ML20128J039

From kanterella
Jump to navigation Jump to search
Insp Repts 50-413/96-12 & 50-414/96-12 on 960804-31. Violations Noted.Major Areas Inspected:Engineering, Summary of Plant Status & Observations & Findings
ML20128J039
Person / Time
Site: Catawba  Duke energy icon.png
Issue date: 09/30/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20128H996 List:
References
50-413-96-12, 50-414-96-12, NUDOCS 9610100163
Download: ML20128J039 (21)


See also: IR 05000413/1996012

Text

,

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos: 50-413. 50-414

License Nos: NPF-35. NPF-52

Report Nos.: 50-413/96-12, 50-414/96-12

1

Licensee: Duke Power Company l

Facility: Catawba Nuclear Station. Units 1 and 2

Location: 422 South Church Street

Charlotte. NC 28242

Dates: August 4 - August 31. 1996

Inspectors: P. Balmain. Resident Inspector

J. Coley, Reactor Inspector ,

N. Economos. Reactor Inspector i

Approved by: L. D. Wert. Acting Chief. Projects Branch 1

Division of Reactor Projects

l

l

i

l

1

l

l

l

ENCLOSURE 2

9610100163

DR 960930

ADOCK 05000413

PDR

- . - - - - . . . - - - - _ - - - - . . - .

. - . . - - - - . _ - - - - -

.

EXECUTIVE SUMMARY

Catawba Nuclear Station. Units 1 & 2

NRC Inspection Report 50-413/96-12. 50-414/96-12

This integrated inspection included aspects of Steam Generator Replacement

Project activities in the area of engineering. The report covers a 4-week

period of announced inspection performed by resident and regional reactor

inspectors.

Enaineerina

  • Two violations were identified regarding secondary system welding. The

first violation with two examples was identified for failure to follow

procedures concerning weld preheat and weld process control packages.

The second violation was identified concerning inadecuate welder

training . The violations and other observations incicated sipificant

weaknesses in the welding program used to fabricate secondary system

welds. The licensee initiated corrective measures to address several

of the identified weaknesses. but it appears that additional steps need

to be taken to address the significant number of welding program

problems identified (Section E1.2 and E1.3).

  • The preparation. assembly, fabrication and testing of Reactor Coolant

System welds without encountering significant problems is considered a

strength in engineering (Section E1.1)

  • A violation was identified for inadequate design control verification

measures. The NRC identified that the as-built configuration of screens

utilized in containment crane wall pipe sleeves and floor drains did not

implement design requirements for minimizing sump screen loading due to

paint chips or blanket insulation material (Section E8).

  • The licensee's foreign object search and retrieval activities were

extensive. The quantity of foreign material retrieved from primary and

secondary system areas was minimal. Evaluations performed for objects

known to be left in the steam generators determined that the objects

would not lodge in the tube bundles and cause fretting problems (Section

E1.4).

ENCLOSURE 2

!

j

__ __ _ _ __ _ _ _ _ . _ _ _ _ . _ _ _ _ _ _ . _ . _ _ . . _ _ _ _

,

I Reoort Details

I

i

\

l

l

1

Summary of Plant Status

)

Unit 1 began the period defueled for the end-of-cycle 9 refueling and steam

generator replacement outage. The unit remained in this condition with steam

generator replacement activities in process for the duration of the inspection

period.

Review of UFSAR Commitments

A recent discovery of a licensee operating their facility in a manner contrary

to the Updated Final Safety Analysis Re) ort (UFSAR) description highlighted

the need for a special focused review tlat compares plant 3ractices,

procedures and/or parameters to the UFSAR descriptions. W1ile performing the

inspections discussed in this report, the inspectors reviewed tie applicable

portions of the UFSAR that related to the areas inspected. The inspectors

verified that the UFSAR wording was consistent with the observed plant

practices, procedures and/or parameters. Identified deficiencies involving

containment sump screens are addressed in Section E8.

I. Enaineerina

El Conduct of Engineering

El.1 Steam Generator Reolacement (50001)

a. Insoection Scooe

Evaluation by direct observation and document review, of the adequacy of

the licensee's Steam Generator Replacement Program (SGRP), with regard

to: welding of piping in primary and secondary systems (i.e. , reactor

coolant, main steam, main feedwater and others), postweld heat  ;

treatment, review of radiographs of in-process and completed welds, and

ultrasonic examination of completed welds per ASME Section XI to verify

compliance with preservice inspection requirements.

b. Observations and Findinos

,

Weldina Reactor Coolant Pioina to Reolacement Steam Generators

Reactor coolant pipe welds joining hot and cold leg piping were

fabricated using a narrow groove joint design and the remote control

machine gas-tungsten arc welding process. Welding of field joints was

performed by Framatome Technologies who was contracted by the licensee

to provide equipment and personnel for this purpose. Details relative

to weld procedure qualification and welder training in preparation for

this activity were discussed in NRC Inspection Reports 50-369,370/94-05,

50-413.414/96-07 and 50-413.414/96-11.

ENCLOSURE 2

. _

._ -_ _

,

.

2

Welding related activities observed during this inspection period

included cleanliness and fitup, in process welding. repairs, cleanup and ,

grinding. visual inspection of completed welds, and review of process

control documents. Within these areas. the following was noted by the

inspector.

