MONTHYEARNRC-14-0033, Annual Non-Radiological Environmental Operating Report for 20132014-04-28028 April 2014 Annual Non-Radiological Environmental Operating Report for 2013 Project stage: Request ML14224A3532014-09-0303 September 2014 License Renewal Environmental Site Audit Regarding Fermi, Units 2 Project stage: Other ML14294A7922014-10-28028 October 2014 Project Manager Change for the License Renewal of Fermi, Unit 2, Project stage: Other ML14294A8122014-11-17017 November 2014 Summary of the Severe Accidents Mitigation Alternatives Environmental Site Audit Related to the Review of the License Renewal Application for Fermi 2 Project stage: Approval ML14308A5302014-11-20020 November 2014 Summary of Phone Call Between the NRC and DTE Electric Co, Concerning RAIs Pertaining to the Fermi 2 LRA Environmental Review Project stage: RAI ML14308A5982014-11-20020 November 2014 10/20/2014, Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Requests for Additional Information Pertaining to Fermi, Unit 2 License Renewal Application Project stage: RAI ML14330A2632014-12-15015 December 2014 Summary of Telephone Conference Call Held on November 17, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Requests for Additional Information Pertaining to the Fermi 2 License Renewal Application En Project stage: RAI ML16190A0842016-06-0808 June 2016 Public Meeting, June 8, 2016 (Pmc Comments1) Project stage: Meeting ML16190A0692016-06-0808 June 2016 Scoping Meeting Transcripts, June 8, 2016 Project stage: Meeting ML16166A0442016-06-22022 June 2016 Schedule Revision for the Environmental Review of the Fermi 2 License Renewal Application Project stage: Approval ML16256A1682016-09-21021 September 2016 Letter to EPA - Notice of Availability of the Final Plant-Specific Supplement 56 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Fermi 2 Nuclear Power Plant Project stage: Other 2014-04-28
[Table View] |
Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 – Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) 2024-09-09
[Table view] Category:Schedule and Calendars
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 22, 2016 Mr. Keith Polson Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4064)
Dear Mr. Polson:
By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).
Enclosed is the staffs revised environmental review schedule for the Fermi 2 license renewal application (LRA). The staff believes the NRC Commissions recent decision concerning severe accident mitigation alternatives (SAMA) analysis1 may be applicable to the SAMA analysis performed for Fermi 2 because Fermi 2s analysis may have relied upon the NUREG-1150 values for two inputs in the MACCS computer analyses (TIMDEC and CDNFRM). The staff is considering whether to update the SAMA analysis in the final supplemental Environmental Impact Statement (FSEIS) accordingly. Therefore, the schedule for publishing the FSEIS will now be September 2016, instead of June 2016.
We would like to emphasize that the NRC staff will make every reasonable effort to meet the revised schedule milestones. The NRC will continue to follow established review procedures and the enclosed safety review schedule to complete the reviews required by 10 CFR Part 54.
1 Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3), CLI-16-07, 83 NRC
__ (May 4, 2016) (slip op.) (ADAMS Accession No. ML16125A150).
K. Polson If you have any questions on this revised environmental review schedule, please contact Ms.
Elaine Keegan, project manager for the environmental review of the Fermi 2 LRA, by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.
Sincerely,
/RA/
Jane Marshall, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Revised Schedule cc w/encl: Listserv
ML16166A044 OFFICE LA:DLR: PM:RPB2:DLR PM:RPB1:DLR BC:RPB1:DLR BC:RPB2:DLR D:DLR NAME IBetts EKeegan LJames YDiaz-Sanabria JDanna JMarshall DATE 6/ 21 /16 6/ 21 /16 6/ 21 /16 6/ 21 /16 6/ 22 /16 6/ 22 /16
FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Schedule Actual Milestones Date Date Receive license renewal application (LRA) 04/30/14 04/30/14 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 06/18/14 Publish FRN - environmental scoping meeting 06/2014 06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 07/24/14 07/24/14 Audit - Scoping and Screening Methodology 08/04/14 08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14 08/18/14 Environmental scoping periods ends 08/2014 08/29/14 Audit - Environmental 09/08/14 09/08/14 Audit - Aging Management Programs (Week 1) 09/15/14 09/15/14 Audit - Aging Management Programs (Week 2) 09/29/14 09/29/14 Regional Inspection - IP 71002, License Renewal Procedure 04/2015 04/13/15 Issue draft supplemental environmental impact statement (SEIS) 10/2015 10/27/15 U.S. Environmental Protection Agency FRN Published - draft SEIS 11/2015 11/13/15 available for comments Public Meeting - draft SEIS meeting 12/2015 12/02/15 End of draft SEIS comment period 12/2015 12/28/15 Issue safety evaluation report (SER) with open item(s) 01/2016 01/28/16 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 03/02/16 meeting 03/2016 Issue final SEIS 09/2016 U.S. Environmental Protection Agency FRN Published - final SEIS 10/2016 available Issue final SER 07/2016 ACRS Full Committee meeting 09/2016 Decision - Director, Office of Nuclear Reactor Regulation 11/2016 Commission decision, if hearing granted TBD ENCLOSURE
Letter to K. Polson from J. Marshall dated June 22, 2016
SUBJECT:
SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4064)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv
D. Melendez-Colon E. Keegan J. Danna D. McIntyre, OPA C. Kanatas, OGC B. Dickson, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII