ML20153E482

From kanterella
Jump to navigation Jump to search
Insp Repts 50-413/88-07 & 50-414/88-07 on 880201-05. Violations Noted:Failure to Establish Qualification of Minco Type RTDs for Submergence.Major Areas Inspected:Environ Qualification of Electrical Equipment
ML20153E482
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 04/26/1988
From: Conlon T, Merriweather N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20153E471 List:
References
50-413-88-07, 50-413-88-7, 50-414-88-07, 50-414-88-7, IEIN-79-03, IEIN-79-3, IEIN-81-29, IEIN-82-52, IEIN-83-72, IEIN-86-003, IEIN-86-071, IEIN-86-3, IEIN-86-71, NUDOCS 8805100023
Download: ML20153E482 (33)


See also: IR 05000413/1988007

Text

.

'

UNITED STATES

[pm Etog

'

NUCLE AR REGULATORY COMMISSION

o,

%' \\

REGloN il

j . I C[ / '

101 MARIETT A STREE T. N W.

'.%

- 't

ATL ANT A, GEORGI A 30323

gv ,#

.....

Report Nos.:

50-413/88-07 and 50-414/88-07

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.:

50-413 and 50-414

License Nos.:

NPF-35 and NPF-52

Facility Name:

Catawba 1 and 2

Inspection Conducted:

F bruary 1-5, 1983

,

Inspector:

j[ht/

'

ate $ ned

2h

N. Merriweather,

eam Leader

Team Members:

S. A. Alexander, Equipment Qualification and Test Engineer, NRR

E. Claiborne, Consultant Engineer, Sandia National Laboratories

Q. Decker, Consultant Engineer, Idaho National Engineering

Laboratory

C. Kido, Consultant Engineer, Idaho National Engineering

Laboratory

W. Levis, Reactor Inspector, RII

C. Paulk, Reactor Inspector, RII

C. Smith, Reactor ospector ,RII

._ f@f

g/

/QF

A p pro v e M'_.

. Conlon, Lhief.

Cate Signed

T.

Plant Systems Section

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was in the area of Environmental

Qualification (EQ) of Electrical Ecuipment and included a review of Duke Power

Company's (DPC) implementation of the requirements of 10 CFR 50.49; plant

walkdown inspections of electrical equipment within the scope of 10 CFR 50.49;

a review of the circumstances and corrective actions relating to previously

identified EQ deficiencies and a review of their evaluations of inspection

findings on how they ef fect restart of Unit 2 and continued operation of

Unit 1.

Results:

Seven violations were identified and are discussed in Paragraphs 2,

3, and 6.

1

8805100023 G80504

PDR

ADOCK 05000413

Q

DCD,

'.

' , ,

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • D. Collings, Senior Engineer, Design Engineering Department
  • M. Cote', Production Spee!alist II, Nuclear Production Department
  • J. Cox, Catawba Training Manager, Production Training Services
  • J. Crenshaw, Senior Engineer, Design Engineering Department
  • C. Origgers, Supervisor, Design Engineering Department
  • G. Gardner, Supervisor, Design Engineering Department
  • G. Grier, Corporate Quality Assurance Manager
  • S. Grier, Nuclear Production Engineer, Nuclear Production Dep!-tment
  • J. Hampton, Manager of Catawba Nuclear Station
  • C. Hartzell, Catawba Compliance Engineer, Nuclear Production Department

)

  • E. Mite, Maintenance Engineer
  • R. Kovacs, Design Engineer - Instrumentation, Design Engineering Department
  • J. Lanier, QA Engineer, QA Technical Services
  • C, Little, System Technical Manager - Instrumentation and Electrical
  • T. McHeckin, Chief Engineer, Design Engineering Department
  • D. Owen, Principal Engineer, Design Engineering Department
  • R. Prior, Vice President Design Engineering
  • G. Smith, Superintendent of Maintenance, Catawba Nuclear Station
  • R. Sokal, Technical Assistant, Design Engineering Department
  • J. Stackley, Instrumentation and Electrical Engineer, Catawba Nuclear

Station

j

  • J. Thomas, Senior Engineer - Electrical, Design Engineering Departirent
  • P. Voglewede, Supervisor, Design Engineering Department
  • R. Weidler, Senior Engineer - Mechanical, Design Engineering Department
  • M. Wilken Shoff, QA Engineer, QA Technical Services

Other Organizations

  • J. Styslinger, EQ Engineering Supervisor, Georgia Power Company
  • H. Vaught, Maintenance Engineer, Georgia Power Company

NRC

  • K. Jabbour, Licensing Project Manager - Catawba, NHC, NRR
  • T. Peebles, Section Chief, NRC, RII
  • P. K. Van Doorn, Senior Resident Inspector, NRC, RII
  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were sumarized e February 5,1988,

with those persons indicated in paragraph 1.

The inspector described the

'

.

.

.

,

,

.

!I

l

2

!

I

areas inspected and discussed in detail the inspection findings listed

!

2

i

beluw.

No dissenting coments were received from the licensee.

Subse-

quant to the inspection, two previously identified unresolved items

have been detemined to be violations of 10 CFR 50.49 ('J,em Nos. 50-413,

3

414/88-07-05) for failure to establish qualification of the MINC0 Typa

l

RTDs for submergence and (Item Nos. 50-413,414/88-07-07) for T-drains

painted over or lack of T-drains on some inside containment Limitorque

'

operators.

In addition, one unresolved item concerning lack of traceabil-

ity for tested versus installed Rosemount transmitters is now considered

,

closed.

';

!

!

4

The following is a list of new items identified during this inspection.

Item Number

Description / Reference Paragraph

j

i

-;

1

50-413/88-07-01

Violation, Licensee's EQ files did not

I

support qualification of the four-to-one

'

electrical tape splice used on the hydrogen

l

1

recombiners in the Unit 1 containment.

The

l

]

installed configuration was not similar to

5

the tested configuration in that the files

l

l

demonstrated qualification for an in line

one-to-one tape splice versus a four-to-

one V-configuration tape splice, Paragraph

'

l

6.1.(19).

,

.

l

504413, 414/88-07-02

Violation. The RCS wide range (hot and cold

l

j

leg) resistance temperature detectors (RTDs)

.

4

(modelRdF)werenotinstalledinaccordance

!

j

with the tested configuration.

The bellows

,

or hydrostatic hose assembly which encap.

,

sulated the RTD pigtail lead wires from

4

i

moisture egress was removed during installa-

i

tion.

Furthermore, the junction box where

f

1

the RTD pigtail wires teminated was not

[

qualified for submergence, Paragraph 6.1.(2),

j

'

t

50-413/88-07-03

Violation, The licensee had unqualified

j

'

limitorque motor operated valves installed

t

on both units in the Containment Air Return

and Hydrogen Skimer System (valve Nos.

t

~

IVX1A, IVX28, 2VX1A, and 2VX28).

The

j

licensee had previously claimed that these

i

l

valves were qualified for outside contain-

t

ment.

However, the licensee could not

!

l

i

support qualification for the use of these

limitorque operators for either inside or

outside containment because the operators

j

were procured as non-safety, Paragraph 3.

I

j

i

I

l

-

.

- - - - -

- - -

- -- - - .

- - - - - - - - - - - - - - - - - -

- -

- .

- - - - - - - -


------


-J

'.

',

3

50-414/88-07-04

Violation, The Joy Reliance fan motors used

inside containment on the Hydrogen Skimer

This appar goajhgr-drains

have the .

fans did not

. . .

.e M in

installed.

accordance with the tested configuration

!

and the licensee did not have an adequate

evaluation in the file, Paragraph 6.1 (1).

50 413, 414/88-07-05

Violation. Licensee's EQ files did not

support qualification for the Hinco type

RTDs in that the RTDs and associated

junction boxes were located below the flood

l

level inside containment.

The file did not

address submergence at the time of the

inspection, Paragraph 6.f.(3).

50-414/88-07-06

Violation

The cover gasket on a Namco

limit switch (tag no. 2NCLLO251) was missing

at one end.

This configuration is not

consideredqualified, Paragraph 6.i.(18).

1

50-413, 414/88-07-07

Violation, Linitorque valves on Unit 2 were

,

observed to have their T-drains painted

over.

Two out of the three limitorques

i

inspected exhibited some kind of obstruction.

'

,

A walkdown by the licensee identified further

,

examples of T-drains obstructed or their

'

ability to properly drain was uncertain,

in

1

addition, some limitorque operators located

inside containment on Units 1 and 2 were

discovered without any T-drains installed,

Paragraph 6.i.(15),

j

i

50-414/88-07-08

Unresolved Item. T-drains on limitorque

valve No. 2N!-1228 were not installed at the

low point.

This configuration does not

appear to be qualified, Paragraph 6.1.(15),

3.

Licensee Action on Previous Enforcement Matters

(Closed) Violation 50-413/86-05-05, Use of Unqualified Limitorque Motor

d

Operated Yalves Inside Unit 1 Containment

The inspectors followed up on a previously identified Violation

413/86-05-05 which identified the lack of proper documentation for the

environmental qualification of IVX1A and IVX28, hydrogen skimmer fan

isolation valves.

