Other: ML14195A221, ML14219A743, ML14237A194, ML14267A267, ML15030A226, ML15030A229, ML15076A468, ML15092A224, ML15092A243, ML15098A175, ML15341A261, ML16005A399, ML16146A799, ML16187A173, ML16187A179, ML16187A180, ML16270A531, ML16270A567, ML16330A117, NRC-15-0068, License Renewal Application 2015 Annual Update, NRC-16-0014, Comments on the NRCs Safety Evaluation Report with Open Items Related to the License Renewal, NRC-16-0061, DTE Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools
|
MONTHYEARML14195A2212014-07-24024 July 2014 Plan for Scoping and Screening Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14219A7432014-07-30030 July 2014 Endangered Species List for Proposed Enrico Fermi, Unit 2, License Renewal Project stage: Other ML14237A1942014-09-0505 September 2014 Plan for the Aging Management Program Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14267A2672014-10-21021 October 2014 Scoping and Screening Audit Report Project stage: Other NRC-14-0070, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12014-10-24024 October 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 1 Project stage: Response to RAI ML14288A6802014-10-29029 October 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 3 Project stage: RAI ML14293A8382014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Requests for Additional Information 2.4-1, 2.4-2, 2.4-3, and 3.5.2.2.2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI ML14294A0622014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Request for Additional Information 2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI NRC-14-0072, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22014-11-18018 November 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 2 Project stage: Response to RAI ML14322A5262014-11-25025 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 8 Project stage: RAI ML14321A7522014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 4 Project stage: RAI ML14322A2032014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 6 Project stage: RAI ML14322A1782014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 5 Project stage: RAI NRC-14-0076, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 32014-12-0101 December 2014 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 3 Project stage: Response to RAI ML14323A8802014-12-0404 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 7 Project stage: RAI ML14329B2332014-12-0909 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 9 Project stage: RAI ML14335A4742014-12-12012 December 2014 Summary of Telephone Conference Call Held on November 26, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Draft Requests for Additional Information B.1.12-1 and B.1.12-4 Pertaining to the Fermi 2 Nu Project stage: Draft RAI ML14335A1882014-12-16016 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 14 Project stage: RAI ML14342A6522014-12-17017 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 15 Project stage: RAI ML14342A8682014-12-17017 December 2014 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 10 Project stage: RAI ML14342A9862014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Project stage: RAI ML14342A9382014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 11 Project stage: RAI ML14350B3582014-12-22022 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 18 Project stage: RAI ML14351A4582014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 13 Project stage: RAI ML14350B3652014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi2 License Renewal Application - Set 16 Project stage: RAI NRC-14-0082, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 82014-12-26026 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 8 Project stage: Response to RAI NRC-14-0083, Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 62014-12-30030 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 6 Project stage: Response to RAI NRC-15-0001, Response to NRC Request for Additional Information for the Review License Renewal Application - Set 72015-01-0505 January 2015 Response to NRC Request for Additional Information for the Review License Renewal Application - Set 7 Project stage: Response to RAI NRC-15-0013, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives2015-01-0909 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives Project stage: Response to RAI ML14356A2122015-01-14014 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 17 Project stage: RAI NRC-15-0009, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 152015-01-15015 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 15 Project stage: Response to RAI ML15002A0462015-01-20020 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 20 Project stage: RAI NRC-15-0006, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 112015-01-20020 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Project stage: Response to RAI ML15015A1942015-01-26026 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 19 Project stage: RAI ML15030A0712015-01-30030 January 2015 Notice (Second Notice Pursuant to 10 CFR Section 2.309 (J)) Project stage: Request NRC-15-0022, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-12015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-1 Project stage: Response to RAI NRC-15-0012, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 182015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 18 Project stage: Response to RAI NRC-15-0010, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 162015-02-0505 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 16 Project stage: Response to RAI ML15030A2292015-02-11011 February 2015 AMP Audit Summary Report Enclosure Project stage: Other ML15030A2262015-02-11011 February 2015 Aging Management Programs Audit Report Regarding the Fermi 2 Nuclear Power Plant Project stage: Other ML15026A3992015-02-11011 February 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 21 Project stage: RAI NRC-15-0011, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 172015-02-12012 February 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 17 Project stage: Response to RAI NRC-15-0029, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-12015-02-19019 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-1 Project stage: Response to RAI ML15035A1302015-02-20020 February 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22 Project stage: RAI ML15051A3482015-02-24024 February 2015 Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application Project stage: Approval NRC-15-0023, Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 22015-03-0505 March 2015 Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 2 Project stage: Response to RAI ML15051A3172015-03-11011 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 24 Project stage: RAI ML15051A5092015-03-11011 March 2015 Summary of Telecon Drai Set 24 - February 9, 2015 Project stage: RAI ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 Project stage: RAI ML15054A1712015-03-13013 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2014-07-24
[Table View] |
Similar Documents at Fermi |
|---|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 6, 2015 LICENSEE:
DTE Electric Company FACILITY:
Fermi 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JANUARY 14, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION, SET 19 PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on January 14, 2015, to discuss and clarify the staffs draft requests for additional information (DRAIs) 4.2.4-1, 4.2.4-2, and 4.2.4-3 concerning the Fermi 2 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs.
provides a listing of the participants and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc: Listserv
ML15175A020
- Concurred via e-mail OFFICE LA:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds DMeléndez-Colón YDiaz-Sanabria DMeléndez-Colón DATE 7/01/15 7/2/15 7/6/15 7/6/15
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JANUARY 14, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION, SET 19 PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource D. Melendez-Colon E. Keegan B. Wittick B. Harris, OGC D. Roth, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII
ENCLOSURE 1 TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JANUARY 14, 2015 PARTICIPANTS AFFILIATIONS Daneira Meléndez-Colón U. S. Nuclear Regulatory Commission (NRC)
Seung Min NRC Matthew Homiack NRC Lynne Goodman DTE Electric Company (DTE)
Kevin Lynn DTE Erica Mullen DTE
ENCLOSURE 2
SUMMARY
OF TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION JANUARY 14, 2015 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on January 14, 2015, to discuss and clarify the following draft requests for additional information (DRAIs) concerning the Fermi 2 license renewal application (LRA).
