QA Program Manual for Midland Nuclear Plant,Vol 1.
ML20052F279
Person / Time
Site: Midland
Issue date: 04/02/1982
From:
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML20052F234 List:
References
CPC-1-A, CPC-1-A-R12, NUDOCS 8205120311
Download: ML20052F279 (102)


Text

._ _. __.._aa . _s-.____e* _ ar . - - ~m.a- __ _ WI - -a . _ ,-,--s -

CPC-1-A O

QUALITY ASSURANCE PROGRAM MANUAL FOR THE MIDLAND NUCLEAR PLANT VOLUME I O

f

n. -

, [m I

I.JO C O D JEi_io__*_ o.n oo n 222 i .

--] -

no .. ,, J, " -

r-""",2 "

A _4 __ K t L -

@e pesar Campagy CONTROLLED ASSIGNED TO:

O _E UNCONTROLL5iD MANUAL NO:

8205120311 820426 PDR ADOCK 05000 A

Page i of xi j

' QUALITY ASSURANCE PROGRAM POLICY Revision 12 eh / Date 4/2/82 AUTil0RITY AND RESPONSIBILITY (V ConstmerS POWtf

[^

oW.x comma o 1 , .c J D setty k\ ' l' .r, C , EGiil2ily he e

(""' */ ' 6' 8* " l

< snj vreudent A

Geneemt officas: 212 West Mkh6een A, eave. Jackssn. Mahlges s9201 * (5ti) 7081600

SUBJECT:

Statttent of Authority and hsponsibility Fecardins; the Censumrs Power Company C;aality Aanurance Frogram for the Midland Nuclear Plant Consumers Power Cenpany has drumented its Quality Assursnee Pro; re.m Nr the Midland ::uclear Plant in a corporate nanual crtitled, Ccr..m. .?r: :' w r Compsny Ounlity Anrur tr.ca Fr.vem : nr-ni for the ?!i.ibn 1 ':rl tr .i i n .

This nsnual outline: t'* acticas tast ere inpio:wnted ' yc Concue.:: iover Company pc.rsonnel during dasi;:n, prccurer.cnt, constrvtion, and uctir.;

of the safety-related portions of the !-fidland D. clear Plant.

m

\ The Consumera Power Cor.prsny Oxality Accurance Prcrrn- for the :tidian1 Nuclear Plant complies with the Quality Assurance Zoquirement: 0 ntsinei in Appendix 3 cf 10CTE50, " Quality Acsarance Criterin. for :helerur Love r

~

Plants and Fuel Reprcces ine. Plents" Snd rcyonds to the nJditicn:s1 guidsnee cont tir.e41 in the A :GI ::k5.2 series of standards an1 cerNspend-ing Regultttery Guides.

As Chief Faceutive Officer of Cor.suners Power Octany, I have the ultir.ste mant,gement rtuthority for the enabli:;ni.ont of corporate QA policy. Tnn policy shrdi be to conply with tPc trovicienc of tpplicabh le:-katier, and reCul'ttions and to crnit to the require.ients stnted in the pre elo .s paracraph. Auti.ority for the establishnent of necific individuil Qaali y Assurance Prorr.e. Policies to ecaply with this overall policy is r.scicne i to the Vice Tresident - Pro.fects, Enr.incerine ard Constracticn f ar the design ar.d ern;truction ph.ses. Aut mrity for tha preparation ci speaific Quality Assurunee Precrrs Procedure.; by which to implencnt these Policies is asrigned, in turn, to the Director, Enviror.ncnts1 and Quality A surance who repcrts t t ne Vice President - Projects, Pr:J ncering i and Construction.

The Quality Acsurance Program Policies and Procedurec are naniitor/ require-ments which mu.st te inplemented and enforced by ull respcnsible orfAni:stions and individuals.

/

/ M A2 O /

U c

1 1

1 QUALITY ASSURANCE PROGRAM POLICY Page 111 of xi l n I h!

  • / -

Revision 12 Date 4/2/82 i CollSumtm Power QUALITY ASSURANCE PROGRAM POLICY INDEX Policy No Title 1 Organization 2 Quality Assurance Program -

3 Design Control 4 Procurement Document Control 5 Instructions, Procedures and Drawings 6 Document Control 7 Control of Purchased Material, Equipment and Services 8 Identification and Control of Materials, Parts and Components 9 Control of Special Processes 10 Inspection I

11 Test Control

(

i j 12 Control of Measuring and Test Equipment 13 Handling, Storage and Shipping 14 Inspection, Test and Operating Status 15 Nonconforming Items 16 Corrective Action 17 Quality Assurance Records l 18 Audits 19 Program Review 20 Progr a Reporting pr0182-0215b-13-167

' i

. QUALITY ASSURANCE PROGRAM POLICY [gc1j-a

,, 2 Date 4/2/82

% VOLUME I Wl:UAL REVISIONS APPROVED BY REVISION C3ns;:3:rs Powtf EJELVE TO THE CONSUMERS POWER COMPANY TOPICAL REPORT Page Rev Page Rev Policy No No No Current Date Policy No No No Current Date Auth & Resp i 12 4/2/82 9 1-3 12 4/2/82 Approvals 11 12 4/2/82 10 1-3' 12 4/2/82 Index 111 12 4/2/82 11 1-3 12 4/2/82 Register iii-a 12 4/2/82 12 1-3 12 4/2/82 Introduction iv '12 4/2/82 13 1-2 12 4/2/82 Introduction v 12 4/2/82 14 1 12 4/2/82 Definitions vi 12 4/2/82 Definitions vii 12 4/2/82 15 1-2 12 4/2/82 Definitions viii 12 4/2/82 16 1-3 12 4/2/82 Definitions ix 12 4/2/82 s 17 1-3 12 4/2/82 1 Definitions x 12 4/2/82 Definitions xi 12 4/2/82 18 1-3 12 4/2/82 1 1-21 12 4/2/82 19 1-2 12 4/2/82 2 1-11 12 4/2/82 20 1-2 12 4/2/82 3 1-3 12 4/2/82 4 1-3 12 4/2/82 5 1-4 12 4/2/82 6 1-4 12 4/2/82 7 1-4 12 4/2/82 8 1-2 12 4/2/82 O

pr0182-021Sb-13-167

QUALITY ASSURANCE PROGRAM POLICY Page iv of xi

@ Revision 12 G \ # Date 4/2/82 CC M um f3 PQw tf The Consumers Power Company Quality Assurance Program B!anual for the !!idland Nuclear Plant consists of policies and procedures which comply with current NRC regulatory requirements and industry codes and standards in effect during design, procurement, construction and preoperational testing of the Plant. Specific NRC and industry documents that contain the requirements, including the issue dates in effect, are identified in the !!idland Nuclear Plant's Safety Analysis Report. The l requirements established by these documents form the basis for the Consumers Power Company Quality Assurance Program, which is implemented to control those structures, systems and components listed in the Plant's Quality List (Q-List).

As additional and revised requirements are issued by the NRC and professional l organizations involved in nuclear activities, they will be reviewed for their impact on this ?!anual, and changes will be made where considered neeessary.

CPC-1-A - Consumers Power Company QA Program Topical Report is Volume I of this

?!anual and contains Quality Assurance Program Policies applicable during the Plant's design and constr.uction and preoperational testing activities. l CPC-2-A - Consumers Power Company QA Program Description for Operational Nuclear Power Plants describes the Quality Assurance Program for the operation phase of the tilaland Nuclear Plant including plant modifications.

C

  • The initial nuclear fuel procurement activities for the l!idland Nuclear Plant were performed under the requirements of CPC-1-A. Sirce these activities are now complete, no reference to them is made in this revision. All future fuel procurement activities will be performed under CPC-2-A.

Spare parts procurement by the !!idland Plant Technical Department is conducted in accordance with the provisions of the !!idland Plant Administrative Procedures which were developed to address the requirements of CPC-1-A, Revision 11. These procedures are currently being revised to meet the requirements of CPC-2-A.

Quality assurance for this activity is the responsibility of the Quality Assurance

- Nuclear Operations Department as described in CPC-2-A.

The " BASIS DOCUMENTS" listed in each policy identifies the specific ccdes, NRC regulatory requirements, and industry standards related to each of the eighteen (18) criteria contained in NRC Document 10 CFR 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reorocessing Plants. Each Quality l Assurance Program Policy defines the action that will be taken by Consumers Power Company or its Suppliers in response to the basis documents, and assigns responsibility for these actions to individuals or organizational units within the Company or to Suppliers. The Quality Assurance Program Policies are approved.by the Vice Presidents in charge of the organizations responsible for their implementation. The Director - Environmental & Quality Assurance is responsible for the preparation, acquisition of approvals, distribution and revision of the Quality Assurance Program Policies.

n

(

  • O' pr0780-0415a-13-167

/' QUALITY ASSURANCE PROGRASI POLICY Page v of xi

((~Q

\p Revision 12 Date 4/2/82 INTRODUCTION C; m !DSf3 POWOT Volume II of the Manual contains a series of Quality Assuran'cc Program Procedures l that describe how the ccmmitments made in the individual Quality Assurance Program Policies are implemented. Each Quality Assurance Program Procedure identifies the organizational element responsibic for a specific activity and the method of accomplishing that activity. The Quality Assurance Program Procedures are approved by the heads of the Consumers Power Company interfaci~ng departments l responsible for their i=plementation. The Director - Environmental & Quality Assurance is responsible for preparation, acquisition of approvals, distribution and revision of the Quality Assurance Program Procedures for Design and l Construction.

The specific action taken by each Consumers Power Company' Department to implement the requirements identified in the Quality Assurance Program Procedures is detailed in Consumers Power Department, Plant, Section or Unit Procedures. These working level procedures are prepared, maintained, controlled, issued, and impicmented by the Departments, Sections, and Units responsible for implementing the Quality Assurance Program.

O O

pr0780-0415a-13-167

Page vi of xi g

QUALITY ASSURANCE PROGRAM POLICY Revision 12

,V } .

Date 4/2/82 LIST OF DEFINITIONS Consumers Power The following terms are used in the Quality Assurance Program Policies. Definitions contained in ANSI N45.2.10, " Quality Assurance Terms and Definitions," are not re-peated in this section. Additional definitions related to the associated Quality Assurance Program Procedures are defined in the individual procedures. l Adiustment - Operational alterations performed on an item of test equipment prior to its use which affect its output, but which do not constitute calibration checks.

Approved Bidder - A Supplier who, by his past record or present Quality Assurance capabilities, is qualified to supply products or services to Consumers Power Company.

Audit - A documented activity performed in accordance with written procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of a Quality Assurance Program have been developed, documented and effectively implemented in accordance with specified requirements. An audit does not include surveillance or inspection for the purpose of process control or product acceptance.

Auditor - One qualified to examine Quality Assurance practices and verify whether p requirements are being =et.

Balance of Plant - Nuclear power plant items and equipment not designed, furnished or installed as a part of the Nuclear Steam Supply System or its auxiliary systems.

Basis Documents - Those NRC and industry documents which contain the requirements that form the basis for the Consumers Power Company Quality Assurance Program.

Bid Package - The total of drawings, specifications, codes, standards, quality and other requirements that describe the task on which a prospective supplier will bid.

Calibration - Comparison of an item of measuring and test equipment (M&TE) with a reference standard or item of M&TE of closer tolerance to detect and quantify inaccuracies and to report or eliminate those inaccuracies by adjustment.

Calibration Standard - Any object or equipment which is used as a known reference or standard against which another piece of test equipment is calibrated.

Certified Personnel - Personnel whose qualifications have been attested to in writing.

Code - A recognized written standard or collection of rules or practices for using or processing materials, or for the skill involved in use or processing.

Construction Phase - Activities at the building site necessary to erect and verify proper installation and performance of nuclear power plant facilities prior to initial fuel loading.

V pr0182-0215b-13-167

Page vii o xi QUALITY ASSURANCE PROGRAM POLICY Revision 1-

, Date 4/2/82 LIST OF DEFINITIONS CC1150mtf3 00Vf2f Construction Tests - Those tests nece'sarys to verify that the installation of systems 12 complete and complies with the applicabic specifications, standards, codes, drawings and engineering information. it includes tests such as: Hydrostatic t:2 ting, meggar testing, continuity testing and cleanliness testing.

Contract - A document for the procurement of services which describes the technical and Quality Assurance requirements by inclusion, reference or attachment.

Corrective Action - Action taken to correct and preclude recurrence of significant c nditions adverse to the quality of items or operations.

Corrective Maintenance - Maintenance performed to correct an abnormal or incorrect situation, such as the replacement of a faulty relay.

D:aign Controls - Methods for assuring that basic design requirements are formalized t.nd translated into design documents with proper review to assure the scheduled release of a valid design.

Dwign Criteria - Statements of the form, function, and interface requirerrents within wall-defined limitations.

Design Documents - Documents furnishing evidence of the quality of the design of structures; systems or components. Includes such documents as drawings, system des-criptions, specifications, standards, material lists, technical manuals, design cciculations, and design analyses.

D: sign Input - Those criteria, parameters, bases and other requirements upon which the detailed final design is based.

Drsign Phase - Procurement, licensing and design activities frem project initiation to initial fuel loading.

Duign Requirements - Documents that set the functional requirements, operating conditions, safety requirements, performance objectives, design margins and design life. Included are any special requirements for size, weight, ruggedness, materials, fabrications or construction, testing, maintenance, operating environments, safety-c2rgins and derating factors.

D: sign Review - Critical review of the design in order to provide assurance that the cctions leading to the design output, such as drawings, calculations, analyses, and sp;cifications have been satisfactorily performed and the information included in the d: sign output is correct.

Document -

Instructions, procedures, drawings or other instructional-type manuals or caterial directly af fecting a quality or safety-related activity.

Equipment - A combination of items or material in either subassembly or complete form.

pr0182-0215b-13-167

Page viii of xi QUALITY ASSURANCE PROGRAM POLICY (pj /w( g' Q ,

Revision 1 Date 4/2/82 Cor4Umsts powtr U3 "3 Hold Point - A checkpoint in a sequential operation at which certain data are taken, inspections made, or approval required before the next sequential step can be taken.

Hot Functional Tests - Tests conducted at completion of preoperational tests. The nuclear steam supply systems and auxiliary systems where possible are brought to rated temperature and pressure to demonstrate satisfactory performance.

Inspection - Characteristic by characteristic, or step-by-step comparison of the "as required" versus "as is" condition by observation or direct measurement for the pur-pose of making a determination as to the acceptability or unacceptability of the item or activity under evaluation.

Inspection and Test Plan - A listing, with optimum sequencing, of all the inspections and tests required to be performed for a specific item, component, structure or system.

Interface Control - Methods to assure that proper interaction and communications are effected for activities. Also includes consider.ation that components and structures are geometrically and functionally compatible and that materials are compatible with both process and environment.

O Maintenance - Tests, calibr;, aon, adjustments and repairs performed in order to keep equipment, components, or systems in satisfactory operating condition. l Measuring and Test Equipment (M&TE) - Devices or systems used to calibrate, measure, gage, inspect or control in order to acquire research, test or operational data; to determine compliance with design, specifications or technical requirements. M&TE does not include permanently installed operating equipment or test equipment used for preliminary checks where absolute accuracy is not required; ie, circuit checking multimeters, etc.

l National Standards - Systems, instruments and materials standards maintained at or issued by the National Bureau of Standards (NBS) or other designated institutions and the values for natural physical constants and conversion factors recommended by the NBS.

Nonconformance - A deficiency in characteristic, documentation, or procedure which renders the quality of an item unacceptable or ind .cerminate and which is considered significant to quality or safety. Examples include: Physical defects, test failures, incorrect or inadequate documentation, or deviation from prescribed processing, inspection, or test prt,cedures.

Nondestructive Testing (NDT) - The determination of the performance capabilities for materials, components, structures, or systems by measurement without imparing their usexulness.

/] Nuclear Fuel - Nuclear fuel assemblies designed and' constructed by a nuclear fuel V fabricator and suitable for use in a nuclear steam supply system and the associated pr0182-0215b-13-167

N Page ix of xi

' QUALITY ASSURANCE PROGRAM POLICY Revision 12

,. Date 4/2/82 LIST OF DEFINITIONS d:pleted, natural or enriched uranium nitrate or uranium hexafluoride and plutonima nitrate or plutonium oxide supplied or to be supplied to the nuclear fuel f abricator fer the construction of nuclear fuel assemblies.

