Letter Sequence RAI |
---|
|
Results
Other: ML14195A221, ML14237A194, ML15030A229, ML15076A468, ML15092A224, ML15092A243, ML15098A175, ML15341A261, ML16005A399, ML16011A009, ML16011A011, ML16011A012, ML16011A013, ML16011A014, ML16011A032, ML16011A036, ML16187A173, ML16270A567, ML16330A117, NRC-16-0014, Comments on the Nrc'S Safety Evaluation Report with Open Items Related to the License Renewal, NRC-16-0061, DTE Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools.
|
MONTHYEARML14195A2212014-07-24024 July 2014 Plan for Scoping and Screening Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14237A1942014-09-0505 September 2014 Plan for the Aging Management Program Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other NRC-14-0070, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12014-10-24024 October 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 1 Project stage: Response to RAI ML14288A6802014-10-29029 October 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 3 Project stage: RAI NRC-14-0072, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22014-11-18018 November 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 2 Project stage: Response to RAI ML14322A1782014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 5 Project stage: RAI NRC-14-0076, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 32014-12-0101 December 2014 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 3 Project stage: Response to RAI NRC-14-0083, Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 62014-12-30030 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 6 Project stage: Response to RAI NRC-15-0001, Response to NRC Request for Additional Information for the Review License Renewal Application - Set 72015-01-0505 January 2015 Response to NRC Request for Additional Information for the Review License Renewal Application - Set 7 Project stage: Response to RAI NRC-15-0013, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives2015-01-0909 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives Project stage: Response to RAI NRC-15-0009, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 152015-01-15015 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 15 Project stage: Response to RAI NRC-15-0006, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 112015-01-20020 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Project stage: Response to RAI NRC-15-0012, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 182015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 18 Project stage: Response to RAI NRC-15-0022, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-12015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-1 Project stage: Response to RAI NRC-15-0010, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 162015-02-0505 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 16 Project stage: Response to RAI ML15030A2292015-02-11011 February 2015 AMP Audit Summary Report Enclosure Project stage: Other NRC-15-0011, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 172015-02-12012 February 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 17 Project stage: Response to RAI NRC-15-0029, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-12015-02-19019 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-1 Project stage: Response to RAI ML15051A3482015-02-24024 February 2015 Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application Project stage: Approval NRC-15-0020, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Sets 19, 20, and 212015-03-0505 March 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Sets 19, 20, and 21 Project stage: Response to RAI NRC-15-0023, Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 22015-03-0505 March 2015 Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 2 Project stage: Response to RAI ML15051A5092015-03-11011 March 2015 Summary of Telecon Drai Set 24 - February 9, 2015 Project stage: RAI ML15051A3172015-03-11011 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 24 Project stage: RAI ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 Project stage: RAI ML15062A3362015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 26 Project stage: RAI ML15054A1712015-03-13013 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15072A2132015-03-19019 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15072A0812015-03-19019 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 25 Project stage: RAI ML15070A1612015-03-19019 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15051A5072015-03-19019 March 2015 Summary of Telecom Drai Sets 4, 5 and 6 - November 14 2014 Project stage: RAI ML15077A1082015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 27 Project stage: RAI ML15082A0462015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 29, Project stage: RAI ML15078A3372015-03-26026 March 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 28 