DRAI 4.2.4-1
Background:
LRA Section 4.2.4 describes the time-limited aging analysis (TLAA) for upper-shelf energy of the reactor pressure vessel beltline materials. The LRA states that the upper-shelf energy values for the beltline materials were evaluated for the period of extended operation using the guidance in NRC Regulatory Guide (RG) 1.99, Radiation Embrittlement of Reactor Vessel Materials, Revision 2, dated May 1988.
Issue:
LRA Table 4.2-4 provides values for the various parameters used in the revised upper-shelf energy analysis. However, this table appears to be incomplete because it does not provide the un-irradiated upper-shelf energy value or the percent decrease in upper-shelf energy value for the N-16 water level instrumentation nozzle. In addition, it is not clear from the information in this table as to what methodology was used to establish the un-irradiated upper-shelf energy value and calculate the percent decrease in upper-shelf energy value for this component.
Request:
(a) Provide the un-irradiated upper-shelf energy value for the N-16 water level instrumentation nozzle and identify and justify the methodology that was used to establish this value.
(b) Provide the percent decrease in upper-shelf energy that is projected for the N-16 water level instrumentation nozzle and identify and justify the methodology that was used to calculate this value.
Alternatively, provide an explanation as to why LRA Table 4.2-4 omits the un-irradiated upper-shelf energy and percent decrease in upper-shelf energy values for the N-16 water level instrumentation nozzle.
Discussion:
The staff provided clarification related to draft RAI 4.2.4-1. The staff discussed the extent of the information requested and needed to complete its review.
The applicant stated that the response to this RAI might include proprietary information.
The applicant understands the staffs concerns and will provide a response to the RAI.
DRAI 4.2.4-2
Background:
LRA Section 4.2.4 describes the TLAA for upper-shelf energy of the reactor pressure vessel beltline materials. LRA Table 4.2-4 indicates that Regulatory Position 2.2 from RG 1.99, Radiation Embrittlement of Reactor Vessel Materials, Revision 2, was used to determine the percent decrease in upper-shelf energy values for the vertical and girth weld materials at Fermi 2 based on data from the boiling water reactor integrated surveillance program (ISP).
LRA Table 4.2-5 provides fluence and upper-shelf energy values from the ISP for plate and weld materials.
Issue:
The LRA does not provide the relevant ISP data that is representative of the Fermi 2 reactor pressure vessel.
Request:
(a) Provide all host reactor capsule testing data from the ISP that apply to the upper-shelf energy analyses for the vertical and girth weld materials in the Fermi 2 reactor pressure vessel. Specifically, for each host reactor capsule, provide: (a) the inside diameter and 1/4 T fluence values for all irradiated capsules, (b) the specific material heats that apply to the Fermi 2 vertical and girth weld materials, and (c) for those specific material heats, the un-irradiated upper-shelf energy values, measured upper-shelf energy values, and the copper, nickel, phosphorous, and silicon values. This response may be accomplished by appropriate references to documents that are available in the NRCs Agencywide Documents Access and Management System (i.e., ADAMS).
(b) Explain how the ISP data were applied to the upper-shelf energy calculations for the Fermi 2 vertical and girth weld materials. As part of this response, indicate whether there is a direct match between the material heats in the host reactors and those material heats that were used to fabricate vertical welds 2-307 A, B, and C; vertical welds15-308 A, B, C, and D; and girth weld 1-313 at Fermi 2. If there is not a direct match, justify the basis for applying the ISP data to the upper-shelf energy calculations for these welds.
Discussion:
The staff provided clarification related to draft RAI 4.2.4-2 and stated it will revise the RAI as follows:
Issue:
The LRA does not provide the relevant ISP data that is representative of the Fermi 2 reactor pressure vessel vertical and girth welds identified in LRA Table 4.2-4.
The applicant stated that the response to RAI 4.2.4-2 might include proprietary information. The applicant understands the staffs concerns and will provide a response to the RAI.
The RAI will be issued as revised.
D-RAI 4.2.4-3
Background:
LRA Section A.2.1.4 provides the Updated Final Safety Analysis Report (UFSAR) supplement summarizing the TLAA for upper-shelf energy of the reactor pressure vessel beltline materials.
Issue:
The proposed description for this TLAA does not compare the results of the revised upper-shelf energy analysis against the upper-shelf energy requirements in 10 CFR Part 50, Appendix G.
As such, the description does not contain adequate information regarding the basis for the demonstration for this TLAA made pursuant to 10 CFR 54.21(c)(1)(ii).
Request:
Provide justification as to why the results of the TLAA are not included in the UFSAR supplement. Otherwise, revise LRA Section A.2.1.4, as appropriate, to include a comparison of the results of the revised upper-shelf energy analysis against the upper-shelf energy requirements in 10 CFR Part 50, Appendix G.
Discussion:
The staff provided clarification related to draft RAI 4.2.4-3. The staff discussed the extent of the information requested and needed to complete its review.
The applicant understands the staffs concerns and will provide a response to the RAI.