SG "C" Hot and Cold Lea Weld Root Reoair

i

,

Weld joint axial mismatch which exceeded specification requirements

required the use of ceramic backing material to facilitate welding the

root over a limited section of the joint. When the weld joint was

partially completed. the weld surface in contact with the ceramic

material was ground and examined with liquid penetrant for evidence of

surface indications. The inspector witnessed the test and noted that it

produced evidence of linear and rounded indications in the root surface

area associated with the backing material. These indications had

, minimal depth and were removed by light grinding. A followup inspection

'

showed the indications had been removed and the root surface in both

joints was satisfactory.

Thickness of Existina Elbows Below Code Allowable

Thickness measurements of the existing cast elbows near the weld joint

indicated that material thickness were either at or close to the code

allowable minimum (2.42 inches). This condition was attributed to the

'

existing casting thickness irregularities and the machining operation

for 3 reparation of the initial weld joints. Machining and the machining

i of t1e counterbore for concentricity and for the tight fitup tolerance

3 required for the narrow gap weld joint design, reduced wall thickness

dimensions to below code minimum. To correct this condition. Framatome

added a sufficient amount of weld metal to the OD surface, adjacent to

the weld: thus restoring material thickness to acceptable levels. By

, review of the Weld Process Control Sheets (WPCS) and associated

Jackages the inspector ascertained that instructions for this activity

1ad been documented on Form CWP-1B. Alteration / Repair Process Control.

These instructions included the weld procedure to be used, approximate

weld metal thickness to be deposited, weld metal surface finish,

geometry, and testing to be performed. Within these areas the inspector

found the weld buildup, workmanshi) and finish satisfactory. However,

the inspector did not agree with t1e licensee's decision to document the

weld metal buildup on the material as a weld joint repair. The

inspector's position was that while the added filler metal was fused to

the weld joint, its sole purpose was to restore material thickness and

not to repair a defect in the weld joint as the documentation on the

.

WPCS would suggest. The metal addition was identified as Repair 1 for

each of the eight weld joints. As such, the inspector stated that this

activity should have been documented on a separate WPCS and given a

unique weld number for future reference. In closing, the licensee's

cognizant engineer agreed with the inspector's position and issued a

ENCLOSURE 2

. __ __ __ _ . - . _ . _ - . _ _ . _ _ - . _ . . _ _ _ - - _ . _ _ _

.

.

3

cover sheet to explain the reason for the repair, the applicable

i controlling code, and the welding process used. Each cover sheet was

attached to the weld package of each of the eight reactor coolant welds.

Review of Stress Analysis Calculations

The weld metal buildup on the crossover and hot legs was performed in

accordance with the ASME code requirement NB-4214 and NB-4130. However,

as an added design conservatism, the inspector requested that the

licensee review the original stress calculation (CNC-1206.02-70-0093) to

determine whether the weld metal buildup and the apparent change in weld

contour could have changed the validity of the above-mentioned stress

calculation. The inspector discussed this concern with the staff at NRC

Headquarters who agreed with the inspector's request for the licensee's

review. On September 17. 1996, the licensee provided the inspectar the

results of the review and evaluation which showed the stress indices at

those locations were well within the limits of the initial calculation.

Review of Radicaraohs - Comoleted Reactor Coolant Welds ,

Completed reactor coo' ant SG hot leg and crossover leg welds were i

radiographed to satisfy ASME Code Section III requirements. The welds  !

were shot in accordance with the licensee's Radiographic Procedure NDE-

10A, Rev. 19. Welds selected for this review were as follows:

Weld

INC22-2 B Hot Leg 2.57"x31" No Rejectable

Indication (NRI)

1NC22-3 B Crossover 2.57"x31" NRI

INC23-2 D Hot Leg 2.57"x31" NRI l

1NC23-3 D Crossover 2.57"x31" NRI  !

1NC24-2 A Hot Leg 2.57"x31" NRI

INC24-3 A Crossover 2.57"x31" NRI ,

1

i

l From this review. the inspector noted that film and radiographic quality I

met the required code minimum standards; however, in several instances,

the inspector observed that film placement was such that it barely

covered the area of interest. Also, the inspector observed that many of

-

the radiographs exhibited numerous artifacts, including roller marks. '

l This observation was discussed with cognizant NDE personnel and

management. They acknowledged that the condition existed and that it

was due in part to a problem in the processor which they were determined

to correct. This condition was subsequently corrected as evidenced by

the quality of radiographs for the CF and SM welds.

Preservice Insoection of Reactor Coolant Welds

As required by ASME Code Section XI. reactor coolant system weldments

must undergo volumetric / ultrasonic examination before the plant returns

ENCLOSURE 2

, --

- -

_ _ - . _ _ __ _ __._ _ . _ _- . . _ _ _ _ _ _ _ _ _ _ _ _ . . _ _ _ _ . _ . _ .

l '

l

l .

4

to power. Procedures used for this purpose must meet the subject code's

minimum requirements. As such, the licensee utilized ultrasonic

examination procedure NDE-610. Rev. 3. which references ASME Code

section XI. 1989 Edition. The examination covered the inner 1/3

thickness of the weldment and 1/4" of the adjacent base metal on each

side of the weld subjec: to accessibility. Because at the time of this

inspection all replacement reactor coolant loop welds had been examined,

the inspector reviewed examination records for adequacy, accuracy.

completeness and compliance with the subject code. Through this review,

the inspector ascertained that each weldment was examined with refracted

l 45 and 60 degree transducers. Welds were scanned in the axial and

l circumferential directions with the 45 degree transducer and only in the

axial direction, from the safe-end side, with the 60 degree transducer.

Weldments for which records were reviewed were 1NC22-2 and -3. 1NC23-2

and -3. 1NC24-2 and -3 and 1NC25-2 and -3. Out of these eight welds,

only 1NC25-2 exhibited geometric reflectors in the root. This weld was

in the hot leg of the "C" loop where some mismatch was encountered

during the fitup and a ceramic backing was used to facilitate root

closure. Therefore, the indication was not totally unexpected. Other

records associated with these examinations that were reviewed included

certifications for instruments, transducers. calibration blocks, and

personnel.

c. Conclusion

The preparation, assembly fabrication and testing of reactor coolant

system welds without encountering problems of any significance is

considered as a strength in engineering. This achievement can be

attributed to the 3 reparation and planning by the licensee's lead

engineers and to tie intense training of the contractor's welding

personnel to achieve the necessary proficiency for performing their

assigned tasks. The licensee's efforts towards attaining this objective

was a significant SGRP group strength.

El.2 Fabrication and Testino of Main Feedwater and Main Steam Welds (50001)

a. Insoection Scooe

This inspection effort was a followup to that documented in NRC

Inspection Report No. 50-413.414/96-07. which covered Main Feedwater

welds that were welded in the licensee's fabrication shop.

The present inspection effort covers welds fabricated in the field

(inside Unit 1 containment) and includes welding, process control,

thermal treatment and testing,

b. Observation and Findinas

The inspector observed various as)ects of field weld fabrication in

several pipe systems, including t1e main steam and main feedwater

ENCLOSURE 2

. . -. __ __ _ _

. - .- -

- -_ - - . .

.

5

systems. Welding activities and practices were observed to verify that

the new welds were being fabricated and tested in accordance with the

l applicable code and regulatory requirements. This provided a reasonable

assurance that replacement components and the plant would operate in a

safe manner. To perform this task, the inspector selected for

observation, welds at various stages of fabrication (i .e. . fitup,

preheat, root closure, welding-out the joint, and postweld heat

treatment). Welds selected for this task were as follows:

Main Steam (SM)

SG A ISM 34-38 Outlet Nozzle to Elbow

ISM 34-37 Riser

SG B 1SM29-36 Outlet to Elbow

1SM29-35 Riser

SG B 1SM39-35 Outlet Nozzle to Elbow

ISM 29-35 Riser

Main Feedwater (CF)

SG A 1CF038-01 Nozzle to Elbow

1CF038-10 Pipe to Elbow

1CF038-14 Pipe to Reducer

1CF002-04 Pipe to Pipe

1CF002-13 Pipe to Pipe

SG B 1CF039-01 Nozzle to Elbow

1CF039-10 Verticle Pipe to Elbow

1CF037-04 Pipe to Pipe

SG B 1CF039-14 18x16 Reducer

1CF039-13 Pipe to Pipe

SG Blowdown Recycle (BB)

SG B 1BB134-04 Nozzle to Pipe

SG Wet Lav-uo Recire. (BW)

SG C 1BW018-34 Nozzle to Pipe

Auxiliary Feedwater (CA)

SG B 1CA68-39 Nozzle to Pipe

Field welds were fabricated utilizing welding procedures from the

licensee's Welding Manual. These procedures were qualified to meet the

recuirements of ASME Code Sections IX. XI and III 1989. Pipe reroute

anc reassembly for the subject systems were addressed in Final Scope

Documents CN-19429. CF Piping Reroute. and CN-19510. Removal and

Installation of SM Lines.

ENCLOSURE 2

. _ . _ _ ____ _ _ _ _. _ _ _ _ _ _ . _ _ _ _ _. _ _

r{

.

j -

6

a

i Fabrication of field welds was controlled by the applicable Process

j Specification and the Field Weld Data Sheet (FWDS) both of which

! contained process variables of the qualified welding procedure. Process

Control Sheet (CWP-1A) from the Maintenance Welding Manual.Section I,

,

Rev.1. provided a historical fabrication record of a given weld and was

used to identify fabrication milestones (e.g., hold points. 0A/0C sign-

offs. Authorized Nuclear Inspector hold Joints, preheat and other

j 3ertinent information relative to the fa)rication of a given weld).

l 41 thin these areas. the inspector made the following observations.

Keeoina Weld Documentation Packaae At The Job Site

S)ecification L-100. Welding Program, paragraph 4.3.3 states in part

j t1at a copy of the FWDS shall be available in the work area of t1at

particular weld. Also Nuclear System Directive 704, Rev. 4. paragraph
704.6 states in part that a copy of the procedure shall be in the

'

possession of the performer (s) at the job site. Contrary to this

requirement, on August 5-9, 1996, the inspector observed that weld

documentation packages were not being kept at the location where welds

were being fabricated.

. Failure to have these records readily available at the job site

i precludes welders and QA/0C inspectors from reviewing information ,

i essential to weld fabrication. to signing off on OC hold points, and to I

'

document random inspections during fabrication. This failure to keep

< weld data packages at the job site as required by procedure is

considered a violation of 10 CFR 50. Appendix B. Criterion V. and will

be identified as VIO 50-413/96-12-01. Failure To Follow Procedures.

Preheatina Welds

, The Licensee's Process Specification L-900. Rev. 3 provides guidelines

! for preheating, maintaining interpass temperatures and postweld heat

i treating of production welds. This s)ecification states in part that

4

the entire joint to be welded, shall 3e preheated to the temperature

saecified on the FWDS...and shall be maintained throughout welding of

j t1e applicable joint. Paragraph 5.2.2 of the subject document requires

! that resistance heating elements (blankets), used for preheat and

interpass temperature control operations, will be placed as closely as

i )ractical to the weld preparation on each side of the joint. Also.

3rocess Specifications L-200 Gas Tungsten Arc Welding and L-300 Shielded
Metal Arc Welding, paragraphs 9.2 and 7.2 respectively, require that

4

preheat be maintained throughout the welding of the applicable joints.

This requirement is further supported by Regulatory Guide 1.50. May

i 1973. Control of Preheat Temperature for Welding of Low-Alloy Steel

J Section C.2 and C.3 which states in part that for production welds, the

i preheat temperature should be maintained until a post-weld heat

i treatment has been performed and, that production welds should be

j monitored to verify that the limits on preheat and interpass

i temperatures are maintained.

! ENCLOSURE 2

j

~ . _ . _

. _ _ _ _ _ . . _ _ _ _ _ _ . _ __ _____

.

7

By observation and through discussions with craft. OC inspectors, and  :

craft supervisors, the inspector noted that the use of a flame torch was )

the preferred method for preheating production welds to the required ,

temperature. Flame torches were used for preheating prior to tacking i

and prior to welding the weld joint. A flame torch was used to reach  !

and maintain minimum

one additional pass. preheat

From thattemperatures during

point on, minimum root temperatures

preheat closure and for

were maintained from heat generated by the welding process during

welding. The inspector observed that preheat was not being maintained

on several partially completed joints where welding had been stopped.

In these instances. the weld joint temperature had returned to

room / ambient temperatures.

Also by observation. the inspector noted that the above-mentioned

preheat requirements were not being followed while welding weld CFO

40-10. In this case only one resistance heating blanket was used for

maintaining preheat instead of one on either side of the joint as

required by the specification. These findings of failure to follow l

procedure are considered an additional example of VIO 50-413.414/96-12-

01 identified earlier in this section.

In discussing preheat practices and concerns with the licensee's  !

cognizant engineer, the inspector stated that although use of a flame l

torch for this purpose was not a prohibited practice, it was not the

preferred method for preheating low-alloy materials e.g. , Cr-Mo piping

and Main Steam Lines in nuclear power plants and particularly on S/G

replacement projects. Also, the inspector stated that because flame

torch heating of welds is heavily dependent on the skill of the craft.

there is little or no assurance that all the requirements specified by

the specification have been followed. To underscore this concern, the

inspector ascertained through discussions with craft, that they had no l

clear understanding or formal instruction on the specified area around

'

the weld joint that had to be preheated and/or the importance of

maintaining minimum preheat temperature throughout weld fabrication.

During this time. the inspector also noted that temperature indicating

crayons (temp sticks) were not in the possession of all welders

fabricating welds. This was noted when the inspector asked welders for

use of their temp sticks to check preheat and interpass temperatures,

but had to wait until one was borrowed from another crew before

proceeding with the test. This further heightened the concern over the

adequacy of preheat temperature control.

On August 8 and 9,1996, the inspector had a preliminary exit interview

with the licensee's site management and oiscussed in detail the concerns

and findings described above. The licensee reacted in a positive manner

ENCLOSURE 2

8

to the inspector's concerns and findings and took the following

corrective actions:

. Stopped work to assess the situation and to discuss welding

practices with craft and supervision.

. Developed preheat guidelines for making tacks and welds. These

guidelines were issued on August 11, 1996.

. Developed maintenance procedure MP/0/A/7650/147 to describe

preheat requirements. Copies of this procedure were placed in all

applicable process control packages. This procedure contains an

attachment for documenting preheat for fabricating tack welds and

welding out of weldments.

. Provided for weld process control packages to be at weld

locations.

. Provided for increased management oversight to ensure compliance

with all welding requirements.

. Provided for all welds requiring preheat to be wrapped using

resistance heaters except where engineering granted an exemption.

. Increased frequency of OC random inspections with emphasis on

preheat /interpass temperature monitoring and for documentation in

the forms provided

. Provided training for line management and craft on welding program

changes being implemented.

. Conducted Laboratory Tests for tack welds and production welds

using a flame torch to determine length of time to reach minimum

preheat temperatures. Tests were performed on Chromium-Molybdenum

(Cr-Mo) material from 2"-6" thick.

. Issued PIP 1-C96-2082 and ]erformed an insight investigation on

main steam weld 1SM34-38 w1en a raridom inspection disclosed that

the 200 degree Fahrenheit minimum preheat tem)erature had not been

maintained over the entire circumference of t1e joint. Preheat

was maintained on opposite sides where welding was in progress.

  • Secured the services of an independent welding consultant to

assess the SGRP and plant secondary side weld program and

practices with emphasis on preheat application.

. Performed overall Weld Program review including other critical

elements of the welding process and made appropriate

recommendations for strengthening the Duke Power Welding Program.

ENCLOSURE 2

- - - _-. . - - -- - - - . - - .- . . . . - - _ . _ - _ _ -

i l

'

,

-

,

'

.

9

Makino of SM and CF Production Welds

Replacement of the SGs required the removal and subsequent

4 reinstallation of main steam piping, immediately off the SGs. As such,

the piping was cut at the SG nozzle and near the bottom of the second

elbow. The design of the new SGs required that the existing CF line be

cut and rerouted to accommodate the new location of the CF nozzle on the

SGs. The replacement piping was made of Chromium-Molybdenum (Cr-Mo),

,

low-alloy steel . This material was selected for its demonstrated

'

resistance to erosion / corrosion attack. This material requires that

welds be preheated and postweld heat treated following fabrication.