Project stage: RAI ML15085A5132015-04-0202 April 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 31 Project stage: RAI ML15099A0162015-04-22022 April 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application Set 32 Project stage: RAI ML15092A2432015-04-22022 April 2015 Summary of Telephone Conference Call Held on November 19, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Concerning Set 7 - November 19, 2014 Project stage: Other ML15076A4682015-04-22022 April 2015 Summary of Telephone Conference Call Held on February 13, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company Project stage: Other ML15099A6632015-04-23023 April 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15082A1882015-04-27027 April 2015 Summary of Conference Call Held on March 16, 2015, Between the U.S. NRC and DTE Electric Company, Concerning Requests for Additional Information, Set 27 Pertaining to the Fermi 2 License Renewal Application Project stage: RAI ML15072A2032015-04-27027 April 2015 Summary of Teleconference March 6, 2015 Between the U.S. NRC and DTE Electric Company, Concerning RAI Pertaining to the Fermi 2 License Renewal Application Project stage: RAI ML15104A5142015-05-0101 May 2015 Summary of Telephone Conference Call Held on November 25, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA Project stage: RAI NRC-15-0045, Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 32015-05-0808 May 2015 Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 3 Project stage: Response to RAI ML15117A5642015-05-13013 May 2015 Summary of Telephone Conference Call Held on April 10, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA Project stage: RAI ML15113A1982015-05-13013 May 2015 Summary of Telephone Conference Call Held on December 8, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA Project stage: RAI ML15104A3882015-05-13013 May 2015 Summary of Telephone Conference Call Held on March 25, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA Project stage: RAI ML15098A3022015-05-13013 May 2015 Summary of Telephone Conference Call Held on April 7,2015, Between the U.S.Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA Project stage: RAI ML15098A1752015-05-13013 May 2015 Summary of Telephone Conference Call Held on March 17,2015, Between the Us Nuclear Regulatory Commission Project stage: Other ML15126A0042015-05-15015 May 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 34 Project stage: RAI ML15104A6322015-05-15015 May 2015 Summary of Telephone Conference Call Held on November 17, 2014 Between NRC and DTE Electric Co Re Requests for Additional Information on Fermi 2 License Renewal Application Project stage: RAI ML15132A4272015-05-18018 May 2015 March 27, 2015 Summary of Telephone Conference Call Held Between the U.S. NRC and DTE Electric Company Concerning Requests for Additional Information Pertaining to the Severe Accident Mitigation Alternatives Review of the Fermi, Unit 2 Project stage: RAI 2015-02-19
[Table View] |
Similar Documents at Fermi |
---|
Category:Meeting Summary
MONTHYEARML23187A4562023-07-0606 July 2023 June 21, 2023, Summary of the Public Outreach to Discuss the NRC 2022 End of Cycle Plant Performance Assessment of Fermi Nuclear Power Plant Unit 2 ML22307A1252022-11-0909 November 2022 Summary of October 19, 2022, Teleconference Meeting with DTE Electric Company Regarding Proposed License Amendment Pertaining to the Emergency Core Cooling System Strainer Performance Evaluation for Fermi 2 ML22144A1052022-05-24024 May 2022 Summary of Public Outreach to Discuss the NRC 2021 End of Cycle Plant Performance Assessment of Fermi ML21187A1662021-07-0606 July 2021 Summary of the June 24, 2021, Public Webinar to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of the Fermi Power Plant, Unit 2 ML20244A3432020-08-31031 August 2020 Summary of the August 27, 2020 Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of Fermi 2 Nuclear Power Plant ML19127A0532019-05-0606 May 2019 Summary of the April 30, 2019 Public Outreach to Discuss the NRC 2018 End-Of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML18344A0652018-12-17017 December 2018 Summary of Meeting with DTE Electric Company Regarding Upcoming License Amendment Request to Transition from an 18 Month Fuel Cycle to a 24 Month Fuel Cycle. ML18194A5402018-07-16016 July 2018 Summary of Public Meeting with DTE Electric Company Regarding Upcoming License Amendment Request to Revise a License Condition Related to Boraflex Storage Racks ML18151A9502018-05-31031 May 2018 Summary of Public Outreach to Discuss the NRC 2017 End-Of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML17237B9672017-08-25025 August 2017 Summary of the July 10, 2017, Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Fermi, Unit 2 ML17067A2712017-03-13013 March 2017 February 9, 2017 Summary of Public Meeting with Dte Electric Company to Discuss the Potential Upcoming Exigent License Amendment Request Regarding TS 3.3.5.1 Emergency Core Cooling System ML16187A1792016-06-30030 June 2016 Enclosure 2 - Summary of Telecon Held on June 9, 2016, Revision 1 ML16187A1732016-06-30030 June 2016 Enclosure 1 - List of Attendees for Telecon Held on June 9, 2016 ML16166A2012016-06-13013 June 2016 Summary of the June 2, 2016, Open House Public Meeting to Discuss NRC Activities, Nuclear Power Issues, and 2015 End-Of-Cycle Performance Assessment of Fermi, Unit 2 ML16131A0662016-05-10010 May 2016 Summary of Telephone Conference Calls Held on February 10 and 25, 2016, Between U.S. Nuclear Regulatory Commission and DTE Electric Company Concerning Response to RAI 4.3.3-3a Pertaining to Fermi License Renewal Application ML15341A2612015-12-11011 December 2015 Summary of Telephone Conference Calls Held on August 4 And18, 2015, Between the U.S. NRC and DTE Electric Company Concerning the Boraflex Monitoring Program Pertaining to Fermi 2 LRA ML15175A0622015-07-0606 July 2015 Summary of Telephone Conference Call Held on May 18, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15175A0392015-07-0606 July 2015 Summary of Telephone Conference Calls Held on April 29 and May 4, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Co. Concerning RAIs Pertaining to Fermi 2 LRA ML15175A0202015-07-0606 July 2015 Summary of Telephone Conference Call Held on January 14, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA (TAC No ML15182A3292015-07-0101 July 2015 June 18, 2015, Summary of Public Open House Meeting to Discuss the NRC 2014 End-Of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML15139A5192015-06-11011 June 2015 Summary of Telephone Conference Call Held on May 13, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Rais Pertaining to the Fermi 2 LRA ML15133A1382015-06-11011 June 2015 Summary of Telephone Conference Calls Held on December 16, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15132A3362015-06-11011 June 2015 Summary of Telephone Conference Call Held on May 5, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAI Pertaining to the Fermi 2 LRA ML15134A1222015-06-0909 June 2015 Summary of Telephone Conference Call Held on December 17, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15119A0582015-05-26026 May 2015 Summary of Telephone Conference Calls Held on December 5, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA (Tac No. Mf 4222) ML15092A2242015-05-26026 May 2015 Summary of Telephone Conference Call Held on March 4, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company ML15104A3032015-05-20020 May 2015 Summary of Telephone Conference Calls Held on April 8, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LAR ML15132A4272015-05-18018 May 2015 March 27, 2015 Summary of Telephone Conference Call Held Between the U.S. NRC and DTE Electric Company Concerning Requests for Additional Information Pertaining to the Severe Accident Mitigation Alternatives Review of the Fermi, Unit 2 ML15104A6322015-05-15015 May 2015 Summary of Telephone Conference Call Held on November 17, 2014 Between NRC and DTE Electric Co Re Requests for Additional Information on Fermi 2 License Renewal Application ML15104A3882015-05-13013 May 2015 Summary of Telephone Conference Call Held on March 25, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15113A1982015-05-13013 May 2015 Summary of Telephone Conference Call Held on December 8, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15098A3022015-05-13013 May 2015 Summary of Telephone Conference Call Held on April 7,2015, Between the U.S.Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15098A1752015-05-13013 May 2015 Summary of Telephone Conference Call Held on March 17,2015, Between the Us Nuclear Regulatory Commission ML15117A5642015-05-13013 May 2015 Summary of Telephone Conference Call Held on April 10, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15104A5142015-05-0101 May 2015 Summary of Telephone Conference Call Held on November 25, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning RAIs Pertaining to the Fermi 2 LRA ML15082A1882015-04-27027 April 2015 Summary of Conference Call Held on March 16, 2015, Between the U.S. NRC and DTE Electric Company, Concerning Requests for Additional Information, Set 27 Pertaining to the Fermi 2 License Renewal Application ML15072A2032015-04-27027 April 2015 Summary of Teleconference March 6, 2015 Between the U.S. NRC and DTE Electric Company, Concerning RAI Pertaining to the Fermi 2 License Renewal Application ML15076A4682015-04-22022 April 2015 Summary of Telephone Conference Call Held on February 13, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company ML15054A1342015-03-19019 March 2015 Summary of Telephone Conference Call Held on January 22, 2015, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Requests for Additional Information Pertaining to the Fermi 2 License Renewal Application ML15051A5072015-03-19019 March 2015 