Nuclear Steam Supply System (NSSS) - That portion of the nuclear power plant which provides steam from nuclear heat. It includes reactor, its control systems, main coolant and steam generation systems, fuel handling equipment, emergency core cooling cystem and other safeguards, associated electrical equipment, instrumentation, and spent fuel handling.

Opsrations Phase - That phase in the life of a nuclear power plant which receives coverage under the QA Program for Operations. It normally begins at core loading and continues until decommissioning. Administrative Controls for the PESC/ES interfaces l prior to core loading are normally identified in a Project Test Program Manual.

lorcing are normally icentitiec in a Projecc Test Program Manual.

I Pr ooerational Tests - Testing prior to initial fuel loading and plant operation to dImonstrate the capability of structures, systems and components to meet performance rcquirements.

Principal Suopliers - These organizations from whom Consumers Power Company has

~

procured equipment, materials or services.

Procured Items - Purchased materials, equipment or services including design and tcchnical services.

Prncurement Documentation - Purchase Requisitions (prs), Purchase Orders (P0s), Local Purchase Orders (LPOs), Return Material Requests (RMRs), drawings, contracts, cptcifications and instructions used to define requirements for the purchase of caterials, equipment and services.

Purchase Requisition - The basic document describing material, equipment or services for which a specific procurement action is necessary. For services, the purchase rcquisition serves as a transitional document to initiate a purchase order that rcferences the contract.

Qu911ty Assurance Program Policies - A series of individual documents that establish rcquirements and assign responsibilities for implementing elements of the Consumers Power Company Quality Assurance Program for the Midland Nuclear Plant. The Policies provide Management direction for complying with applicable regulatory requirements, l industry codes and standards, and corporate policies and instructions. The Policies ars approved for issue and implementation by the affected Consumers Power Company Vice Presidents, Executive Managers or Executive Directors.

Quality Assurance Program Procedures - A series of individual documents that define the interdepartmental relationships and responsibilities among tho:,e departments involved in implementing the Consumers Power Company Quality Assurance Program for pr0182-0215b-13-167

Page x of xi p r- QUALITY ASSURANCE PROGRAM POLICY Revision 12

'g (#^6 Q Y' Date 4/2/82 CODS'Jmtf5 power the Midland Nuclear Plant. The Procedures are approved for issue and implementation by the affected Consumers Power Company Department Managers or Directors.

Quality Assurance Record - Those records which furnish documentary evidence of the quality of items and of activities affecting quality.

Quality List (Q-List) - A list of safety-related structures, systems, components, and l activities designated by Consumers Power Company to receive coverage under the Consumers Power Company Quality Assurance Program. The Q-List.is prepared and maintained for each plant.

Quality-Related Activity - Any task performed on safety-related items during the design, construction, or maintenance of a nuclear power plant that affects quality.

Reference Standards - Standards of the highest accuracy in a calibration program.

These standards establish the basic accuracy limits for that program.

( Request for Bid - Invitation to bid on a specifi.c task made to Supplier of materials, l goods or services.

Safety-Relcted - The term applied to:

J Structures, systems, omponents, materials, services or activities named on the Q-List as necessary to assure:

1. The integrity of the reactor coolant pressure boundary.
2. The capability to shut down the reactor and maintain it in a safe condition.

t 3. The capability to prevent or mitigats the consequences of an accident which could i result in potentiel offsite exposures to individuals in excess of exposures specified in 10 CFR 100.

I

, Secondary Standard - An item of measuring and test equipment (M&TE) used to calibrate

! other M&TE. They are periodically calibrated using Reference Standards and reserved for use in the calibration of working plant or field M&TE.

Section - A subdivision of a department, usually made along lines of a technical specialty; eg, Nuclear Licensing, Health Physics, Nuclear Fuel, etc.

Services - Work performed by an organization or department having no deliverable hardware type end item other than the results of construction, modifications, repairs, inspections, audits, reviews, etc.

Source Inspection - Inspection of an item at a Supplier's facility during its manufacture, or at completion of manufacture, to verify implementation of the O procurement requirements.

V pr0182-0215b-13-167

QUALITY ASSURANCE PROGRAM POLICY Page xi of xi Revision 12 s ,.

r Date 4/2/82 LIST OF DEFINITIONS Spare Part -

An item available for replacement for an item in use.

Special Nuclear Material (SNM)

1. Plutonium. Uranium 233; uranium enriched in the Isotope 233 or in the Isotope 235; and any other material which the NRC, purstant to the provisions of Section 51 of the Atomic Energy Act of 1954 as amended, determines to be special nuclear material, but does not include source material; or
2. Any material artificially enriched by any of the foregoing, but does not include

, source material.

Sp:cial Process - Those metallurgical, chemical, or other processes where assurance of the process activity is dependent on the use of qualified procedures, personnel, or equipment; and where assurance of quality cannot be by direct inspection of the in process activity or final product. These include, but are not limited to, walding, heat-treating, NDE and environmental testing of the work process.

Start-Up Tests - Precritical tests, criticality tests, low power tests and power ascension tests, all performed after each fuel loading or refueling.

Supplier - Any individual or organization who furnishes equipment, materials or ssrvices. It includes the terms: Vendor, Seller, Contractors, Subcontractor, Fcbricator, Consultant and lower tier levels of these, where appropriate.

Surveillance - Verification of the implementation of administrative controls through review of documentation and/or of work activites.

Tcat - An activity for determination of the physical and functional properties of items or systems.

Tcst Plan - An outline, narrative description or flow diagram indicating the tests to bra parformed, :he methods to be used and the points in the process where they are to ba executed. May be a test procedure.

Traceable Calibration Standards - Standardr. having a known valid relationship to nttionally recognized standards or accepted values of natural physical constants. If no national standard exists, the basis for calibration is documented.

1 O l l

pr0132-0215b-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 1 f'f

%), Page 1 of 21 j

sd '

d,-

Revision 12 ORGANIZATION Date 4/2/82 1.0 GENERAL The President and Chief Executive Officer of Consumers Power Company is responsible for the safe and efficient construction of its nuclear power l plants. Consumers Power Company retains responsibility for the Quality Assurance Program although it may delegate to its Principal Suppliers, the establishment and implementation of certain portions. Authority to develop and implement the Quality Assurance Program for the design & construction of the Midland Nuclear Plant is assigned by the President, to.the Vice President

- Projects, Engineering and Construction.

I Responsibility is further assigned by:

a. The Vice President - Projects, Engineering and Construction (1) For the development and implementation of the Quality Assurance Program for the Midland Nuclear Plant Project, as follows: {

(a) Midland Project Office consisting of the Vice President -

Projects, Engineering and Construction assisted by the Midland i Project Manager, two Executive Managers and the Director -

,O Environmental and Quality Assurance and reporting to the Midland Project Office:

Manager - Safety and Licensing Manager - Design Production Manager - Quality Assurance Manager - Administrative Site Manager (b) Director - Environmental & Quality Assurance and reporting to him:

Manager - Quality Assurance Section Head - Audit & Management Systems (c) Executive Manager - Transmission & Department Services and reporting to him:

Manager - Electric Transmission - Engineering & Construction O

V 3r0780-04155-13-167

QUALITY ASSURANCE PROGRA31 POLICY Policy No 1 Page 2 of 21 Revision 12 ORGANIZATION Date +/2/82

b. The Executivo Vice President - Energy Supply (1) For providing quality-related support during design and construction, of the Midland Nuclear Plant to personnel reporting to l him, as follows:

(a) Vice President - System Operations and reporting to him: l Executive Manager - Production & Transmission and reporting to him:

l Manager - System Protection and Laboratory Services I

(b) Director - Management and Budget (Management Services)

c. The Executive Vice President - Region Operations, Energy Distribution, Customer Services and General Services (1) For providing quality-related support during design and construction of the Midland Nuclear Plant, in the areas of procurement and l graphic services, as requested, and to personnel reporting to him, as follows:

(a) Vice President - General Services and reporting to him: l Director - Purchasing i

The organization relationship of these positions is shown in Figures 1, 2, 3, and 4, 2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 1, " Organization"
b. ANSI N45.2, Criterion 3, " Organization" 1

3.0 POLICY 3.1 PROJECTS, ENGINEERING & CONSTRUCTION ORGANIZATIONAL RESPONSIBILITIES 3.1.1 Midland Project Management Organization Consumers Power Company has established a project management organi-zation to provide effective management of the Midland Nuclear Plant Project. The Midland project management organization is shown in Figure 5. The project msnagement organization is headed by the l

Midland Project Office consisting of the Vice President - Projects, Engir.eering and Construction assisted by the Midland Project Office l

pr0780-0415b-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 1 Page 3 of 21 lV) Revision 12 +

ORGANIZATION Date 4/2/82 team. The Site Management Office is headed by a Site Manager assisted l

by the Assistant Site Manager / Plant Superintendent. The Site Management Office organization is shown in Figure 6. The Vice Presi- l dent - Nuclear Operations provides staff guidance on operational activities until fuel load. At the time of fuel load, the Vice Presi-dent - Nuclear Operations is assigned responsibility for the Midland Site Management Office and the Plant Superintendent becomes the head of the Site Management Office.

The Vice President - Projects, Engineering and Construction will con-tinue to have direct responsibility for completing all engineering and construction activities required to complete the Plant but will work through the Site Management Office in a staff capacity after fuel load.

The Midland Project Office has overall responsibility for all activ-ities related to the Midland Nuclear Plant (until all major construc- l tion activities are complete) including design and procurement (except nuclear fuel); construction; licensing; permits; preoperational, hot functional and initial start-up testing; quality assurance, budgeting, contracts, cost and schedule and operations. These responsibilities (Vl include coordination of the activities between the Architect-Engineer, Constructor, Nuclear Steam Supply System Supplier, and other suppliers and Consumers Power Company departments. Within the Midland project management organization, Consuiers Power Company overall design activities rest with the Design Production Manager; licensing activities with the Manager of Safety and Licensing; construction and testing activities on site with the Site Management Office; cost and schedule activities with the Schedule and Cost Manager; budgeting, contract administration and records management activities with the Administrative Manager.

3.1.2 Midland Project Quality Assurance Department (MPQAD)

MPQAD is responsible for establishing quality assurance standards for design and construction consistent with Consumers Power Company objectives, and for assuring the establishment and implementation of policies and procedures to meet these standards.

In performing their assurance-type responsibilities, MPQAD personnel have no responsibility for cost or scheduling effects of their findings; have the authority and organizational freedom to identify assurance-related problems, initiate, recommend or provide corrective action and verify implementation of corrective action; and are independent from the individuals or groups performing the activities being inspected, tested or audited. Additional assurance-related Q activities, as given below, are assigned to MPQAD for work performed i either by Consumers Power Company or by Principal Suppliers, major pr0780-0415b-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No i Page 4 of 21 Revision 12 Consumeft POWtf ORGANIZATICN Date 4/2/82 subcontractors and subtier suppliers, or the activities may be delegated to a Principal Supplier's corresponding organization. The decision as to whether or not these activities are to be delegated shall be made with the mutual concurrence of both the Midland Project Office and MPQAD. Nevertheless, MPQAD retains authority and responsibility for these activities and for assuring their adequate and timely accomplishment. The objective of the assignment of authorities and responsibilities to MPQAD is to yield a total assurance program resulting in the attainment of a facility which is designed in accordance with its design basis criteria and which is constructed in accordance with its drawings and specification requirements.

Following is a more detailed discussion of the responsibilities of the Midland Project Quality Assurance Department. Figure 7 shows the Department organization.

The Midland Project Quality Assurance Department is responsible for:

l

a. During the design activity:

(1) Assuring that appropriate Quality Assurance standards are applied to the design process; (2) Assuring that the design process is conducted in accordance with approved procedures; and (3) Assuring the maintenance and repor*ing of hardware design quality and corrective action status,

b. During the hardware and services procurement activities (excluding spare parts procurement):

(1) Establishing supplier Quality Assurance requirements; (2) Performing preaward supplier evaluations for Quality Assurance and quality control activities; (3) Preparing and implementing plans and procedures for procured item inspections, nondestructive examinations and tests (within the Department's jurisdiction);

(4) Evaluating and, when necessary, approving supplier Quality Assurance related documentation; (5) Determining the acceptability or nonacceptability of hardware items; and pr0780-0413b-13-167

Policy No 1 m QUALITY ASSURANCE PROGRAM POLICY Page 5 of 21 (V ) Revision 12 ORGANIZATICN Date 4/2/82 (6) Maintaining and reporting hardware procurement quality and corrective action status,

c. During the installation and construction activity:

(1) Preparing and implementing plans and procedures for the inspections, nondestructive examinations and tests (other than checkout and functional tests for the establishment of inservice baselines) for installed items and determining the acceptability or nonacceptability of the items; (2) Identifying inspection and examination problems and test problems (within the Department's test jurisdiction), and causing their timely and adequate correction; (3) Participating in the resolution of hardware and systematic nonconformances (which are within the jurisdiction of the Department) and obtaining process corrective action;

- (4) Assuring that nonconforming items are properly dispositioned;

/ i

'v' (5) Maintaining and reporting quality and corrective action status; and (6) Assuring the effectiveness of primary quality control activities and the conformance of all construction and installation activities to the established Program Procedures through audit and overinspection.

d. Prior to the performance of preoperational, hot functional and functional inservice baseline tests, directly verifying the accomplishment of quality-related construction prerequisites and signing off on each such prerequisite to signify:

(1) That there has been a turnover acceptance of the test unit (s);

(2) That each nonconformance and deficiency, both preturnover and post-turnover, has been identified; (3) That each such nonconformance and deficiency has been adequately dispositioned; (4) Contributing to the identification of Plant quality status by transmitting Midland Quality Assurance Department originated NCRs to the Technical Superintendent for their incorporation into the overall Plant status accounting system; and (5) Assuring the maintenance and reporting of test quality and f corrective action status.

b]

pr0780-0415b-13-167

QUALITY ASSURANCE PROGRA31 POLICY Policy No 1 Page 6 of 21 Revision 12 Cornumtm Power

e. During the checkout, preoperational test, hot functional test and functional inservice baseline test activities:

(1) Reviewing the Project Testing Program Manual with respect to complJance with the Quality Assurance Program and annotating satisfactory completion of such review by a concurrence signature; (2) Auditing the individual preoperational, hot functional and functional inservice baseline test procedures, jointly or in coordination with, Audit and Management Systems and Quality Assurance - Nuclear Operations to assure:

(a) The preparation of procedures in compliance with the requirements of 10 CFR 50, Appendix B, ANSI N45.2, Quality Assurance related Regulatory Guides, Codes and Standards, and Consumers Power Company procedures; (b) The establishment of quality-related prerequisites for the performance of each test; and (c) The adequacy of the data collection format and content relative to the needs of the Quality Assurance Program regarding quality records.

(3) Preparing and implementing procedures for the inspection, nondestructive examination, tests (within the Department's test jurisdiction) and test verification for preventive and corrective maintenance activities; and (4) Reviewing Corrective Action Requests for adequacy of disposition and need for further quality statusing or additional part or process corrective action.

f. At any time, prior to or during the performance of the preoperational and hot functional tests and other prerequisites, signifying the prerequisites actually audited by the application of a Midland QA Department signature for each such prerequisite.
g. During the performance of the checkout and preoperational and hot functional tests, and functional inservice baseline tests, evaluating compliance with test procedures on an audit and surveillance basis, signifying the test procedural steps actually audited and surveilled by the application of Midland QA Department signatures adjacent to those steps.

