ML15051A348: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(9 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML15051A348
| number = ML15051A348
| issue date = 02/24/2015
| issue date = 02/24/2015
| title = Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application (TAC No. MF4222)
| title = Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application
| author name = Miller C G
| author name = Miller C
| author affiliation = NRC/NRR/DLR
| author affiliation = NRC/NRR/DLR
| addressee name = Kaminskas V
| addressee name = Kaminskas V
Line 14: Line 14:
| page count = 5
| page count = 5
| project = TAC:MF4222
| project = TAC:MF4222
| stage = Approval
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001   February 24, 2015 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166 SUBJECT: SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 24, 2015 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166
MF4222)
 
==SUBJECT:==
SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.
MF4222)


==Dear Mr. Kaminskas:==
==Dear Mr. Kaminskas:==


By letter dated April 24, 2014, DTE Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you of a change in the safety review schedule for the Fermi 2 license renewal review. Regarding the staff's safety review, the regional inspection activities associated to the Inspection Procedure 71002, "License Renewal Inspection", have been moved from March 9, 2015 to April 13, 2015, to avoid a conflict in staff's availability for conducting the inspection, as previously communicated (Agencywide Documents Access and Management System Accession No. ML15022A174). Also, on February 6, 2015, the Atomic Safety and Licensing Board admitted three contentions related to the Fermi 2 license renewal review proceedings. The new date for the issuance of the renewed license is "To Be Determined" (TBD) pending the results of the hearing proceedings. In addition, this letter provides notification of a change to the Environmental Project Manager assigned to Fermi 2 license renewal review. Effective February 9, 2015, Ms. Elaine Keegan became the Environmental Project Manager for Fermi 2.
By letter dated April 24, 2014, DTE Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you of a change in the safety review schedule for the Fermi 2 license renewal review.
All correspondence for the Project Manager associated with the environmental review for the Fermi 2 license renewal should be sent to:  
Regarding the staffs safety review, the regional inspection activities associated to the Inspection Procedure 71002, License Renewal Inspection, have been moved from March 9, 2015 to April 13, 2015, to avoid a conflict in staffs availability for conducting the inspection, as previously communicated (Agencywide Documents Access and Management System Accession No. ML15022A174).
Also, on February 6, 2015, the Atomic Safety and Licensing Board admitted three contentions related to the Fermi 2 license renewal review proceedings. The new date for the issuance of the renewed license is To Be Determined (TBD) pending the results of the hearing proceedings.
In addition, this letter provides notification of a change to the Environmental Project Manager assigned to Fermi 2 license renewal review. Effective February 9, 2015, Ms. Elaine Keegan became the Environmental Project Manager for Fermi 2.
All correspondence for the Project Manager associated with the environmental review for the Fermi 2 license renewal should be sent to:
Ms. Elaine Keegan, Senior Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC 20555


Ms. Elaine Keegan, Senior Project Manager Projects Branch 2 Division of License Renewal  Office of Nuclear Reactor Regulation  U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC  20555 V. Kaminskas - 2 -  Enclosed is the NRC staff's revised review schedule for the Fermi 2 license renewal application. If you have any questions related to the environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or to the revised safety schedule, please contact Daneira Meléndez-Colón at 301-415-3301 or by e-mail at Daneira.Melendez-Colon@nrc.gov. Sincerely,  
V. Kaminskas                                   Enclosed is the NRC staff's revised review schedule for the Fermi 2 license renewal application.
      /RA/ Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341  
If you have any questions related to the environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or to the revised safety schedule, please contact Daneira Meléndez-Colón at 301-415-3301 or by e-mail at Daneira.Melendez-Colon@nrc.gov.
Sincerely,
                                                                                  /RA/
Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341


==Enclosure:==
==Enclosure:==


Revised Schedule cc w/encl: Listserv V. Kaminskas - 2 -  Enclosed is the NRC staff's revised review schedule for the Fermi 2 license renewal application. If you have any questions related to the environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or to the revised safety schedule, please contact Daneira Meléndez-Colón at 301-415-3301 or by e-mail at Daneira.Melendez-Colon@nrc.gov. Sincerely,        /RA/  Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation 
Revised Schedule cc w/encl: Listserv
 
