Schedule Revision for the Environmental Review of the Fermi 2 License Renewal Application
ML16166A044
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/22/2016
From: John Marshall
NRC/NRR/DLR/RERB
To: Polson K
DTE Electric Company
Keegan E, NRR/DLR, 415-8517
References
DLR-16-0146, TAC MF4064
Download: ML16166A044 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 22, 2016 Mr. Keith Polson Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4064)

Dear Mr. Polson:

By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).

Enclosed is the staffs revised environmental review schedule for the Fermi 2 license renewal application (LRA). The staff believes the NRC Commissions recent decision concerning severe accident mitigation alternatives (SAMA) analysis1 may be applicable to the SAMA analysis performed for Fermi 2 because Fermi 2s analysis may have relied upon the NUREG-1150 values for two inputs in the MACCS computer analyses (TIMDEC and CDNFRM). The staff is considering whether to update the SAMA analysis in the final supplemental Environmental Impact Statement (FSEIS) accordingly. Therefore, the schedule for publishing the FSEIS will now be September 2016, instead of June 2016.

We would like to emphasize that the NRC staff will make every reasonable effort to meet the revised schedule milestones. The NRC will continue to follow established review procedures and the enclosed safety review schedule to complete the reviews required by 10 CFR Part 54.

1 Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3), CLI-16-07, 83 NRC

__ (May 4, 2016) (slip op.) (ADAMS Accession No. ML16125A150).

K. Polson If you have any questions on this revised environmental review schedule, please contact Ms.

Elaine Keegan, project manager for the environmental review of the Fermi 2 LRA, by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.

Sincerely,

/RA/

Jane Marshall, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341

Enclosure:

Revised Schedule cc w/encl: Listserv

ML16166A044 OFFICE LA:DLR: PM:RPB2:DLR PM:RPB1:DLR BC:RPB1:DLR BC:RPB2:DLR D:DLR NAME IBetts EKeegan LJames YDiaz-Sanabria JDanna JMarshall DATE 6/ 21 /16 6/ 21 /16 6/ 21 /16 6/ 21 /16 6/ 22 /16 6/ 22 /16

FERMI 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Schedule Actual Milestones Date Date Receive license renewal application (LRA) 04/30/14 04/30/14 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/14 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 06/18/14 Publish FRN - environmental scoping meeting 06/2014 06/30/14 Public Meeting - License Renewal Overview and Environmental Scoping Meeting 07/24/14 07/24/14 Audit - Scoping and Screening Methodology 08/04/14 08/04/14 Deadline for filing hearing requests and petitions for intervention 08/18/14 08/18/14 Environmental scoping periods ends 08/2014 08/29/14 Audit - Environmental 09/08/14 09/08/14 Audit - Aging Management Programs (Week 1) 09/15/14 09/15/14 Audit - Aging Management Programs (Week 2) 09/29/14 09/29/14 Regional Inspection - IP 71002, License Renewal Procedure 04/2015 04/13/15 Issue draft supplemental environmental impact statement (SEIS) 10/2015 10/27/15 U.S. Environmental Protection Agency FRN Published - draft SEIS 11/2015 11/13/15 available for comments Public Meeting - draft SEIS meeting 12/2015 12/02/15 End of draft SEIS comment period 12/2015 12/28/15 Issue safety evaluation report (SER) with open item(s) 01/2016 01/28/16 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 03/02/16 meeting 03/2016 Issue final SEIS 09/2016 U.S. Environmental Protection Agency FRN Published - final SEIS 10/2016 available Issue final SER 07/2016 ACRS Full Committee meeting 09/2016 Decision - Director, Office of Nuclear Reactor Regulation 11/2016 Commission decision, if hearing granted TBD ENCLOSURE

Letter to K. Polson from J. Marshall dated June 22, 2016

SUBJECT:

SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4064)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv


D. Melendez-Colon E. Keegan J. Danna D. McIntyre, OPA C. Kanatas, OGC B. Dickson, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII