Summary of Telecon Drai Set 24 - February 9, 2015
ML15051A509
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/11/2015
From: Melendez-Colon D
License Renewal Projects Branch 1
To:
DTE Electric Company
Melendez-Colon D, 415-3301
References
TAC MF4222
Download: ML15051A509 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 11, 2015 LICENSEE: DTE Electric Company FACILITY: Fermi 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 9, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on February 9, 2015, to discuss and clarify the staffs draft request for additional information (DRAI) B.1.19-8a concerning the Fermi 2 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAI. provides a listing of the participants and Enclosure 2 contains the DRAI discussed with the applicant, including a brief description on the status of the items.

The applicant had an opportunity to comment on this summary.

/RA/

Daneira Meléndez-Colón, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341

Enclosures:

1. List of Participants
2. Summary of Telephone Conference Call cc w/encls: Listserv

ML15051A509 *Concurred via e-mail OFFICE LA:RPB1:DLR PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds DMeléndez-Colón RPlasse YDíaz-Sanabria DMeléndez-Colón DATE 3/10/15 3/10/15 3/10/15 3/11/15 3/11/15

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 9, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND DTE ELECTRIC COMPANY, CONCERNING REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE FERMI 2 LICENSE RENEWAL APPLICATION (TAC NO. MF4222)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource D. Melendez-Colon Y. Diaz-Sanabria E. Keegan B. Wittick B. Harris, OGC D. Roth, OGC M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII

TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS FEBRURARY 9, 2015 PARTICIPANTS AFFILIATIONS Daneira Meléndez-Colón U. S. Nuclear Regulatory Commission (NRC)

William C. Holston NRC Lynne Goodman DTE Electric Company (DTE)

Kevin Lynn DTE Chris Redmond DTE Jeff Chase DTE ENCLOSURE 1

SUMMARY

OF TELEPHONE CONFERENCE CALL FERMI 2 LICENSE RENEWAL APPLICATION February 9, 2015 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of DTE Electric Company (DTE or the applicant) held a telephone conference call on February 9, 2015, to discuss and clarify the following draft request for additional information (DRAI) concerning the Fermi 2 license renewal application (LRA).

DRAI B.1.19-8a

Background:

One of the plant-specific operating experience examples cited in the license renewal application (LRA) describes fire suppression flow testing that demonstrated degrading conditions in the underground piping system. The LRA states that the frequency of testing and evaluation of this piping has been increased from 3 years, as required in the current licensing basis, to annual testing.

The response to RAI B.1.19-8, dated January 15, 2015, states an enhancement to the LRA Section B.1.19 corrective action program element. The enhancement states, [r]evise Fire Water System Program procedures to consider in accordance with the Corrective Action Program increasing test frequency if there is a decreasing trend in flow in the fire water system flow test.

Issue:

The staff recognizes that if an adverse trend in system performance is detected during the period of extended operation, the condition adverse to quality will be evaluated in accordance with the Corrective Action Program. However, given the existing degraded condition, the staff lacks sufficient information to:

  • Find the enhancement acceptable because the use of the term consider leaves it indeterminate whether the frequency of fire water system flow testing will be increased during the period of extended operation if the current decreasing trend in system performance reveals that the system may not be capable of performing its intended function throughout the period of extended operation.
  • Conclude that existing corrective actions will be sufficient to correct the adverse trend prior to the period of extended operation.

Therefore, the staff cannot conclude that plant-specific operating experience associated with flow testing of the underground fire water system has been adequately evaluated.

ENCLOSURE 2

Request:

State and justify the basis for why the current trend in fire water system performance will be corrected prior to the period of extended operation, or state a commitment to continue the increased frequency of fire water system flow tests until such time as trend data demonstrates that the system will be capable of performing its intended function throughout the period of extended operation.

Discussion:

The staff provided clarification related to its request in draft RAI B.1.19-8a and stated it will revise the request as follows:

State and justify the basis for why the current trend in fire water system performance will be corrected prior to the period of extended operation, or state a commitment to continue the increased frequency of fire water system flow tests until such time as the current trend data demonstrates that the system will be capable of performing its intended function throughout the period of extended operation.

The applicant understands the staffs concerns and will provide a response to the draft RAI.

The RAI will be issued as revised.