The initial concern was that these motors operated

. .

.

. . .

'

.

,

4

4

valves were intended for outside containment applications but were

actually used inside containment. Duke Power Company Report No. SES-JR-45

dated June 15, 1984, discussed the variations between these outside

containment motor operated valves and those intended for inside

containment applications.

The report concluded that the Class B motor

insulation system was acceptable for inside containment use at Catawba

based on previous testing conducted by limitorque on MOV's with Class B

motors since the environmental parameters experienced by the Catawba

actuators was less severe than that in the limitorque outside containment

test. The following weaknesses were noted this methodology:

l

Evaluation considered only the motor and did not include other

electrical components such as torque switch, limit switch and

termination means

'

Ef9ets of chemical spray not evaluated. Limitorque tests have shown

that some outside containment materials are not acceptable in

chemical spray environments

In addition, when the licensee was asked to verify that the MOV was indeed

qualified for outside containment harsh environments he discovered the

MOV's were procured comercial grade and that no documentation existed to

justify their ust. in outside containment EQ applications.

These MOV's

1

were replaced in February 1986.

As stated in previous Inspection Report

No. 50-413/86-05 the use of these unqualified motor opereted valves

constitutes a violation of 10 CFR 50.49.

However Violation 413/86-05-05

will be closed out and a new number will be assigned to this violation,

413/88-07-03, Use of Unqualified Limitorque Motor Opersted Valves Inside

Unit 1 Containment.

This problem also existed on Unit 2 Valve Nos. 2VXIA

!

and 2VX28.

4.

Unresolved Items

Unresolved items are ratters about which more information is required to

determine whether they are acceptable or may involve violations or

deviations.

One unresolved item identified during this inspection is

discussed in paragraph 6.1.(15).

5.

Background

'

NUREG-0588 was issued in December 1979 to promote a more orderly and

'

systematic implementation of equipment qualification programs by industry

and to provide guidance to the NRC staff for its use in ongoing licensing

<

reviews.

The positions contained in that report provide

(1) how to establish environmental service conditions, (2) guidance on

how to select

methods that are considered appropriate for qualifying equipment in

different areas of the plant, and (3) other areas such as margin, aging,

and documentation.

In February 1980, the NRC asked certain near-tem OL

,

!

'

- - -

-

.

-

.

.

.

-

- - -

-

-

. _

'.

'..

5

1

applicants to review and evaluate the environmental qualification

documentation for each item of safety-related electrical equipment and to

identify the degree to which their qualification programs were in

compliance with the staff positions discussed in -NUREG-0588.

The

i

applicable requirements fo' Catawba Units 1 and 2 are - NUREG 0588,

Category II.

A final rule on environmental qualification of electrical equipment

important to safety for nuclear power plants became effective on

February 22, 1983. This rule, 10 CFR 50.49, specifies the requirements to

be met for demonstrating the environmental qualification of electrical

equipment important to safety that is located in a potentially harsh

environment.

This rule also states that equ;pment which was previously

qualified in accordance with NUREG 0588, Category II need not be

requalified to 10 CFR 50.49.

'

To document the degree to which the environmental qualification program at

Catawba complies with the NRC environmental qualification requirements and

,

criteria, the licensee provided equipment qualification information by

'

letters dated June 17, 1982, and February 7, February 8 April 25 May 14,

'

and June 6,1984, to supplement the infonnation in FSAR Section 3.11.

>

,

The three categories of electrical equipment that must be qualified in

accordance with the provisions of 10 CFR 50.49 are:

1

,

i

a

a.

safety-related electrical (equipment relied to remain functional

j

during and following design-basis events),

b.

non-safety-related electrical equipment whose feilure under the

'

postulated environmental conditions could prever.t satisfactory

,

-

accomplishment of the safety functions by the safety-related

equipment, and

c.

certain post accident monitoring equipment (RG 1.97, Categories 1

and 2 post-accident monitoring equipment).

The staff reviewed the adequacy of the Catawba environmental qualification

i

program for electrical equipment important to safety as defined above.

The results of the staff's evaluations were documented in Safety

3

Evaluation Report, NUREG-0954. Supplements 3, 4, 5 and 6 in Section 3.11.

i

j

The status of the licensee's compliance to Regulatory Guide 1.97 for

post-accident monitoring equipment is addressed in Supplements 4 and 5 of

'

the Safety Evaluation Report for Units 1 and 2.

j

This inspection reviewed the licensee's implementation of a program to

meet the requirements of 10 CFR 50.49 and corrective actions on previously

identified EQ issues.

l

!

i

E---------------

-

- - . - - - - - - - - - - - - - - - - -

- - - -

- - - -

- --

.- -

---

-

- - -

.

'

.

..

6

6.

Findings

The NRC inspectors examined the licensee's program for establishing the

environmental qualification of electric equipment within the scope of

10 CFR 50.49.

The program was evaluated by physical inspection of EQ

equipment, examination of the EQ files, interviews of personnel involved

in EQ activities, review of procedures for controlling the EQ Master List,

and examination of the licensee's maintenance program for maintaining the

qualified status of the covered electrical equipment.

Although some significant EQ deficiencies were identified and are being

considered for enforcement,

the inspection team determined that Duke has

implemented a program to meet the requirements of 10 CFR 50.49 for the

Catawba Nuclear Station.

The root cause of the deficiencies identified

may be related to the lack of adequate EQ training for Catawba plant

personnel. The area of EQ training is discussed further in paragraph 6.h.

-

A more detail review of maintenance; IE Notices and Bulletins; EQ

procurement; EQ master list; EQ files and walkdown results are discussed

in the paragraph's that follows:

a.

EQ maintenance Program

The EQ maintenance program review was conducted by reviewing

maintenance procedures, EQ maintenance requirements, equipment

histories, and preventative maintenance schedules. The sampling also

included work requests and replacement of equipment at the end of

qualified life.

During the plant walkdown portion of the inspection, several EQ

discrepancies were identified that could be attributed to inadequate

maintenance practices.

One maintenance related item was found on a

NAMC0 limit switch and is discussed in paragraph 6.i.(18).

Another

maintenance related item involved Limitorque actuators with T drains

plugged with paint.

This is discussed further in paragraph 6.i.(15).

The cause for these and other maintenance EQ deficiencies appear to

be the result of inadequate or lack of training provided to site

personnel.

With the exception of the above discrepancies, the licensee has

implemented an acceptable EQ maintenance program and, by strict

procedure compliance, is maintaining equipment in a qualified state.

b.

Inspection and Enforcement Notices (IENs) and Bulletins (IEBs)

IE Notices are handled by the Nuclear Production Department in

accordance with D,rective No. 4.8.1(s), Revision 0,

"Operating

Experience Program Description."

The General Office Licensing

section is responsible for any other NRC generated documents (i.e.,

Bulletins, Generic Letters, and etc.).

Prior to 1987, the licensing

section handled all NRC documents.

. . -

'

' . .

s

7

,

A walkthrough of the directive provided assurance that notices

1

affecting EQ would be addressed properly.

It also included

discussions of how the various organizations and sections would

interface to resolve any EQ issue.

Based on the review and walkthrough of the directive, it is concluded

that the licensee has a program for distributing, reviewing, and

evaluating IENs and IEBs relative to equipment within the scope of

10 CFR 50.49.

Specific IENs examined were:

IEN 86-03, 86-53, and 84-90.

c.

Environmental Qualification Master Equipment List

The methodology used by the licensee to determine which equipment

items require qualification is detailed in Section II.4.5, Paragraph

4.1 of Design Engineering Department Manual, latest revision dated

'

January 31, 1986.

This procedure requires that safety-related

equipment located in a harsh environment, as defined in the Environ-

mental Qualification Criteria Manual, and required to mitigate the

consequences of the accident causing the harsh environment be

environmentally qualified.

In addition, any safety-related or

i

non-safety-related electrical equipment whose failure under the harsh

environmental parameters experienced during design basis accidents,

would degrade safety systems or mislead the operators are also

j

required to be environmentally qualified.

Post accident monitoring

i

equipment located in a harsh environment is also covered as shown in

Duke Power Company's response to Regulatory Guide 1.97.

i

The list of environmentally qualified equipment is contained in

i

Duke Power Company, Catawba Nuclear Station response to NUREG 0588,

document CNLT-1780-03.02.

This document identifies the safety-

related electrical equipment located in a harsh environment by

generic type, manufacturer, and model number along with its worst

<

case qualification requirements.

Equipment specific tag numbers are

listed in Tabs A through C of the Equipment Qualification Reference

Index,documentCNLT1780.03-1(Rev 6).

Both documents are controlled and updated in accordance with the

normal design control process.

To assess the completeness of the list, the Safety Injection System

was selected for review.

The following flow diagrams and the FSAR

were reviewed to determine the system comp (onents such as Motor

Operated Valves (MOVs), Solenoid Valves

S0Vs), motors and

instrumentation that are required to bring the plant to a safe

shutdown condition:

CN-1562-1.1 Rev. 5

CN-1562-1.2 Rev. 5

CN-1562-1.3 Rev. 4

-

,

t,

8

All items noted as requiring qualification were included on the

licensee's equipment list.

