Forwards Ebasco Vol I - Book 9 (Part 4) to Multimode Response Multiplier - Studies. Studies Performed to Further Substantiate Conservatism of 1.25 Multiple Response Multiplier
ML20202J622
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/11/1986
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Noonan V
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
Shared Package
ML20202J626 List:
References
TXX-4754, NUDOCS 8604160130
Download: ML20202J622 (3)


Text

_ _ _ _ _ _ _ _ .

Log # TXX-4754 File # 10068 TEXAS UTILITIES GENERATING COMPANY NKYWAY TOWER

  • 400 NORTH OLIVE RTMEET. L.B. 81 e DA11AS. TEXAS 75301 April 11, 1986 N M O d ?.?fn'A Director of Nuclear Reactor Regulation Attention: Mr. Vince S. Noonan, Director Comanche Peak Project Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NOS. 50-445 AND 50-446 MULTIPLE RESPONSE MULTIPLIER STUDIES

Dear Mr. Noonan:

Attached for your review is EBASCO Report, Volume I - Book 9 (Part 4) entitled "Multimode Response Multiplier Studies." These studies were performed to further substantiate the conservatism of the 1.25 Multiple Response Multiplier.

, Very truly yours,

$a W. G. Counsil wnd BSD/ arm Attachment Original + 1 copy c- Mr. R. E. Camp w/o attachment Mr. H. A. Harrison w/o attachment Mr. J. P. Padalino w/o attachment Mr. L. D. Nace w/o attachment Mr. J. T. Merritt w/o attachment Mr. C. R. Hooton w/o attachment Mr. David Jeng U. S. Nuclear Regulatory Commission Mail Stop 244 0 7920 Norfolk Avenue Bethesda, MD 20814 k 'l g"tBa n880P ...musorrexAs emuries stecrnsccoursur

E Log # TXX-4754 File # 10068 TEXAS UTILITIES GENERATING COMPANY SKYWAY TOWER . 400 NORTH Of IVE WFREET, L.B. a t . DALLAS. TEXA5 78301 April 11, 1986

  1. !!bl^Ja?SEn'A Director of Nuclear Reactor Regulation Attention: Mr. Vince S. Noonan, Director Comanche Peak Project Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NOS. 50-445 AND 50-446 MULTIPLE RESPONSE MULTIPLIER STUDIES

Dear Mr. Noonan:

Attached for your review is EBASCO Report, Volume I - Book 9 (Part 4) entitled "Multimode Response Multiplier Studies." These studies were performed to further substantiate the conservatism of the 1.25 Multiple Response Multiplier.

Very truly yours, MO V' W. G. Counsil BSD/ arm Attachment Original + 1 copy c- Mr. R. E. Camp w/o attachment Mr. H. A. Harrison w/o attachment Mr. J. P. Padalino w/o attachment Mr. L. D. Nace w/o attachment Mr. J. T. Merritt w/o attachment Mr. C. R. Hooton w/o attachment Mr. David Jeng U. S. Nuclear Regulatory Commission Mail Stop 244 7920 Norfolk Avenue Bethesda, MD 20814 A DEVISION OF TEXAS LTELITIES ELECTRIC COMPANY