O pr0780-0415b-13-167 l

l

QUALITY ASSURANCE PROGRAM POLICY Policy No 1 Psge 7 of 21

(]/

(, Revision 12 ORGANIZATION Date 4/2/82

h. Throughout all activities:

-(1) Evaluating the implementation of the Quality Assurance Program and recommending improvements; (2) Issuing "Stop Work Order" at any time that Quality Assurance Program commitments are violated,if necessary to preclude a safety risk; (3) Performing quality audit, as requested; (4) Maintaining a trend program to identify adverse repetitive quality conditions; (5) Maintaining a tracking program to assure all quality-related action items from NRC inspections, 50.55(e) items, etc, are scheduled and completed; (6) In accordance with Title 10 of the Code of Federal Regulations, Part 21 and 50.55(e), making the determination as to the need to report any nonconformances and test deficiencies to the NRC and reporting (3, them;

-I (7) Reviewing and cdhcurring with other Departmental Program Procedures (Midland Specific) which are quality related; (8) Participating in problem resolution to assure that part and process corrective action are appropriate and are implemented in a timely manner; (9) Preparing responses to NRC Construction I&E Reports (except for those relating to preoperational, hot function and initial start-up testing which are handled by the Site Management Office); and (10) Preparing 50.55(e) reports.

l l

l l

t i

l l

/'~N {

l \_ /

pr0780-0415b-13-167 l

QUALITY ASSURANCE PROGRAM POLICY Policy No 1 Page 8 of 21 Revision 12 Consumers power

>A Date M2 3.1.3 Environmental & Quality Assurance Within E&QA, there is one section with quality assurance responsibilities for the Midland Project - namely: The Audit &

Management Systemt Section (A&MS). Figure 8 depicts this organization. A&MS is responsible for:

a. Performing audits of activities which may impact design and construction quality for the Midland Nuclear Plant. More specifically, for:

(1) Evaluating the adequacy of quality policies and procedures; l (2) Evaluating the degree of compliance with quality policies and l procedures; (3) Obtaining corrective action, as necessary, based on audit l findings; NOTE: Items (1), (2), and (3)above, apply to primary suppliers as l well as to "in-house" activities.

b. Performing departmental administrative functions, especially with l regard to budgets, and other special assignments;
c. Providing Quality Assurance education, training and indoctrination; l
d. Preparing, releasing and controlling inter- and intra-departmental l quality-related policies and procedures; and
e. Issuing "Stop Work Orders" at any time that Quality Assurance Program commitments are violated, if necessary to preclude a safety risk.

3.1.4 Transmission and Department Services l The Executive Manager - Transmission and Department Services is responsible for the Electric Transmission - Engineering which is responsible for the Engineering Records Center.

l The Engineering Records Center's nuclear Quality Assurance l responsibilities for the Midland Project are the collection, l microfilming, storage, maintenance, control and distribution of Plant l drawings and specifications. Figure 9 shows the Department organization.

O pr0780-0415b-13-167

QUALITY ASSURANCE PROGRAM ^

POLIbY Policy Page 9 No I of 21 V k.-\*h y

Fevision 12 au WM CCHSU3 f5 POWtr 3.2 SUPPORT ORGANIZATIONS FOR DESIGN AND CONSTRUCTION PHASE 3.2.1 Purchasing Department The Purchasing Department reporting relationship is shown in Figure 2.

The Director - Purchasing, who reports to yice President - General Services, is responsible for procuring requested caterials, equipment and services in accordance with approved specifications and from>

approved Principal Suppliers. .

3.2.2 Systo Protection and Laboratory Services Department (SPSLS)

The SP&LS reporting relationship is shown in Figure 10. TheManageb of SP&LS is responsible through tht, Executive Manager - Production and Transmission to the Vice President - Systems Operations for providing ^

quality-related support in the following areasy Design of the electrical protection o.f the power plants and determines 1 the settings for the electrical protective equipment systems and relay control systems of the Midland Nuclear Plant.

O Checkout and testing service for electrical equipment and controls, plant metering, telemetering and protective devices for the turbine / generator and its auxiliary systems to the project test group during the construction phase of the Midland Nuclear Plant. [

Conducting periodic maintenance testing of electrical protective l equipment (down to but not including 480 volt switchgear) and applying setting changes (including 480 volt switchgear) and providing technical assistance, as required, in such areas as generator electrical tests, telemetering, supervisory control systems, etc.

Controlling the Company's Echelon II (Reference and Secendary j Standards) calibration facilities and for providing calibration ,

services for transportable measuring and testing equipment for other departments.

Providing, upon request, the review and evaluation of nondestructive testing procedures and personnel qualification and certification. It also provides as requested, certified NDT Level III examiners, nondestructive testing, technical and NDT design calculations, review and test services utilizing visual, radiography, ultrasonic, dye penetrants, eddy current and magnetic particle methods.

Providing technical consultation and special test and evaluation services such as chemical testing services, mechanical and metallographic tests and evaluations, and additional technical pr0780-0415b-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 1 rg'C. Page 10 of 21

& ORGANIZATION Revision 12 Date 4/2/82 CCAStmtf3 PCEf assistance as requested by other Consumers Power Company organizations. l 3.3.3 Management and Budget Department (Management System Section)

The Management System Section of the Management and Budget Department is responsible for the development and implementation of a records management system for quality related documents. The reporting relationship is shown in Figure 11.

l 3.3.4 Quality Assurance Department - Nuclear Operations QA-N0's design and construction responsibilities under CPC-1-A, Revision 12 are limited to quality assurance audits of preoperational and hot functional testing activities and are performed jointly with MPQAD and Audit & Management Systems. The QA-N0 organization and their operational responsibilities are described in CPC-2-A.

3.4 RESOLUTION OF CONFLICTS If a difference of opinion arises between Quality Assurance personnel and those of other departments, the dispute is resolved as follows: The Supervisor of the Quality Assurance unit involved first tries to resolve the matter with the organization responsible for conducting the activity. If a resolution cannot be obtained, the matter is referred up through the following Management personnel until it is resolved:

a. Director - E&QA;
b. The Vice President responsible for conducting the activity;
c. The President and Chief Executive Officer of Consumers Power Company.

O pr0780-0415b-13-167

lj,ll il l

\

oc.>CHS >(nn*CM>2nM mMOONh" top OA gw ,, -

i m

P, O  %

oE% $d@

m $.

an.

~

o ag 8 u gt 2$$ gQ T &

N  ;

t E ,G D NI 0 ISI T STRC ECEU R

PXER OI S

! 1 t

ERGN  ; N CPt O O I EC I V T A

Z I

N A

G R

O E

T A

R O

P R

O O

C T

NY Y EL N TFE EDP A NEV VI P P EIIR I SU M DHTE TES O ICUC UR C S CI CPY EDEF E G R RtI XF XER E PAE0 ECE W I N 0 VE F S

R E

M U

S N-O C

1 E

N& R

,O U SI SS G TNTEE !l F

iOUCC t

EEIBI I VDTI VV IIARRR TSRTEE UEESSS CRPI I

EPODRL X EA EENYMR COGOE I IRTN VGESE ENUG REC O

40 g? I >"

I llll,Ill1lIl lli1l11

=

x b

n ,q.- 1 S

EutollVL VICE PRESIDEllT

$M

  1. REGIC:t 0FERt.TIONS, 2 EfERGY DISTRIBUTION W Y CUSTOMER SERVICES &

E r,rt:r9ai srRVirFS O

~n C

--4 Wi \

in C

o A E >

VICE PRESIDEllT > 7.

GENERAL SERVICES O Ea I

O O

lc m

O r

MNif,GER 8 DIRECTOR ADMINISTPATIVE <

E PURCllASING SERVICES PROTECT 10il (GRAPillC SERVICES)

F M' ? 7

12

C '.

FIGURE 2 - REGION OPERATIONS, ENERGY DISTRIBUTION, CUSTOMER SERVICE & GENERAL SERVICES E=5 ~

O O O

x

Ohcd< >WMCN>znM T$oW>d mOCh E -

NY. E% A[g. '

E1?8 n Ela i $

o$p,a sloI  ? ll ${au T

RNT OEE TMG CED EGU RAB I N DA&

M N

O I

T A

Z I

N A

G N

S N

R O

/ T TO NY NI Y EEL ET E L VDP DA R C P I I P I R OYN P TSU SE TTA U UES EP CI R S CR RO ELU EPY P RAS Y X G R I US G EER EA DQA R CE CE E I N I L N VE VC E U

N -

3 e

E R

U G

I F

S TN NO EI DT I A SR EE RP PO ES CM I E VT S

Y S

N 5 , i C T Y E

l 1l l1i1

=

5 @

? U (7s e

add.i y

T n C

i VICE PRESIDENT

$ PROJECTS c

ENGINEERING & c>

CONSTRUCTI0ft C

-1

~',

u)

C o N 5

>  ?

/

d n' U m d m

9. M o

DIRECTOR O

EXECUTIVE MANAGER EXECUTIVE MANAGER z MIDLAND PROJECT OFFICE TRA!1SMISSION & PLANT MODIFICAT!0i!S A ENVIRONMENTAL >

g 's DEPARTMENT SERVICES MISCElLN4E00S PROJECTS QUALITY ASSURANCE y O

C n

-t EEEE "12 0~3 C8"z 3 G "' $

FIGURE 4 - PROJECTS, EriGINEERING & C/f;5TRUCTION ORGAflIZAT10ft "

d O O O

O O O E D y

[ MIDLAND PROJECT OFFICE N'h*/

O D Y

.'. VICE PRESIDENT-PE&C 8%

Y 5 O

" PROJECT OFFICE MEMBERS ** C c--i

' U) u)

C SITE MGT. e f rk:AGER OFFICE DIRECTOR - QA S */.

SAFETY M!D MANAGER  ;

SITE MANAGER MANAGER $ n ADMINISTRATIVE LICEl:Sli:G MANAGER MANAGER - QA sh

  • @ M ASST. SITE O MNIAGER/ O PLANT >

SUPERINTENDENT M m

O C

n THE PROJECT OFFICE MEMBERS CONSIST OF THE DIRECTOR - ENVIRONMENTAL

& QUALITY ASSURANCE, THE PROJECT MANAGER AND TWO EXECUTIVE MANAGERS

{*;*R

{2 7 et?

FIGURE 5 - MIDLAND PROJECT MANAGEMENT ORGANIZATION - PRIOR TO FUEL LOAD

~

e

e E . STAFF Gulf >.CCt. 0 4 OPERATIO!!AL n ACTIVITIES PR*0R 10 FUEL LOAD. L!t:E Es

'j g RESP 0ISIBILITY AFIER ft:EL LOAD

$ 3 ').

G C' .3 u

O ,Q "J .

HIDLNiD PROJECT C>

SITE PWiAGEl'itiT OFFICE VICE PRESIDElli C

- _ _ _ _ _ H SITE fWIAGER d fiUCLEAR OPERATIO'JS ASSISTNiT SITE l'NiACER/ (/)

PLNii SUPERltiliNDEili (/)

C o

w &.N O 2 M n M

_ U d m o 'A x O O

N

-e

~

ScitECtA E Pt NIT PUBtIC Pt A*lT Cfc3Th0L A!IllfilSTRATIVE CONTROLLER l'E R50'i::t L PROJECT ATTAIPS SUPERitilf t:DEril TECit.'ll CAL T SUPERVIS0a SUPLRVISOR DIRE C TOR SUPERINTENDENT Dll:LCIOR OPERAT10t35 SUPERif3IE:iDErli O 11Alfillt:N;CE

[

t r k r ,

n M

    • N0 QUALITY RELATED RESPONSIBILITIES E' E' ? E 2;i2=

l1 4!

C8*x L% ?,

OG B J W FIGURE 6 - MIDLAND PROJECT SITE 00GANIZATION S O O O

O O O

, R

$' O G

y MIDLAND PROJECT OFFICE ,

., (,/

$ VICE PRESIDENT - PE&C l

[. DIRECTOR - ENVIRONMENTAL

$ & OUALITY ASSURANCE $

5:

c-Y MIDLMD PROJECT QUALITY ASSURAftCE *<

DIRECTOR g W

MANAGER C o :z E

y ~/

U S SITE QUALITY ASS'T MANAGER D ADMIN & SPECIAL E :n ASSURANCE '

SUPERINTENDENT PROJECTS O O

lc D

i m

O i

SECTION HEAD SECTION HEAD SECTION HEAD C SECTION HEAD SECTION HEAD QUALITY O FLUIDS & ELECTRICAL M CIVIL QA ASSURANCE

MECHANICAL QA & IC QA HVAC QA SERVICES

? E' ? E GROUP g

. gg 7 SUPERVISOR ga ADMINISTRATIVE R 8 " ,.

j QA Rm 14 2. H I

l' FIGURE 7 - t1IDLAND PROJECT QUALITY ASSURANCE DEPARTMENT ORGANIZATION l

l

'N O

u 8 8 6 a

<- 5 5

c C

r SECTION HEAD ~.;

AUDIT & MANAGEMENT <

SYSTEtts p m

m C

o N

> */

$ n E'

M d e O O O

c GROUP SUPERVISOR s

GROUP SUPERVISOR ~

MANAGEMENT SYSTEMS OUAllTY AUDIT

  • t:I O

C n

FIGURE 8 - AUDIT & MANAGEi1ENT SYSTEMS ORGANIZATION 2 5. % ~

,3 A

8 "' 2 U

O O O

t N \,, N)

A S U 8 E i a G E T $

= '

MANAGER

$ ELECTRIC TRANSMISSION c

ENGINEERING & c>

CONSTRUCTION C H

M w

C o N

> */,

DIVISION NEAD O SUBSTATION ENtdNEERING h

g

.e.

O O

N d

m O

SUPERVISOR C ENGINEERING n RECORDS CENTER M s'5'28 g 5,.

u

% o FIGURE 9 - ENGINEERING RECORD CENTER ORGANIZATION t { G ',),

L' ~ *

?i , , ~

~

u 2> D s R

? E F 3 5 I a =

i u

! ku O VICE PRESIDENT C SYSTEM GPERATIONS a  ;

M l (n \

in C I I

  • o  % I

! E{ >

1 */

l EXECUTIVE MANAGER b n' l PRODUCTION & TRANSMISSION L3 M

! m I 9-  %

l O O

i c d

1 m

O MANAGER C SYSTEM PROTECTION AND O l LABORATORY SERVICES *  !

1 l

8' %' ? E 1 23,.

o

'so; FIGURE 10 - SYSTEM PROTECTION & LABORATORY SERVICES ORGANIZATION 4-9; os M "

"E on O

l O O O

O C> C4<

- ymmCc>2nM uC

oo[v OCn< g 3. z ~

O oEga U!9-g 2 ,,~ R ,,~

gi28 ~"

g2 C t' ?l "Na0 =28 N _

O I

T A

Z I

N A

G R

O T

E T G S E D M G U RE D B OT U R TS B O O&

T CT Etl RE AY RS T

ST I N T

N I M NE E DE I M M G ME E A DG G N AA A A N N M A A M M 1

1 E

R U

G I

F O

E Y ;"

Xo5o h ,

QUALITY ASSURANCE PROGRAM POLICY Policy No 2

[s') Page 1 of 11

\_) Revision 12 QUALITY ASSCRANCE PROGRAM Date 4/2/82 1.0 GENERAL The President and Chief Executive Officer of Consumers Power Company has issued a " Statement of Authority and Responsibility" which commits the Company to develop and implement a Quality Assurance Program for the design and construction of the Midland Nuclear Plant, in compliance with NRC Regulatory Requirements and applicable Industry Codes and Standards. The Quality Assurance Program is documented in the Consumers Power Company Quality Assurance Program Manual for the Midland Nuclear Plant (this document). The Manual defines the Quality Assurance Program established by Consumers Power Company to assure that the Midland Nuclear Plant is designed and constructed with the controls required to prevent or mitigate the consequences of postulated accidents that could cause undue risk to the health and safety of the public. The scope of this Quality Assurance Program covers design, procurement, construction and preoperational testing activities associated with the Plant. The Quality Assurance Program assures that activities affecting quality are accomplished by use of appropriate equipment and under suitable environmental conditions. The program establishes the requirements for special controls, processes, test equipment, tools and qualified personnel.

