Other: ML14195A221, ML14219A743, ML14237A194, ML14267A267, ML15030A226, ML15030A229, ML15076A468, ML15092A224, ML15092A243, ML15098A175, ML15341A261, ML16005A399, ML16146A799, ML16187A173, ML16187A179, ML16187A180, ML16270A531, ML16270A567, ML16330A117, NRC-15-0068, License Renewal Application 2015 Annual Update, NRC-16-0014, Comments on the NRCs Safety Evaluation Report with Open Items Related to the License Renewal, NRC-16-0061, DTE Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools
|
MONTHYEARML14195A2212014-07-24024 July 2014 Plan for Scoping and Screening Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14219A7432014-07-30030 July 2014 Endangered Species List for Proposed Enrico Fermi, Unit 2, License Renewal Project stage: Other ML14237A1942014-09-0505 September 2014 Plan for the Aging Management Program Regulatory Audit Regarding the Fermi 2 License Renewal Application Review Project stage: Other ML14267A2672014-10-21021 October 2014 Scoping and Screening Audit Report Project stage: Other NRC-14-0070, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12014-10-24024 October 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 1 Project stage: Response to RAI ML14288A6802014-10-29029 October 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 3 Project stage: RAI ML14293A8382014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Requests for Additional Information 2.4-1, 2.4-2, 2.4-3, and 3.5.2.2.2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI ML14294A0622014-11-10010 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Draft Request for Additional Information 2.1-1 Pertaining to Fermi, Unit 2, License Renewal Application Project stage: Draft RAI NRC-14-0072, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22014-11-18018 November 2014 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 2 Project stage: Response to RAI ML14322A5262014-11-25025 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 8 Project stage: RAI ML14321A7522014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 4 Project stage: RAI ML14322A2032014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 6 Project stage: RAI ML14322A1782014-11-26026 November 2014 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 5 Project stage: RAI NRC-14-0076, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 32014-12-0101 December 2014 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 3 Project stage: Response to RAI ML14323A8802014-12-0404 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 7 Project stage: RAI ML14329B2332014-12-0909 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 9 Project stage: RAI ML14335A4742014-12-12012 December 2014 Summary of Telephone Conference Call Held on November 26, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Draft Requests for Additional Information B.1.12-1 and B.1.12-4 Pertaining to the Fermi 2 Nu Project stage: Draft RAI ML14335A1882014-12-16016 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 14 Project stage: RAI ML14342A6522014-12-17017 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 15 Project stage: RAI ML14342A8682014-12-17017 December 2014 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 10 Project stage: RAI ML14342A9862014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Project stage: RAI ML14342A9382014-12-19019 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 11 Project stage: RAI ML14350B3582014-12-22022 December 2014 Requests for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application - Set 18 Project stage: RAI ML14351A4582014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 13 Project stage: RAI ML14350B3652014-12-23023 December 2014 Requests for Additional Information for the Review of the Fermi2 License Renewal Application - Set 16 Project stage: RAI NRC-14-0082, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 82014-12-26026 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 8 Project stage: Response to RAI NRC-14-0083, Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 62014-12-30030 December 2014 Response to NRC Request for Additional Information for the Review of License Renewal Application - Sets 4, 5, and 6 Project stage: Response to RAI NRC-15-0001, Response to NRC Request for Additional Information for the Review License Renewal Application - Set 72015-01-0505 January 2015 Response to NRC Request for Additional Information for the Review License Renewal Application - Set 7 Project stage: Response to RAI NRC-15-0013, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives2015-01-0909 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives Project stage: Response to RAI ML14356A2122015-01-14014 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 17 Project stage: RAI NRC-15-0009, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 152015-01-15015 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 15 Project stage: Response to RAI ML15002A0462015-01-20020 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 20 Project stage: RAI NRC-15-0006, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 112015-01-20020 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Project stage: Response to RAI ML15015A1942015-01-26026 January 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 19 Project stage: RAI ML15030A0712015-01-30030 January 2015 Notice (Second Notice Pursuant to 10 CFR Section 2.309 (J)) Project stage: Request NRC-15-0022, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-12015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 12 Questions 4.2.2-1 and 4.2.2-2 and Set 15 Question 4.2.6-1 Project stage: Response to RAI NRC-15-0012, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 182015-01-30030 January 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 18 Project stage: Response to RAI NRC-15-0010, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 162015-02-0505 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 16 Project stage: Response to RAI ML15030A2292015-02-11011 February 2015 AMP Audit Summary Report Enclosure Project stage: Other ML15030A2262015-02-11011 February 2015 Aging Management Programs Audit Report Regarding the Fermi 2 Nuclear Power Plant Project stage: Other ML15026A3992015-02-11011 February 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 21 Project stage: RAI NRC-15-0011, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 172015-02-12012 February 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 17 Project stage: Response to RAI NRC-15-0029, Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-12015-02-19019 February 2015 Response to NRC Request for Additional Information for the Review of License Renewal Application - Set 11 Question B.1.22-1 Project stage: Response to RAI ML15035A1302015-02-20020 February 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22 Project stage: RAI ML15051A3482015-02-24024 February 2015 Schedule Revision and Project Manager Change for the Review of the Fermi 2 License Renewal Application Project stage: Approval NRC-15-0023, Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 22015-03-0505 March 2015 Response to NRC Request for Additional Information for the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives Set 2 Project stage: Response to RAI ML15051A3172015-03-11011 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 24 Project stage: RAI ML15051A5092015-03-11011 March 2015 Summary of Telecon Drai Set 24 - February 9, 2015 Project stage: RAI ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 Project stage: RAI ML15054A1712015-03-13013 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2014-07-24
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 22, 2015 LICENSEE:
DTE Electric Company FACILITY:
Fermi 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON NOVEMBER 19, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION, SET 7 PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on November 19, 2014, to discuss and clarify the staffs draft request for additional information (DRAI) B.1.8-2 concerning the Fermi 2 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAI.
provides a listing of the participants and Enclosure 2 contains the DRAI discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc w/encls: Listserv
LICENSEE:
DTE Electric Company FACILITY:
Fermi 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON NOVEMBER 19, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION, SET 7 PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on November 19, 2014, to discuss and clarify the staffs draft request for additional information (DRAI) B.1.8-2 concerning the Fermi 2 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAI.
provides a listing of the participants and Enclosure 2 contains the DRAI discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc w/encls: Listserv DISTRIBUTION: See next page Accession Number: ML15092A243
- Concurred via e-mail OFFICE LA:RPB1:DLR PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds*
DMeléndez-Colón JDaily YDiaz-Sanabria DMeléndez-Colón DATE 4/15/15 4/16/15 4/17/15 4/ 22 /15 4/ 22/15 OFFICIAL RECORD COPY
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON NOVEMBER 19, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION, SET 7 PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick B. Harris, OGC D. Roth, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII
TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS NOVEMBER 19, 2014 PARTICIPANTS AFFILIATIONS Daneira Meléndez-Colón U. S. Nuclear Regulatory Commission (NRC)
Seung Min NRC Lynne Goodman DTE Electric Company (DTE)
Kevin Lynn DTE Al Brooks DTE ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION NOVEMBER 19, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on November 19, 2014, to discuss and clarify the following draft request for additional information (DRAI) concerning the Fermi 2 license renewal application (LRA).
DRAI B.1.8-2
Background:
License Renewal Application Section B.1.8 states that the applicants BWR Stress Corrosion Cracking Program is consistent with Generic Aging Lessons Learned (GALL) Report Aging Management Program (AMP) XI.M7, BWR Stress Corrosion Cracking. In its review of the applicants program and related information, the staff noted that the following references indicate that the applicants condensate and feedwater systems include 24 Category D welds per Generic Letter (GL) 88-01 (i.e., welds with materials non-resistant to intergranular stress corrosion cracking and with no stress improvement process).
Letter from the Detroit Edison Company to the NRC (NRC-92-0090), Fermi 2 Response to Generic Letter 88-01, Supplement 1, NRC Position on Intergranular Stress Corrosion Cracking (IGSCC) in BWR Austenitic Stainless Steel Piping, July 29, 1992 Letter from the NRC to the Detroit Edison Company, Fermi-2 Removal of 24 Condensate and Feedwater System Welds from the Inservice Inspection Nondestructive Examination (ISI-NDE) Program (TAC No. M84177), December 18, 1992 The staff also noted that the following tables of the LRA describe the applicants aging management review (AMR) items for the condensate and feedwater systems.
Table 3.4.2-3-2, Condensate System, Nonsafety-Related Components Affecting Safety-Related Systems Table 3.4.2-2, Feedwater and Standby Feedwater System Table 3.4.2-3-3, Feedwater and Standby Feedwater System, Nonsafety-Related Components Affecting Safety-Related Systems Issue:
The staff noted that the AMR tables for the condensate and feedwater systems in the LRA do not include any AMR items to manage IGSCC for the Category D welds that were identified in the 1992 communications between the Detroit Edison Company and NRC. The staff cannot determine the adequacy of the applicants program and AMR results without additional information to justify the omission of relevant AMR items.
ENCLOSURE 2
The staff also noted that the 1992 communications indicate that these Category D welds are located outboard of the containment isolation valves and at least 10 percent of these welds should be inspected during each refueling outage as part of the applicants inservice inspection.
The staff further noted that the extent and frequency of the applications inspections are different from the inspection guidance provided in GL 88-01 and BWRVIP-75-A. For example, BWRVIP-75-A states that in the case of the implementation of hydrogen water chemistry 100 percent of Category D welds should be inspected every 10 years and at least 50 percent of these welds should be inspected in the first 6 years. However, the LRA does not identify this difference as a program exception.
Request:
- 1. Explain whether or not the condensate and feedwater systems include Category D welds.
Provide adequate justification for why the LRA AMR tables for condensate and feedwater systems do not include AMR items to manage IGSCC for the Category D welds.
- 2. Clarify why the LRA does not identify the inspection extent and frequency for Category D welds as a program exception to GALL Report AMP XI.M7. In addition, provide technical justification for why the inspection extent and frequency for Category D welds are acceptable for adequate aging management. As part of the response, discuss whether the plant-specific operating experience, including inspection results, justify the adequacy of aging management for Category D welds.
Discussion:
The staff provided clarification related to its concerns in draft RAI B.1.8-2.
The applicant and the staff discussed the inspection scope and the frequency for the Category D welds in the condensate and feedwater systems. The discussion also included the inspection scope per Generic Letter 88-01 for the reactor water cleanup system welds.
The applicant understands the staffs concerns and will provide a response to the draft RAI.
This request will be sent as a formal RAI.