The only deficiency identified with the

EQ master list related to a failure to identify some EQ equipment

that becomes submerged during design besis accidents.

This item is

discussed further in paragraphs 6.i.(2) and 6.i.(3).

d.

Cable Identification

During the plant walkdown the inspectors identified cable ID numbers

from cable connected to EQ devices to the licensee so that

traceability could be established to the cables identified on the EQ

list.

In all cases the licensee was able to identify the cable by

manufacturer, cable type, manufacturer order number and cable reel

number and could show the applicable test report for that cable type

was included in their qualification files.

No further questions were

asked in this area.

e.

EQ Equipment Replacement and Spare Parts Procurement

The Environmental Qualification Reference Index (EQRI) procurement

section specifies the administrative controls applicable to the

procurement of equipment within the scope of 10 CFR 50.49.

It

provides for the procurement of new equipment, direct replacement

parts and components, and upgraded procurement in accordance with

the requirements of 10 CFR 50.49(1).

In addition, it provides

administrative controls applicable to the procurement of comercial

grade items and establishes limitations on their use.

Station Directive 2.4.1,

"Purchasing of Materials, Labor, and

Services" describes the procurement process and establishes require-

ments for performance of EQ Reviews of QA Condition 1 procurement

documents.

EQ equipment is procured as QA Condition 1 to ensure

that quality requirements such as applicable tests and vendor-

supplied quality records are specified on the purchase requisition.

The QA organization reviews all QA Condition 1 procurement documents

to verify inclusion of quality requirements on the procurement

documents.

Additionally, the requirements of 10 CFR 21 are imposed

on these procurement activities.

Technical requirements for new procurements are defined during

l

the design-engineering process.

Information such as applicable

i

'

specifications, drawings, codes and standards and EQ requirements

are documented on the purchase requisition.

i

Upgraded procurement in accordance with the requirements of

10 CFR 50.49(1) are perfomed within the controls of the design-

engineering program.

Design Engineering Department Manual, Section

11.4.9, "Equipment Replacement Summary Form", provides specific

l

l

.

.

.

.

.

. .

. .

.

.

.

'

.

,

9

guidance for documenting the process by which a detennination is

reached to upgrade EQ equipment.

Additional guidance is provided in

the EQRI, "Guidelines for Completing Spares Evaluation and Equipment

Replacement Summary", for performing an annual evaluation to assess

the need for upgrading spares and replacement parts.

Reasons to the

contrary are required to be documented on the form for procurement

activities not in compliance with 10 CFR 50.49(1).

The procurement of commercial grade items for use in EQ applications

is controlled by the nuclear station modification program.

Specific

guidance on the procurement of comercial grade items for use in QA

Condition 1 applications is provided in Design Engineering Department

Manual,Section II.4.1, "Nuclear Station Commercial Grade Evalua-

tion."

A Commercial Grade Items List consisting of a computer data

base with three categories of commercial grade items have been

established by licensee management.

Responsibilities have been

assigned to the Design Engineering organization for performing

commercial grade item evaluations.

Additional requirements for

conditioning (i.e., dedication) prior to use and restriction in use

of the various categories have been established.

The inspector reviewed purchase requisitions and/or purchase orders

for various equipment types within the scope of 10 CFR 50.49.

No EQ

related deficiencies were identified.

f.

QA/QC Interface

Pursuant to discussions with on-site QA organization personnel, the

inspector determined that surveillances had been performed on plant

detivities with a potential for degradation of the environmental

qualification of plant equipment.

Typical of these surveillance is

surveillance No. CN-87-16, Electrical Enclosures - Environmental

Qualification.

This surveillance was conducted from March 23 to

April 3,

1987, and involved an assessment of the problem of

improperly secured NEMA 4 electrical enclosures documented on Problem

Investigation Report (PIR) No. PIR-1-C86-0061.

Other PIR's and

surveillance reports prepared by site QA personnel and/or Nuclear

Production Department (NPD) personnel were reviewed to assess the

adequacy of-the corrective actions developed for EQ related problems.

No deficiencies were identified during this review.

The Corporate QA organization performs audits of the Operational QA

program in accordance with the requirements of the Technical

Specifications.

Interviews with staff members revealed that the

following audit of the environmental qualification program were

performed from July 22 - September 20, 1985, Audit No. SP-85-2 (GO),

Environmental Qualification of Electrical Equipment.

The scope of

the audit included EQ records, station maintenance, personnel

',

.

10

qualification and training, procurement activities, station modiff-

cation, document control and records management, and QA and QC

inspections.

Deficiencies identified and documented in the audit

report for Catawba were discussed. with . licensee management.

The

inspector performed a review of selected developed corrective action

plans for the identified deficiencies.

No EQ related problems were

identified during this review.

The inspector detennined from additional discussions with licensee

management that the audit schedule does not specifically provide for

audit of the EQ program.

Instead, EQ related activities and/or EQ

program requirements are included within the scope of the audit if

they fall within the performance area being audited.

The following

audits were reviewed by the inspector pursuant to this discussion;

Departmental Audit SP-86-1 (MM), Material Control, and Departmental

Audit ' DE-87-03 (ALL), Design Engineering.

No violations or

deviations were identified in this area.

g.

EQ Modification Program

Station Directive 3.3.12, "Equipment Qualification Program," speci-

fies the program established to ensure equipment within the scope of

10 CFR 50.49 is qualified, and assigns responsibilities to the Design

Engineering organization for maintaining the EQRI (CNLT-1780-03.01

andCNLT-2780-03.01) through the station problem report (SPR) program.

Station problem reports may be dispositioned within the controls

of the nuclear station modification program.

The Nuclear Station

Modification Manual, revision 5, is the controlling procedure for

the preparation and implementation of Design Change Packages (DCPs)

prepared by either the site engineering organization or the corporate

engineering office.

This manual specifies the design controls that

ensure applicable regulatory requirements and design bases are

correctly translated into specifications, drawings, procedures, and

instructions to form a DCP.

Considerations of the environmental

qualification requirements of equipment to be installed via a design

change is included as a design input to the design process.

The Design Engineering Department Manual. Section

11.4.5,

"Environmental Qualification of Electrical Equipment", and Catawba's

Environmental Qualification Criteria Manual provide specific guidance

to the responsible engineer regarding environmental qualification

considerations such as equipment location and environmental

parameters.

The design process further provides for the update of

vendor technical manuals and shop drawings upon implementation of a

,

DCP.

The Environmental Qualification Reference Index (EQRI) which

specifies maintenance requirements, replacement schedules, and other

controls necessary to ensure continued EQ status is also updated to

,

reflect equipment changes caused by plant modifications.

I

_ _ _

l

._.

'c

1,.

11

The inspector reviewed two design changes (Variation Notices Serial

No. CE-1564, and CE-1237) prepared by the site engineering

organization that involved EQ equipment. No EQ related deficiencies

were identified during this review,

h.

EQ Personnel Training

The Employee Training, Qualification, .and Safety, (ETQS) program

provides for training of craft personnel in specific task.

The

employee is trained to a procedure which is written .to be task

specific.

Discussions with the Training Manager and other licensee

personnel revealed that training in the requirements of Catawba EQ

Program had not been provided to Nuclear Maintenance I&E, or site

QA/QC staff members.

The NRC EQ inspection at McGuire in July 1986

identified similar training deficiencies.

Licensee management, as

part of their corrective action, reviewed this inspection finding for

generic application to other operating facilities.

They determined

that similar EQ training deficiencies existed at Catawba.

Review of an I&E working group meeting minutes dated November 4,

1987, showed that the EQ lesson plan developed for McGuire had been

transmitted to Catawba for review by site personnel who would

detennine its applicability at their location.

Additionally, from

discussions with site personnel it was determined that the Catawba EQ

1esson plan is scheduled to be completed by March 15, 1988.

The issue of providing EQ training to Nuclear Maintenance I&E and

site QA/QC personnel was addressed at the exit interview and the need

for timely corrective action was emphasized.

The Corporate QA organization performed an audit of the EQ program

for electrical equipment during July 22, 1985 to September 20, 1985.

1

The results of this audit are documented in Departmental Audit

No. SP-85-2(G0) dated September 24, 1985. Audit finding SP-85-2(G0)(3)

identified a deficiency in training of design engineering personnel.

j

In response, the Design Engineering Organization committed to develop

i

'

and implement a formal training class on the requirements of the EQ

program. The inspector reviewed various correspondence on this subject

and conducted interviews with engineering personnel.

It was determined

that engineering personnel had participated in Electrical Power

Research Institute (EPRI) training sessions on environmental qualification

'

of equipment. However, objective evidence was not presented to document

implementation of the EQ training to which.the Design Engineering

organization had comnitted. A memo-to-file dated April 8,1987, from

R. J. Smith, Design Engineer, documents plans to establish an annual

training program beginning in 1988.