[ ')

(_/ 2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 2, Quality Assurance Program
b. NRC Regulatory Guide 1.28, (6/7/72) Quality Assurance Program Requirements - Design and Construction (Endorses ANSI N45.2) l
c. NRC Regulatory Guide 1.58, Rev 1 Qualification of Nuclear Power Plant Inspection, Examination and Testing Personnel (Endorses ANSI N45.2.6)
d. NRC Regulatory Guide 1.74, (Feb 1974) Quality Assurance Terms and l Definitions (Endorses ANSI N45.2.10)
e. ANSI N45.2, Criterion 2, Quality Assurance Program
f. WASH 1283, 5/24/74; WASH 1284, 10/26/73; and WASH 1309, 5/10/74 l
g. NRC Regulatory Guide 1.146, Qualification of b ality Assurance Program Audit Personnel for Nuclear Power Plants (Endorses ANSI N45.2.23) 3.0 POLICY 3.1 QUALITY ASSURANCE PROGRAM COMPLIANCE WITH NRC REGULATORY GUIDANCE The Consumers Power Company Quality Assurance Program for the Midland Nuclear

( Plant is committed to the guidance and requirements contained in NRC Quality

(]) Assurance Regulatory Guider., and the NRC Grey, Green and Orange Books, pr0780-0416a-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 2 Page 2 of 11 Revision 12 QUALITi ASSURANCE PROGRAM Date 4/2/82 referred to as the Rainbow Books and/or WASH Documents (1283, S/24/74; 1309, 5/10/74; and 1284, 10/26/73, respectively). Exceptions and/or explanations follow:

a. Subsection "a" of Section D-1 in the Grey Book requires that, "A schedule of all safety-related nuclear power plant activities to be performed by each organization along with the required procedures or instructions to implement the corresponding Quality Assurance Program for the activity should be prepared (and periodically updated to ir.dicate status) to assure timely development, approval and implementation of these Quality Assurar e Procedures or instructions prior to initiation of the activity." Consumers Power Company does not have a schedule relating to timely development, approval and implementation of procedures and instructions. In lieu of this schedule, Consumers Power Company does require that procedures or instructions be prepared prior to initiation of safety-related activities (and revised when necessary) and does verify, during audits, that the procedures have been prepared and are being implemented.
b. Only thos portions of the Orange Book relating to preoperational and hot

. functional testing will apply.

c. Consumers Power Company uses the definitions of terms provided in ANSI l N45.2.10-1973 for safety-related activities with the following exceptions:

Audit is defined as "A documented activity performed in accordance with written procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of a Quality Assurance Program have been developed, documented and effectively implemented in accordance with specified requirements. An audit does not include surveillance or inspection for the purpose of process control or product acceptance."

Construction Phase is defined as " Activities at the building site necessary to erect and verify proper installation and performance of nuclear power plant facilities prior to initial fuel loading."

Nonconformance is defined as "A deficiency in characteristic, documentation, or procedure which renders the quality of an item unacceptable or indeterminate and which is considered significent to quality or safety. Examples include:

" Physical defects, test failures, incorrect or inadequate documentation, dwiation from prescribed processing, inspection, or test procedures."

Procurement Documentation is defined as " Purchase Requisitions (prs),

Purchase Orders (P0s), Local Purchase Orders (LP0s), Returned Material pr0780-0416a-13-167

n QUALITY ASSURANCE PROGRASI POLICY Policy so 2 Page 3 of 11

'N) Revision 12 C3f!$umtf3 POWtf

' Date U2/82 Requests (RMRs), drawings, contracts, specifications, and instructions used to define requirements for the purchase of materials, equipment or s e rvices . "

d. bection 5.6 of ANSI N45.2.9 requires that the permanent record storage l facility have " structure, doors, frames, and hardware should be Class A fire-rated with a recommended four-hour minimum rating." In lieu of this, the existing Consumers Power Company permanent record storage facility has a two-hour fire rating.
e. Consumers Power Company follows the guidance of NRC Regulatory Guide 1.58 with the following exceptions:

Section C.1 Requirement "However, for qualification of personnel (1) who approve preoperational, start-up and operational test procedures and test results and (2) who direct or supervise the conduct of individual preoperational, start-up and i 7y operational tests, the guidelines contained in Regulatory

('~' ) Guide 1.8, Personnel Selection and Training, should be fol'1 owed in lieu of the Guidelines of ANSI N45.2.6-1978."

Exception / Interpretation This requirement is interpretated to not apply to System Protection and Laboratory Services. This department has developed its qualification program based on ANSI N45.2.6 and provides services throughout the construction phase of the Midland Nuclear Plant. The program includes the certification of First-Line Supervisors to ANSI N45.2.6 and additional specific requirements determined by the work l activity involved.

l Section C.5 Requirement l

l l "In addition, the individual should be capable of reviewing and approving inspection, examination, and testing procedures and of evaluating the adequacy of such procedures to accomplish the inspection, examination, and l

test objectives."

l Section C.5 Exception / Interpretation While a Level III individual should be capable of reviewing

,3 and approving inspection, examination and testing

( , procedures and of evaluating the adequacy of such

- procedures to accomplish the inspection, examination and pr0780-0416a-13-167

5 I

QUALITY ASSURANCE PROGRAM POLICY Policy No 2 Page 4 of il Revision 12 QUALITY ASSURASCE PROGRAM Date 4/2/82 test objectives, this is not construed by Consumers Power  !

Company as requiring personnel who review, approve or evaluate such procedures to be certified as Level III personnel.

Section C.6 Requirement j

"Since only one set of recommendations is provided for the education and experience of personnel, a commitment to comply with the regulatory position of this guide in lieu of providing un alternative to the recommendations of the standard means that the specified education and experience recommendations of the standard will be followed."

Exception / Interpretation The education and experience recommendations given in ANSI S45.2.6, Section 3.5 will be treated as such, since the Consumers Power Company qualification and certification program is based upon these recommendations, and more significantly, upon satisfactory completion of capability testing prior to certification. It is the Consumers Power Company position that a candidate should not be required to be a high school graduate or have earned the GED equivalent for the above reasons.

Section C.10 Requirement "Use of the measures outlined in these actions to establish that an individual has the required qualifications in lieu of required education and experience should result in documented evidence (ie, procedure and record of written test) demonstrating that the individual indeed does have comparable or equivalent competence to that which would be gained from having the required education and experience."

Exception / Interpretation Consumers Power Company will maintain documented objective evidence that demonstrates that an indivdua) does have

" comparable" or " equivalent" competence to that which would be gained from having the required education and experience. However, this may take the form of documentation other than " procedures and records of written test" such as documentation or oral tests and on-the-job performance demonstrations.

O pr0780-0416a-13-167

n QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 2 Page 5 of 11

(' ) Revision 12 QUALITY ASSURANCE PROGRAM Date 4/2/82 General Imposition of this Regulatory Guide on Consumers Power Company Suppliers and subtier Suppliers will be on a case-by-case basis depending upon the item or service to be procured.

f. The remaining guides and/or standards below are listed because the draft revision or released edition implemented by Consumers Power Company is later than that contained in the respective WASH Document in which they appear:

Regulatory Guide 1.146 Regulatory Guide 1.64 - Revision 1.(February 1975)

Regulatory Guide 1.88 (August 1974)

ANSI N45.2.9-1974

( ) Regulatory Guide 1.94 (April 1975)

ANSI N45.2.5-1974 ANSI N45.2.8-1975 ANSI N45.2.12 (Draft 4, Revision 1)

ANSI N45.2.13 (Draft 3, Revision 3)

ANSI N45.2.23-1978 Consumers Power Company requires its Suppliers to respond to the Grey and Green Books (WASH Documents 1283 and 1309) and assigns responsibility for this action to the Supplier. Alternates or exceptions taken by the Supplier to comply with or implement the regulatory guidance contained in these documents will be described and delineated in the Safety Analysis Report.

3.2 CLASSIFICATION OF STRUCTURES, SYSTEMS AND COMPOSINTS The Quality Assurance Program assures that structures, systems and components important to the safety of the power plant; le, " safety-related" items, have been designed, fabricated, erected and tested to standards commensurate with l the safety functim. to be performed. Design documents, procurement documents and Quality Assurance Program documents reflect the importance to safety of

,_, the item or activity affected by the documents.

(v I pr0780-0416a-13-167

l 1

)

QUALITY ASSURANCE PROGRA.TI POLICY Policy No 2 Page 6 of 11 Revision 12 QUALITY ASSURANCE PROGRAM Date 4/2/82 The Architect-Engineer, with input from the NSSS Supplier, develops the l original list of safety-related structures, systems and components (Q-List).

The list is reviewed and approved by the Manager - Design Production with assistance in reviews from the Midland Project Quality Assurance Department to assure that the listing properly identifies and classifies safety-related items. This list identifies and classifies those safety-related items according to the requirements of 10 CFR 50.55(a) and the guidance of NRC Regulatory Guides 1.26 and 1.29. The safety-related items are specified in the applicable design documents and a listing of the iteus and their classification level is prepared. The classification listing is revised as l design changes, modifications and regulatory requirements dictate. The Manager - Design Production is responsible for controlling the classification listing and its revisions.

3.3 QUALIFICATION OF PERSONNEL Qualification requirements for heads of departments which are implementing the Quality Assurance Program are documented by the appropriate Vice Presidents. For personnel within each department, the qualification requirements are documented by the head of the department.

The Director - Environmental & Quality Assurance must have an engineering or scientific degree with five or more years of appropriate experience in such areas as Quality Assurance, design, manufacture, testing, construction, or operations; and five or more years experience in the management of appropriate engineering, construction, operations functions, administrative activities, program development or nuclear plant quality-related activities.

3.4 TRAINING OF PERSONNEL To assure that safety-related operations and activities are performed correctly, Consumers Pover Company conducts formal training programs for Company personnel and requires Principal Suppliers to have formal training programs. These training programs include general, continuing and specialty training. Training is accomplished in accordance with documented instructions with the objectives of indoctrinating personnel in disciplines such as quality assurance, testing, industrial safety and security, etc.

l Training is also accomplished to aid in developing specific job skills and updating and maintaining these skills. Records are maintained for each trained Consumers Power Company e=ployee and are reviewed on a periodic basis to assure completeness and determine requirements for continuing training.

Training of person el within the scope of the Quality Assurance Program is accomplished by Projects - Engineering and Construction, and other l departments involved, and is subject to appropriate audit as follows:

O pr0780-0416a-13-167 4

e QUALITY ASSURANCE PROGRAM POLICY Policy No 2

!m ' Page 7 of 11 Revision 12 QUALITY ASSURANCE PROGRAM Date 4/2/82

a. Projects, Engiteering and Construction Personnel Training - Personnel who perform activities during the design and construction of the Midland Nuclear Plant require various levels of proficiency to properly perform their job responsibilities.

Each Director or Manager in Projects, Engineering and Construction provides the necessary training and indoctrination and maintains his own personnel training records.

l

b. Other Suoport Services Training - Personnel who perform quality-related support activities require various levels of proficiency to properly l

perform their job responsibilities. Training is accomplished in accordance with the individual's departmental training plan.

l

c. Quality Assurance Training - Supervisors or managers responsible for work activities which af fect quality are trained or indoctrinated as appropriate to assure their understanding of quality functions and interfaces. Training and indoctrination of Consumers Power Company Projects, Engineering and Construction, or other Company personnel to the l

73 requirements of the Quality Assurance Program are performed under the

('^' ) direction of the Director - Environmental & Quality Assurance. They l

provide for such training and indoctrination and assign responsibility for developing and conducting training programs. The respective Quality Assurance groups coordinate with other departments to develop schedules, select personnel and conduct retraining as deemed necessary. Personnel training records are maintained by the respective departments. The Quality Assurance training provides the mechanism for communicating to all responsible organizations and individuals that quality policies, Quality Assurance manuals, and procedures are mandatory requirements which must be implemented and enforced.

3.5 QUALITY ASSURANCE PROGRAM REVIEW t

The status and adequacy of the Quality Assurance Program is reviewed on a regular basis. The results are documented and reported to senior Consumers l

Power Company Management personnel in accordance with Quality Assurance Program Policy 20, " Program Reporting."

3.6 QUALITY ASSURANCE PROGRAM MATRIX The index of CPC-1-A provides a matrix of major Quality Assurance Program policies keyed for 10 CFR 50, Appendix B, criteria. The number of the policy (Arabic) is the same as the criterion number (Roman). Two additional subjects, Policy 19, " Program Review," and Policy 20, " Program Reporting,"

are added to cover special interest areas.

f%

( }

U pr0780-0416a-13-167

QUALITY ASSURANCE PROGRA.\I POLICY Policy So 2 Page S of 11 Revision 12 i QUALITY ASSURANCE PROGRA>! Date 4/2/82 l

The index of Volume II (Attachment A) of Consumers Power Company's Quality l Assurance Program .'!anual for the !!idland Nuclear Plant pro'. ides a matrix of I the Quality Assurance Program procedures. The key to determine which 1 10 CFR 50, Appendix B, criterion the procedure implements is the first set of digits of the policy or procedure number. For example, Quality Assurance Program Procedure 4-1 (QAP 4-1) implements Criterion IV and Policy 4. l 9

O pruio0-0* loa-13-loi

QUALITY ASSURANCE PROGRAM POLICY Policy No 2 (o') Page 9 of 11 Revision 12

~

Consumtis POWif QUALITY ASSURANCE PROGRAM PROCEDURES - VOLUME II Criterion Procedure No Criterion & Procedure Title No l DEFINITIONS -

I ORGANIZATICN l Organization 1-1 II QUALITY ASSURANCE PROGRA'!

l Quality Assurance Policies 2-1 Quality Assurance Program Procedures 2-2 Identification of Safety-Related Structures, 2-3

/

O Systems, Components, and Services i

Quality Assurance Training 2-4

~

l l Project Quality Assurance Plan For 2-5 Remedial Soils k'ork III DESIGN CONTROL Design Document Preparation 3-1 Design Change Control 3-2 Design Verification and Interface Control 3-3 IV PROCUREMENT DOCUMENT CONTROL l Processing Procurement Requisitioning 4-1 Documents and Requests for Proposals V INSTRUCTIONS, PROCEDURES, AND DRAWINGS l Department Procedures 5-1 VI DOCUMENT CONTROL l

g Document Control 6-1

( (u- )

l 1

l pr0780-0416b-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 2 Page 10 of 11 Revision 12 QUALITY ASSURANCE PROGRAM - ATTACHMENT A Date 4/2/82 QUALITY ASSURANCE PROGRAM PROCEDURES - VOLUME II Criterion Procedure No Criterion & Procedure Title No l l

VII CONTROL OF PURCHASED MATERIAL, EQUIPMENT I AND SERVICES Principal Supplier Evaluation 7-1 Source Inspection and Surveillance 7-2 VIII IDENTIFICATION AND CONTROL OF MATERIAL, l

PARTS AND COMPONENTS Identification and Control of Material, 8-1 Parts and Components IX CONTROL OF SPECIAL PROCESSES  !

Control of Special Processes 9-1 O X INSPECTION l

Inspection 10-1 Functional Turnover to Consumers Power Company 10-2 XI TEST CONTROL l

~

Preoperational Testing 11-1 XII CONTROL OF MEASURING AND TEST EQUIPMENT l Control of Measuring and Test Equipment 12-1 XIII HANDLING, STORAGE, AND SHIPPING l Handling, Storage, and Shipping 13-1 XIV I!UPECTION, TEST AND OPERATING STATUS l Control of Nonconformances 14-1 QA Status Tagging 14-2 O

pr0780-0416b-13-167

(q QUALITY ASSURANCE PROGRAM POLICY Policy No 2 Page 11 of 11 Revision 12 g QUALITY ASSURANCE PROGRA'! - ATTACHMENT A Date 4/2/82 QUALITY ASSURANCE PROGRAM PROCEDURES - VOLUME II Criterion Procedure No Criterion & Procedure Title No l XV NONCONFORMING MATERIALS, PARTS, CS [

COMPONENTS -

NRC Bulletins, Circulars and Information 15-1 Notices Manufacturer's Notices 15-2 Stop Work Orders 15-4 Allegations 15-5 XVI CORRECTIVE ACTION l

('s)

Corrective Action 16-1 XVII QUALITY ASSURANCE RECORDS

[

Collection, Storage, and Maintenance of 17-1 Quality Assurance Records NVIII AUDITS I

Audit 18-1 N/A QUALITY ASSURANCE PROGRAM REVIEW  !

Quality Assurance Management Meatings 19-1 N/A REPORTING g

Reporting Nonconformances to NRC 20-1 Safety Concerns and Reportability Evaluation 20-2

't !

)

pr0780-0416b-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 3 (o ) f Page 1 of 3 Revision 12 DESIGN CONTROL Date 4/2/82 1.0 GENERAL Consumers Power Company is ultimately responsible for, and maintains cognizance and control of, the design of the Midland Nuclear Plant. This responsibility is carried out by Projects, Engineering and Construction. The Nuclear Steam Supply System (NSSS) Supplier, the Architect-Engineer (A-E),

and other Suppliers and Consultants, perform the detailed design work. The l flidland Design Production Manager is assigned direct responsibility for coordinating the activities between design organizations and within Consumers Power Company in areas where Consumers Power Company acts as lead designer.