Field welds in the SM and CF systems were fabricated using gas tungsten

Arc (TIG) and shielded metal arc welding procedures from the Duke

Welding Manual. By record review the inspector ascertained that both i

'

welding procedures and welders were qualified in accordance with ASME

Code Section IX requirements. Welders and their supervisors assigned to

this project were from the licensee's Electric System Support (ESS)

Department.

Between August 5-9, 1996, the inspector observed welding activities in

both systems and the findings were discussed earlier in this section of

this report. As a result of these observations, through reviews of

radiographs of in process and completed welds, and from discussions with

technical personnel the inspector became concerned over the relatively

high rate of rejections in these two systems and particularly in the BB  ;

system where the nozzles were buttered with inconel material. Weld  !

rejections, when they occurred, were for the most part associated with

the root and were identified as incomplete penetration and/or incomplete

fusion. Slag, porosity, and crack indications were also observed in l

weld locations. These rejectable indications were observed in various

degrees in all of the three systems inspected and more predominately in l

the BB system nozzle welds where repair rates ranged from 2 to 11 )

repairs per nozzle weld joint, Rejections in the CF and SM system were

'

not as high, but still higher than would be expected based on the ,

'

inspector's past experience with similar SGRPs where the same manual

processes were utilized. For example, out of the eight weld joints that

were fabricated in the SM system. five were rejected by radiography and

required weld repairs. One of these welds (No. ISM 29-36, outlet nozzle

to elbow weld on SG A) required seven repairs before it was accepted by

radiography. The inspector requested, and the licensee agreed, to

stress relieve /postweld heat treat this joint as a precautionary measure

to guard against the residual stresses which may have been built up by

the multiple weld repairs. In the CF system, weld rejections were

similarly high, as approximately 50% to 55% of the field welds required

anywhere from one to five weld repairs before being accepted by

radiography.

Through observations, discussions with craft and field supervisors and

by reviews of the licensee's assessment and other SGRP documents. the

ENCLOSURE 2

- . - -

l

.

'

10

following was ascertained by the inspector.

Trainina of Welders

l

CN-19420. CF Piping Reroute. Section 10.6.2 Materials Section and

Fabrication, states in part that Duke complies with Regulatory Guide

1.71 Welding Qualification for areas of Limited Accessibility. However. l

Duke took exception to the regulatory position for welders to be tested

for proficiency under simulated access conditions such as those that

would be encountered when fabricating production / field welds. Duke's l

approach was to use only highly skilled personnel as a means of assuring

acceptable welds. As such, welders used for this project came from

Duke's ESS group for their familiarity and expertise in welding these

materials.

Through discussions with craft, supervisors and SGRP management the

inspector ascertained that welders were brought onsite immediately l

before work was to begin. They were provided little or no formal

'

training or indoctrination on the requirements of the welding 3rogram

and were given no mock-up training to achieve proficiency in t1e

production of radiograph quality welds under field conditions.

Therefore the inspector believes that the licensee's decision to rely

heavily on the welder's past experience with welding these materials

instead of spending the time and resources to adequately train them was

a major contributor to the poor welding performance demonstrated during

this outage.

Failure to provide adequate indoctrination and training of personnel

performing activities affecting quality to assure that suitable

proficiency was achieved and maintained is considered a violation of 10

CFR 50. Appendix B. Criterion II Quality Assurance Program and will be

identified as VIO 50-413/96-12-02. Failure to Adequately Train Welders

To Perform Their Assigned Tasks.

Postweld Heat Treatment CF Welds

Postweld heat treatment (PWHT) of completed CF welds was performed to

satisfy applicable code requirements. This activity was controlled by

Duke's Welding Manual Process Specification L-900. This specification

provides the guidelines for thermal treatment of welds and uses data

sheets for specific ap)lications. Data sheets used for PWHT of CF pipe

and nozzle welds were _-924. Rev. 2 and L-923. Rev. 1. respectively.

The inspector reviewed the specification and the subject PWHT data

sheets for technical content, adequacy, and compliance with applicable

code requirements. Following is a list of welds that underwent PWHT and

the inspector observed the activity in progress or reviewed heat treat

charts and associated records.

ENCLOSURE 2

_ _ _

.

11

Weld Descriotion Parameters

CF037-3 and -4 Pipe to Elbow 1hr @ 1150 F

CF038-1 Nozzle to Pipe Ihr @ 1135 F

CF038-10 Pipe to Elbow 1hr @ 1180 F

CF038-14 Pipe to Reducer Ihr @ 1180 F

CF039-1 Nozzle to Elbow 1hr @ 1135 F ,

CF039-10 Pipe to Pipe Ihr @ 1150 F

'

CF039-14 Pipe to Pipe Ihr @ 1150 F

  • 1SM29-36 Nozzle to Pipe 1 1/2hr @l150 F
  • This weld did not require PWHT but was done in response to the

inspector's concern over the numerous re) airs and associated residual

stresses which may have accumulated in t1e process. Through

observations and reviews the inspector ascertained that PWHT was

consistent with code and specification requirements and that

documentation of the activity was satisfactory.

