Other: ML14195A221, ML14219A743, ML14237A194, ML14267A267, ML15030A226, ML15030A229, ML15076A468, ML15092A224, ML15092A243, ML15098A175, ML15341A261, ML16005A399, ML16146A799, ML16187A173, ML16187A179, ML16187A180, ML16270A531, ML16270A567, ML16330A117, NRC-15-0068, License Renewal Application 2015 Annual Update, NRC-16-0014, Comments on the NRCs Safety Evaluation Report with Open Items Related to the License Renewal, NRC-16-0061, DTE Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools
|
MONTHYEARML14195A2212014-07-24024 July 2014 Plan for Scoping and Screening Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14219A7432014-07-30030 July 2014 Endangered Species List for Proposed Enrico Fermi, Unit 2, License Renewal Project stage: Other ML14237A1942014-09-0505 September 2014 Plan for the Aging Management Program Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14267A2672014-10-21021 October 2014 Scoping and Screening Audit Report Project stage: Other NRC-14-0070, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12014-10-24024 October 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 1 Project stage: Response to RAI ML14288A6802014-10-29029 October 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 3 Project stage: RAI ML14293A8382014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Requests for Additional Information 2.4-1, 2.4-2, 2.4-3, and 3.5.2.2.2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI ML14294A0622014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Request for Additional Information 2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI NRC-14-0072, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22014-11-18018 November 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 2 Project stage: Response to RAI ML14322A5262014-11-25025 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 8 Project stage: RAI ML14321A7522014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 4 Project stage: RAI ML14322A2032014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 6 Project stage: RAI ML14322A1782014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 5 Project stage: RAI NRC-14-0076, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 32014-12-0101 December 2014 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 3 Project stage: Response to RAI ML14323A8802014-12-0404 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 7 Project stage: RAI ML14329B2332014-12-0909 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 9 Project stage: RAI ML14335A4742014-12-12012 December 2014 Summary of Telephone Conference Call Held on November 26, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Draft Requests for Additional Information B.1.12-1 and B.1.12-4 Pertaining to the Fermi 2 Nu Project stage: Draft RAI ML14335A1882014-12-16016 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 14 Project stage: RAI ML14342A6522014-12-17017 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 15 Project stage: RAI ML14342A8682014-12-17017 December 2014 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 10 Project stage: RAI ML14342A9862014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Project stage: RAI ML14342A9382014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 11 Project stage: RAI ML14350B3582014-12-22022 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 18 Project stage: RAI ML14351A4582014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 13 Project stage: RAI ML14350B3652014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi2 License Renewal Application - Set 16 Project stage: RAI NRC-14-0082, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 82014-12-26026 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 8 Project stage: Response to RAI NRC-14-0083, Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 62014-12-30030 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 6 Project stage: Response to RAI NRC-15-0001, Response to NRC Request for Additional Information for the Review License Renewal Application - Set 72015-01-0505 January 2015 Response to NRC Request for Additional Information for the Review License Renewal Application - Set 7 Project stage: Response to RAI NRC-15-0013, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives2015-01-0909 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives Project stage: Response to RAI ML14356A2122015-01-14014 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 17 Project stage: RAI NRC-15-0009, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 152015-01-15015 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 15 Project stage: Response to RAI ML15002A0462015-01-20020 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 20 Project stage: RAI NRC-15-0006, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 112015-01-20020 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Project stage: Response to RAI ML15015A1942015-01-26026 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 19 Project stage: RAI ML15030A0712015-01-30030 January 2015 Notice (Second Notice Pursuant to 10 CFR Section 2.309 (J)) Project stage: Request NRC-15-0022, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-12015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-1 Project stage: Response to RAI NRC-15-0012, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 182015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 18 Project stage: Response to RAI NRC-15-0010, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 162015-02-0505 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 16 Project stage: Response to RAI ML15030A2292015-02-11011 February 2015 AMP Audit Summary Report Enclosure Project stage: Other ML15030A2262015-02-11011 February 2015 Aging Management Programs Audit Report Regarding the Fermi 2 Nuclear Power Plant Project stage: Other ML15026A3992015-02-11011 February 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 21 Project stage: RAI NRC-15-0011, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 172015-02-12012 February 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 17 Project stage: Response to RAI NRC-15-0029, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-12015-02-19019 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-1 Project stage: Response to RAI ML15035A1302015-02-20020 February 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22 Project stage: RAI ML15051A3482015-02-24024 February 2015 Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application Project stage: Approval NRC-15-0023, Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 22015-03-0505 March 2015 Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 2 Project stage: Response to RAI ML15051A3172015-03-11011 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 24 Project stage: RAI ML15051A5092015-03-11011 March 2015 Summary of Telecon Drai Set 24 - February 9, 2015 Project stage: RAI ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 Project stage: RAI ML15054A1712015-03-13013 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2014-07-24
[Table View] |
Similar Documents at Fermi |
|---|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 2, 2015 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION - SET 31 (TAC NO. MF4222)
Dear Mr. Kaminskas:
By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title10 of the Code of Federal Regulations Part 54, to renew the operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
This request for additional information was discussed with Ms. Lynne Goodman, and a mutually agreeable date for the response is within 35 days from the date of this letter. If you have any questions, please contact me at 301-415-3301 or e-mail Daneira.Melendez-Colon@nrc.gov.
Sincerely,
/RA/
Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Request for Additional Information cc w/encl: ListServ
ML15085A513
- concurred via e-mail OFFICE LA:RPB1:DLR PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds
- DMeléndez-Colón JDaily YDíaz-Sanabria DMeléndez-Colón DATE 3/31/15 4/2/15 4/2/15 4/2/15 4/2/15
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE FERMI 2 LICENSE RENEWAL APPLICATION - SET 31 (TAC NO. MF4222)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick D. McIntyre, OPA B. Harris, OGC D. Roth, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII C. Lipa, RIII S. Sheldon, RIII
FERMI 2 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION SET 31 (TAC NO. MF4222)
RAI B.1.2-2a
Background:
License Renewal Application (LRA) Section B.1.2 states that the Bolting Integrity Program is an existing program, with enhancements, that will be consistent with Generic Aging Lessons Learned (GALL) Report Aging Management Program (AMP) XI.M18, Bolting Integrity. In its response to Request for Additional Information (RAI) B.1.2-2, dated January 20, 2015, DTE stated, in part, the following:
Quarterly surveillance runs of the [residual heat removal service water] RHRSW,
[emergency equipment service water] EESW, and [emergency diesel generator service water] EDGSW pumps are performed. The pump performance parameters are trended to determine if corrective actions are needed. Pump degradation during surveillance runs would lead to pump repair or refurbishment.
During this maintenance, the associated bolting would be inspected, including the bolting threads. To ensure that loss of material in crevice locations that are not readily visible can be detected, the LRA will be revised to include these opportunistic inspections of the submerged bolting threads as part of the Bolting Integrity Program.
Issue:
GALL Report AMP XI.M18 recommends periodic inspections (at least once per refueling cycle) of closure bolting for signs of leakage to ensure the detection of age-related degradation due to loss of material and loss of preload. The staff notes that a submerged environment limits the ability to detect leakage of submerged bolted connections. Therefore, additional information is needed for the staff to understand how the Bolting Integrity Program will ensure the detection of loss of material and loss of preload, and adequate aging management of bolts in the RHRSW, EESW, and EDGSW systems submerged environment.
The Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR) states that the AMP frequency of inspections may be linked to plant specific or industry wide operating experience and a discussion should provide justification that the frequency is adequate to detect the aging effects before there is a loss of structure and component (SC) intended function. The SRP-LR also states that the detection of aging effects should occur before there is a loss of SC intended function. The staff is concerned about the possibility that an opportunistic inspection approach may result in inspections not done frequently enough to detect degradation of the bolt thread area of the submerged bolts before there is a loss of intended function. Therefore, it is not clear how opportunistic inspections based on pump maintenance activities will be adequate to detect loss of material in the thread region of the submerged bolts before there is a loss of intended function.
ENCLOSURE
Request:
- 1. Provide the number of times (including year) that maintenance activities (e.g., pump repair or refurbishment) have been performed for the RHRSW, EESW, and EDGSW systems with submerged bolting.
- 2. Provide the technical basis as to how the proposed inspections will ensure that the aging effects for the threaded area of the submerged bolting will be timely detected and adequately managed before there is a loss of intended function.