The design organizations identify the applicable regulatory requirements, design bases, codes and standards; develop the design and specify the design interfaces; perform design verification and prepare design documents. Each design organization prepares procedures for controlling its own design activities. Consumers Power Company audits selected supplier design documents to an extent deemed appropriate.

2.0 BASIS DOCL?!ENTS

/m

a. NRC 10 CFR 50, Appendix B, Critericn 3, Design Control
b. 10 CFR 50, Appendix A, General Design Criteria for Nuclear Power Plants
c. 10 CFR 50, Section 50.55a, Codes and Standards
d. NRC Regulatory Guide 1.64, Rev 1, Quality Assurance Requirements for l Nuclear Power Plants (Endorses ANSI N45.2.11)
e. ANSI N45.2, Crite: ion 4, Design Control 3.0 POLICY 3.1 ORGANIZATION FOR DESIGN The Midland project management organization provides overall management and control of the Midland Nuclear Plant Project throughout design, construction and testing until plant turnovar to Nuclear Operations. The Design Production Department controls and coordinates design activities between the NSSS Supplier, A-E, Contractors and other organizations that provide design services. l Audit & Management Systems assures by audits that design controls are instituted and adequate during design and construction and verifies that design control records are complete.

/

\. /

pr0780-0416c-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 3 Page 2 of 3 Revision 12 DESIGN CONTROL Date 4/2/82 3.2 DESIGN INTERFACES A single design organization (eg, the A-E) is assigned as the lead design j organization. The lead design organization, at the direction of the !!idland Project Design Production ?!anager, establishes and controls the interf aces with other design organizations. These interfaces include !!echanical, Electrical, Civil, ?!etallurgical, Instrumentation and Control, and Nuclear disciplines as well as functional interfaces. The lead design organization reviews the designs of other organizations to assure compatibility of design and equipment.

3.3 DESIGN DOCDIENTS Each group or organization performing detailed design translates the applicable regulatory requirements, design bases, codes, standards and design criteria into design documents, such as: specifications, drawings, standards, materials, lists, process procedures and other types of requirements documents.

3.4 DESIGN VERIFICATION The assigned lead design group or organization assures that the designs and materials are suitable and that they comply with design criteria and O

regulatory requirements. Verification of design is performed by individuals other than those who performed the original design. The extent of the design verification is determined by the complexity of the system, the safety-related function to be performed, and the applicability of regulatory requirements, codes, standards, SAR commitments and Quality Assurance requirements. The lead design group or organization identifies the particular verification methods to be utilized, and if a test program is used, it includes testing of a prototype under the most adverse design conditions. Audit & ?!anagement Systems with assistance from other Consumers l Power Company departments, conducts audits to assure that the design is reviewed, and the review documented in such areas as: Stress, thermal, hydraulics. transient and accident analysis, compatibility of materials, accessibility for inservice inspection, maintenance and repair, and acceptance criteria for inspections and tests. The assigned lead group or organization establishes procedures to assure that errors and deficiencies in the design process that adversely affect safety-related structures, systems and components are documented and corrective action is taken to preclude repetition.

Standard off-the-shelf commercial or previously approved materials, parts and equipment essential to the safety-related functions of structures, systems and components are reviewed for suitability of application before they are selected.

O pr0780-0416c-13-167

,q QUALITY ASSURANCE PROGRA.TI POLICY Policy No 3 g Page 3 c: 3 Revision 12 DESIGN CONTROL Date 4/2/82 3.5 DESIGN CHANGES AND MODIFICATIONS Changes to the design require the same review and approval as the original l design by the group or organization delegated lead design responsibility.

Design reviews are documented and revised design documents are issued to the same distribution as the original documents.

J

\s' pr0780-0416c-13-167

,c4 i QUALITY ASSURANCE PROGRA.\1 POLICY Policy No a i

f Page 1 of 3 Revision 12 PROCUREMENT DOCUMENT CONTROL Date 4/2/82 1.0 GENERAL Procurement procedures describe the sequence of actions to be acccmplished in l the preparation, review, approval and control of procurement documents for procurements by Consumers Pcwer Company. l Assigned Quality Assurance personnel review procurement specifications to verify the adequacy of quality recuirements stated therein. This review determines that quality requirements are correctly stated, inspectable and controllable; that there are adequate acceptance and rejection criteria; and that procurement documents have been prepared, reviewed and approved in accordance with Quality Assurance Program requirements. Records of this Quality Assurance review of procurement documents are made and kept available for verification.

Midland Project Quality Assurance personnel review the Quality Assurance l provisions in procurement documents issued by the Company for the services of princi;.a1 nuclear power plant suppliers, such as the Architect-Engineer.

Constructor, Nuclear Steam Supply System Supplier, and suppliers to Consumers ex Power of other safety-related equipment, materials and services. These

) principal suppliers are responsible for reviewing and approving the procurement documents issued to their lower-tier suppliers. Audit &

Management Systems personnel or Quality Assurance personnel under contract to Consumers Power Company audit the activities of these suppliers to ass.re l

their procurement document controls are effective.

These reviews are accomplished to assure that Consumers Power Company procurement documents contain or reference provisions such as the following:

a. Basic technical requirements including drawings, specifications, codes and standards with applicable revision data, test and inspection requirements, and special requirements, such as for designing, fabricating, cleaning, erecting, packaging, handling, shipping and storage.
b. Quality Assurance requirements, such as invoking the requirements for a Quality Assurance Program, or ele:nents of a program in accordance with the rewirements of 10 CFR 50, Appendix B; ANSI N45.2 and ANSI N45.2.13.
c. Designation of records to be prepared, maintained, submitted, or retained available for review, such as drawings, specifications, procedures, procurement documents, inspection and test records, personnel and procedure qualification records, and material, physical and chemical test results. As a minimum, documentation to be submitted by the supplier must specifically identify (eg, by purchase order number): l g

pr0780-0417a-13-167

QUALITY ASSURANCE PROGRAM POLICi Policy No a Page 2 of 3 Revision 12 Csr.summ power PROCUREME H DOCUME H C0 HR E Date 4/2/82 (1) The purchased material or equipment and the specific procurement requirements (codes, stcndards, specifications, etc) which are met by the items.

(2) Procurement requirements which have not been met, together with a description of those nonconformances dispositioned " accept as is" or

" repair."

d. Provisions for extending applicable requirements to lower-tier subcon-tractors and suppliers.
e. Provisions for access to vendors' or contractors' facilities for the purpose of source inspection, surveillance and audit.

f., SAR commitments and regulatory requirements.

g. Applicable requirements of the Consumers Power Company Quality Assurance Program Manual for the Midland Nuclear Plant.

l When Consumers Power Company procurement documents do not contain or reference the preceding provisions, these procurement documents do require the principal supplier to provide a Quality Assurance Program description.

This Quality Assurance Program description will be evaluated and approved by the appropriate Consumers Power Company department. Approval is based, in part, on compliance with the preceding provisions. Approval of the principal supplier's Quality Assurance Program is necessary prior to initiation of activities covered by the procurement document.

2.0 BASIS DOCDtENTS

a. NRC 10 CFR 50, Appendix B, Criterion 4, Procurement Document Control
b. ANSI N45.2, Criterion 5, Procurement Dccument Control
c. ANSI N45.2.13, Quality Assurance Requirements for Control of Procurement of Equipment, Materials and Services for Nu: lear Power Plants l

3.0 POLICY 3.1 PROCUREMENT The Midland Project Manager is responsible for planning and coordinating the selection of the Architect-Engineer, Constructor, Nuclear Steam Supply System l and other principal suppliers. He recommends principal suppliers and requests an evaluation for nonconstruction contractor services from the project management organization, as applicable. The Midland Project Quality Assurance Department evaluates the proposed supplier's Quality Assurance pr0780-0417a-13-167

s QUALITY ASSURANCE PROGRAM POLICY Policy No !.

) Page 3 of 3 Revision 12 PROCURE!!ENT DCCU51EST CONTROL Date 4/2/82 Programs. Principal suppliers of contractor construction field labor are evaluated for technical capability by the !!idland Project ?!ana ge r .

The Midland Project Quality Assurance Department evaluates the contractor's Quality Assurance Program.

The Design Production Manager coordinates preparation of the required procuremen.- documents and obtains approval of the appropriate departments , l including the !!idland Project Quality Assurance Department prior to forwarding the request for purchase to the Purchasing Department.

Consumers Power Company delegates the procurement of the Nuclear Steam Supply System (NSSS) items and services to the NSSS supplier, and the procurement of certain other items and services to the Architect-Engineer. The Audit &

!!anagement Systems Section revi:ws the procurement documents issued by these l principal suppliers during scheduled audits to assure that the appropriate Quality Assurance requirements are being incorporated.

3.2 I PROCURE!!ENT CHANGE CONTROL

/~N i j Changes in procurement documents by Consumers Power Company, its suppliers, D and their suppliers, are subject to equivalent reviews, approvals, and audits as those in effect during the preparation and processing of the original procurement documents.

O V

pr0780-0417a-13-167

(n i QUALITY ASSURANCE PROGRAAI POLICY Policy No 5 Page 1 of '.

Revision 12 INSTRUCTIONS, PROCEDURES AND DRA'n'INGS Date 4/2/82 1.0 GENERAL Instructions for controlling and performing activities affecting quality of equipment or activities such as procurement, manufacturing, construction, installation, inspecting and testing are documented in instructions, precedures, specifications, checklists and other forms of documents. These documents provide qualitative and quantitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

(NOTE: Thin policy does not apply to design documents, such as drawings and procurement documents which are covered by Policies 3 and 4.)

The various Consumers Power Company departments and suppliers which perform a safety-related activity prepare required instructions, procedures and other instructional type documents prior to initiation of safety-related activities. Reviews of Consumers Power Company departmental procedures for adequacy are conducted by the Audit & Management Systems Section. They also l Verify through audits that the required instructions and procedures are prepared and implemented.

I 2.0 BASIS DOCUMENTS

'" )

\

a. NRC 10 CFR 50, Appendix B, Criterion 5, Instructions, Procedures and Drawings
b. NRC 10 CFR 50, Appendix E, Emergency Plans for " oduction and Utilization Facilities
c. American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section III
d. NRC Regulatory Guide 1.17, (June 1973), Protection of Nuclear Plants l Against Industrial Sabotage (Endorses ANSI N18.17)

I

e. NRC Regulatory Guide 1.68, (Nov 1973), Appendix C, Preparation of Frocedures l
f. ANSI N18.17, Industrial Security for Nuclear Power Plants l
g. ANSI N45.2, (1971), Criterion 6, Instructions, Procedures and Drawings l 3.0 POLICY 3.1 QUALITY ASSURANCE PROGRAM POLICIES Quality Assurance Program Policies are documents which establish requirements and assign responsibility for implementing elements of the Consumers Power Company Quality Assurance Program. The policies respond to the eighteen (18)

V criteria delineated in 10 CFR 50, Appendix B, and two additional criteria.

l pr0780-0417b-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 3 Page 2 of a Revision 12 i

4 C;nsumen power INSTRUCTIONS, PROCEDURES AND DRAWINGS Date 4/2/82 There is one policy for each criterion. The policies provide the Consumers Power Company interpretation of the requirements of the criteria and formulate a Management commitment to comply with the requirements of the basis documents listed in Section 2 of each policy. The policies provide the basis for preparing Quality Assurance Program Procedures, described below.

3.2 CUALITY ASSURANCE PROGRAM PROCEDURES Qus11ty Assura te Program Precedures for Design and Construction are used to implement the Consumers Power Company Quality Assurance Program Policies.

Quality Assurance Program Procedures are prepared by Audit & Management Systems for the Midland Nuclear Plant Project. They describe the system and methods for accomplishing the various quality-related activities, define the departmental relationships and assign responsibilities in a manner that assures compliance to the quality requirements delineated in the Quality Program Policies. Approved Quality Assurance Program Procedures are retained in Quality Assurance Program Manuals assigned to specified functions and are maintained current.

3.3 QUALITY ASSURANCE PROGRAM DEPARTMENTAL PROCEDURES Departmertal procecures are prepared by each department that is responsible for implementing portions of the Quality Assurance Program.

O

a. Department Procedures - Projects, Engineering and Construction Organizations within Projects, Engineering and Construction prepare and maintain procedures as necessary to provide instructions for administrative control and technical support during the Midland Nuclear Plant Project. They provide the basis for a consistent method of performing recurring engineering, construction and Quality Assurance activities. They also control the interfaces between Consumers Power Company and its suppliers. These procedures establish the system for offsite Management control and visibility and for control of onsite quality-related activities which assure the Quality Assurance Program is
implemented, maintained and its effectiveness is measured and reported.
b. Support Organization Decartment Procedures The Support Organizations such as System Protection and Laboratory Services, Purchasing and Management and Budget, prepare and maintain procedures for their activities that are within the Quality Assurance Program. These procedures provide the basis for a consistent method of performing their internal department quality-related activities and also define the interfaces between other Consumers Power Company departments sad suppliers.

O pr0730-0417b-13-167

o QUALITY ASSURANCE PROGRA.41 POLICY Policy No 3 Page 3 of a Revision 12 INSTRUCTIONS, PROCEDURES AND DRA'n'INGS Date 4/2/82 3.4 QUALITY ASSURANCE PROGRAM SITE PROCEDURES Special procedures are prepared by various responsible departments or organisations for use at the Midland site. l I

a. Preoperational and Hot Functional Test Procedures Projects, Engineering and Construction is responsible for providing for the preparation of:

(1) Preoperational test procedures for preliminary testing of components and systems prior to initial fuel loading to assure that construction and installation are complete and to verify design and function of systems.

(2) Hot functional test procedures for testing the NSSS and auxiliary systems where possible at rated temperature and pressure to demonstrate their satisfactory performance.

N I Test procedures are prepared in compliance with the NRC Regulatory Guide 1.68.

b. Quality Control Procedures Quality Control Procedures are working level documents which prescribe quality control activities. These Procedures provide detailed l instructions for the physical inspection, test and measurement of parts, components and materials to assure compliance to engineering requirements, specifications, codes, standards and procurement documents.

The Procedures also provide additional detailed instructions for carrying l out the quality functions specified by Quality Assurance Program Procedures. These procedures are included in the Midland Project Quality

. Assurance Department Procedures Manual.

c. Special Process Procedures

( Special Process Procedures are those procedures which control special processes, including welding, heat-treating and nondestructive testing.

Special Process Procedures require qualification of personnel, equipment, or procedures through tests and examinations by examiners, or approved examination techniques. Special Process Procedures are prepared in i

compliance with ANSI N45.2, Section 10, and requirements of applicable standards and codes such as the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code.

D J

pr0780-0417b-13-167 L

QUALITY ASSURANCE PROGRAM POLICY Policy No 5

? age 4 of 4 Revision 12 INSTRUCTIC.SS, PROCEDURES AND DRAWINGS Date 4/2/S2

d. Suppliers' Work and Insoection Procedures Prior to performing work or inspection on a safety-related item (structures, systems and ccaponents), suppliers are required to develop written procedures for accomplishing quality-related work activities and performing required inspections and tests. Thesa procedures reference applicable drawings, specifications, codes and standards. The Midland Pro *ect Quality Assurance Department reviews field inspection plans or inspection precedures prier to implementation.

1 O

O pr07S0-0417b-13-167

(N QUALITY ASSURANCE PROGRAM POLICY Policy No 6 C) Page 1 of 4 Revision 12 CJA$Um8m POW 8f 1.0 GENERAL Documents which prescribe activities affecting quality, including instruc-tions and procedures, are prepared, reviewed, issued, and controlled according to written procedures. Measures are included to assure that documents, including changes, are reviewed for adequacy and approved for release by the supervisory personnel of the organization preparing the document 2nd are distributed 1ccording to a controlled distribution to the user functions. The document control system provides for:

a. Identification of individuals and organizations responsible for pre-paring, reviewing, approving, and issuing documents and revisions.
b. Identifying the proper documents to be used in performing a quality-related or safety-related activity (refer to Quality Assurance Program Policy 5),
c. Coordination and control of interface documents.

rN d. Ascertaining that proper documents are being used.

e. Establishing current and updated distribution lists.

(NOTE: This policy does not apply to Engineering Records such as drawings, specifications, vendor drawings, etc. which are covered by Quality Program Policies 3 and 4.)