Preservice Examination of CF and SM Welds

SM welds were radiographed to satisfy ASME Code Section XI requirements

for a volumetric examination prior to the plant returning to power l

operations. The procedure used and ap)licable code was discussed

earlier in this report. A review of tie radiographs for the eight new

welds was performed. This review indicated that the radiographs met

minimum code requirements and that the welds were free of rejectable '

indications.

CF welds were ultrasonically examined and the results evaluated.

Procedures used included NDE-640. Rev. 1. with applicable code

requirements used to detect planar or laminar flaws in the base metal

while NDE-600. Rev. 7. was used to detect flaws in the weld metal. The

latter provides for axial and circumferencial scanning of the weld with

shear and or long wave transducers.

Because ultrasonic examination of the subject welds was complete at the

time of this ins)ection, the inspector reviewed records of the

examinations. T1ese records were reviewed for completeness, accuracy,

and adequacy of evaluations for indications. Certifications of

equipment. materials and personnel were reviewed at this time. This

work effort was performed for the following welds:

Weld Nc. Results

ICF 39-2 Root condition evaluated as acceptable.

documented for future reference.

1CF 39-12 and -13 No recordable indications (NRI).

1CF 40-11 and -13 NRI.

ENCLOSURE 2

._ .- - - - - - - . - . . - . - . - . . . . . _ _ - __.__ - _.-

i

-  !

12

1CF 41-2 NRI.

1CF 41-15 Root condition evaluated as acceptable,  ;

documented for future reference.

1(,F 36-5 Geometric indications due to counterbore  !

configuration.

1CF 36-2 Geometric indications due to counterbore

configuration. l

1CF 37-5 Geometric indications due to counterbore

configuration.

c. Conclusion:

The welding program used to fabricate plant secondary side welds showed

significant weaknesses. These were demonstrated by: the failure to 7

adequately train welders to produce radiograph quality welds in the

restricted environment of the containment building; the use of flame  :

torches for preheating safety-related low-alloy pipe welds and failure

to comply with specification requirements: failure to provide process  !

control information at the work stations; failure to establish minimum

standards for random QC surveillances and to enforce its documentation:

and failure of line supervision to provide adequate oversight and

guidance in identifying and resolving weld fabrication problems and poor

welding practices.

The licensee initiated corrective measures to address several of the

identified weaknesses, but it appears that additional steps need to be

taken to address the significant number of problems identified.

E1.3 Review of Radicarachic Film for Steaq ffnerator Reolacement Pioina Welds

a. Insoection Scoce (50001)

Radiographic film for steam generator replacement piping field welds

were reviewed by the inspectors. This review was conducted to verify

that the radiographic process, including the acceptability of welds, met

ASME Code requirements. In addition, the inspectors reviewed and

assessed the high weld reject level experienced by manual welders on the

steam generator replacement project. In order to fully assess the

welding problem, radiographic film of acceptable and rejectable welds

were reviewed. The rejectable radiographs were reviewed to determine i

the location in the weld where the defects were occurring, what type of

welding defect conditions were involved, and if corrective measures

taken by the licensee to improve welding proficiency were effective.

ENCLOSURE 2

.- - . . . - . . - . -. -. .-- .-

13 j

b. Observations and Findinas

Acceptable radiographs for the reactor coolant (NC), main feedwater

(CF). steam generator blowdown (BB). steam generator wet layup (BW) and

mainsteam (SM) field welded pipe welds delineated below were reviewed.

The licensee's code implementing 3rocedure for this examination was NDE

10 Revision 19. General Radiograplic Procedure, which referenced ASME

Code Sections III. V and XI. 1989 Edition. The inspector reviewed the

radiographs to verify proper penetrameter type, size, placement,

sensitivity, film density, proper film identification, weld coverage, j

and evaluation and disposition of weld discontinuities.

Weld No. Weld No, )

l

NC23-2 CF37-04

NC22-3 CF3-14

CF38-10 BB129-04

CF39-10 BW16-02

CF38-14 CF38-01  ;

CF2-15 CF39-01 1

CF36-14 SM34-38 i

CF40-14

'

NC24-2

CF37-16 BW19-34

CF36-15

4

In addition to the above acceptable film, the following rejectable film

packages for the welds delineated below were reviewed:

Weld No. Weld No.

'

BB128-8 CF41-10

BB128-7 CF37-15

BB127-4 CF2-13

BW16-1 BB134-4

CF40-10 BB132-4

CF39-14 SM29-36

CF40-14 CF34-1

CF2-4 BW19-1

Through the review of the film for the welds listed above, the inspector

concluded that film accepted by the licensee's NDE staff were

acceptable, and the film rejected by this staff were rejectable. The

inspector's review also determined that almost all weld rejects, whether

initial welds or repairs, were occurring in the weld root area. The

deficient weld conditions were generally the result of lack of weld

fusion or lack of a weld Jenetration. The licensee had determined and

the inspector concurred tlat the inconsistency in welding an acceptable

weld root pass was indicative of lack of welding proficiency caused by

inactivity in the area of welding. The licensee was giving welders

additional training on mockups to improve this trend before starting the

ENCLOSURE 2

!

!

.

14 ,

i

'

auxiliary feedwater system welding. In addition. manual welding

equipment with enhanced welding features were being sent to the Catawba

site. Several issues were raised by the inspector and addressed by the

licensee during the week of the inspection. They consisted of the l

following:  ;

  • Due to multiple repairs which extended to the weld root for the 3-

inch diameter BB and BW nozzles to pipe welds, the inspectors

questioned whether sufficient inconel buttering remained on the

nozzle end preps. To address this issue the licensee provided the

inspector with appro)riate drawings for the NC, BB, and BW systems

which depicted 1-inc1 of inconel weld butter applied on each

nozzle end prep. In addition, the licensee had engineers verify

that sufficient inconel butter could be seen remaining on each

nozzle.

