ML19329F193
ML19329F193 | |
Person / Time | |
---|---|
Site: | Midland |
Issue date: | 11/09/1976 |
From: | CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.) |
To: | |
Shared Package | |
ML19329F192 | List: |
References | |
NUDOCS 8006200878 | |
Download: ML19329F193 (20) | |
Text
l5 a ,
3
) s
- l. ' '
(C ,
QUALITY ASSURANCE PROGRAM Subject to those effectivity dates shown in Section II below, the Midland Project Quality Assurance Program will comply with the requirements of the following documents:
- 1. For Consumers Power Activities; The Consumers Power Company Quality Assurance Program Manual (Topical Report No. CPC-1A Revision h) 12 . For Bechtel (Arahitect-Engineer, Constructor) Activities; Bechtel Quality Assurance Program for Nuclear Power Plants (Topical)
Report No. BQ-TOP-1, Revision lA)
- 3. For Babcock and Wilcox (Nuclear Steam Supply System Supplier) Activities; B&W N.P.G.D. Quality Assurance Program for Nuclear Equipment (Topical Report No. BAW-10096A, Revision 3)
This compliance is subject to the following alternatives, interpretations, and exceptions:
I BECHTEL ALTERNATIVES AND INTERPRETATIONS Note: Unless specifically noted otherwise all organizations, groups, and personnel discussed in thisSection I are Bechtel organizations, groups, and personnel.
The following alternatives and interpretations apply to the implementation of the Bechtel QA Topical Report (BP-TOP-1):
A. Construction Work Procedures The Bechtel Quality Assurance Topical (Section 1.5.4, page 12, paragraph 1) requires that " Construction Managers are responsible for the management and technical direction of assigned projects, and for assuring that construction projects are provided with appropriate personnel, and are following prescribed division practices and procedures for conduct of construction activities.
80 6200
[ .
o . .
Chief ' Construction Engineers are responsible for providing division standard I work procedures to the projects". The Topical (Section 1.5.2, page 11, sub-paragraph 3) further requires that the Quality Assurance Manager be responsible for " Approving quality related procedures and manuals prepared by departments and projects within his division for conformance to quality assurance policies".
In lieu of this requirement the Bechtel Midland Quality Assurance Pro-gram requires that Construction personnel perform their quality program related functions using either division standard work procedures prepared by Construc-tion Engineering or project work procedures prepared by Project Field Engineer-ing personnel. The final decision on which to use rests with the Project Field Engineer. All quality program related procedures used by Construction personnel are approved by Project Quality Assurance.
Project Field Engineering has already prepared and is in the process of preparin- -imately 75% of the required construction work procedures.
Many ot .ae work procedures were prepared prior to the existence and issue of procedures issued by the Division Chief Construction Engineer.
B. Review of Quality Control Instructions The Bechtel Quality Assurance Topical (Section 1.6.1, page 14, subparagraph
- 13) requires that Project Quality Assurance " Review, prior to use, . . . Quality Control Instructions..."
In lieu of this requirement the Consumers Power Company Quality Assurance Topical Report reqaires that all Quality Control Instructions be reviewed and approved by Consumers Power Company Quality Assurance prior to use. This review implements the commitments for review described in Section 1.6.1 sub-paragraph 13 of the Bechtel Quality Assurance Topical.
-The Bechtel-Midland Quality Assurance Program also requires that this
- activity be audited "uy the Project Quality Assurance Engineer.
s m, - m
. 'N .
=
C. Titles In the following cases, Midland Project organizations and personnel
. have titles differing from those in Bechtel Quality Assurance Topical Report but the responsibilities are the same.