Summary of Telecom Drai Sets 4, 5 and 6 - November 14 2014 ML15069A6152015-03-18018 March 2015 February 25, 2015, Summary of Pre-Application Teleconference with DTE Electric Company for a Proposed Relief Request Regarding the Core Spray System Pumps (Tac No. MF5700) ML15051A5092015-03-11011 March 2015 Summary of Telecon Drai Set 24 - February 9, 2015 ML15027A3552015-02-11011 February 2015 Summary of Telephone Conference Call Between NRC and DTE Electric Company Concerning RAIs Pertaining to the Fermi, Unit 2 LRA SAMA Review ML15005A5382015-01-12012 January 2015 121814, Summary of Telephone Conference Call Between NRC and DTE Electric Company Concerning Responses to RAIs Pertaining to the Fermi 2 LRA Environmental Review ML14330A2632014-12-15015 December 2014 Summary of Telephone Conference Call Held on November 17, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Requests for Additional Information Pertaining to the Fermi 2 License Renewal Application En ML14308A5982014-11-20020 November 2014 10/20/2014, Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Requests for Additional Information Pertaining to Fermi, Unit 2 License Renewal Application ML14308A5302014-11-20020 November 2014 Summary of Phone Call Between the NRC and DTE Electric Co, Concerning RAIs Pertaining to the Fermi 2 LRA Environmental Review ML14233A4502014-09-18018 September 2014 Public Meeting to Discuss the License Renewal Process and Environmental Scoping Process for Fermi, Unit 2 ML14254A4652014-07-24024 July 2014 Scoping Meeting Afternoon Trancript ML13133A3672013-06-0606 June 2013 4/16/2013 - Summary of Meeting with the U.S. EPR Design Center Working Group 2023-07-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 15, 2015 LICENSEE: DTE Electric Company FACILITY: Fermi 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON NOVEMBER 17, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on November 17, 2014, to discuss and clarify the staffs draft requests for additional information (DRAIs) B.1.42-2, B.1.42-4, B.1.2-3, and B.1.22-1 concerning the Fermi 2 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs. provides a listing of the participants and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc w/encls: Listserv
ML15104A632 *Concurred via e-mail OFFICE LA:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds D Meléndez- Y Diaz-Sanabria D Meléndez-Colón Colón DATE 4/15/15 5/13/15 5/14/15 5/15/15
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON NOVEMBER 17, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource
D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick B. Harris, OGC D. Roth, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII
TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS NOVEMBER 17, 2014 PARTICIPANTS AFFILIATIONS Daneira Meléndez-Colón U. S. Nuclear Regulatory Commission (NRC)
Samuel Cuadrado de Jesús NRC Angela Buford NRC Alice Erickson NRC George Thomas NRC Juan López NRC Lynne Goodman DTE Electric Company (DTE)
George Abdallah DTE Timothy Hoffman DTE Andrew Kulikowski DTE Reza Ahrabli Entergy ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION NOVEMBER 17, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on November 17, 2014, to discuss and clarify the following draft requests for additional information (DRAIs) concerning the Fermi 2 license renewal application (LRA).
DRAI B.1.42-2
Background:
Section 54.21(a)(3) of Title 10 of the Code of Federal Regulations (10 CFR) requires the applicant to demonstrate that the effects of aging for structures and components will be adequately managed so that the intended function will be maintained consistent with the current licensing basis (CLB) for the period of extended operation. As described in the Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR),
an applicant may demonstrate compliance with 10 CFR 54.21(a)(3) by referencing the Generic Aging Lessons Learned (GALL) Report and when evaluation of the matter in the GALL Report applies to the plant.
GALL Report Aging Management Program (AMP) XI.S6 addresses the detection of aging effects for inaccessible, below-grade concrete structural elements, which depends on the plants specific ground water/soil condition. For plants with non-aggressive ground water/soil, the program recommends: (a) evaluating the acceptability of inaccessible areas when conditions exist in accessible areas that could indicate the presence of, or result in, degradation to such inaccessible areas and (b) examining representative samples of the exposed portions of the below grade concrete, when excavated for any reason. For plants with aggressive ground water/soil (pH less than 5.5, chlorides greater than 500 ppm, or sulfates greater than 1500 ppm) and/or where the concrete structural elements have experienced degradation, the GALL Report recommends a plant specific AMP to manage the concrete aging effects during the period of extended operation.