  • Radiographic examination reports used by the licensee had a column

labeled " dimensions" for film interpreters to record the size of

discrepant indications. The inspectors noted one case where an

interpreter had not done so. Although, this is not a Code

requirement it aids a second reviewer in determining whether the

interpreter based his acceptance of an indication on rounded

indication or an elongated indication criteria. This difference

becomes important when indications approach their minimum or

maximum allowable dimensions in a classification category. This

item was discussed with the cognizant supervisor who informed the j

film interpreters to record the dimensions of all relevant i

indications.

. The inspector held discussions with cognizant engineers to

determine whether the radiographic results were considered when

assigning welders to weld joints that were ex)eriencing multiple

repairs. The engineers stated that this had Jeen taken into

consideration.

c. Conclusion

Deficient welding on the steam generator replacement piping was

controlled by the licensee through effective and conservative

radiographic film review. The high weld reject rate was caused by the

lack of welder proficiency in making manual field weld root passes

particularly when using inconel weld filler material. The licensee was

taking appropriate corrective actions for this problem.

El.4 Foreian Obiect Search and Retrieval Activities (50001)

a. Insoection Scooe (50001)

During this inspection period the inspector reviewed the results of the

licensee's investigation of a loss of Foreign Material Exclusion (FME)

ENCLOSURE 2

. _ _ _ _ _ __ ________._ ______ _ _ _ . ,

.

.

15

controls at the steam generator (SG) fabrication facility that resulted

, in three weld wires being left in one of the SG moisture separators.

The inspector reviewed and observed search and retrieval activities for

several unaccounted for objects and also reviewed the results of Foreign

Object Search and Retrieval (FOSAR) inspections performed in the SG

secondary areas, reactor coolant system hot and crossover legs, and the

reactor vessel.

b. Observations and Findinas

The licensee's investigation concluded that the three weld wires found

in the 1A SG were left in the SG at the Babcock & Wilcox International

(BWI) facility following FOSAR inspections performed during

manufacturing of the SG (PIP 1-C96-2099). The licensee performed

extensive FOSAR inspections of the up)er tube bundle areas and the top

of the tube sheets in all the SGs. T1e inspector witnessed portions of ,

these inspections. No additional weld wires were identified during the i

inspections. Several items were retrieved during the inspections

including a small quantity of weld slag. wire and tape. Two items were

known to be left in the 1B SG, a screwdriver tip and a piece of weld

slag. BWI concluded that due to their small size they would not cause

fretting problems in the bundle and would likely deposit in a low

velocity area or exit through the blowdown system.

Foreign material exclusion plugs used in the Reactor Coolant System

(RCS) hot legs and crossover legs were not effective in preventing

debris from entering the RCS piping. Sponge material used in the pipe

end decon process was found in these areas after the alugs were removed.

The licensee performed FOSAR inspections of each of t1e hot and

crossover legs. The inspector reviewed video tapes of the C SG F0SAR

and verified that the licensee was effective in removing sponge debris

from the RCS piping. The inspector verified by reviewing work order

(WO) documentation that quality control (OC) inspections performed

following the F0SARs found cleanliness conditions in all of the RCS

piping to be acceptable and all of the sponge material was removed (WO 95098510.20.21.22 and PIP 1-C96-2257).

c. Conclusions

The licensee's foreign object search and retrieval activities were

extensive. The quantity of foreign material retrieved from primary and i

secondary system areas was minimal. Evaluations performed for objects i

known to be left in the steam generators determined that the objects '

would not lodge in the tube bundles and cause fretting problems.  ;

l

l

l

ENCLOSURE 2

l

- . __ _ . . _ . . <

,

1

,

.

16

E8 Hiscellaneous Engineering Issues (92903)

(Closed) URI 50-413.414/96-11-01: As Built Discrepancies Could Allow 3

Debris Transport to Containment Sump Screens. This item was opened  ;

pending com)letion of the licensee's evaluation of several discrepancies

identified )y the inspector during a walkdown of Unit 1 containment sump

areas. The discrepancies included: (1) Floor drains that were not

covered with a screen that had a finer mesh than the sump screen as i

required by design calculation (CNC-1223.11-00-0005, Justification for

Using Flexible Blanket Insulation Inside Containment) and (2)

containment crane wall pipe sleeves that were not covered with screens

as specified in FSAR section 6.3.4.1. ECCS Performance Tests.

Subsequent to the initial identification of these problems the licensee

also recognized that four additional floor drains that did not have any

form of filter or screen. The discrepancies were not an immediate

concern for Unit 1 since the unit was defueled.

The licensee took actions to plug the Unit 2 crane wall pipe sleeves and

determined that the operability of Unit 2 recirculation sump would not

be adversely impacted by the potential transport of insulation to the

sump screen. The inspector reviewed the licensee's operability

evaluation (PIP 2-C96-1958), which was initiated following the

inspector's identification of this issue. The inspector agreed that

the impact on the Unit 2 sump operation would be minimal because

quantity of installed insulation was relatively small, the transport

path to the open pipe sleeves and floor drains was tortuous, and the

1/4-inch installed floor drain screens would limit insulation debris

that could reach the sump screen. The licensee determined that the

cause of using 1/4-inch floor drain screens instead of 1/8-inch screens

was because of an incomplete use of reference material during the

preparation of a modification which changed the size of the floor drain

screens. The licensee also determined that design basis information

relative to the size of the recirculation sump screens was incorrect and

confusing.