Bechtel Quality Assurance Topical Report Midland Project Title Title Materials, Fabrication and Quality Materials and Quality Services Control Services Department Department Field Construction Manager Project Superintendent Project Construction Quality Control Project Field Quality Control Engineer Engineer Field Contracts Administrator Field Subcontracts Administrator Division Chief Engineer Cognizant Chief Engineer D. Supplemental Interpretations of Regulatory Guide 1.37 (ANSI N45.2.1-1973)
Section 4 (Pre-Installation cleanliness) of ANSI N45.2.1 states " Items should not be delivered to the point of installation site sooner than neces-sary unless the installed 1:<tation is considered a better storage area". In lieu of this requirement items might, in some cases, be delivered to the in-sta11ation site sooner than necessary at the direction of the Project Field Engineer and will be protected in accordance with Section 5 of ANSI N45.2.1.
E. Supplemental Alternates and Interpretation of Regulatory Guide 1.38 (ANSI N45.2.2-1972)_
The following alternates and interpretation apply to ANSI N45.2.2:
- 1) Section 2.7. Classification of Items. The listings in paragraph 2.7.1 through 2.7.4 will be used as a guide in determining the categorizing of items under-levels A through D for the project. Categorization dif-fering from Section 2.7 will be considered acceptable provided that no
! degradation in commodity quality is assured. I k
\
' iT '
As in the case of electric motors, exterior pumps, and exterior valves, which are designed for outside service and could possibly be stored in
-areas other than those in which they are designated, i.e. outside service electdic motors shown in Level B could 'possibly be placed in a Level C area.
a The same would apply to exterior pumps and valves shown in Level C which I could possibly be placed in a Level D area. In al1 cases however, the 4
classifications shown in ANSI N45.2.2 will be reviewed and considered by field engineering.
- 2) .,Section 2.7.4 Level D Classification. The last sentence 1st. paragraph is interpreted to read "These items require protection against the elements, airborne contamination, and physical damage as necessary and commensurate with the ultimate use of the item". This determination is made by Field Engineering in accordance with Project prepared and Project Quality Assurance approved procedures.
- 3) Section 6.2.2 Cleanliness and Housekeeping Practices in Storage Areas.
Detrimental soil is defined as material or items which could degrade i
the stored material. '
F. Supplemental Alternates to Regulatory Guide 1.39 (ANSI Uh5.2.1 - lo73)
- 1) Section 2.1 Planning. The Project will use four cleanliness zones instead of the five zones listed in this paragraph. These zones will provide the necessary cleanliness and will provide less confusion in the field. l l
The requirements of zones I and II in the standard will be included in 1 1
Zones A auxi B of the field procedure. The requirements of Zone III of I I
the standard.will be. covered by including these items into Zone B or upgrading Zone C for the particular items. Zone IV will be included in Zone C except the restrictions on tobacco.or eating is not required.
x .1 !
- .c .
c
_ , - , m . _, _
. 'N .,,
'This zone can be upgraded to include these restrictions for particular items if necessary.
Zone V will be incorporated into Zones C or D as required.
Note:
Zone C provides no restriction except.that the areas will be maintained free of detrimental scrap materials and will be swept regularly. Protec-
- tive coverings will be utilized in work areas to minimize grease and oil spillage on finished surface. Zone D areas will be heavy construction areas without cleanliness restrictions and will be upgraded to Zone C when the heavy construction is completed.
Restriction List Zones A B C D Clothing changes Yes No No No Clean gloves, shoe covers, Yes Yes No No head covering
- Filtered air .
Yes No No No Material precleaning Yes No No No Material accountability Yes Yes No No Personnel accountability Yes Yes No No !
No use of tobacco or eating Yes Yes No No
- 2) ' Para 2.2 Procedures and Instructions. This paragraph requires procedures for safety and fire regulations. The Project will use procedures which I describe existing National State and Local codes and regulations to control' safety and fire. NFPA is the national fire code followed at the site.
G. . Alternates and Interpretations of Regulatory Guide 1.54 (ANSI N101.4-1972)
The following alternates and interpretations apply to the implor.entation ;
of Regulatory Guide 1.54 and ANSI N101.h. !