During the audit, the staff noted that the LRA AMP basis document indicates that the Fermi 2 concrete structures are subject to an aggressive ground water/soil environment. The staff also noted that in Updated Final Safety Analysis Report (UFSAR) Table 2.5-16, Chemical Analysis of Ground Water, the ground water tested in Fermi 2 had sulfate content above the 1500 ppm limit stated in the GALL Report for aggressive groundwater. The LRA AMP provided an enhancement to the detection of aging effects program element to revise the plant procedure to include the performance of opportunistic inspections if normally inaccessible areas become accessible due to plant activities, and to provide additional inspections of inaccessible areas in environments where observed conditions in accessible areas exposed to the same environment indicate significant degradation.
ENCLOSURE 2
Issue:
LRA Section B.1.42, "Structures Monitoring," states that the program is an existing program that, following enhancement, will be consistent with GALL Report AMP XI.S6. However, the proposed enhancement to the Structures Monitoring does not appear to be consistent with the GALL Report recommendations for either an aggressive or non-aggressive water/soil environment. Additionally, the enhancement for inspections of inaccessible areas based on observations of accessible areas with the same environment appears to limit the scope of inaccessible areas that will be inspected. This is due to the potential that certain environment conditions may not exist for both accessible and inaccessible areas (i.e. a soil type environment may exist for an inaccessible area and not for an accessible area). Additional information is requested to verify consistency with the GALL Report for the detection of aging effects in inaccessible, below-grade concrete structural elements exposed to an aggressive ground water/soil environment.
Request:
- 1. Clarify how the enhancement for the detection of aging effects program element is consistent with that described in the GALL Report AMP XI.S6 for inaccessible areas exposed to aggressive ground water/soil.
- 2. If criteria other than that described in the GALL Report are being used, provide the basis to justify the adequacy of the proposed exception to manage the aging effects in inaccessible areas.
Discussion:
The staff provided clarification related to draft RAI B.1.42-2 and stated it will revise the RAI as follows:
First sentence of the second paragraph in the Background section:
GALL Report AMPs XI.S6 and XI.S7 address the detection of aging effects for inaccessible, below-grade concrete structural elements, which depends on the plants specific ground water/soil condition.
Third paragraph of the Background section:
During the audit, the staff noted that the LRA AMP basis document indicates that the Fermi 2 concrete structures are subjected to an aggressive ground water/soil environment. The staff also noted that in UFSAR Table 2.5-16, Chemical Analysis of Ground Water, the ground water tested in Fermi 2 had sulfate content above the 1500 ppm limit stated in the GALL Report for aggressive groundwater.
Issue section:
LRA Section B.1.42, "Structures Monitoring", states that the program is an existing program that, following enhancement, will be consistent with GALL Report AMPs XI.S6 and XI.S7. However, the proposed enhancement to the Structures Monitoring does not appear to be consistent with the GALL Report recommendations for an aggressive water/soil environment. Additional information is requested to verify consistency with the GALL Report for the detection of aging effects in inaccessible, below-grade concrete structural elements exposed to an aggressive ground water/soil environment.
Request 1:
Clarify how the enhancement for the detection of aging effects program element is consistent with that described in the GALL Report AMPs XI.S6 and XI.S7 for inaccessible areas exposed to aggressive ground water/soil.
The applicant understands the staffs concerns and will provide a response to the RAI.
The RAI will be issued as revised.
DRAI B.1.42-4
Background:
Section 54.21(a)(3) of 10 CFR requires the applicant to demonstrate that the effects of aging for structures and components will be adequately managed so that the intended function(s) will be maintained consistent with the CLB for the period of extended operation. As described in SRP-LR, an applicant may demonstrate compliance with 10 CFR 54.21(a)(3) by referencing the GALL Report and when evaluation of the matter in the GALL Report applies to the plant.
