Submits Response to Violations Noted in Insp Rept 50-382/96-11.Corrective Actions:Operations Mgt Reviewed Event W/Operations Crew That on Shift When ACCW Pump B Inadvertently Started
ML20129B961
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/21/1996
From: James Fisicaro
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
W3F1-96-0173, W3F1-96-173, NUDOCS 9610230170
Download: ML20129B961 (5)


Text

.

g-

- Ent;rgy Operitirns,Inc.

"h PO. Box B Kiliona. LA 70066 Tel 504 739 6242 am s J. Fisicaro Nai%5?'

W3F1-96-0173 A4.05 PR October 21,1996 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPF-38 NRC Inspection Report 96-11 Reply to Notice of Violation Gentlemen:

In accordance with 10CFR2.201, Entergy Operations, Inc. hereby submits in Attachment 1 the response to the violation identified in Enclosure 1 of the subject inspection Report.

The staff expressed concern with the violation in the cover letter of Inspection Report 96-11, because the susceptibility of the auxiliary component cooling water (ACCW) system to a waterhammer had been addressed previously in inspection Report (IR) 95-23. Additionally, concern arose because the written instructions for an instrument l loop calibration activity were not sufficient to prevent a July 29,1996, inadvertent ACCW pump start and system waterhammer. Waterford 3 shares your concerns, and as detailed in IR 96-23, has taken comprehensive corrective actions to address I those matters. These corrective actions included, among other things: (1) instituting administrative controls to manually close ACCW pump discharge valves before starting the pumps at any time, and (2) operating the ACCW pumps continuously, with periodic venting to detect air intrusion. Those interim measures are intended to forestall future waterhammer events, until a more permanent solution (Design Change 3470) can be implemented during Refuel Outage 8.

9610230170 961021 23uvof PDR ADOCK 05000382 M'// l i

NF3C Inspection Report 96-11 Reply to Notice of Violation W3F1-96-0173 Page 2 October 21,1996 Regarding concern with respect to the inadvertent ACCW pump start and system waterhammer, due to the inadvertent nature of the pump start Operations was unable to first close and then throttle the associated discharge valves. Waterford 3 agrees that the Work Authorization Instructions should have been more prescriptive.

The corrective action (including implementation of DC-3470) as outlined in the violation response should address this concern.

If you have any questions concerning this response, please contact me at (504) 739-6242 or Tim Gaudet at (504) 739-6666.

Very truly yours, J.J. Fisicaro l Director l Nuclear Safety JJF/ PRS /ssf Attachment cc: L.J. Callan (NRC Region IV)

C.P. Patel (NRC-NRR)

R.B. McGehee N.S. Reynolds NRC Resident inspectors Office  ;

Attachmsnt to W3F1-96-0173 Page 1 of 3 ATTACHMENT 1 ENTERGY OPERATIONS. INC. RESPONSE TO THE VIOLATION IDENTIFIED IN ENCLOSURE 1 OF INSPECTION REPORT 96-11 VIOLATION NO. 9611-03 Technical Specification 6.8.1.a requires, in part, that written. procedures shall be maintained covering the applicable procedures recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978. Appendix A, Section 9, requires that the licensee have maintenanca procedures / written instructions appropriate to the circumstances.

Contrary to the above, on July 29,1996, Work Authorization (WA) 01149346, which provided written instructions for adjusting the process temperature meter for component cooling water temperature control loop manual / automatic station CC ITIC7070 B, was not appropriate to the circumstances in that the written instructions did not require returning the manual / automatic setpoint to its original state prior to returning the system to service and, as a result, Auxiliary Component -

Cooling Water Pump B inadvertently started automatically and caused a waterhammer in the system.

This is a Severity Level IV violation (Supplement 1) (50-382/9611-03)

RESPONSE I (1) Reason for the Violation Entergy believes the root causes of the violation are inadequate administrative controls and personnel error for the following reasons:

. Procedure Ml-005-563, Component Cooling Water Temperature Control Loop Calibration, Precaution Step 4.1.2 and Section 8.17, System Restoration, are misleading. This procedure provides instructions for the calibration of Control Loops CC IT7075A, CC IT7076A, CC IT70758, and CCIT7076B. The procedure must be used for calibration or periodic testing, and may be employed in troubleshooting suspected instrument malfunctions. Step 4.1.2 states,"When performing system restoration, the Auxiliary Component Cooling Water Pump A or B may start if the Nuclear Plant Operator (NPO) has not returned the setpoint on Manual / Automatic (M/A) Station CC ITIC7070 A or 8 to its original state, before connecting wires during performance of Section 8.17 (System Restoration)." The Caution in Secucq 8.17 states, " Failure to perform Step 8.17.1 may result in starting of the ACCW pump." Step 8.17.1 states,"Have Operations return M/A station CC ITIC7070 A or B Setpoint to its original state." An I&C Technician could misconstrue from the wording that a reset of the

- =

l .