- 1) The painting requirements for the Midland project are specified in four project painting specifications, most of which were developed prior to the~ issuance of Regulatory Guide 1 5h. ANSI N101.h was l 1
zused extensively in the development of these snecifications and 1
_5 l
'w -
g i -
- q -- e - ,,y **~ , -
. ^% ..,
compliance to ANSI Nh5 2 is required by Consumers Power Company for equipment procured for the Midland project. Althourh not specifically required in all four specifications, ANSI N101.h and ANSI N101.2 are generally referenced and are used in the evaluation and approval of vendor painting procedures.
- 2) In instances where non-LOCA qualified paint is used on small components with a limited painted surface, such as valve operators, instrumentation, small accessory components and equipment trim, the FSAR vill provide the total surface area painted with these non-LOCA qualified paints to substantiate their limited application and therefore acceptable use. It is the applicant's position that upon completing the tabulation of the amount of non-LOCA qualified paint used inside the Midland containment, should this amount be below 100 kilograms, the amount vould be acceptable. In the calculation of this total weight, only components exposed to the LOCA environment vill be consider,ed. If upon completion of the tabulation of the amount of non-LOCA qualified paint used inside containment, this amount exceeds 100 kilograms, it is the applicant's position that the following vill be considered in conjunction with system characteristics (sump screen size and spray nozzle openings) to determine acceptability or necessity of any corrective actions:
- a. The areas of paint exposed to the containment LOCA atmosphere
- b. The mode of paint failure (i.e. , flakin6 or solubility)
- c. The potential of the paint reactants reaching the containment sump, considering possible surrounding traps such as insulation, ete H. Alternate to Pegulatory Guide 1.58 (ANSI Nh5.2.6-1973)
The Regulatory Guide states that the provisions of ANSI Nh5.2.6-1973 are." generally applicable.....during fabrication prior to receipt of items
at the construction site". The project will not impose ANSI N45.2.6 on suppliers during fabrication prior to receipt of items at the construction site. Instead, the following activities are performed to ensure that off-
' : site inspection, exam'ination or testing is performed adequately. Bechtel
. procurement documents will require that the supplier's Quality Assurance program _ provfie measures to assure that' personnel performing safety-related
. inspections, examinations and tests are qualified to perform these activities.
Such measures include procedures for qualification of personnel describing
_the minimum experience, training and proficiency testing required for quali-1 fication. The measures also include requirements for records documenting qualifications for each of the supplier's inspection, examination, and testing y personnel. Personnel qualification procedures will be reviewed by Bechtel prior to initiation of inspections, examinations, or tests.
! Also, Bechtel performs surveillance inspection at suppliers. facilities by using inspectors qualified in accordance with ANSI N45.2.6. Quality Assurance-j audits are performed ~ on suppliers and additionally, nondestructive examinations performed according to-the quality requirements of Section III of the ASME ,
Boiler and Pressure Vessel Code are performed by supplier personnel certified
^ '
to SNT-TC-1A.
I.- Supplemental Alternate to Regulatorv Guide 1.64 (ANSI N45.2.ll-1974)
Paragraph C-2, of the Regulatory Guide places restrictions on the use of the supervisor for design verification. As an alternate the following controls will be exercised. Design verification may be performed by the 4
originator's supervisor if the supervisor is the only individual in the project team competent to perform the design verification. In such cases..an addi-
. tional1 review will be performed by either the next higher-level of supervision
- or'by,off-project per'sonnel. -These personnel are qualified in the area of design review and verification.
-T-
. N .s J. Alternate to Regulatory Guide 1.88 (ANSI Nh5.2.9-197h)
Section 5.6 of ANSI Uk5 2.9 requires that the permanent record storace facility have " structure, doors, frmnes, and hardware class A fire rated with a recommended four hour minimum rating." In lieu of this the existing Jobsite record storage facility has a two hour fire rating.
K. . Alternates and Intervretations of Regulatory Guide 1.9h (ANSI Nh5.2.5-197h)
The following alternates and interpretations apply to ANSI Nh5.2.5:
- 1) Sections 1.h Definition of Sampling Point and h.8 In-Process Tests on Concrete and Reinforcing Steel. These sections seem to require the sampling of concrete at the truch discharge or the end of the pump line. For the Midland project, the concrete receives its
, final mix at the central batch plant, and is transported by agitator trucks to the final conveying system.