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 6, Document Control
b. ANSI N45.2, Criterion 7, Document Control
c. ASME Boiler and Pressure Vessel Code,Section III, Nuclear Power Plant Components 3.0 POLICY 3.1 DOCUMENT PREPARATION The head of the depr . ment within the Consumers Power Company organization that is responsible tor activities that are quality-related is responsible for directing the preparation of instructions or procedures for performing the activities. He or his designated representative is responsibic for the identification of regulatory requirements, industry standards, Consumers f-ss Power Company Quality Assurance Program requirements, Safety Analysis Report

( ) requirements, and Management instructions which relate to his area of l

'- / responsibility and that the applicable requirements / standards / instructions pr0780-0417c-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 6 i Page 2 cf a Revision 12 DOCUMENT CONTROL Date 4/2/82 are complied with. He is responsible to assure that une documents and revisions recognize and establish interfaces with cther functions or organizations, and he coordinates the review and resolution of comments with those organizations. The reviewer has access to backgrcund information to l assure adequate understanding of the requirements for the document and the document's contents. A system for the preparation of documents and revisions, and their interdepartmental and intradepartmental review, approval and administration which preclude the cossibility of the use of outdated or inappropriate documents is defined by specific department precedures.

3.2 DOCUMENT DISTRIBUTION AND CONTROL Instructional documents are distributed to users and to other personnel according to a distribution list maintained by the person responsible for preparation and control of the document. The head of the department responsible for the document distributes up-to-date issues of the documents and maintains an up-to-date document index. The assigned holders of the document are responsible for maintaining the latest revisions of the documents. The Audit & Management Systems Section audits to assure that the documents are maintained current and are at the locations where the information is to be used.

3.3 RESPONSIBILITY FOR DOCUMENT PREPARATION AND CONTROL The following sections list the responsibilities for the preparation, review, approval and distribution of policies, procedures and other instructional documents:

3.3.1 Quality Assurance Program Policies The Director - Environmental & Quality Assurance formulates Quality Assurance Program Policies. The Director coordinates and acquires the approval of the policies by the Vice Presidents who have the authority and responsibility for the elements of the Quality Assurance Program addressed by the policy.

Programmatic changes are submitted to the NRC for review and acceptance prior to implementation. Organizational changes are submitted to the NRC for information within 30 days of the announcement of the change.

3.3.2 Quality Assurance Program Procedures The Director - Environmental & Quality Assurance is responsible for the preparation, approval and control of Quality Assurance Program Procedures for Design and Construction which cover quality-related activities for the Midland Nuclear Plant Project. l g

pr0780-0417c-13-le7

QUALITY ASSURANCE PROGRAM POLICY Policy No 6 (n)

Page 3 of a Revision 12 DOCC'IENT CONTROL Date 4/2/82 3.3.3 Quality Assurance Program Departmental Procedures The head of each department is responsible for the preparation, review, approval, distribution and control of departmental procedures which describe the departmental quality-related activities for the Midland Nuclear Plant Project.

3.3.4 Test Procedures Test procedures required for the implementation of the construction and preoperational and hot functional test programs are prepared by personnel from the NSSS Supplier, A-E, Constructor and Consumers Power Company organizations. The Midland Project Office is responsible for coordinating the preparation, review, distribution and control of test procedures.

3.3.5 Quality Control Procedures Quality Control Procedures are prepared and appr>ved by Midland l Project Quality Assurance. Distribution and control are the

) responsibility of Audit and Management Systems. These procedures are

' contained in the Midland Project Quality Assurance Department Procedures Manual.

3.3.6 Special Process Procedures Special Process Procedures, used during design construction and l testing, are prepared and controlled by Consumers Power Company organizations or the suppliers who perform work for Consumers Power Company. Copies of procedures used at the Midland Nuclear Plant Site are retained by Consumers Power Company as records (refer to Quality Assurance Policy 17, " Quality Assurance Records"). Responsibilities for preparation and control of Special Process Procedures used by Consumers Power Company personnel are assigned as follows:

(a) Nondestructive Testing (NDT) Procedures - Manager, System Protection and Laboratory Services or Manager, Midland Project Quality Assurance (Midland Project QA NDT Procedures Only)

(b) Cleaning Procedures- Midland Technical Superintendent 3.3.7 Supplier Work Procedures Preparation, review, approval and distribution of Supplier Work Procedures are by the individual suppliers.

O N,)

pr0780-0417c-13-167

/fD QUALITY ASSURANCE PROGRASI POLICY Policy No 6 Page 4 of 4

(( h.ibgy) Revision 12 DOCCENT CONTROL Date 4/2/S2

$5;:.03.7 Entt 3.3.8 Calibration Precedures Preparation, review, approval, and distribution of calibration procedures for portable !!&TE, when calibratien responsibility has been assigned to SPLLS, are the responsibility of the llanager, System Protection and Laboratory Services. The .'fidland Technical Departcent has similar responsibilit'/ for plant' installed instrumentation.

3.4 REVISIONS TO INSTRUCTICSAL DOCUSIE.NTS Revisions to precedures and instructions are processed, distributed and controlled as required by regulatory requirements. l O

O pr07S0-0417c-13-le7

g g

QUALITY ASSURANCE PROGRAM POLICY Policy No 7 Page 1 of a Revision 12 Consumers power CONTROL OF PCRCHASED MATERIAL, EQUIPMENT AND SERVICES Date 4/2/82 1.0 GENERAL Suppliers furnishing safety-related materials, equipment and services are selected on the basis of their capability to provide these items. The Midland Project Office and the Midland Project Quality Assurance Department verify that procurement requirements are met. This is accomplished through review of procurement documents, source evaluation and inspection, audits end obtaining objective evidence of quality such as physical and chemical test reports and certificates of conformance.

I If the material, equipment, or services is procured by Consumers Power prin-cipal suppliers, or their suppliers, these principal suppliers or suppliers verify that purchased items conform to requirements. Audit & Management Systems audits these suppliers to verify that the established procurement controls are adequate and effective.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 7, Control of Purchased Materials, Equipment, and Services
b. ANSI N45.2, Criterion 8, Control of Purchased Material, EqtIipment, and Services l c. ANSI N45.2.2, Paragraph 5, Receiving
d. ANSI N45.2.13, Quality Assurance. Requirements for Control of Procurement of Equipment, Materials, and Fervices for Nuclear Power Plants
e. ASME Boiler and Pressure Vcssel Code,Section III, Nuclear Power Plant Components 3.0 POLICY l 3.1 EVALUATION OF SUPPLIERS l

l The evaluation of suppliers is based on one or more of the following:

l l a. The ability of the supplier to currently comply with those elements of NRC 10 CFR 50, Appendix B, and ANSI S45.2 that are applicable to the type of material, equipment and services being procured.

b. A review of previous records and performance of suppliers who have i supplied similar articles.

l

c. An evaluation of the supplier's facilities and Quality Assurance Program, when no previous quality records are available, to determine the j k/ capability to supply a product which meets required design, manufacturing l

l l

l pr0780-0417d-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 7 Page 2 of 4 Revision 12 CONTROL OF PURCHASED MATERIAL, EQUIPMENT AND SERVICES Date 4/2/82 and quality requiremen*s. Results of these evaluations are documented and filed in the appropriate Quality Assurance files.

An evaluaticn of technical and Quality Assurance capability is required for suppliers providing safety-related items or services to Consumers Power Company.

Quality Assurance evaluations are performed using source qualification programs, historical quality performance data, or scurce surveys er audits.

Source qualification programs may include:

a. The ASME Nuclear Certifications Programs
b. The Nuclear Regulatory Commissian Licensee Contractor and Vendor Inspection Program (LCVIP)
c. The Coordinating Agency for Supplier Evaluation Program (CASE)
d. Other Similar Programs When such programs are used, the Midland Project Quality Assurance Department l assures the suppliers' Quality Assurance Programs meet applicable elements of Policy 4.

l Preaward evaluation of the principal supplier's Quality Assurance capability i

is the responsibility of the Midland Project Quality Assurance Department.

Design, fabrication and managerial capabilities of principal suppliers of l nonconstruction contractor type services'are evaluated by the Midland Project l Office. Commercial capabilities of the principal supplier are evaluated by j the Purchasing Department. When a specific supplier's program has been l approved, this information is forwarded to the Purchasing Department by the Midland Project Office. l l 3.2 SELECTION OF SUPPLIERS l

Selection of suppliers is based on the preaward evaluations and the capability of the supplier to provide established procurement requirements.

The Midland Project Office initiates purchase orders (via the Purchasing l Department) for safety-related items and noncenstruction contractor services, l other than engineering and construction field labor, with approved suppliers.

Principal suppliers of contractor construction field labor are evaluated for i

construction and managerial capability by the Midland Project Office. The l Midland Quality Assurance Department evaluates the contractor's Quality l Assurance Program.

O 1

pr0780-0417d-13-le7 f

QUALITY ASSURANCE PROGRAM POLICY Policy No 7 I Page 3 of I.

Revision 12 CONTROL OF PURCHASED MATERIAL, EQUIPMENT AND SERVICES Date 4/2/82 3.3 AUDIT, SURVEILLANCE AND INSPECTION OF SUPPLIER OPERATIONS The Manager - Quality Assurance, Midland Project, assigns qualified personnel l to the supplier's facility to implement source inspection and surveillance requirements at predetermined points during the procurement cycle in accordance with inspection procedures, checklists and schedules. Based on l the requirements, an inspection plan and checklist are prepared to outline the method of performance and to advise the suoplier of his obligation to seccamodate sad respend to the requirements. The plan includes witness and hold points and tentative schedules.

Onsite and offsite audits of principal supplier operations are conducted to assure that all procurement requirements are met, with audit intervals consistent with the importance, complexity, and quality of the item or service provided. These audits are conducted in accordance with Quality Assurance Program Policy 18, " Audits."

Source surveillance or inspection, including designated hold points, are made a requirement of the procurement document when conditions such as the p)

\

U following exist:

a. Determination of conformance of the item to procurement document require-ments at the site would require uneconomic disassembly or destructive l testing.
b. Special instruments, gauges or facilities rectired for inspection or test at the source would be uneconomical to reproduce at the site. l
c. Inspection at the site would require replacement of special preservation l or packing.
d. Inspections and tests are an integral part of the manufacturing process and a physical verification prior to final assembly is necessary to assure the required quality.

3.4 RECEIVING INSPECTION Receipt inspections are made to verify that the items are undamaged, that they conform to procurement requirements not verified by source surveillance or inspection, and that the required documentation is available. Documented evidence that the items meet requirements such as receiving inspection reports, physical and chemical test reports, and certification of conformance must be available at the plant site prior to installation or use of the items The Section Head - Audit & Management Systems assigns personnel to l audit the procurement control activities of these onsite suppliers of services. In cases where documentary evidence is not available, the associated equipment or materials is considered nonconforming, l pr0780-0417d-13-167

(

QUALITY ASSURANCE PROGRASI POLICY Policy No 7 E  ? a ge :. o f '.

Revision 12 CONTROL OF PURCHASED !!ATERIAL, EQUIPMENT AND SERVICES Date '/2/82 Until suitable documentary evidence is available to show the equipment or material is in conformance, affected systems are considered inoperable and reliance is not placed on such systems to fulfill their intended safety functions. l Nonconforming items are identified and controlled in accordance with Quality Assurance Program Policy 15, " Nonconforming Items."

l O

l pr07S0-0417d-13-lo?

l l

1

(.

s 1 I I

QUALITY ASSURANCE PROGRAM POLICY Policy No 8 Page 1 of 2 Revision 12 CMSumtf5 POWtf IDENTIFICATION AND CONTROL Date 4/2/82 0F MATERIALS, PARTS AND COMPONENTS 1.0 GENERAL Consumers Power Company and its principal suppliers such as Architect- i Engineers and NSSS suppliers, and their onsite suppliers exercise a system of controls to assure that only correct and accepted materials, parts and components (items) are used and installed. These items are identified by marking the items or by records traceable to the items. This identification is maintained frem initial receiot throughout fabricatien, installation. l repair, modificatien and use and of the items. The identification requirements applicable to each procurement are established by the suppliers or by Consumers Power Company with review by Midland Project Quality Assurance. Requirements for identification and control are incorporated into l the appropriate procurement documents in accordance with the provisions established in Quality Assurance Program Policy 4, " Procurement Document Control." l 2.0 BASIS DOCUMENTS

a. h3C 10 CFR 50, Appendix B, Criterion 8, Identification and Contrcl of Materials, Parts, and Components O b. NRC Regulatory Guide 1.33, (3/16/73), Quality Assurance Requirements for l Packaging, Shipping, Receiving, Storage, and Handling of Items for Water-Cooled Nuclear Power Plants (Endorses ANSI N45.2.2)
c. ANSI N45.2, Criterion 9, Identification and Control of Materials, Parts, and Components
d. ANSI N45.2.2, Paragraph 5.4, Status Indicating System, and Paragraph 5.6, Marking 3.0 POLICY 3.1 ITEM IDENTIFICATION Physical identification is required where possible. Identification through documentation is required where physical identification is not practical.

Identification requirements are such that the item identified can be traced to the associated cocumentation, such as drawings, specifications, Purchase Orders, manufacturing and inspection documents, deviation reports or physical and chemical mill test reports. Consideration is given to assure that the location and the method of identification do not affect the function or quality of the item being identified.

The Design Production Manager specifies in contracts or procurement documents l that requirements for identification and marking be in accordance with nU applicable codes, standards and Company requirements (eg, heat number, part number, serial number, lot number, etc). He obtains assistance as required pr0780-0418a-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No s I Page 2 of 2 Revision 12 I

  • IDENTIFICATION AND CONTRCL Date 4/2/S2 CF MATERI ALS , PARTS AND COMPONENTS from other appropriate organizations and the Midland Project Quality Atsurance Department. The identification and marking requirements are l incorporated into Consumers Power Company design and procurement documents and are made a part of the purchase orders or contracts placed with the Architect-Engineer, Constructor, Nuclear Steam Supply System supplier and other principal suppliers. These procurement documents also include requirements for the principal suppliers to place appropriate requirements for the identification, control and traceability of materials , carts and components on their lower tier suppliers.

l Audit & Management Systems audits to verify that items are properly l identified.

3.2 ITEM CONTROL Items are inspected upon receipt at the plant site by the supplier of construction services. These inspections include checks to verify that the l items are properly marked for identification purposes when specified as a requirement in the procurement documents.

During subsequent fabrication and installation of the items, in process surveillance is made by Midland Project Quality Assurance personnel and inspection by the construction contractor's onsite inspection personnel to verify that the required identification is nct obliterated or hidden.

Identification markings are maintained for each part of an item or on records traceable to the item.

If the required identification is missing, abliterated or hidden, the item is identified as nonconforming and is placed in a segregated area, where practical. The item cannot be used until its identification marking conforms to the procurement document, drawing or specification requirements.

1 i

1 l

till or0730-041Sa-13-167 l

y g

(O"-

QUALITY ASSURANCE PROGRA31 POLICY Policy No 9 Page 1 of 3 Revision 12 gg CONTROL OF SPECIAL PRCCESSES Date A/2/82 i

1.0 GENERAL -

t The Midland Project Office is responsible for requiring the principal l i supplier or the responsible Consumers Power Company department that uses special processes to develop and implement requirements of appropriate codes,

standards or specifications as indicated in the design or procurement documents. Principal suppliers require their lower tier suppliers to implement these requirements. '4hether performed by Consumers Pcwor Company

, or a principal supplier, special processes tre performed using qualified

! procedures, equipment and personnel.

The responsible Department Managers assure that special process procedures l are prepared in accordance with Quality Assurance Program Procedures.

Special Process Procedures contain the necessary prerequisites, personnel requirements and qualification test procedures and limitations, acceptance criteria or standards, results interpretation, records, etc, as applicable to the particular requirements of the methods and material employed.

For such special processes such as welding, heat-treating, chemical analysis, nondestructive testing and cleaning, where the required level of quslity

, cannot be measured by inspection only of the item, Consumers Power Company, its suppliers and their lower-tier suppliers accomplish these processes under controlled conditions in accordance with applicable codes, standards and specifications using qualified procedures, equipment and personnel. For special processes not covered by codes or standards, qualifications of procedures, equipment and personnel are specified.