Discussions with the Corporate QA organization personnel revealed

that training in the requirements of the EQ program for McGuire,

Oconee, and Catawba had been given by an outside consultant.

This

-

-

.-

..

_

_

.-

' . .

'.

12.

training session titled, "Training Seminar on Equipment Qualification

and Replacement Parts and Equipment," was given on December 7 and 8,

1987.

Review of objective evidence further showed that select staff

members from the Catawba site had also been trained in' the

requirements of the EQ program on August 26, 1986.

In summary, the licensee was aware of the weaknesses in the EQ

training program for selective personnel and is now vigorously taking

steps to improve their overall EQ Training Program to be more in-line

with industry standards and NRC requirements,

i.

EQ Documentation Files and Walkdown Items

The required qualification level for Catawba Units 1 and 2 original

10 CFR 50.49 scope equipment is NUREG 0588, Category II, "Interim

Staff Position on Environmental Qualification of Safety-Related

Electrical Equipment."

The replacement equipment is required to

meet the requirements of 10 CFR 50.49 or reasons to the contrary

must be documented.

The EQ documentation is composed of Master

Equipment List (0588 Submittal), Environmental Profiles and the

Central file.

The Central File contains EQ Test Reports; Report

Evaluation Checklists and Summaries; System Component Evaluation

Worksheets (SCEW); EQ Component Lists with Maintenance and Procure-

ment Requirements (EQRI); and other supporting documentation.

The licensee's generic EQ files were reviewed in detail against

the requirements of the rule to determine if qualification had

adequately been established and to determine if records were main-

tained in an auditable fashion.

Some of the EQ files were found

to be deficient requiring additional analysis to establish qualifi-

cation. These deficiencies are identified as Violations 413/88-07-01

)

and 413, 414/88-07-05 and are discussed in Paragraphs 6.i.(19) and

j

6.i.(3), respectively.

The inspection team considered item 01 to

'

be fully qualifiable with the information developed during the

inspection. Thelicensee provided supplemental information on item 05

subsequent to the inspection which indicated that this item may also

be qualifiable. For more details on this item, see Paragraph 6.i.3.

The NRC inspectors examined files for approximately 20 equipment

items, where an item is defined as a specific type of electrical

equipment, designated by manufacturer and model, which is

representative of all identical equipment in a plant area exposed to

the same environmental service conditions.

In addition to comparing

plant service conditions with qualification test conditions and

verifying the bases for these conditions, the inspectors selectively

reviewed areas such as (1) required post-accident operating time

compared to the duration of time the equipment has been demonstrated

to be qualified, (2) similarity of tested equipment to that installed

in the plant (e.g., insulation class, materials of components of the

equipment, test configuration compared to installed configuration,

.

.

.

..

13

and documentation of both), (3) evaluation of adequacy of test

conditions, (4) aging calculations for qualified life and replacement

interval detennination , (5) effects of decreases in insulation

resistance on equipment performance, (6) adequacy of demonstrated

'

accuracy, (7) evaluation of test anomalies, and (8) applicability of

EQ problems reported in IEBs/IENs and - their resolution.

Although

deficiencies were identified with the EQ Master List and EQ component

qualification files, overall, a majority of the EQ files were

auditable and documented qualification of. the equipment.

The

following comments on both EQ records and walkdown items are

considered the most significant findings.

(1) Joy / Reliance Fan Motors

During the review of the qualification file for Joy / Reliance fan

motors,

file CNM-1211.00-1009, the inspector noted in

Section I .1.1 Part 5, Rev.1 dated August 29, 1986 of the

Equipment Qualification Reference Index that the installation /

mounting of the Joy / Reliance Fan Motors be accomplished per

reference document CNM-1211.00-1065.

This technical manual,

supplied by the vendor, requires the use of breather drains on

the bottom of the main conduit box and the low point of the

motor.

During the walkdown of this equipment the inspectors

noted that there were no breather drains installed on the

Hydrogen Skimmer Fans for Unit 2 (Tag Numbers HSF 2A and

HSF28).

Further conversation between the licensee and the

vendor on February 4,1988, File No. CN-1211.00-19, show that

the Reliance Fan Motors were qualified with the drain breathers

installed and that in containment applications should have them.

Normally, these devices are installed by the vendor prior to

shipment.

However, the licensee had to replace both motors

after initial installation.

Apparently, when the new motors

were installed, the drain breathers were not removed from the

old motors and put into the new motors as required. The failure

to have adequate documentation in the file, at the time of the

inspection, to support qualification of the fan motors without

the drain breathers installed is a violation of 10 CFR 50.49 (K)

and NUREG 0588, Category II, Section 5.(1).

This item will be

identified as Violation 50-414/88-07-04, Joy / Reliance Fan Motors

not installed in accordance with the tested configuration.

(2) RDF Corporation Wide Range Resistance Temperature Detectors EQ

File No. CNM 1399.03-0328

The qualification basis for these RTDs was NUREG-0588

Category II.

Westinghouse's WCAP 8587 was used to qualify the

RTDs.

The test conditions enveloped the plant requirements and the

test specimens was similar to the equipment to be installed.

The functional test did indicate that the insulation resistance

-

-

. - _ - ________

_

l

'.

.

14

I

of the splice was on the order of 10 K-ohms (worst case). This-

insulation resistance resulted in a 8.57% error on the high

temperaturerange(DukePowercalculations). The test specimens

did not have a protective casing and were directly sprayed with

water.

This was the major cause of 10X-ohm reading.

The RTDs

installed at Catawba were supposed to have a protective casing

consisting of a stainless steel bellows hose with a stainless

steel overbraid which was to be terminated in a sealed

enclosure.

During the installation, however, the installer cut

the steel ' bellows hose off and connected the uncovered RTD

cables into the vapor tight box, thus, leaving an unsealed

connection at the box.

On November 5,1987, it was discovered

by a Duke Power engineer that Catawba Unit 1 Reactor Coolant

System W/R RTD's cable termination junction boxes were not

sealed.

On November 13, 1987, following a review of the

problem, the station management was notified of the possible

inoperability of both units hot and cold leg W/R RTDs.

Both

Catawba units have operated in all modes of operation with the

affected W/R RTDs being technically inoperable before corrective

measures were implemented. This was reported to the NRC since the

affected Units 1 and 2 W/R RTDs had been unknowingly technically

inoperable in excess of the time limit specified in the

technical specification (see LER 413/87-43).

In response to NUREG-0588 dated March 1984, Duke Power stated

that the RTDs were hermatically sealed units with Flexonics Type

401 H stainless steel hydrostatic hose covering the RTD leads.

Additionally, the RTD leads terminate to the field cables above

the maximum post accident flood level thereby precluding a

submergence problem with the RTD terminators.

A walkdown verified that the RTDs were not installed in

accordance with the design drawings nor in accordance with the

tested configuration in that the sealed bellows hose had been

removed, the junction box was below submergence level, and the

junction box was not adequately sealed.

The failure to install

the RCS wide range RTDs in accordance with the qualified tested

configuration is considered a violation of 10 CFR 50.49.

This

'

item is being identified as Violation 50-413, 414/88-07-02, RCS

Wide Range RTDs Installed in an Unqualified Configuration.

The problem that existed in Unit 1 RTD junction boxes has been

corrected by completely filling the boxes with qualified epoxy

(Scotchcast 9) and replacing the RTDs with new RTDs. that have

the leads covered with stainless steel bellows hose with a

stainless steel overbraid.

The epoxy filled boxes now

completely cover the Raychem splices, thus reducing the

possibility of any leakage current.

The affected Unit 2 RTD

junction boxes will be sealed with epoxy or replaced with

environmentally qualified (sealed) junction boxes.

It was

i

J

_

.

^

.

..

.

15

determined that the fix for these RTD junction boxes is fully

qualified for their application at Catawba, after reviewing

qualification documents supplied by Duke Power Company.

No findings were identified with the file for the W/R RTDs.

(3) Minco Resistance Temperature Detectors (RTDs), EQ File

No. 1399.03-0357

The inspector reviewed the file for the Mir.co RTDs Numbers S8809

and S8810.

The qualification basis was NUREG-0588 Category II.

The Westinghouse WCAP Report 8587 was used to qualify these

units.

The test specimen was identical to the installed

equipment and the plant profile was enveloped by the test. The

minimum allowable insulation resistance measurements were within

the range to guarantee a functional accuracy of 1.0*F.

Minco Model S8809 and S8810 Resistance Temperature Detectors

(RTDs) are used for temperature / density compensation for the

impulse lines of the reference and variable legs of the reactor

vessel level indication system (RVLIS).

The inspector was not

able to physically examine the termination ends of these RTDs

as desired due to time constraints.

Therefore, the inspector

requested Duke to provide documentation as to the location of

the RTD junction boxes with respect to the DBE submergence

level in their vicinity.

Duke was unable to provide such

documentation stating that there were no drawings that showed

'

the exact installed location of the junction boxes for the

Hinco RTDs.

Duke further stated that since the EQ

documentation contained a letter from Westinghouse stating that

the termination ends of these RTDs should be above flood level,

Duke had purchased them with extra length of stainless steel

sheathed mineral insulated cable to accommodate their

installation above flood level.