The sampling point for the compressive strength test cylinders is from the discharge of the central batch plant stationary mixer, based on the following:
ANSI Nh5 2.5 Section h.8 states that " Samples for inprocess tests shall be taken at the sampling point in accordance with ASTM C 172."
ASTM C 172, Section 2, Note 3, reads: " Sampling should normally j .
be performed es the concrete is delivered from the concrete mixer to the conveying vehicle used to transport the concrete to the forms." ASTM C 172, Paragraph 3.2.1, Sampling from Stationary Mixers Except Paving Mixers, gives explicit instructions for stationary mixer sampling.
O I
^
- l Compressive strength test ' cylinders are cast from representative I samples taken from the discharge of the batch plant stationary l
! mixer in accordance with Pararraph 3, ASTM C 172. Slump, air I content, unit weight and temperature of the concrete vill be recorded when cylinders are being cast. For purposes of correla- i tion, cylinders vill also be cast from a sample taken at the trans-
! port discharge of the same batch from which a sample was taken at the stationary mixer. After correlation has been established, correlation cylinders are continued on a periodic basis to verify the correlation.
The conveying vehicle is defined as an agitator truck. The drums are turned at agitating speeds and not at mixirg speed: because the t
concrete is completely mixed before being loaded as evidenced by the mixer uniformity tests of ASTM C 94.
Concrete samples from the-batch plant mixer allow for better control f
of preparing samples, as well as less disturbance of cylinders from preparation through initial curing.
The sampling point for final acceptance of air content, slump and ,
I temperature is at the truck discharge except for concrete conveyed by pump. Pumped concrete is sampled at the pump line discharge.
l The production control for air content, slump and temperature can be at the batch' plant discharge or truck discharge provided that a correlation program is developed as recommended by ACI/30h
~
_9 .
-s j Paragraph 9 7. The correlation program compares the test results for the same batch between the batch discharge and truck or pump discharge. ,
- 2) Section h.5, Concrete Placement. Regulatory Guide 1.9h (C-3) requires that ACI-309-72 be used to determine the adequacy of t
consolidation equipment. ACI 309-72 was incorporated into the construction specification in 1973, uubject to the following i alternates:
a) Alternate to Equipment Requirements i
. ,/
The project concrete placement specification was written in 1970, and based on the then current ACI Committee 609 report.
U f The equipment currently in use on the project was purchased in accordance with the ACI Committee 609 report, and has been maintained in conformance with it to date. Field inspection of concrete placements and concrete cores indicate satisfactory concrete consolidation has occurred. We therefore see no sound reason to justify the replacing of the project equip =ent to meet the recommendations of ACI 309-72, and discarding equip-ment that is currently performing in a satisfactory manner, b) Alternate to Lift Thickness Requirements ACI 309-72 section 7.1 states: "The concrete should normally be deposited in layers 12 to 18 inches (.30 to h5 cm) thick (depending on the length of the vibrator head and other factors)."
Other ACI specifications and recommendations for lift thickness 4
are as follows:
-, -,~- ~~
g n,--- - ~- g , , -- g ,yg -
g-
s i) ACI 301-72 Chapter 8 on " Placing," Section 8.3.1 states:
" Concrete shall be deposited continuously, or in layers of such thickness that no concrete vill be deposited on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness within the section."
ii) ACI 301-72 Chapter lh on " Massive Concrete," Section Ih.h.3 states: " Concrete shall be placed in layers approximately 18 inches thick."
iii) ACI 301-72 Section 8.3 references ACI 30h for detailed recommendations for depositing concrete. ACI 30h-73 Chapter 6,. Section '6.1 states: "It (concrete-ed.) should be placed in horizontal layers not exceeding 2 ft. (60 cm) in depth, avoiding inclined layers and cold joints."