2.0 BASIS DOCUMENTS
a. NRC 10 CFR 50, Appendix B, Criterion 9, Control c4 Special Processes
b. NRC Regulatory Guide 1.58, Rev 1 Qualification of Nuclear Power Plant l Inspection, Examination, and Testing Personnel (Endorses ANSI S45.2.6)
c. ANSI N45.2, Criterion 10, Control of Special Processes
d. ASME Boiler and Pressure Vessel Code

l (1)Section III, Nuclear Power Plant Components and Appendix IX, Nondestructive Examination Methods (2)Section V, Nondestructive Examination (3)Section IX, Welding Qualifications (4)Section XI, Rules for Inservice Inspection of Nuclear Reactor Coolant Systems

~

1 J i

l p r0780-01. lSb 16 7

i QUALITY ASSURANCE PROGRAM POLICY Policy No 9 Page 2 of 3 Revision 12 CONTK5L CF SPECIAL PROCESSES Date 4/2/32

e. SNT-TC-1A and Supplements, American Society for Nondestructive Testing Recommended Practices 3.0 POLICY 3.1 PRCCESS QUALIFICATION AND CONTROL Soecial orocesses are cerformed bv either Consumers Power Comnenv or sucolier i personnel. When specihl pro:erses areperformedbyC:nsumers'PwerCc=[any, ll the requirements are established during the design phase by the Design Production Manager with assistance from other Consumers Power Company departments as required. When performed by a supplier, the requirement to perform special processes in accordance with applicable specifications, codes and standards is made a provision of the procurement documents pla.ed with Consumers Power Company principal supplierr such as the Architect-Engineer, Constructor and NSSS supplier. These principal suppliers are also required to establish provisions for the control of special processes in their lower-tier procurement documents. Whether performed by Consumers Power Company or its principal supplier, special processes are accomplished with written process sheets, shop procedures, checklists, travelers or equivalent with recorded evidence of verification. Qualification records of procedures and equipment associated with special processes are available and maintained.

Personnel are assigned by the Midland Project Quality Assurance Department l and the Midland Project Design Production Department with assic:ance, as requested, from other departzents or organizations to review the process control requirements placed in procurement documents as indicated in Quality Assurance Policy 4, " Procurement Document Control."

3.2 PERSONNEL QUALIFICATION Consumers Power Company and supplier personnel responsible for the performance of special processes are qualified in accordance with applicable codes, specifications and standards. This includes conducting the necessary training and examinations to deter =ine the capability of each individual.

Qualification records of personnel associated with special processes are established, filed and kept current. The period of validity for qualifications will be in accordance with applicable codes, specifications and standards. The Midland Project Quality Assurance Department monitors the process control activities of onsite personnel or suppliers during construction, installation, preoperational and hot functional testing activities.

O pr0780-0418b-13-167

I l

i I QUALITY ASSURANCE PROGRAM POLICY Policy No 9 Page 3 of 3 Revision 12 CONTROL OF SPECIAL PROCESSES Date 4/2/32 4

3.3 PROCESS CONTROL RECORDS Consumers Power Company and supplier personnel performing special processes

,aaintain records to verify that the required activities were accomplished in accordance with qualified procedures by qualified personnel. These records I are maintained as indicated in Quality Assurance Policy 17, " Quality Assurance Records."

r i

i I

1 i

l l

i 1

i l pr0750-0418b-13-167

p QUALITY ASSURANCE PROGRA31 POLICY Policy No 10 d 5**1 nevision f3 1.

Casumers power INSPECTION Date 4/2/82 1.0 CENERAL Inspection and surveillance are performed to assure that activities affecting quality comply with documented instructions, design documents and applicable codes and standards. When direct inspection of an item cannot be performed or is impractical, surveillance of the process or procedure and the resulting documentation assure ccmpliance. Inspection and surveillance are performed according to written instructions.

Inspection procedures, instructions and checklists used by personnel checking the quality of work, provide the following: l

a. Identification of characteristics to be inspected.
b. Identification of individuals or groups responsible for performing the inspection.
c. Acceptance and rejection criteria.
d. Description of the method of inspection.

\ e. Verification of completion and certification of inspection.

f. Record of results of inspection.
g. Provision for identifying mandatory inspection hold points for witness by an authorized inspector.
h. Provision for indirect control by monitoring processing methods, equip-ment and personnel if direct inspection is not possible.

Procedures for receipt innpections are either prepared or reviewed by Quality l Assurance personnel (Consumers Power Company or its principal suppliers) to determine the need for an independent inspection and the degree and method if such an inspection is required and to assure the identification of inspection personnel and the documentation of inspection results.

An inspection is made upon completion of work on a system or component prior to declaring the system operable. Surveillance of procedures and inspection activities is performed according to a scheduled, planned program. l The organization (eg, corporation) responsible for the work normally performs the inspections. The personnel performing inspections have the necessary qualifications and are independent of the supervisor directly responsible for performing the work being inspected.

Midland Project Quality Assurance is responsible for assuring adequate inspection and surveillance activities. Audit & Management Systems is l

pr0780-0418c-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 10 l

? age 2 of 3 Revision 12 Cusumers nwer INSPECTION Date 4/2/82 i

responsible for audit of the inspection and surveillance activities.

Nonconformances are documented according to Quality Assurance Program l Policy 15, " Nonconforming Items."

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 10, Inspection
b. NRC 10 CFR 50, Paragraph 50.55a, Codes and Standards
c. NRC Regulatory Guide 1.30, (8/11/72), Quality Assurance Requirements for l Installation, Inspection and Testing of Instrumentation and Electric Equipment (Endorses ANSI N45.2.4)
d. NRC Regulatory Guide 1.58, Rev 1, Qualification of Nuclea. Power Plant Inspection, Examination and Testing Personnel
e. ANSI N45.2, Criterion 11, Inspection l
f. ANSI S45.2.8, Supplementary Quality Assurance Requirements for l Installation, Inspection and Testing of Mechanical Equipment and Systems for the Construction Phase of Nuclear Power Plants
g. American Society of Mechanical Engineers (ASME) Boiler and Pressure l

Vessel Code,Section III, Nuclear Power Plant Components

h. ASME Boiler and Pressure Vessel Code, Section NI, Rules for Inservice Inspection of Nuclear Power Plant Components l 3.0 POLICY 3.1 INSPECTION AND SURVEILLANCE Work activities are performed by Consumers Power Company personnel and by l contractors and suppliers. These work activities are acccmplished according to approved procedures or instructions which include inspection hold points beyond which the work does not proceed until the inspection is complete or written consent for bypassing the inspection has 'aeen received from the organization authorized to perform the inspection. Midland Project Quality l Assurance and/or supplier quality control personnel perform inspections or witnessing of inspections at each hold point and upon completion of the identified segment of work. The inspection includes review and verification of the related documentation. The results of inspections are documented and nonconformances are reported as indicated in Quality Assurance Program Policy 15, " Nonconforming items." Consumers Power Company and/or suppliers provide qualified personnel, procedures, equipment and measuring devices as necessary to conduct inspections as indicated in Quality Assurance Program Policy 9, " Control of Special Processes."

pr0730-041Sc-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 10 Page 3 of 3 Revision 12 Caf!Sumers power l

The Midland Project Quality Assurance Department performs inspections and l overinspections of supplier inspection activities. Inspections and overinspections are performed in accordance with inspection plans and written procedures. l 3.2 INSERVICE INSPECTION Insoections which provide the baseline for inservice inspection are performed at the direction of the Manager of Design Pr ducti:n, in accordance with l written procedures. The Design Production Department and, when required, assisted by other organizations, is responsible for coordinating the development of baseline inspection procedures for their approval and control and for design criteria for arrangement of components for adequate clearance for inspection. l The procedures are prepared according to the applicable requirements of the ASME Boiler and Pressure Vessel Code, the SAR and NRC Regulatory Guide 1.31.

Results of baseline inspections are maintained as lifetime plant records in l the Document Storage Room in the General Office.

Records of baseline and inservice inspection results, corrective action, standards for repair, results of inspections of repairs and baseline inspections of replacements are maintained and compared with the results of subsequent inservice inspections.

(

pr0780-0418c-13-167

p QUALITY ASSURANCE PROGRA.M POLICY Policy No 11 Q Page 1 of 3 Revision 12 C3nsumers power C N ROL Date U2/82 1.0 GENERAL The following are tests conducted during the construction of the Midland Nuclear Plant:

a. Construction Tests - Those tests necessary to verify that the installa-tion of systems is complete and complies with the applicable specifica-tions. standards , codes , drawin gs and engineering information. It includes tests such as hydrostatic testing, megger testing, continuity I testing and cleanliness testing.
b. Preoperational Tests - Tests prior to initial fuel loading and plant operation to demonstrate the apability of structures, systems and components to meet performance requirements.
c. Hot Functional Tests - Tests conducted at completion of preoperational tests. The Nuclear Steam Supply Systems and auxiliary systems, where possible, are brought to rated temperature and pressure to denonstrate satisfactory performance. l O

t / Tests are performed according to written procedures and the test results are documented. Tests are conducted by trained, qualified or licensed personnel.

The construction contractor provides and implements appropriate construction tests.

l The Midland Technical Superintendent is responsible for the development and implementation of checkout, preoperational and hot functional test proce-dures.

During construction, testing of modifications, re,. irs and replacements is in l accordance with the original design and testing requirements, or acceptable alternatives, and is procedurally controlled.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 11, Test Control
b. NRC Regulatory Guide 1.30, (S/11/72), Quality Assurance Requirements for l the Installation, Inspection and Testing of Instrumentation and Electric Equipment (Endorses ANSI N45.2.4)
c. NRC Regulatory Guide 1.68, (Nov 1973), Preoperational and Initial Test l Programs for Water-Cooled Power Reactors
d. ANSI N45.2, Criterion 12, Test Control

\

'w )

pr0780-0418d-13-167

QUALITY ASSURANCE PROGRA.\1 POLICY 3

Q q

Policy so 11 Page 2 of 3 nevision 12 g

TEST CosTROL Date v2/s2 c:nnmen awer

e. ANSI S45.2.8, Supplementary Quality Assurance Requirements for Installation, Inspection and Testing of Mechanical Equipment and Systems for the Construction Phase of Nuclear Power Plants 3.0 FOLICY 3.1 TEST PROCEDURES Construction test procedures are prepared by the supplier of construction services or Consumers Power Company with coordination of preparation, review and control by the Midland Project Office. Preoperational, checkout and hot functional test procedures are provided by the Midland Technical Superintendent with assistance from the NSSS Supplier, A-E, Constructor and Consumers Power Company Engineering organisations, as necessary. The Midland Site Manager is responsible for the preparation of the Midland Project Testing Program Manual which delineates: A planned program for preoperational and hot functional testing, as applicable; defines the test organization and objectives; identifies responsibilities and provides an index of Testing Program Manual procedures. The Midland Project Testing Program Manual is reviewed and approved by the Vice President - Nuclear Operations; the Vice President - Projects, Engineering and Construction, the Director - Environmental & Quality Assurance; the Site Manager; and the Director, Quality Assurance - Nuclear Operations or assigned delegates. l Test procedures which include prerequisites, requirements and acceptance limits are provided by the organization responsible for the design of the item, unless otherwise designated. The procedures also specify the required test equipment, its accuracy, acceptable calibration status and recording requirements. Hold points are identified in the test procedures where witnessing of the tests is required. Test results are documented and checklist and iata sheets may be attached as addenda to complex procedures.

3.2 CCNDUCT OF TESTS 3.2.1 Construction Tests Construction tests are performed and documented by supplier or l Consumcrs Power Company personnel with surveillance by Midland Project Quality Assurance. Documented test results are retained for record.

3.2.2 Preoperational and Hot Functional Tests Midland Project Quality Assurance and Technical Department personnel review and evaluate the completion of systems construction and installation prior to turnover to Consumers Power Company for testing.

Midland Project Quality Assurance also assures that construction testing prerequisites have been met prior to running of preoperational and hot functional tests. The Midland Project Technical pr0780-OLISd-13-167

N t,

I QUALITY ASSURANCE PROGRA.TI POLICY Policy No 11 Dage 3 o: 3 1 i

Revision 12 l Consumers power TEST CONTROL Date 4/2/82 i l

Superintendent coordinates system turnover and the implementation of preoperational and hot functional testing activities. l The !!idland Project Quality Assurance Department in coordination with Audit & ?!anagement Systems performs audits and surveillance cf the l test activities to assure that tests are performed in accordance with written procedures, results are documented, test results are reviewed and approved accr.rding to the >!idland Project Testing Program ?!anual and nonconformances or test anomalies are dispesitioned prior to initial start-up tests.

O v

pr0780-0413d-13-167

1 f- j QUALITY ASSURANCE FROGRAM POLICY policy No 12 l

I

('~3) Page 1 of 3 Revision 12 C33umers Mwer CME & NRN N W EWW Date UW I.0 GENTRAL Devices used for quality verification which are utill:ea to calibrate, measure, gauge, test or inspect safety-related materials, components, parts, systems and structures are controlled, calibrated and records maintained in accordance with approved procedures. Calibration of portable and laboratory measuring and test equipment is performed at prescribed intervals or prior to use using secondary or reference standards which are traceable to nationally recognized standards. Where no standards exist, the basis for calibration is documented. Approved procedures prescribe tha method and the interval of calibration based on the type of equipment, stability, required accuracy and other conditions affecting measurement control. A calibration control recall system is established to assure calibration prior to the equipment calibration expiration date and tags or labels are attached which identify the calibration status. Special calibrations are performed when the accuracy of equipment is suspect. When equipment is found to be consistently out of calibration, it is repaired or replaced. Nonconforming test and measuring equipment is identified and controlled and evaluations are conducted to determine the validity of previous inspections or tests which utilized the defective equipment. Calibration records are maintained and controlled. The

(,~) Project Manager is responsible for assuring that the A-E, NSSS Supplier, V

Constructors, principal suppliers and Consumers Power Company organizations develop procedures to maintain and control measuring and test equipment within their respective areas. The responsible Quality Assurance l organizations assures compliance to procedures through surveillance and audits.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 12, Control of Measuring and Test Equipment
b. ANSI N45.2, Criterion 13, Control of Measuring and Test Equipment 3.0 POLICY 3.1 MEASURING AND TEST EQUIPMENT LIST Lists of measuring and test equipment required for construction and construction testing are developed by the A-E, constructor or other suppliers. The lists identify the test equipment, method and interval of calibration. The availability of these lists and the control of measuring and test equipment on the lists are audited by Audit & Manage =ent Systems.

i l Lists of measuring and test equipment required for preoperational and hot functional testing are prepared at the direction of the Midland Technical O Superintendent. Included on lists of measuring and test equipment are test equipment and laboratory test equipment.

I or0780-0!.18e-13-167

i 4@ QUALITY ASSUR \NCE PROGRAM POLICY N11cy No 12

%f).

O ;.

Page 2 of 3 Revision 12 h'

CONT 7.3L CF ::EASCTsl:;0 AND ~'23T E;"1F"~.';T Ca:e 1./ .'. / 3 2 C 3 5t.T. .7 EQYltf I

3.2 PR0r".DURT.S Calibration control precedures are prepared by the group who provide the measuring and test equipment. A calibration recall system for portable and laboratory test equipment (PL-MSTE) and standards, which identifies when calibration is required, is developed, documented by precedures and maintained by the group who is using the equipment. Action is taken to recalibra:e the equipment before the expira:ica date or prior to use.

When a user group assigns complete calibration and repair of MLTE responsi-bi(itics to SP&LS, the recall system is developed, documented by precedures and maintained by the Calibration and Instrument Services Supervisor, SPLLS.

The user group is notified prior to calibration expiration dates te return the MSTE.

Calibration procedures require that Reference Standards used for calibrating

- PL-MLTE hsve an uncertainty (ie, error) requirement of no more than one- l quarter of the tolercnce of the equipment being calibrated. A greator uncertainty may be acceptable where limited by the accuracy of ccmmercially available star.dards. All other PL-M&TE (including Secendary Standards) have an uncertainty requ recent of less thaa or equal to the :olcrance of the equipment being calibrated.

The procedures are submitted for reviev and approval in accordance with Quality Assurance Prograc Policy 6 " Document Centrol."