They also stated that a site

engineer had personally supervised the installation of the

junction boxes and routing of the RTD cable and termination

.

ends to ensure they were installed above flood level.

Nevertheless, Duke reported subsequent to the inspection that

"

they had walked down the RTDs and had found some junction boxes

and termination ends below DBE submergence level.

Duke also

developed and provided to the NRC shortly after the inspection

information that indicated that the Minco RTDs were qualifiable

for submergence.

After review of the information developed,

the NRC inspector received verbal confirmation from Duke as to

the results of the evaluation of the EQ test parameters being

used with respect to Catawba DBE conditions including

submergence and evaluation of EQ test performance data with

respect to the functional performance requirements of the

specific Catawba application of the RTDs.

Duke determined that

the tests were usable to support qualification of the RTDs for

.

-

-

-

-

-

.

-

-

-

-

-

- -

-

' ' .

..

16

submergence in that test perfonnance data was acceptable for the

plant specific applications and test environmental parameters '

enveloped Catawba DBE environmental - parameters with sufficient

margin with the exception that the temperature of the water in

the long term water absorption tests at 160*F did not envelope

the peak Catawba submergence water temperature of 190*F.

The ovarall approach to this qualification was a combination

of type testing and analysis based on similarity of the RTD

termination end to a submergence qualified conduit seal and on

loss-of-coolant-accident (LOCA) and long term water absorption

data on the wire of which the RTD external lead wires were made.

Duke had compiled data that indicated that the predominant

factor in determining the degradation of the wire's insulation

resistance (IR) (the functional performance variable of interest)

was temperature.

The data indicated that identical and similar

insulation materials of the same and different manufacturers

consistently behaved similarly in terms of IR and variation of

IR with temperature was consistent with that expected with the

materials in question.

The effects of submergence and water

absorption were observed to be no more significant than LOCA

effects except for temperature.

Since the variation of IR

with temperature was relatively predictable and there was

consistent and bounding data from the RTD LOCA test, Duke

determined the IR at 190 F analytically by interpolation between

the data at 160 F and LOCA temperatures and noted that the irs

had been acceptable at LOCA temperatures for the application.

This method of qualification provided reasonable assurance of

satisfactory post-DBE submerged performance of the RTDs and

after consultation with other knowledgeable NRC staff as well

as NRC technical consultants, the inspector found it to be an

acceptable approach.

However, the EQ documentation files at the time of the inspec-

tion did not have such additional data and analyses as it was

not originally intended to show submergence qualification for

the termination ends and external lead wires of the RTDs because

they had been designed to be terminated in junction boxes above

flood level.

Having some RTDs terminated below flood level

rendered the EQ documentation deficient in that qualification.

for submergence had not been demonstrated.

This constitutes a

violation of NRC regulations pertaining to EQ as specified below

and is identified as Violation 50-413,414/88-07-05, Inadequate

Documentation for Qualification of Minco RTDs.

(4) Rockbestos Firewall III Coaxial Cable EQ File

No. CNM-1354.00-0077

The qualification basis for this cable was NUREG-0588,

l

Category II.

The cables inside the Reactor Containment were

second and third generation, with the third generation

!

.

o.

6*

17

qualification test report and the Rockbestos similarity analysis

for second generation cables used for qualification. The plant

profile was enveloped by the_ test conditions. No findings were

identified.

(5) Brand-Rex Instrument Cable EQ File No. CNM-1354.00-0070

The qualification basis for this cable was NUREG-0588, Category

II.

The cables are used inside and outside the containment

for power, control, and instrumentation.

The file contained

,

Franklin Test report F-C5120-4 dated January 11, 1982.

The

tested specimens had the same materials as the installed cable

with an analysis to qualify other sizes of cable.

The test

conditions enveloped the plant profile.

No findings were

identified.

(6) Rockbestos Firewall (FW) III Chemically Cross-Linked Polyethylene

(XLPE) Cable, EQ File No. CNM-1354.00-0069

The qualification basis for this cable was NUREG-0588, Category

II.

The cable specimens tested used the same insulation as

the installed cables.

The test conditions enveloped the plant

requirements and the cable passed mandrel bend and high poten-

tial testing following the DBA.

The package iricluded the

current Rockbestos test report.

No findings were identified.

(7) Okonite Flame Retardant, Cross-Linked Polyethylene (XLPE) Cable

EQ File No. CNM-1354.00-0063

The qualification basis for this cable was NUREG-0588, Category

II.

A number of different sizes are installed inside and out-

side containment.

All cables installed inside containment are

run in conduit.

The installed cables are identical to the

test specimens with the exception of sizes.

The test environ-

ments enveloped the plant accident profile and the cables had

satisfactory insulation resistance and all passed the withstand

test.

No findings were identified.

(8) Rockbestos Firewall III Irradiation Cross-Linked Polyethylene

(XLPE) Insulated Low Voltage Power, Control, and Instrumentation

'

Cable EQ File No. CNM-1354.00-0072

The qualification basis was NUREG-0588, Category II.

One

concern was identified with this cable file.

The cable was

listed as above flood level.

However, during the review it

was learned that the cable would be submerged.

This issue

was resolved before the end of the inspection changing the

qualification documents to show that the cable would be

submerged and placing submergence qualification dccuments in

the file for this cable.

- - -

-

. ' .f..

18

The current Rockbestos report on radiation XLPE cable was

included in the file.

The plant conditions are . easily enveloped by the test.

The

installed cables were identical to the tested cable.

No

findings were identified.

(9) Rotork Motor Operated Valve Actuator (Model NA-1, Pre-1978),

File No. ChH-1205.19-65

The actuators covered by this file are qualified by a combina-

tion of type tests and similarity analyses in accordance with

the requirements of NUREG-0588, Category II.

The actuators

are required to be operational for 10 days post-accident.

The

qualified life is 40 years with periodic surveillance of the

oil.

Several concerns were discussed with the licensee and were

adequately resolved.

First, the EQ file was comprised of many

individual test reports, rather than a single qualification

document.

It was not clear that the licensee had reviewed and

approved all of these reports as the basis for qualification of

!

'

the NA-1 actuators.

The licensee explained that in order to

'

comply with the requirements of IEEE 382-1972, Rotork undertook

a complete qualification test program for a model 16NA actuator.

'

The results were documented in TR-116 which became the parent

document for various other test reports (43152-1, TR-334,

TR-408, TR-222, TR-404, and TR-178).

The combination of these

'

test reports applies to the Rotork NA-1 actuators shipped to

Catawba before 1987.

The letters of correspondence between the

licensee and manufacturer were included in the EQ file.

The

'

3-tier signature approval sheet verified that the EQ file was

complete.

This was acceptable.

Second, the basis for qualification by similarity was not

i

readily apparent.

The licensee explained that all of the

"A"

range actuators are constructed of the same materials and are

based on the same design.

The electrical properties, stress

levels, clearances, etc. for the 7NA through 90NA actuators are

similar to the 16NA actuator that was tested. Applicability of

the test reports as the basis for similarity was addressed in

document: AE1/4 and NA1.

These documents were briefly reviewed

and found to be acceptable.

The walkdown inspection was perfonned on equipment tag number

2ND0002A.

The actuator assembly was found to be partially

disassembled; the covers were removed from the terminal box and

switch enclosure, the motor was laying on its side on top of

,

'

some adjacent pipes, and oil was spread everywhere. There were

V ,.

.

19

no tags visible to indicate that work was in progress, although

tools were found next to the valve. The manufacturer nameplate

was read and found to match the master equipment list

description except for the lubricant Nucleol 528.

The nameplate identified Nucleol 528 as the lubricant, although

the electricians stated that Spartan EP150 was used for all

Rotork actuators regardless of the nameplate.

During the file

review, the licensee provided the Rotork maintenance manual and

Catawba preventive maintenance procedure for review. The review

confirmed that Rotork recommends either Spartan EP150 or Castrol

Nucleol 528 and that Catawba uses EP150 only.

This was

acceptable.

Internal inspection of the terminal box identified a concern

that was resolved during the audit.

There were six wires from

field cable 2ND20 that were found to be cut off inside the

terminal box.

The cut ends of the wires were not taped over and

the conductors were visible.

The licensee performed an

investigation and verified that the other end of the cable was

grounded, and did not carry any load. This was acceptable.

The partial disassembly of the Rotork actuator for Valve 2ND2A

was discussed with the licensee during the EQ audit.

The

licensee performed an investigation of this matter and issued a

Problem Investigation Report (PIR 2-C88-0048).

The progress of

the investigation is summarized below.

f

The Rotork actuator was found with its motor completely

separated from the actuator gearcase.

The separation

occurred at the bolted flange connection between the motor and

gearcase.

The bolt holes in the replacement motor flange are

larger than the original motor.

There was insufficient load

bearing surface on the flange which allowed the motor operator

to separate from the valve gear box when an extremely high

(stall) torque was applied.

The stall torque condition occurred

after the torque switch had been jumpered out (personnel

.