The project construction specifications require that concrete be ,
placed.in horizontal layers "of not greater depth than 2h inches t
so that satisfactory consolidation can be achieved with vibrators." ,
i Field inspections of concrete placements and concrete core samples I I
indicate satisfactory consolidation and placement of concrete has ,
, 1
- l occurred. By combining the foregoing requirements and other I related factors (concrete mix consistency, and results of field inspection), the use of lifts not exceeding 2h inches is in accordance with ACI specifications.
l 1
1
\
l l
4 -
h
- 3) Table B Required In-Process Tests. This table requires that the compressive strength of grout be in-process tested daily during production to the requirements of ASTM C 109 The following alternates to the testing of grout will be implemented:
a) ~ Batch Plant Mixed Grout The specifications require that each class of concrete has a companion grout mixture for use on construction joints, buttering pu=p lines and such other applications as shown on the drawings. As appropriate to the concrete mix, the grout mix is specified to be the concrete mix vith the coarse aggregate removed, leaving the cement, pozzolan, sand and admixtures in the same ratio a$s before and enough water to provide the desired consistency, but not exceeding the maximum vater /(cement +
pozzolan) ratio established for the concrete mix. Since this vill produce a grout at least as strong as its companion concrete (due to the high cement content per cubic yard), testing of all the materials used in manufacturing grout is done as part of the concrete in process testing program, and this accomplishes satisfactory quality control of the grout.
b) Premixed Grout Factory packaged grout which requires addition of water and mixing in accordance with the manufacturer's instructions vill be tested in accordance with ASTM C 109 for each lot purchased as a quality control check on the factory's production. Since the project specifications require proper storage to prevent deterioration, there is no reason to require daily testing.
i i
1
m 3
h) Section b.91, Qualificatica of Cadweld Operators. The standard can be interpreted to imply that qualifications of splicinr crews is required for each position and each bar. size. The Bechtel position is that the qualifications for each position vill be for the largest bar to be used. This is also consistent with the May 15, 1973 staff memo and CPCo's Regulatory Guide 1.10 position.
- 5) Section 5.h, High Strength Bolting a) The installation and inspection of high strength bolted joints are accomplished by one of three methods. Two of these methods, (i.e. , automatic cutoff impact vrench, and the turn-of-the-nut method), concur with ANSI Uh5.2.5 requirements.
The third method, the use of direct tension indicators, is a new method permitted by the Errata of October 22, 197h to the "AISC Specification for Structural Bolts Using ASTM A 325 or A h90 Bolts."
- The quality control procedures required for the use of direct tension indicators are as follows:
i) To verify the load indicating qualities of the load indicators, at least three load indicators from each bag or box shall be verified in a calibration device similar to that required for vrench calibration. If nut face vashers are used between the indicators and the nuts, the indicators shall be tested with vashers at the rate of three washers from each bag or box.
Each verification test shall show not less than the specified gap when bolt is tightened to the specified tension.
. l I
u'
N ii) Load indicator washers chall be installed in accordance with the manufacturer's instructions. When a load indicator is required under the nut a special nut face vasher shall be fitted between the indicator and the nut.
iii) Bolted joints made with load indicators shall be inspected visually to ensure that all bolts have the load indicators
- properly installed and to the proper gap. At least 20%
of the bolts in each connection but not less than two bolts shall be checked with a feeler gage to determine the bolts are properly tightened.
iv) Direct tension indicators used with bolts that have been tightened to the full extent specified in Section 5 of the AISC specification shall not be reused.
b) The Midland project permits waiving of the AISC requirements for inspection by torque or power vrench provided special inspection procedures are followed.
