B12992, Advises That fitness-for-duty Program Developed & Implemented That Applied to Individuals Obtaining Unescorted Access at Plants.Program Based on Industry Guidelines

From kanterella
(Redirected from ML20151W664)
Jump to navigation Jump to search
Advises That fitness-for-duty Program Developed & Implemented That Applied to Individuals Obtaining Unescorted Access at Plants.Program Based on Industry Guidelines
ML20151W664
Person / Time
Site: Millstone, Haddam Neck, 05000000
Issue date: 08/15/1988
From: Mroczka E, Sears C
CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
B12992, NUDOCS 8808250076
Download: ML20151W664 (2)


Text

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

e

'"o N UTILITIES cenerai Orrices . seiden street. seriin. Connecticut

  • ART O CONNECTICUT 06141-0270 August 15, 1988 Dockat Nos. 50-213 50-245 50-336 50-423 B12992 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Gentlemen:

Haddam Neck Plant Millstone Nuclear Power Station, Unit Nos. 1, 2, and 3 Fitness for Duty for NRC Contractors Connecticut Yankee Atomic Power Company (CYAPC0) and Northeast Nuclear Energy Company (NNECO) have developed and implemented a "Fitness-for-Duty" program that is applied to those individuals obtaining unescorted access at the Haddam Neck Plant and Hillstone Unit Nos.1, 2, and 3, respectively. The program is based on industry guidelines and requires that fitness for duty be ensured for all individuals requesting unescorted access to the protected area.

In order to provide the Staff unfettered access to th: plants (see 10CFR50.70(b)(3)), NRC Staff employees have been exempt from our "Fitness-for-Duty" program requirements. Periodically, CYAPC0 and NNEC0 receive letters from Region I requesting unescorted access for certain NRC Staff contractor personnel acting as representatives for the NRC. CYAPC0 and NNEC0 hereby document our understanding that the NRC Staff is taking responsibility to certify the "fitness for duty" of contractor personnel representing the NRC. On that basis these individuals are exempt from our "Fitness-for-Duty" program requirements. This will allow CYAPC0 and NNEC0 to support the Staff written requests that these individuals be granted unfettered access to the protected area.

.'O.

(

U.S. Nuclear Regulatory Commission B12992/Page 2 August 15, 1988 Please contact us if you do not concur with this interpretation or if you have any questions.

Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY NORTHEAST NUCLEAR ENERGY COMPANY E.h. N M E. J. Mroczka Senior Vice President By: C. F. Sears Vice President cc: W. T. Russell, Region I Administrator M. L. Boyle, NRC Project Manager, Millstone Unit No.1 D. H. Jaffe, NRC Project Manager, Millstone Unit Nos. 2 and 3 A. B. Wang, NRC Project Manager, Haddam Neck Plant W. J. Raymond, Senior Resident Inspector, Millstone Unit Nos. 1, 2, and 3 J. T. Shedlosky, Senior Resident Inspector, Haddam Neck Plant s