Judgement error).

All work on the valve was stopped at that

!

time pending an investigation,

i

The licensee determined that the failure mechanism occurs if the

valve is taken :s stall conditions. The licensee evaluated the

various valves using Rotork actuators and determined that the

two valves (NV9 and NV10) with the highest potential torque are

not vulnerable to this problem because they do not have the

subject replacement motors.

The investigation reduced the

population of valves with the subject motor to two (1WL805A and

2NV89A).

Both valves go to the closed position in an accident

and are not required to reposition.

i

l

_

..

c',.

.

20

The investigation war, still in progress at the conclusion of the

EQ audit.

The licensee will assess adequacy of the bolted

flange connection and training of maintenance personnel.

The

licensee has discussed the matter with the NRC Resident

Inspector, who will track the investigation.

This issue has

been transferred to the NRC Resident Inspector for tracking and

closure.

No unresolved /open items were identified during the file review

or walkdown.

(10) Rotork Motor Operated Valve Actuator (Model NA-1, Post 1978),

File No. CNM-1205.66

The actuators covered by this file are qualified by a

combination of type tests and similarity analyses in accordance

with the requirements of NUREG 0588, Category II. The actuators

are required to be operational for 10 days post-accident.

The

qualified life is 40 years with periodic oil checks.

The post-1978 actuators are nearly identical to the products

shipped prior to 1978 except for the switch mechanism.

The

post-1978 design uses an electronic latching mechanism on the

torque switch while the pre-1978 design uses a mechanical latch.

Both switch mechanisms are made from the same material.

Both

switches have been tested to meet the required parameters.

The basis of qualification of the post-1978 actuators was a

general test plan to meet the intent of the October 1978 draft

of IEEE 382.

Rotork undertook a complete qualification test

program for actuator models 11NAZT1 and 90NAZT1.

The results

were documented in TR-4379-1, 43979-3, and 58364 for actuators

shipped to Catawba after 1978.

Additional test reports were

included to address steam impingement and confirmation of

operability for specified seismic loads.

The qualified life

(41.5 years) was determined by accelerated thermal aging tests

(140'F and .8 ey activation energy).

The walkdown was performed on valve number 2N000037A.

The

nameplate was consistent with the EQ file data.

Visual

inspection of the terminal box and switch enclosure did not

identify any concerns.

The connections were secure, wires were

labelled and in good condition; Rockbestos jumper wires were

used, and the electrical cab s connection appeared to be

properly installed.

No violations or unresolved items were discovered during the

file review or component walkdown.

-

-

-

-.

. _ - _ - _

8

,g

g.

21

(11) Rcsemount Transmittar 1153 Series B, File No. CNM-1210.04-0262

The transmitters covered by this EQ file are qualified by a

combination of type tests and similarity analyses in accordance

with the requirements of NUREG-0588 Category II.

The

transmitters are required to be operational for 1/2-hour post-

accident.

The 10-year qualified life was based on the results of thermal

aging tests using 125 C internal temperature for '38 days and

an activation energy of .78 ev.

The Equipment Qualification

Reference Index (EQRI) was reviewed and verified that the

replacement and maintenance activities were consistent with

the results of the qualification report.

Several concerns

were discussed with the licensee and adequately addressed.

First, the licensee was asked to verify that the spare cable

entrance is properly environmentally sealed.

The Duke Power

specification CNS-1390.01-0167 required the spare cable entrance

to be sealed.

The specification references the Rosemount

,

instruction manual CNM-1210.04-0245 which includes the same

sealing requirements. Second, Rosemount Report 108026 paragraph

15.4.1 describes a failure of the fill tube closure solder for

the high static pressure housing.

The recommended fix was to

spot weld the fill tube.

The licensee contacted Rosemount, who

stated that the fill tube qualification fix was implemented

prior to the sale of any high static pressure design units. The

supplemental tests were completed and referenced in Rosemount

reports 108025, Revision D, paragraph 7.1.9 and Report 88114.

Due to limited review time these latter reports were not

reviewed.

However, the record of conversation between the

licensee and the vendor, was reviewed and was acceptable.

The licensee's response to IE Notice 85-100 was reviewed.

In

it, the licensee stated that corrective action has been taken to

compensate for the zero shift in transmitter output due to high

,

static pressure.

The new Rosemount instruction manual has

i

'

already been issued for Catawba.

(12)

Rosemount Transmitter Model 1153DB

A walkdown inspection was performed on two Rosemount 1153DB

transmitters, namely tag numbers 2NVLT5740 and 2NVLT6070.

The

Catawba tag numbers were verified by the embossed metal labels

attached to each transmitter.

However, both manufacturer

nameplates were missing.

There were no marking to positively

identify the model type as 1153DB. This concern was brought to

the licensee's attention.

)

1

4

--,___________________m.

.

..

22

The licensee explained that the equipment tag number is a unique

identification used for tracking all document records.

Due to

the limited audit time, the licensee was unable to present a

review copy of the receipt inspection records which tie the

manufacturer nameplate to the Catawba tag number. The licensee

committed to perform a field inspection of the two transmitters

to confirm the model type, to restore their nameplate data, and

to survey a representative sample of all models of Rosemount

transiaitters to ensure that the miss.ing nameplate concern is an

isolated case.

Subsequent to the inspection the licensee

provided a copy of a Receiving Inspection Report which shows

that the transmitters are model 1153D84 which are qualified by

their Master EQ List.

(13) Barton Transmitter Model 764 (B0P), File CNM-1210.04-0261

The transmitters covered by this file are qualified by a combi-

nation of type tests and similarity analyses in accordance with

'

the requirements of NUREG 0588, Category II.

The transmitters

are required to be operational for 1/2 hour post accident. They

are located in various harsh environments inside the auxiliary

building, reactor building, and dog house.

The review of the EQ files included the following reports:

ITT Barton Report R3-764-9, "Class 1E Qualification Test

Program and Results for ITT Barton Differential Pressure

Electronic Transmitter Model 764," October 1982.

l

'

R3-764-11, "Investigation of 763 and 764 DBE Anomalies."

R3-764-16

"Investigation of Post-LOCA Long Term Severe

,

Environmental Anomalies of Model 764, Class IE Nuclear

Grade Transmitters."

R1-764-57, "Post LOCA Severe Environment Test of Model

764," August 1, 1983.

R3-764-17. "Effects of Temperature on Model 764 during DBE

(LOCA/HELB)."

'

R1-764-H2, "Accelerated Aging of Model 764," August 2,

1982.

Addendum to R3-764-9, December 9, 1983.

c'..

.

23

Several concerns were discussed with the licensee and were

adequately addressed.

First, as reported in Test Report

FR-032175, the lead wire separated at the gland seal of the

housing during the post-test examination of the transmitter.

The recommended fix was to replace the 8-foot copper wire

with stainless steel for added tensile strength and corrosion

resistance.

The licensee was asked to determine how these

suggestions were incorporated into the qualification of the

transmitters.

The licensee determined that the test set-up

method caused an unwanted pressure differential across the wire,

forcing steam and water into the pin area of the gland seal

and along the entire length of the wire.

The installation at

Catawba utilizes a physical discontinuity at the vessel pressure

boundary, resulting in zero differential pressure along the

wire.

Therefore, the licensee considers that the stainless

steel wire does not need to be incorporated into the transmitter

design, qualification, or loop accuracy calculations.

Second, the test report R3-764-9 and Addendum showed that

the

5% error test acceptance criteria for the DBE 5-minute

condition was not met.

The licensee was asked to provide

technical justification for acceptance.

In reply, the licensee

stated that all Balance of Plant (B0P) Barton 764 transmitters

in a LOCA or HELB environment have a 10% accuracy requirement

for environmental effects.

The responses to IE Notices81-029, 82-052, and 83-072 were

reviewed and considered to be acceptable.

The leakage current calculations were reviewed and found to

be acceptable.

The impact of an increased instrument loop

,

inaccuracy due to post-accident cable leakage has been assessed

l

by the licensee for the setpoints used in the station emergency

procedures.

The pressurizer level instrument error was deter-

mined to have increased in the nonconservative direction.

Due

to the magnitude of the instrument error and existing error

allowance, there is no urgent need to reverse the setpoints.

j

The setpoints will be revised on a schedule consistent with

the ongoing emergency procedure maintenance program.

This is

acceptable.

A walkdown inspection was performed on two Barton 386A trans-

mitters, namely 2NILT5260 and 2NILT5270.

The devices were

'

identified by the manufacturer nameplate and Catawba equipment

tag.

The wire splices and cable attachment appeared to be

properly installed.

The Raychem splices were found to be bent

in half to fit inside the conduit housing.

Investigation of the

Raychem splice qualification file determined that the installed

configuration (i.e., small bend radius) was acceptable.

The

junction box for each transmitter could not be easily traced

through the cable tray. However, it was observed that the cable

trays and transmitters were located above flood level.

. .

.

_ - _ _

__

  • , .

,

24

(14) Foxboro Pressure Transmitter Model N-E10 Series TX File No.