Based on this review, the inspector concluded that the licensee's design

control measures were not adequate to ensure the as-built configuration

of screens utilized in containment crane wall pipe sleeves and floor I

drains implemented design requirements for minimizing sump screen l

loading due to paint chips or blanket insulation material. The  !

protection of sump screens from debris is significant since clogging of  !

sump screens can potentially result in a reduction or loss of reactor  !

core cooling flow following a loss of coolant accident. This issue is a l

violation of 10 CFR 50. Appendix B. Criterion III Design Control, and

will be identified as VIO 50-413,414/96-12-03. Inadequate Design  !

Controls For Ensuring Containment Crane Wall And Floor Drain Screens

Implemented Design Requirements.

ENCLOSURE 2

_ _

\

'

I

,

17

II. Manaaement Meetinas

X1 Exit Meeting Summary i

l

l The inspectors 3 resented the inspection results to members of licensee l

management at t1e conclusion of the inspection on September 5.1996. The l

licensee acknowledged the findings presented. No proprietary information was l

identi fied. i

1

i

l

)

I

1

ENCLOSURE 2

_. _ _ _ . _ . _ _ . . _ _ _ _ _ _ _ _ _ _ _ . _ _ . . _ . _ . _ . _ . _ _ . _ _ _ _ _ . .

-

i

.

  • 18

\

PARTIAL LIST OF PERSONS CONTACTED

Licensee

Benoit. R., SGRP Engineer

Bowers. B.. Manager. ESS. SGRP

'

Cheezem. C. , Manager. NDE Diversified Services

Connell K., Licensing and Procurement Manager. SGRP

i Crump. J. SGRP Engineer

.

Forbes J., Engineering Manager

i Hallman G., Project Director. SGRP

. Kent. G., SGRP Engineer

! Kitlan. M.. Manager. Regulatory Compliance

i McCollum. W., Catawba Site Vice-President

Medlin. R.. ESS Customer Support Manager

l Nicholson. K., Compliance Specialist

Patrick. M., Manager. Safety Assurance

f Peterson, G., Station Manager

Pitser. K., SGRP Engineer

Sharpe. R., SGRP Licensing

Sills. S., SGRP Site Manager

Stout. D. , Engineering Supervisor

Tower. D., Compliance Engineer

Van Malssen. S., ESS

ENCLOSURE 2

_ _ . _ _ . _ . _ . _ . _ ._ . _. . _ _ _ _ . _ - . _ _ _ ._

-_ _ _ . _ _ _ _ . . _ _ . . _ . . . _ _ _

-

_ _ .

1

J

j

. .

.

'

19

INSPECTION PROCEDURES USED

IP 50001: Steam Generator Replacement Inspection

i

j IP 92903: Followup - Engineering

i

!  !

4 ITEMS, OPENED, CLOSED, AND DISCUSSED 1

)

'

i Ooened

50-413/96-12-01 VIO Failure To Follow Procedures-Two Examples

(Section E1.2).

+

l 50-413/96-12-02 VIO Failure To Adequately Train Welders To Perform

i Their Assigned Tasks (Section E1.2).

50-413.414/96-12-03 VIO Inadequate Design Controls For Ensuring

i

Containment Crane Wall And Floor Drain Screens

Implemented Design Requirements (Section E8).

]

Closed

i

! 50-413.414/96-11-01 URI As Built Discrepancies Could Allow Debris

j Transport To Containment Sump Screens (Section

i

E8).

,

i

)  !

5

!

!

1

i

l

i

.

!

!

l ENCLOSURE 2

1

<

- , -

-. - . -- -. . -. . .. - .. --._- -.- . - - __ _.- - - ~. . . - . - . -

l

t .

! *

j 20

LIST OF ACRONYMS USED

ANSI -

American National Standard Institute

1 ASME - American Society of Mechanical Engineers

i BB -

Blowdown Recycle

BW -

Wet Lay-up Recirculation

i BWI -

Babcock & Wilcox International

i

CA -

Auxiliary Feedwater

CF -

Main Feedwater

i CFR -

Code of Federal Regulations

i

CNS -

Catawb6 Nuclear Station

ECCS - Emergency Core Cooling System

. ESS -

Electrical System Support

l FME -

Foreign Material Exclusion

. F0SAR - Foreign Object Search And Retrieval

' FSAR - Final Safety Analysis Report

FTI Framatome Technologies Inc.

I- FWDS - Field Weld Data Sheet

.

IR -

Inspection Report

NDE -

Nondestructive Examination

NC -

Reactor Coolant System

NRR -

Office of Nuclear Reactor Regulation

i NSD -

Nuclear Station Directive

'..

NSM -

Nuclear Station Modification

OD -

Outer Diameter

4 PIP -

Problem Investigation Process

l

'

PWHT - Post Weld Heat Treatment

OA -

Quality Assurance

4

OC -

Quality Control

'

RCS -

Reactor Coolant System

SG -

Steam Generator

SGR -

Steam Generator Replacement

'

SGRP - Steam Generator Replacement Project

i SM -

Main Steam

. URI -

Unresolved Item

VIO -

Violation

i WPCS - Weld Process Control Sheet

I

1

!

!

'

!

a

4

ENCLOSURE 2

>

I

i

... _. - -

. -