Docket No. 50-341 


==Enclosure:==
ML15051A348                                    *concurred via email OFFICE    LA:DLR:RPB1 PM:RPB2:DLR          PM:RPB1:D      BC:RPB2:DLR      BC:RPB1:DLR    D:DLR LR NAME      YEdmonds        EKeegan          DMeléndez-      BWittick          YDiaz-Sanabria  CMiller Colón DATE      2/24/15        2/24/15          2/24/15        2/24/15          2/24/15        2/25/15


Revised Schedule cc w/encl:  Listserv 
Letter to V. Kaminskas from C. Miller dated February 24, 2015


DISTRIBUTION:  See next page ADAMS Accession No.:  ML15051A348    *concurred via email OFFICE LA:DLR:RPB1 PM:RPB2:DLR PM:RPB1:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR NAME YEdmonds EKeegan DMeléndez-Colón BWittick YDiaz-Sanabria CMiller DATE 2/24/15 2/24/15 2/24/15 2/24/15 2/24/15 2/25/15 OFFICIAL RECORD COPY Letter to V. Kaminskas from C. Miller dated February 24, 2015  SUBJECT: SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.
==SUBJECT:==
SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.
MF4222)
MF4222)
DISTRIBUTION:
DISTRIBUTION:
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv  
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv
---------------------
---------------------
D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick D. McIntyre, OPA B. Harris, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII S. Sheldon, RIII C. Lipa, RIII FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestones Schedule Date Actual Date Receive license renewal application (LRA) 04/30/14 04/30/14 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 06/18/14 Publish FRN - environmental scoping meeting 06/2014 06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 07/24/14    07/24/14 Audit - Scoping and Screening Methodology 08/04/14 08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14 08/18/14 Environmental scoping periods ends 08/2014 08/29/14 Audit - Environmental 09/08/14 09/08/14 Audit - Aging Management Programs (Week 1) 09/15/14 09/15/14 Audit - Aging Management Programs (Week 2) 09/29/14 09/29/14 Regional Inspection - IP 71002, "License Renewal Procedure04/2015 Issue draft supplemental environmental impact statement (SEIS) 06/2015 U.S. Environmental Protection Agency FRN Published - draft SEIS available for comments 06/2015  Public Meeting - draft SEIS meeting 07/2015 End of draft SEIS comment period 08/2015 Issue safety evaluation report (SER) with open item(s) 09/2015 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting   11/2015 Issue final SEIS 02/2016 U.S. Environmental Protection Agency FRN Published - final SEIS available 02/2016 Issue final SER 02/2016 ACRS Full Committee meeting 04/2016 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision, if hearing granted TBD ENCLOSURE
D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick D. McIntyre, OPA B. Harris, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII S. Sheldon, RIII C. Lipa, RIII
}}
 
FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Schedule    Actual Milestones Date       Date Receive license renewal application (LRA)                           04/30/14   04/30/14 Publish Federal Register Notice (FRN) - LRA availability             05/2014   05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing       06/2014   06/18/14 Publish FRN - environmental scoping meeting                         06/2014   06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting                                                     07/24/14    07/24/14 Audit - Scoping and Screening Methodology                           08/04/14   08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14   08/18/14 Environmental scoping periods ends                                   08/2014   08/29/14 Audit - Environmental                                               09/08/14   09/08/14 Audit - Aging Management Programs (Week 1)                         09/15/14   09/15/14 Audit - Aging Management Programs (Week 2)                         09/29/14   09/29/14 Regional Inspection - IP 71002, License Renewal Procedure         04/2015 Issue draft supplemental environmental impact statement (SEIS)       06/2015 U.S. Environmental Protection Agency FRN Published - draft SEIS     06/2015 available for comments Public Meeting - draft SEIS meeting                                 07/2015 End of draft SEIS comment period                                     08/2015 Issue safety evaluation report (SER) with open item(s)               09/2015 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting                                                             11/2015 Issue final SEIS                                                     02/2016 U.S. Environmental Protection Agency FRN Published - final SEIS     02/2016 available Issue final SER                                                     02/2016 ACRS Full Committee meeting                                         04/2016 Decision - Director, Office of Nuclear Reactor Regulation             TBD Commission decision, if hearing granted                               TBD ENCLOSURE}}