.CNM 1211.00-1792

These transmitters are located in mild and harsh environments

'

in the auxiliary building.

The transmitters covered by this.

file are qualified by type tests and similarity analyses to

the intent of IEEE 323-1974 and 344-1975, in accordance with

NUREG 0588 Category 11 requirements.

The EQ file included the

Wyle Test Report 45592-4 for Foxboro N-E10 series pressure

transmitters.

A cursory review of the EQ file was performed.

The file

includes a statement of qualification by similarity on the basis

of materials, mounting method, weight, dimension, center of

gravity, and functional performance.

A complete justification

of similarity is provided in Foxboro Document Q0AAC012.

This

report was not reviewed for lack of time.

The licensee's response to IE Notice 85-52 was reviewed.

The

licensee stated that Foxboro Model E controllers are not used at

Ca tawba.

-

The reviewer noted that radiation exposure for the annulus

filter transmitters exceeded the qualification level 2.0E8 Rads.

The licensee provided a letter summarizing.a pinpoint radiation

analysis for these transmitters.

The highest Total Integrated

Dose was calculated as 3.83E7 Rads. This was acceptable.

(15) Limitorque Motor Operated Valves, EQ File CNS-1205.19-00-0001

The file for Limitorque Valve Actuators SMB/SBD (containment-

type) and SMB (outside containment-type) included the following

reports:

Limitorque Test report B0058, dated 1980.

1

Limitorque Test Report 600376A (App. B), dated 1972.

Limitorque Test Report 600456 (App. C), dated 1975.

Limitorque Test Report 80003 (App. D), dated 1975.

Limitorque Lubrication Data Form LC8.

Limitorque Maintenance Form LC9.

)

.

..

25

In addition to the above test reports, the licensee supplied

for review the following documents pertaining to EQ issues at

Catawba:

Significant Deficiency Report number SD 413-414/84-15,

dated 7/6/84, and associated letters from Duke Power to the

NRC dated 9/11/84 and 12/27/84.

Duke Power maintenance procedures for Limitorque MOVs.

Environmental Qualification References Index (EQRI).

Duke Power internal letter concerning the resolution to IE

Notice 86-71, dated 10/10/86.

Limitorque Hookup Wire Functional Verification, Duke Power

Test Report Number TR-076, (IE Notice 86-03 response),

Installation Specification Manual, "Inspection of Jooer

Wiring in the Limit Switch Compartment of Limitorque KNs."

dated 9/15/86.

During the review of the files the following issues weri

discussed with the licensee. Each issue / concern w s resolve <. "y

the licensee and are presented below.

Are motor brakes (Ding or Inertia) used on Limitorque M0Vs

at Catawba?

No motor braking devices are used.

Are T-drains and Grease Reliefs installed where required?

j

T-drains not installed during initial installation

were installed per Significant Deficiency Report

413-414/84-15.

Subsequently the EQRI was revised

to note the requirement to install T-drains during

actuator installation.

Actuators receiving grease

reliefs are shipped with these reliefs already

installed as required per the procurement orders.

However, walkdown of limitorque operators on Unit 2

identified that paint had been applied over the

drains .

Address IE Notice 79-03 concerning the use of Beacon 325

lubricant in the main and intermediate gear boxes.

Are

there any actuators in an environment of

140'F that

~

contain Beacon 325 lubricant?

There are no Limitorque actuators installed in

locations where normal (non-accident) temperatures

exceed 140'F.

- _ _ _ _

_

W ,.

.

26

What are the procedure for cycling the Limitorque actuators

twice a year as recommended in test report B0058?

All safety-related valves are cycled periodically (as

allowed by nuclear safety or operational criteria) per

the IWV program.

Duke Power considers this item a

'

recommendation rather than a necessity for environ-

mental qualification.

Are any motor or limit switch compartment heaters

installed? If so are they de-energized?

All heaters have been. de-energized per the work

request supplied in response to IE Notice 86-71.

What type of internal wiring (jumpers) are used in the limit

switch compartments?

Duke Power has addressed this issue in their response

to IE Notice 86-03.

All internal jumper wire has been

replaced with qualified Rockbestos or Raychem wire for

in-containment MOVs.

Are there any terminal boards used in the limit switch

compartments?

Inside containment Limitorque MOVs, that are required

for long-term post-accident conditions, utilize

terminal blocks in control circuits only (120 V). All

other Limitorque M0Vs are containment isolation valves

and do not utilize terminal blocks.

Raychem splices

are used in place of connection boards.

Have "Megger" tests been perfonned on the motors and leads?

Megger tests were performed by the Construction Depart-

ment during installation.

Cocumentation is available

at the station and was supplied to the inspector.

Supply documentation identifying the type of cable used to

replace unqualified wire (field run) in the limit switch

compartment as stated in your response to IE Notice 86-03.

Documentation was supplied showing that all unquali-

fied wire installed in the MOVs have been replaced

with qualified Rockbestos or Raychem wire.

The worst-case radiation (TID) parameters for this environ-

mental zone is 6.0E8 rads.

The Limitorques are qualified

to 2.04E8 rads TID.

You have stated that pinpoint analysis

is being conducted to demonstrate a lower required T!D.

Has this analysis been completed?

-

__

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ . _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _

-.-_

_

__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ -

.

=. a o.

,

27

The M0Vs in question are 1YE4, IVE9, 2VE4 and 2VE9.

An evaluation of the TIO for these Limitorque

operators was performed. The results of this analysis

can be found in calculation # CNC-1229.00-00-0014,

Rev. 10, page 2421.

The 're:;ults show that the

worst-case is 1.9E7 TID.

,

'

Provide justification for submergence requirements for

in-containment Limitorque MOVs.

The submergence question is resolved in FSAR, chapter

6.3, page 6.3.2.1.

This states that there is suffi-

cient time for them to close before being flooded.

To prevent possible repositioning after flooding, the

valves motor control circuits have been modified to

prevent any spurious limit switch operation from

repositioning the valves. Also breakers and fuses are

coordinated such that, in the case of faults caused

by submergence, the faulted valve. circuits will be

isolated without adversely affecting the upstream

class IE power sources.

4

!

During the plant walkdown the following Limitorque Motor

Operators were physically inspected:

2KC3648, size SMB-00, with Reliance Motor class RH

insulation.

2KC345A, size SMB-00, with Reliance motor class R

,

i

insulation.

2VX001A, size SMB-000, with Reliance Motor class RH

insulation.

'

The above actuators and motors were inspected to TI 2515/75

instructions.

The only item of concern that was determined

during the inspection of the actuators was the possibility of

]

the "T-drains" being plugged with paint and not allowing water

l

~

to drain as required.

This was brought to the attention of the

i

'

licensee as a generic concern.

The licensee later performed an

inspection of all limitorques on both Catawba units for plugged

or missing T-drains.

A total of 42 actuators were discovered

with plugged T-drains or with T-drains not installed at all.

Table 1 is a list of the affected tag numbers.

Functional

T-drains have since been installed on all the affected actua-

tors.

In addition, Duke performed an operability analysis to

show that the limitorque operators could have performed their

safety function.

The root cause of these deficiencies (clogged

,

1

and missing T-drains) appear to be due to inadequate training

and procedures to ensure correct and complete T-drain instal-

J

lation and maintenance.

To prevent recurrence the licensee

i

t

.

-

.

s',.

.

,

20

connitted to the following corrective actions (1) the Construc-

tion and Maintenance Department will retrain painter craf t

by March 30, 1988, (2) Station I&E will revise procedures to

clarify T-drain installation requirements by February 25, 1988,

and (3) Station I&E will conduct fonnal T-drain installation

training by March 30, 1988.

This item is a violation of

10 CFR 50.49 for failure to ensure the as-built configuration

was in accordance with the qualified tested configuration.

This item is identified as violation 50-413, 414/88-07-07,

Plugged or Missing T-Drains on Limitorque Valve Motor Operators.

One additional concern was identified regarding the installation

of T-drains on Limitorque Motor Operators.

During the walkdown

T-drains on limitorque valve No. 2NI-1228 were not installed at

the low point.

This configuration does not appear to be quali-

fied.

This item was identified to the licensee as Unresolved

Item 50-414/87-07-08, T-Drains on Limitorque operator not

installed at low point.

Table 1

Total List of Limitorque Actuators With Plugged or Missing T-Drains

IKC364B

INM201A

IVX002B

2KC394A

2NC253A

2NV055A

i

1KC394A

INV055A

IVE004

2KC413B

INM187A

2VC0078

1NI115A

INV066A

IVE009

2KC429B

2NM190A

2WL450A

1NI183B

INV236B

1N0024A

2NC054A

2NM197B

2VE009

f

l

1NM0078

INUO35A

IND059B

2NC250A

2NM2008

2VE004

1NM0269

IVF001A

INIO47A

2NC251B

2NM207A

2NM025A

INM200B

IVX001A

2KC345A

2NC2528

2NM210A

2NI183B

(16) Conax Electrical Penetrations, Type N, EQ File

.