~II. EFFECTIVITY DATES
. Subject to the exceptions contained in Section III below, the pre- )
ceding commitments will be implemented on the following dates for all subsequent safety-related activities relative to the Midland Project:
A. For Consumers Power Activities; April 21, 1976
-lk- ,
m 5
. . q l
B. For Bechtel Activities; April 1, 1977 C. For Babcock and Wilcox Activities .hw^vhd Wh E
&O h2 0MM W O '
T&L P&-
III. EXCEPTIONS
'The following exceptions relate to specific commitments which vill not be implemented because i=ple=entation vould require unwarranted modifications of the Midland Project design, procurement, fabrication or construction:
A. General Excention to Consumers Pove , Bechtel and Babecek and Wilcox Co.mitments No attempt vill be made to change procurement documents which have been issued prior to the effectivity date established for the Consumers Power, Bechtel or Babcock and Wilcox commitments in order to comply with thone' commitments. The relevant commit-ments vill be applied to procurement documents which are issued on or.after the effectivity date.
B. Specific-Exceptions to Babcock and Wilcox Co mitments
- 1) Section 2.2.1, paragraph 1 of the B&W Topical Report reads as follows: "The degree of QA involvement with any specific
, equipment / component is determined by the safety classificatien system defined in the B&W Safety Classification Specification
' derived from Ecculatory Guide 1.26 and IEEE Standard 308-1973."
In addition to the precedinF;, the Project Position for Regulatory Guide 1.26 (as described in R. C. Bauman's
\
l
, e L
'S T
October 10, 1975 letter to Mr Roger Boyd and as supplemented by R. C. Bauman's February 5, 1976 letter to Mr Roger Boyd aunt as evaluated in S. A. Varga's September 2h,1976 letter to S. H. Howell) is also a basis of the safety. classification system.
- 2) The following design documents are discussed in the B&W Topical Report:
Topical Design Document Report Section Pararrach System Requirements Specification (S.R.S.) 2.2.2 2 3.2 1 3.2 12 4.0 1
. h.0 2 System Descriptions (S.D.) 3.2 1 3.2 7 3.2 12 Balance of Plant Criteria (BOP) 3.2 12 Contract Information Sheets (CIS) h.0 1 In addition, B&W procedures which implement the Topical Report identify a Plant Parameter List (PPL) and Technical Deviation List (TDL). The TDL is a tabulation of all the technical and performance differences between the B&W Standard Plant and the
,e "As-Sold" contract plant. For new projects, the issuance of
,. the TDL establishes the preliminary contract technical baseline and is the basis for preparation of the contract technical documents. The PPL is used for new contracts to identify major factors of plant design.
e 8
- 4-
,- . . s, None of the above documents have been (or vill be) prepared for the non-fuel components supplied for the Midland Project. For new projects, these documents are used as the basis documents for the preparation of Equipment Specifications and Balance of Plant Criteria. However, these documents became a require-ment of the B&W Design Control system after Equipment Specifications were issued and procurement activities initiated for the Midland Project. In addition, Balance of Plant Criteria requirements have been satisfied by other means without recourse to these documents. Formal Balance of Plant Criteria documents vill not be prepared since this criteria has been forwarded to the Architect Engineer in the form of correspondence from B&W to Bechtel and B&W vill review Bechtel desiEn documents which contain NSSS interfaces for the adequacy of those interfaces.
Therefore, since Equipment Specifications and Balance of Plant Criteria have been prepared without recourse to the SRS, SD, PPL, CIS and TDL documents, these documents are not needed for the Midland Project.
- 3) Section 17 and Appendix A of the Topical Report cor.mit B&W to implement the requirements of ANSI Nh5.2.9-1974. Section h.3.1 of ANSI Nh5 2.9-197h requires for receipt control of QA Records that the system shall include: "A Records Checklist designating the required QA Records."
A Records Checklist has not been (and vill not be) prepared for the Midland Project. The majority of B&W generated QA records
\
4 4
'T
. . )-
(i.e., calculations, specifications, procurement documents, etc) have been prepared and filed without recourse to a records checklist. However, they are listed on the Documents Historical Listing (DHL). The DHL is the output of an automated system that identifies and reports the status of contract documents originated by B&W. It also provides a convenient means of verifying that the necessary records have in fact been generated.