Attachment to VV3F1-96-0173 .

Page 2 of 3 associated setpoint is required only where a wiring reconnection is necessary, since that is the only discussion. The caution, precaution, and

restoration section do not discuss action to be taken (setpoint reset) when
a card is removed and reinstalled as was the case in this event or for any other maintenance, f

j e Standards, Policies, and Administrative Controls are not sufficiently l prescriptive. WA packages are planned in accordance UNT-005-i 015 " Work Authorization Preparation and implementation", MD-001-

026 " Maintenance Work Center Planning," and the Planning Information Guide Notebook (PIGN). Requirements are in place that specify that the planner assemble appropriate work instructions

} in the job plan. For this event, the planner may have been influenced by the foreman's prior knowledge of the scope of the job, i since it appears that a thorough review of requirements was not i performed. Considering the importance and sensitivity of the i system being worked on, this job plan warranted more specific j' steps.

I q

l

  • The supervisor pre-job briefings did not include discussion on equipment
restoration which might have been expected, but was not specifically
l. required. The initial pre-job brief held on 7/18/96 to perform

. troubleshooting covered the precautions, limitations, and initial condition j section of procedure Ml-005-563, but the supervisor did not cover the

! restoration section of Ml-005-563. Another briefing was conducted with a j new crew ten (10) days later on 7/28/96 to continue troubleshooting and i corrective maintenance. This briefing also did not include discussion on  ;

the restoration section.

e Operations failed to appropriately reset the associated setpoint due to
inadequate turnover notes. The I & C Technician involved in completing
the M/A Station meter adjustment verbally notified, just prior to Operation's
turnover, the NPO that work had been completed but did not communicate i the need for setpoint restoration. During the Control Room Supervisor .

! (CRS) turnover from day shift to night shift the CRS noticed that the CCW  ;

temperature setpoint needed to be reset and communicated that to the oncoming CRS. The on
,oming CRS made a note on his list of turnover

! items. Later that night, while reviewing his list of turnover items, the CRS i on duty noticed an item dealing with ACCW, but due to the lack of detail in i his notes failed to recognize that he needed to reset the setpoint.

4 i

1

l Attachment to 1 W3F1-96-0173 Page 3 of 3 '

(2)_ Corrective Steos That Have Been Taken and the Results Achieved a) The ACC-126B setpoint was immediately readjusted to 85 F and the ACCW Pump B was secured.

b) Management expectations of what must be discussed in the course of pre-job briefings with respect to equipment restoration was presented to all Maintenance Personnel via a September 26,1996 j memorandum from the Maintenance Manager. )

l c) Operations management reviewed this event with the operations crew that was on shift when the ACCW Pump B inadvertently started.  ;

1 (3) Corrective Steos Which Will Be Taken to Avoid Further Violations a) Procedure Mi-005-563 will be revised to provide a clearer understanding of what the intent is and the consequences are for  ;

restoring a M/A Station as described in Step 4.1.2. l b) More guriance will be provided for the maintenance planners on when 1 more deta.i!ed work instructions are needed in a job plan, through  !

revision of the Planning information Guide Notebook. l

)

c) Operations will review the method by which turnovers are performed. 1 Particular emphasis will be placed on establishing how important items which have been discussed during the course of a turnover and which need to be performed at a later time in the shift are not overlooked.

d)- All of the control loops in the plant that utilize NTD cards to generate setpoints will be identified and a review will be completed to determine whether procedure changes are required to ensure that the setpoints are restored properly following any maintenance.

1 e) Management expectations of what must be discussed in the course of pre-job briefings will be reiterated to the Maintenance Department personnel through presentations at shop meetings.

(4) Date When Full Comoliance Will Be Achieved Based on the measures taken, Waterford 3 is in full compliance. Waterford 3 will complete Corrective Steps 3(a), 3(b), and 3(c) by 11/30/96, while Corrective Steps 3(d) and 3(e) will be finished by December 31,1996.

i

-