CNS-1361.00-048-001

The qualification file contains the following Conax test

reports:

Report IPS-1037, Rev. D1,10/31/83, "Design Qualification

Report for Electric Penetration Assemblies for McGuire/

Catawba Nuclear Stations 1 and 2."

j

- - -

- -

-

-

- - -

.

'

-

.

>-

,

l

29

Report IPS-1332, Rev. A, 2/18/86, "Design Qualification

Report of 50 Ohm Triac. Feedthrough Kits Installed in

i

Electric Penetration Assemblies for Catawba /McGuire Nuclear

Stations 1 and 2."

Two issues that were identified during the review of the file

were discussed with the licensee and resolved prior to the

conclusion of the audit. They were:

The file did not contain documentation which determined

the qualified life of the Conax Penetrations.

This

documentation was supplied in files CNM-1361.00-0062-001

(conax test report IPS-325) and an auditable trail was

provided to the auditor.

,

It was noted during the walkdown that Litton connectors

were associated with the Conax Penetration enclosure box.

The licensee was requested to provide documentation

supporting the qualification of these connectors. The file

provided was CNM-1354.12-0026-001, which included test

reports:

CE-NPSD-230-P, 4/83; CE-NPSD-275-P; and Retrofit

r

report CE-NPSD-296-P, 5/85.

During the walkdown Conax Electrical Penetration 2 PENT 121 was

physically inspected.

It was observed that plastic caps were

attached to the spare Litton connectors outside of the enclosure

l

box.

When the licensee was asked to justify this, the response

was that they are for housekeeping purposes only. Environmental

sealing is not required since the conductors are solid wire and

,

the connector is potted. Moisture intrusion into the electrical

penetration cannot occur.

They also stated that the caps are

not required for equipment qualification.

Documentation was

provided to the auditor to support the above statements.

No

other discrepancies or anomalies were identified.

(17) D. G. O'Brien Electrical Penetrations, Types F, G and K, EQ Files

CNS-1361.00-0016-002, Rev. 6 and CNS-1351.00-0016-0003, Rev. 7

This equipment penetrates the wall between the inside of

containment and the annulus to form part of the pressure

barrier.

These penetrations are actually installed on the

inside of containment.

The worst case environmental parameters

in both the inside of containment and the annulus have been

considered.

The qualification file numbers are CNS-1361.00-0002 and -0003

which contain the following test reports:

D. G. O'Brien report number ER-252, Rev. A., dated 8/15/77,

"Prototype Test Report low Voltage Power and Instrumenta-

tion Electrical Penetrations."

i

i

i

rY

r

's.

'

a

30

D. G. O'Brien report number ER-327, "Qualification report

for Triaxial Connectors for Electrical Penetrations."

Wyle Laboratories Report Number 45869-1

A cursory review of the qualification file for the D. G. O'Brien

Electrical Penetrations was made.

One item of concern that was

addressed was how Duke Power responded to IE Notices 81-20 & 29.

The licensee's response was that the Type

"K" electrical

penetration plugs were tested at Wyle Laboratories (Wyle Report

Number 45869-1).

More emphasis was placed on accurately

simulating the actual station environment under accident

conditions.

The qualification of the Type

"K" electrical

penetration plugs were reverified as documented in file

CNM-1361.00-0016-001, pages 5-1 through 5-335, pages 6-1 through

6-91 and pages 7-1 through 7-25.

During the walkdown

D. G. O'Brien Electrical Penetrations

2 PENT 105, Type F, 2 PENT 111, Type K, and 2 PENT 112, Type G were

physically inspected.

No discrepancies or anomalies were

identified during the inspection.

(18)Namco Limit Switches,

EQ

Files CNM-1205.19-0042 and

CNM-1225.00-0063

During the plant walkdown inside Unit 2 containment, the NRC

L

inspector noted that the switch compartment cover plate gasket

on a NAMC0 Model EA 180 limit switch, plant ID No. 2NCLLO251,

i

was improperly installed rendering the limit switch environ-

mentally unqualified.

The inspector confirmed that the switch

was listed on the EQ master list as requiring qualification.

No other NAMCO limit switches required to be qualified were

observed to have improperly installed gaskets.

This was

identified as an unresolved item at the exit meeting pending

i

determination of the safety function of the switch and the

i

conditions under which it must perform that function.

Subse-

'

quent to the inspection, Duke informed the NRC that the sole

function of the switch was to provide open indication for

normally-open reactor vessel head inner omega seal leakage

detection line isolation valve 2NC 25A.

Duke stated that the

switch provides non-essential position indication which will

not mislead the operator.

They further stated that the gasket

had been promptly replaced (See Problem Investigation Report

2-C88-0054), that other limit switches had been inspected with

no other deficiencies identified, and that an investigation into

the cause of the improper installation was being initiated.

This is identified as violation 50-414/88-07-06, Unqualified

Namco Limit Switch.

!

'

.

s

- .

-

t

E

s

a*

31

(19) Electric Hydrogen Recombiners, EQ File WCAP-7709-L

During the walkdown of the Unit 2 Hydrogen Recombiners, the

splice configuration was questioned. The Unit 2 recombiners had

a Raychem sleeve over the splice joint in what appeared to be a

one-to-four configuration.

The inspectors were told that the

Unit 1 configuration was different and was actually a taped

splice done in accordance with an engineering evaluation.

Investigation by the licensee on the Unit 2 recombiners showed

that there was a qualified four-to-one Raychem breakout kit

underneath the sleeve; therefore; the splice was found to be

acceptable.

The licensee also looked at the Unit 1 splices to

measure seal lengths on the conductors.

By using at least three

test reports, the licensee was able to show that the Unit 1

splices were qualifiable.

However, the qualification file did

not demonstrate qualifiability and the licensee stated that

the file would be corrected by the addition of the similarity

analysis and several test reports.

This is identified as

Violation 50-413/88-07-01, Inadequate Documentation of Qualifi-

cation of Splices for Hydrogen Recombiners.

(20) Raychem

The NRC inspector evaluated Duke's actions in response to

IE Information Notice (IN) 86-53 (Improper Installation of

Heatshrink Tubing) for Catawba in accordance with the guide-

lines of Temporary Instruction (TI) 2500/17.

The inspector

reviewed Catawba Nuclear Specification No. CNS 1390.01-0074,

Rev. 20, dated February 14, 1988, for installation of Raychem

heatshrink splice insulation.

Duke stated that plant work and

inspection procedures for installation of Raychem heatshrink

tubing splice insulation are based directly on this specifica-

tion.

The Duke specification was found to be consistent with

Raychem specifications.

While the date of the current revision

to the Raychem specification was quite recent, the acceptance

criteria most often seen violated in the field had been incorpo-

rated in a revision prior to Revision 18, dated October 2, 1986,

indicating that installation specifications consistent with

manufacturer's specifications had been in effect no later than

shortly after the issuance of IN 86-53 (July 1986).

The inspector then reviewed records of Duke walkdown inspections

of Raychem splices in response to IN 86-53.

The documentation

indicated that splices had been chosen on a sample basis with

j

the emphasis on the harshest environments and splices that

i

records showed had been installed before implementation of the

l

installation procedures in accordance with Raychem specifica-

tions.

Duke personnel found that splices were either in com-

pliance with Raychem qualified configurations or that deviations

l

k

.

.

-

-

. .

.

.

-

-. _ _ _ _ _

. .. * .

,

32

from Raychem specifications were within the bounds of recent EQ

testing of non-standard configurations sponsored by the Nuclear

Utility Group on Environmental Qualification (NUGEQ) of which

Duke is a member. Duke had incorporated reports of this testing

in EQ documentation files for Raychem splices to demonstrate

qualification for the as-found conditions, however they stated

that many of the splices had been replaced anyway to provide

extra margin and all replacement /new splices are done to the

latest specifications.

Duke further stated that no splices

,

were found that were not qualifiable under the NUGEQ testing.

The NRC inspector's review of training documentation indicated

that ETQS Training and Qualific~ation Guide, Task No. IE-9025,

"Stripping, Splicing, et.

al., Wiring Class 1E Cables and

Devices, Rev. 2, dated June 1,1987, referenced installation

procedure IP/0/A/3890/08C which was based on CNS 1390.01-00-0074,

!

Rev. 20.

Training and Qualification records indicated that the

,

appropriate craft personnel hed been trained in proper Raychem

j

installation techniques and were qualified to Task No. IE-9025

'

by satisfactory perft.,rmance and explanaticn of the referenced

'

procedure.

7.

Inspector Followup Item (IFI)

(Closed) IFI 50-413/87-20-02, Unqualified Wire in Annulus Ventilation

(VE) System.

This item was opened as a result of a licensee review of the

qualification #ile for the VE system.

It was noted that the file

l

required qualification of the wire to 8.0E6 Rads and the file showed

qualification to 1.0E6 Rads.

j

The licensee provided a justification for continued operation in June

1987 which had information showing the wire needed to be qualified for

only 2.0ES.

Additionally, during the inspection, information was

provided to show that the wire was actually qualified for greater than

8.0E6.

Based on the fact that the wire is qualified, this item is considered

closed.

t