The remainder of QA records to be generated by B&W for the Midland Project consist primarily of documents to sunport FSAR activities, Core design and site support activities (i.e., Field Changes , Site Problem Reports, etc. ). The need for the forcroing records is identified in vork authorisations approved by the B&W Project Manager for the Midland Project. As these documents are prepared, they vill be listed on the DHL.
The Quality Requirements Matrix (ORM) described in Section h of the Topical Report will continue to serve as the Records Checklist for vendor generated documents. The QEM identifies the QA Records required from vendors by the B&W procurement documents. As vendor documents are received, they are listed on the DHL described above. The B&W QA Engineer for the Midland Project is required by B&W administrative procedures to verify that the vendor QA Records required by the QRM have been received and properly dispositioned.
In summary, because the majority of B&W generated QA Records have been prepared and over 60% of the required vendor QA
., . . - . , - - ~ . ,.i.,.,.
. . , ).
Records ~have been received, a Records Checklist will not be prepared. The DliL and QRM provide an adequate r.eans of verifying that the required QA Records have been generated.
4 4
i h
. I o
[
I :
1 i
I k
. t O h i y $ 1 % y w -
g --- *? t-*re+ t We y -=--ga pw*- T- v-- m- -r + 7v ~ -+-e
N_C A;w 195 U.s. NUCLEA9 RECULATCGY CL AISSION DOCKET Nuunr n a.res , ,,
g, 3 2Y3.30
'""~~~
NRC DISTRIBUTION roR PART 50 DOCKET MATERI AL TO: Mr Boyd FROM: Consumers Power Company DATEor D cu N 9-76 Jackson, Michigan R C Bauman DATE RECEIVED 11-10-76 CLETTER ONOTORIZED PROP INPUT FORM NUMBER oF COPIES RECE!VED C ORIGIN AL $UNC LASSIFIE D OCopY one signed DESCRIPTION ENCLOSURE ,
Ltr re their 11-3-76 Itr. .'.trans the follow: Quality Assurance Reg Guide Responses.........
(10 Cys enc 1 rec'd)
PLANT NAME: Midland 1 & 2 SAFETY FOR ACTION /lNFORMATION ENVTRO 11-11-76 ehf A53IGNED AD: Aegycian an. , , , , , , ,
BRANCll CHIEF: . , BRANCIT CHTEF?
/ PROJECT MANAGER: ffsa e,. // PROJECT PANAGER!
/ LIC. ASST.: .54 **
- c. U 4h*" LIC. ASST.!
INTERNAL DISTRIBUTION
[TEG FILE 7 SYSTEMS SAFETY p;2h u qTEMR SITE SAFETY S
/ NRC PDR llEINEMAN TEnpscn ENVIRO ANALYSIS
/ I&E (4 SCHROEDER BENAROYA DENTON & M"T T ER OELD L41HAS COSSICK & STAFF ENGINEERING IPPOLITO ENVIRO TECH _
H,LFC MACCX~RRY KI_RKk'OOD ERNST
. CASE KNIGHT BALLARD HANAUER SIHWEIL OPERATING REACTORS SPANCT.ER
_ JgRLEjs PAWLICKI STELLO RTTE TECH _
PROJECT MANAGE!ENT REACTOR SAFETY OPERATING TECH. CMfiTLL BOYD ROSS EISENHITr STEPP
,/L _ COLL _ INS NOVAK SHAO HULMAN HOUSTON ROSZTOCZY BAER /
PETERSON CilECK BUTLER SITE _AFALYSIS I MELTZ GRIMES VOLLMER \
Z UcuEMES AT .s I nusCn SKOV110LT SALT 7. MAN J COLLINS RUTHERG KRMCFR
, , EXTt!HNAL DISTRIBUTION CONTHOL NUMBC H _
/ LPDR:f M7Fg A4_ #il NAT_IAB : BR00KIIAYI;N_ JET,.L41) _
TIC: REC. VIE ULRIKSON(ORNM NSIC. IA PDR ASI.B ;
" g
~ CONSULTANTS .. s ACRS CYS IIOLDING/' ENM' ---
bD w L
Nild t ohm sub Q #d)
-