LRA Section B.1.39, RG 1.127, Inspection of Water-Control Structures Associated with Nuclear Power Plants, which is implemented by the applicant as part of LRA Section B.1.42, Structures Monitoring, states that the programs are existing programs that, following enhancement, will be consistent with GALL Report AMPs XI.S6 and XI.S7. The parameters monitored or inspected, detection of aging effects, and acceptance criteria program elements of GALL Report AMPs XI.S6 and XI.S7, explicitly address the aging management of high-strength (measured yield strength greater than or equal to 150 kilo-pounds per square inch (ksi)) structural bolts greater than 1 inch in diameter. The GALL Report recommends that visual inspections of high-strength structural bolts be supplemented with volumetric or surface examinations to detect cracking.
Based on a review of information in the LRA and provided during the AMP audit, the staff noted that sufficient information was not provided to determine whether high-strength structural bolts (other than ASTM A325, F1852, and A490 used in civil structures) are used in the structures and how stress corrosion cracking (SCC) will be managed by the AMP(s). The staff also noted that the LRA AMP basis document for the Structures Monitoring Program states that plant
procedures prevent the use of molybdenum disulfide as a lubricant for bolting, and uses this explanation as the basis for justifying that [high-strength] structural bolting is not susceptible to SCC. However, the staff notes that the use of molybdenum disulfide is not the only contributor to SCC of high-strength bolts.
Issue:
It is not clear if there are high-strength structural bolts used in Fermi 2 structures (other than ASTM A325, F1852, and A490 used in civil structures) and, if used, whether the preventive actions, parameters monitored or inspected, and detection of aging effects, program elements of LRA Sections B.1.42 and B.1.39, are consistent with the recommendations in GALL Report AMPs XI.S6 and XI.S7 regarding the provision to monitor for SCC in high-strength structural bolts greater than 1 inch in diameter through supplemental volumetric or surface examinations to detect cracking. The staff notes that the use of molybdenum disulfide is not the only contributor to SCC of high-strength bolts and preventing its use does not assure that high-strength structural bolts will not be susceptible to SSC.
Request:
- 1. State whether high-strength (measured yield strength greater than or equal to 150 ksi) structural bolts greater than 1 inch in diameter are used in Fermi 2 structures (including those within the scope of the Structures Monitoring Program and RG 1.127, Inspection of Water-Control Structures Associated with Nuclear Power Plants Program).
- 2. If high-strength structural bolts greater than 1 inch in diameter are used (other than ASTM A325, F1852, and A490 used in civil structures), state how the preventive actions, parameters monitored or inspected, and detection of aging effects program elements are consistent with the GALL Report recommendations to monitor for SCC through supplemental volumetric or surface examinations.
- 3. Clarify whether molybdenum disulfide was used as a lubricant for high-strength structural bolts greater than 1 inch in diameter prior to prohibiting its use, and if so, state what actions will be taken to ensure that these high-strength structural bolts will be adequately managed during the period of extended operation.
Discussion:
The staff provided clarification related to draft RAI B.1.42-4 and stated it will revise the RAI to remove the discussion on the use of molybdenum disulfide and incorporate this discussion in draft RAI B.1.2-3.
The applicant understands the staffs concerns and will provide a response to the RAI.
The RAI will be issued as revised.
DRAI B.1.22-1
Background:
The LRA states that the Inservice Inspection - IWF Program, with enhancements, is consistent with GALL Report AMP XI.S3, ASME Section XI, Subsection IWF. The detection of aging effects program element in GALL Report AMP XI.S3 recommends that, for high-strength structural bolting (actual measured yield strength greater than or equal to 150 ksi) in sizes greater than 1 inch nominal diameter, volumetric examinations should be performed in addition to VT-3 to detect cracking. GALL Report AMP XI.S3 recommendations for aging management of high-strength structural bolting include the following:
- The scope of program program element states that the scope of the program includes high-strength structural bolting.
- The preventive actions program element recommends using bolting material that has an actual measured yield strength less than 150 ksi.
- The preventive actions program element states that molybdenum disulfide (MoS2) should not be used as a lubricant due to its potential contribution to SCC, especially for high-strength bolts.