Latest revision as of 15:19, 31 October 2019

Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application
ML15051A348
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 02/24/2015
From: Chris Miller
Division of License Renewal
To: Kaminskas V
DTE Electric Company
Melendez-Colon D, 415-3301
References
TAC MF4222
Download: ML15051A348 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 24, 2015 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.

MF4222)

Dear Mr. Kaminskas:

By letter dated April 24, 2014, DTE Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you of a change in the safety review schedule for the Fermi 2 license renewal review.

Regarding the staffs safety review, the regional inspection activities associated to the Inspection Procedure 71002, License Renewal Inspection, have been moved from March 9, 2015 to April 13, 2015, to avoid a conflict in staffs availability for conducting the inspection, as previously communicated (Agencywide Documents Access and Management System Accession No. ML15022A174).

Also, on February 6, 2015, the Atomic Safety and Licensing Board admitted three contentions related to the Fermi 2 license renewal review proceedings. The new date for the issuance of the renewed license is To Be Determined (TBD) pending the results of the hearing proceedings.

In addition, this letter provides notification of a change to the Environmental Project Manager assigned to Fermi 2 license renewal review. Effective February 9, 2015, Ms. Elaine Keegan became the Environmental Project Manager for Fermi 2.

All correspondence for the Project Manager associated with the environmental review for the Fermi 2 license renewal should be sent to:

Ms. Elaine Keegan, Senior Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC 20555

V. Kaminskas Enclosed is the NRC staff's revised review schedule for the Fermi 2 license renewal application.

If you have any questions related to the environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or to the revised safety schedule, please contact Daneira Meléndez-Colón at 301-415-3301 or by e-mail at Daneira.Melendez-Colon@nrc.gov.

Sincerely,

/RA/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341

Enclosure:

Revised Schedule cc w/encl: Listserv

ML15051A348 *concurred via email OFFICE LA:DLR:RPB1 PM:RPB2:DLR PM:RPB1:D BC:RPB2:DLR BC:RPB1:DLR D:DLR LR NAME YEdmonds EKeegan DMeléndez- BWittick YDiaz-Sanabria CMiller Colón DATE 2/24/15 2/24/15 2/24/15 2/24/15 2/24/15 2/25/15

Letter to V. Kaminskas from C. Miller dated February 24, 2015

SUBJECT:

SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO.

MF4222)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv


D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick D. McIntyre, OPA B. Harris, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII S. Sheldon, RIII C. Lipa, RIII

FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Schedule Actual Milestones Date Date Receive license renewal application (LRA) 04/30/14 04/30/14 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 06/18/14 Publish FRN - environmental scoping meeting 06/2014 06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 07/24/14 07/24/14 Audit - Scoping and Screening Methodology 08/04/14 08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14 08/18/14 Environmental scoping periods ends 08/2014 08/29/14 Audit - Environmental 09/08/14 09/08/14 Audit - Aging Management Programs (Week 1) 09/15/14 09/15/14 Audit - Aging Management Programs (Week 2) 09/29/14 09/29/14 Regional Inspection - IP 71002, License Renewal Procedure 04/2015 Issue draft supplemental environmental impact statement (SEIS) 06/2015 U.S. Environmental Protection Agency FRN Published - draft SEIS 06/2015 available for comments Public Meeting - draft SEIS meeting 07/2015 End of draft SEIS comment period 08/2015 Issue safety evaluation report (SER) with open item(s) 09/2015 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 11/2015 Issue final SEIS 02/2016 U.S. Environmental Protection Agency FRN Published - final SEIS 02/2016 available Issue final SER 02/2016 ACRS Full Committee meeting 04/2016 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision, if hearing granted TBD ENCLOSURE