be hardware changes, procedure changes, or enhancements to programs, including training and surveillance programs. Hardware changes should not be limited to permanent changes involving addition of new, safety-grade equipment, but should also include lower cost alternatives, such as temporary connections using commercial grade equipment (e.g., portable generators and temporary cross-ties).
NEI 05-01 further states:
If a SAMA was not evaluated for a dominant risk contributor, justify why SAMAs to further reduce the contributor would not be cost-beneficial.
The dominant contributor to internal flooding risk is water propagation in the electric board room and was evaluated in SAMA 68. In SAMA 68, Entergy proposed to install permanent flood doors to prevent water propagation to the electric board room. The WF3 plant specific cost estimate for the flood doors was determined to be approximately 1.3 million dollar. In comparison, the benefit for removing this internal flooding risk is approximately three hundred thousand dollars. Therefore, Entergy found SAMA 68 to not be cost-beneficial.
The staff requested in RAI 6.i for Entergy to consider a lower cost alternative than a permanent flood door, such as a flood barrier.
RAI 2
Consider a lower cost alternative to the flood doors, such as a flood barrier, for SAMA 68 or explain why a lower cost alternative was not considered or necessary. Provide a cost-benefit comparison or justify why SAMAs to further reduce the water propagation in the electric board room would not be cost-beneficial.
Regulatory Basis for RAI 3 NEI 05-01 provides the following regarding potentially cost beneficial SAMAs:
This analysis may not estimate all of the benefits or all of the costs of a SAMA. For instance, it may not consider increases or decreases in maintenance or operation costs following SAMA implementation. Also, it may not consider the possible adverse consequences of procedure changes, such as additional personnel dose. Since the SAMA analysis is not a complete engineering project cost-benefit analysis, the SAMAs that are cost-beneficial after the Phase II analysis and sensitivity analyses are only potentially cost-beneficial.
Thus, in the ER, Entergy stated:
Although the above SAMA candidates do not relate to adequately managing the effects of aging during the period of extended operation, they have been submitted for detailed engineering project cost-benefit analysis to further evaluate implementation of these potentially cost beneficial SAMAs.
In the response to several RAIs, Entergy revised the calculated benefits for several of the Phase II SAMAs, performed additional sensitivity analyses, and evaluated potentially lower cost alternatives. As a result of these analyses, 5 new potentially cost-beneficial SAMA candidates were identified.
RAI 3
Will the potential cost beneficial SAMAs added as a result of the RAIs dated 11/22/2016 and 03/28/2017 be submitted for detailed engineering project cost-benefit analysis to further evaluate implementation of these potentially cost beneficial SAMAs?