- The parameters monitored or inspected program element recommends that high-strength structural bolting susceptible to SCC be monitored for cracking.
- The detection of aging effects program element states that the volumetric examination may be waived with adequate plant-specific justification.
Issue:
License renewal application Section B.1.22, Inservice Inspection-IWF, includes enhancements to revise plant procedures to emphasize the use of lubricants and sealants for high-strength bolting, and to identify unacceptable conditions such as cracked or sheared bolts, including high-strength bolts. However, it is not clear whether there are high-strength structural bolts (actual measured yield strength greater than or equal to 150 ksi) in sizes greater than 1 inch nominal diameter within the scope of the Inservice Inspection-IWF Program. In addition, it is not clear how the applicant plans to manage aging for these components consistent with GALL Report AMP XI.S3 recommendations in the preventive actions, parameters monitored or inspected, and detection of aging effects program elements described above.
The LRA also states that [p]lant procedures prohibit the use of lubricants containing molybdenum disulfide. Since the use of this type of lubricant is prohibited in plant procedures and plant procedures provide the technical guidance for installation requirements [], the potential for [SCC] for high-strength structural bolting material, i.e., ASTM A325 and A490, is not plausible. Given that the use of molybdenum disulfide is not the only contributor to SCC of high strength bolts; the staff has not determined that there is sufficient basis to waive volumetric examination of high-strength structural bolting (actual measured yield strength of 150 ksi) in sizes greater than 1 inch diameter.
Request:
- 1. State whether or not there are high strength structural bolts (actual measured yield strength greater than or equal to 150 ksi) in sizes greater than 1 inch diameter within the scope of the Inservice Inspection-IWF Program.
- 2. If high-strength structural bolts (actual measured yield strength greater than or equal to 150 ksi) in sizes greater than 1 inch diameter are within the scope of the Inspection-IWF Program, state how the recommendations for managing degradation of high-strength bolts described in the preventive actions, parameters monitored or inspected, and detection of aging effects program elements will be implemented for the Inservice Inspection-IWF Program.
- 3. If the above recommendations will not be implemented (i.e., an exception is being taken to the GALL recommendations), provide the associated technical justification. If applicable, provide additional information regarding plant-specific justification to waive volumetric examinations to address the potential of SCC for high-strength structural bolts consistent with the GALL Report AMP.
Discussion:
The staff provided clarification related to draft RAI B.1.22-1 and stated it will revise the RAI to remove the discussion on the use of molybdenum disulfide and incorporate this discussion in draft RAI B.1.2-3.
The applicant understands the staffs concerns and will provide a response to the RAI.
The RAI will be issued as revised.
DRAI B.1.2-3
Background:
GALL Report AMPs XI.M18 and XI.S3 state that molybdenum disulfide (MoS2) should not be used as a lubricant due to its potential contribution to SCC, especially for high-strength bolts.
The GALL Report also states that the applicant is to evaluate applicable operating experience to support the conclusion that the effects of aging are adequately managed.
LRA Sections B.1.2 and B.1.22 state that the Bolting Integrity and Inservice Inspection-IWF programs are existing AMPs, with enhancements and an exception, that will be consistent with GALL Report AMPs XI.M18 and XI.S3.
Issue:
LRA Sections B.1.2 and B.1.22 state that [p]lant procedures prohibit the use of lubricants containing molybdenum disulfide. During its onsite audit, the staff confirmed that the bolting procedures had been revised to prohibit the use of MoS2; however, it is not clear whether MoS2 lubricants have been used at Fermi 2 before plant procedures were revised to prohibit their use.
Request:
State whether MoS2 lubricants have been used on high-strength bolts of any kind within the scope of the Bolting Integrity and Inservice Inspection-IWF programs. If these lubricants have been used, explain how the affected closure bolts will be managed for age-related degradation.
Discussion:
The staff provided clarification related to draft RAI B.1.2-3 and stated it will revise the RAI to include its concerns regarding the use of molybdenum disulfide as described in DRAIs B.1.42-4 and B.1.22-1.
The applicant understands the staffs concerns and will provide a response to the RAI.
The RAI will be issued as revised.