3.3 CALI? RATION Calibration procedures are prepaced by the group responsible for calibration of the measuring and test equipment. The procedures are submitted for review and approval in accordance with Quality Assurance Program Policy 6 "Decument Control." The calibratica system provides that measuring and test equipment and standards are maintained and used in an envircnment which will not adversely affect their accuracy. Certification of traceability to nationally recognized standards is supplied by the facility performing the calibration.

When no National Standard exists, the basis for the calibration is documented.

Portable measuring and test equipment and standards are identified with a label or tag which describes tne calibraticn status and includes a traceable identification number. Equipnent which is not identified or has an expired l calibration date is withheld frca use.

Midland Project Quality Assurance and Audit and 'icnagement Systems audits to l assure proper calibration, according to procedures, within the recall period, and that equipment and instruments are identified and their calibratica status indicated.

pr07E0-041Su-13-167

o QUALITY ASSURANCE PROGRAM POLICY Policy No 12 I

Page 3 of 3 Revision 12 CONTROL OF !!EASURING AND TEST EQUIP)!EST Date 4/2/82 3.4 NONCONFOR.4ANCES Failure of portable measuring and test equipment, standards or installed instrumentation and control equipment to successfully pass accuracy require-ments at the time of calibration or which become suspect prior to calibration is reported using 3 nonconformance reporting system. Evaluations are conducted to determine the validity of previous tests, inspections or operations which utilized the defective or susoect ecuipment and the results of evaluations documented. If the evaluation is negative, materials, components, parts, systems and structures which were verified by the tests or inspections are considered nonconforming.

3.5 RECORDS Records of portable measuring and test equipment and standards used during construction and preoperational, hot functional and start-up testing are l traceable to the test and inspections performed. Consumers Power Company calibration records of installed instrumentation and control equipment are maintained and controlled. These records are traceable to the test equipment l s calibration record and, when necessary, to the standard calibration record.

Records are retained for the period identified in the Safety Analysis Report or Departmental Procedures in accordance with Quality Assurance Program Policy 17, " Quality Assurance Records."

A pr0780-0418e-13-167

w QUALITY ASSURANCE PROGRA.\1 POLICY Policy No 13 Page 1 of 2 Revision 12 C:nsumers power HMEN, STORAGE, AW SHNG Date U2m 1.0 GENERAL The Midland Project Office assures that the principal suppliers, such as the l Architect-Engineer, Nuclear Steam Supply System supplier and constructor prepare procedures and instructions to control the handling, packaging, preservation, storage, lay-up, cleaning and shipping of safety-relate? items.

When necessary, special protective covering, equipment identification and environmental conditions are specified. Midland Project Quality Assurance l Department personnel verify compliance to procedures and instructions through inspections and audits. Also, Audit & Management Systems conducts audits to assure that the controls for handling, storage and shipping are established, implemented, adequate and effective.

Suppliers of items shipped to Consumers Power Company provide control of their storage, handling and shipping activities as specified by procurement documents.

I Special handling tools and equipment are inspected and tested at specified l times to verify that they are being adequately maintained.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 13, Handling, Storage, and Shipping
b. NRC Regulatory Guide 1.37, (3/16/73), Quality Assurance Requirements for l Cleaning of Fluid Systems and Associated Components (Endorses ANSI N45.2.1)
c. NRC Regulatory Guide 1.38, (3/16/73), Quality Assurance Requirements for l Packaging, Shipping, Receiving, Storage, and Handling of items for Water-Cooled Nuclear Power Plants (Endorses ANSI N45.2.2)
d. NRC Regulatory Guide 1.39, (3/16/73), Housekeeping Requirements for l Water-Cooled Nuclear Power Plants (Endorses ANSI N45.2.3)
e. NRC Regulatory Guide 1.54, (June 1973), Quality Assurance Requirements l i for Protective Coatings Applied to Water-Cooled Nuclear Power Plants I

(Endorses ANSI N101.4)

f. ANSI N45.2, Criterion 14, Handling, Storage, and Shipping 3.0 POLICY l 3.1 SPECIAL HANDLING PRIOR TO SHIPMENT Requirements for special handling and storage, including cleaning, packaging 3 and preservation of safety-related materials, spare parts and equipment, prior to shipment by the manufacturer or supplier, are conditions of the pr0780-0419a-13-167 i

. - . . . - . _ = , - -- , , _

QUALITY ASSURANCE PROGR.Ol POLICY Policy No a l Page 2 Of 2 Revision 12 HANDLI.NG, STORAGE, AND SHI? PING Date 4/2/82 1

procurement documents prepared in accordance with Quality Assurance Program Policy 4, " Pro arement Document Control." When required, the supplier or manufacturer prepares written procedures that provide special handling and storage instructions.

3.2 PREPARATICN FOR SHIPMENT Special requirements for protective packaging, preservation and segrecation of materials, shipping methed, shipping containers, cleanliness, pressurin-tion, desiccation and labeling of purchased items are specified in the procurement document. When the preparatien for shipment is extensive or involves special considerations, the supplier prepares written procedures l which address Regulatory Guides 1.37, 1.33 and 1.39, as applicable.

Source inspections by Consumers Power Company, Architect-Engineer, constructor or other supplier personnel may be employed to assure proper preparation for handling and shipping. Source inspection, when used, is specified in the procurement documents and the inspection results are documented for use.

3.3 RECEIPT AND STORAGE Suppliers provide plans, facilities, handling equipment, procedures and l personnel to receive, inspect, store, maintain and control items upon arrival at the site. Items, when inspected upon receipt, are identifed by marking or tagging in accordance with Quality Assurance Program Policy 8,

" Identification of Materials, Parts, and Components." When required, a supplier also maintains storage and inventory records applicable to the items which are acceptable for use.

Preservation and special onsite storage conditions, such as inert gas atmosphere, humidity controls, special cleanliness requirements, etc, are provided as specified in written instructions which address Regulatory Guides 1.37, 1.38 and 1.39. Micland Project Quality Assurance assures l through periodic inspection, surveillance and audits that supplier personnel adhere to the written instructions, follow acceptable housekeeping practices and proper use of storage facilities and handling equipment. Audit &

Management Systems conducts audits to assure that the controls for handling, storage and shipping are established, implemented, adequate and effective.

l l

e-pr0780-0419a-13-167

I QUALITY ASSURANCE PROGRASI POLICY Policy No la Page 1 of 1 Revision 12 I PECTION, TEST, AaB OPERATING STATUS Date 4/2/82 Consumen Mwtf 1.0 GENERAL The principal suppliers, such as the Architect-Engineer, Constructor and l other responsible onsite suppliers provide indicators which show the inspection, test and operating status of plant structures, systems and components. The Midland Technical Superintendent provides indicators which l shew the inspection, test and operating status of items during preoperational and ;.ot functional resting. The appropriate Ouality Assurtuce orgtni:stion  !

conducts tudits te verify cceplianc2s :: the established requir3ments I

Bypassing /resequencing of required inspections, tests and other critical l operations is procedurally controlled to assure that bypassed /resequenced inspections or tests are properly documented and that the effect of bypasssing/resequencing the inspection or test is evaluated by the organization responsible for specifying the inspection or test.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 14, Inspection, Test, and Operating

, Status

b. ANSI N43.2 Criterion 15, Inspectien, Test, and Operating Status I 3.0 POLICY 3.1 INDICATION OF STATUS BY SUPPLIERS Safety-related items received at the plant site are identified and controlled by the responsible supplier at the site in accordance with the supplier's approved procedures. These procedures define the methods used to assure identification as to inspection or test status, traceability to manufacturers and log and status of the item with respect to release for use. The procedures also include requirements for the identification and control of nonconforming items, item removed from subassemblics, in process systems and equipment and the status of related tests and inspections. Devices such as receiving and in-process inspection reports, nonconformance logs, hold tags and reject' tags are used to indicate the status of the items.

3.2 INDICATION OF STATUS BY CONSUMERS POWER COMPANY The Midland Technical Superintendent identifies the inspection, test and operating status of systems undergoing preoperational and hot functional testing in accordance with document 3 procedures. These procedures include requirements for the use of Workmen's Protection Tags, Caution Tags, Equipment Turned Over Tags and test procedures.

s I or0780-0419b-13-lo7

. __ _ - . -. - - - - . =. . _ - - - .- -- -

d m ' QUALITY ASSURANCE PROGRAM POLICY Policy No 13 i I Page 1 of 2 Revision 12 MMumm1 MWW NONCONFORMING ITEMS Date 4/2/82 1

1.0 GENERAL Procedural controls are established for identifying, documenting, l segregating, reviewing, reporting end disposing of nonconforming safety-related materials, parts, components or services.

Items, services or activities which are defleient in characteristic, documen-tation or procedure which renders the cuality unacceptable or indeterminate and which is censidered significant to safety are identified as nonconf ar:-

ances. Nonconforming items (structures, systems, components, parts, materials) are identified by marking, tagging, segregating or by documenta-tion. Nonconforming items are controlled to prevent their inadvertent 4 installation or use. The nonconformance is evaluated to determine a j disposition for the item; la, repair, rework, use-as-is, scrap or test to i

determine quality of the item; and the evaluation and disposition is  !

documented. Nonconforming items and activities are recorded and are considered for corrective action to prevent recurrence in accordance with Quality Assurance Program Policy 16, " Corrective Action." The Director -

Environmental and Quality Assurance is responsible for assuring that s

j g nonconformances are documented and controlled.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 15, Nonconforming Materials, Parts, or Components

! b. NRC 10 CFR 50, Section 55, Conditions of Construction Permits, Para-graph (e) (10 CFR 30.55(e))

c. ANSI N45.2, Criterion 16, Nonconforming Items 3.0 POLICY 3.1 RESPONSIBILITY FOR CONTROL OF NONCONFORMANCES

! l Control of nonconformances during the design and construction phase and

! during tests prior to initial fuel loading are the responsibility of the Consumers Power Company organizations responsible for the work. This activity may be delegated to the A-E, NSSS Supplier, constructor and other principal suppliers. These suppliers prepare procedures for nonconformance identification, disposition, reporting to Consumers Power Company and corrective action. Consumers Power Company organizations are responsible for notifying the applicable Quality Assurance organization of nonconformances observed or discovered as a result of inspection, calibration, test or verification activities by their personnel. Consumers Power Company Department Procedures control these activities. The Quality Assurance

[\d') organizations are responsible for documenting and controlling Consumers Power Company issued nonconformances. They also assure adherence to procedures by pr0780-0419c-13-167

i .

I.

QUALITY ASSURANCE PROGR.OI POLICY Policy No 13 Dage 2 of 2

. Revision 12 NONCONFCRMING ITEMS Date ;/2/d2 g ,

i i i suppliers and Consumers Power Company organizations by surveillance and audits and monitor statas of nonconformances. Status reports are submitted to the Vice President - Projects, Engineering and Construction.

I 3.2 IDENTIFICATION AND DCCUMENTATION OF NONCONFORMANCES When a nonconforming item or activity is discovered or observed, the l responsible surplier or Consumers Power Comoanv orzanization assures that the condition is docimented and that renconfo ming items tre ta;ged, marked, segregated or controlled to prevent inadvertent use or installation until the items are properly dispositioned. .

3.3 RESOLUTICN AND DISPOSITION OF NONCONFORMANCES Nonconformances ace reviewed and an investigation made to determine the extent and effect of the nonconformance. The review and investigation is made by technically qualified personnel designated by the suppliers and Censumers Pcwer Company Department Heads respcnsible for the item, area or activity. Upon completion of the resiew and investigation, the disposition of the conditien and (when appropriate) action to prevent recurrence is documented.

Acceptability of rework or repair of equipment, material, components or parts is verif;ed by reinspecting the item as originally inspected or by a method which is at least equal to the original inspection method and by documented inspection rework and repair procedures. Nonconforming items dispositioned "use-as-is" and " repair" having departures from design specifications and drawing requirements are reviewed and approved by the principal supplier, if applicable, and by the appropriate Quality Assurance organization. l The responsible Quality Assurance organization assures by audits the disposi-tion, completion and resolution of nonconformances.

3.4 SIGNIFICANT NCNCONFORMANCES l Sonconfermances identified by either a supplier or Consumers Power Company l l organization, are reviewed by the Midland Prcject Quality Assurance l Department. Nonconformances identified during preoperatienal and hot

! functional testing, by either a supplier or Censumers Power Company organization, are reviewed by the Site Management Office. Significant nonconformances meeting the criteria set forth in 10 CFR 50, Section 55,

Paragraph (e), are reported to Management and the NRC by the Manager -

l ?lidland Project Quality Assurance according to Quality Assurance Program Tolicy 20, " Program Reporting."

l l

pr07S0-0419c-13-167 l

QUALITY ASSURANCE PROGRAM POLICY Policy No 16 Page 1 of 3 Revision 12 CORRECTIVE ACTION Date 4/2/82 t

1.0 GENERAL Corrective action is that action taken to correct and preclude recurrence of significant ccaditions adverse to the quality of items or activities. Condi- l tions or trends observed or identified which are adverse to quality are considered for corrective action; however, nonconformances or departures from specified requirements which are not significant to safety, occur randomly, are of a minor nature or which are routinely corrected without the need for a technical evaluation may not require c0rrective actien. Correttive actica i includes an evaluation of the conditions that led to a nonconformance, the disposition of the nonconformance and completion of the action necessary to prevent or reduce the possibility of recurrence. Nonconformances are evaluated to determine the need for corrective action under the control of established procedures. Corrective action is documented and corrective action status is reported to Management. The organication responsible for the item or activity identified for corrective action is responsible for completion of the action and maintaining corrective action status. The Quality Assurance organizations are responsible for verifying completion of corrective action for their respective responsibility areas. l 2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 16, Corrective Action
b. NRC 10 CFR 30, Paragraph 50.55, Conditions of Construction Permits
c. ANSI S45.2, Criterion 17, Corrective Action I

3.0 POLICY 3.1 INITIATION OF CORRECTIVE ACTION Corrective action is initiated to correct conditions adverse to the quality of items and activities. The head of the organization or department responsible for the item or activity is responsible for initiating action to correct the immediate condition. He is also responsible for evaluating the condition to determine if additional action is required to prevent or reduce the possibility of recurrence. Conditions which require additional action to prevent recurrence are a matter of judgment, but the following conditions are always evaluated:

a. Failure of safety-related structure, system, component or part which is significant to safety.
b. Defect of a safety-related item that could, if uncorrected, lead to fr.ilure or malfunction which is significant to safety.

1 t

e pr0730-041]d-13-167

=

I 1

QUALITY ASSURANCE PROGR.OI POLICY Policy No 16 Pay 2 of 3 Revisien 12 g CORRECTIVE ACTICS Date 4/2/32

c. An in-use or inservice instrument or item of tes: equipment that is found to be out of calibration or has exceeded the calibratica due date.
d. Repetitive niner problems or defects which may be symp cmatic of a larger problem.

I

e. Significant deficiencies identified during quality audits.
f. Uns e.is f *:: cry cendit ions which could rntribut? :: majer 12 a;e, i personnel injury or schedule dalays.
g. Unsatisfactory conditions identified by the NRC.

I In general, corrective action is initiated to correct conditions adverse to quality and additions 1 action is taken to prevent recurrence of significant noncenformances, occurrences reportable to NRC, unsatisfactory conditions and audit deficiencies.

3.2 DOCUS:ENTING CCRRECTIVE ACTICN Action taken to wrrect a nonconforming item or activity is documented. If l additional action (including evaluation, investigation or analysis) is re-quired to prevent recurrence, the required action is indicated.

If significant additional action (including evaluation, investigation or analysis) is required to prevent recurrence, a separate corrective action report is initiated to assign and document the required action.

I 3.3 REPORTING CCRRECTIVE ACTION The Director - Environmental and Quality Assurance and the >!anager, 5:idland Project Quality Assurance review Consu:r.ers Power Company ncnconformance reports and replies. The Director - Environmental & Quality Assurtnce prepares a monthly status report which is issued to the Vice President -

Projects, Engineering and Ccastruction.

I It is the responsibility of the Vice President - Projects, Engineering and Construction to transmit pertinent ncnconformance reports and replies to the l President and Chief Executive Officer.

O pr07S0-0419d-13-167

s j QUALITY ASSURANCE PROGRAM POLICY Policy No 16 Page 3 of 3 Revision 12 Consumers power CORRECTIVE ACTION Date 4/2/82 3.4 CORRECTIVE ACTION BY SUPPLIERS Suppliers, including the A-E, NSSS Supplier, Constructor and others who pro-vide major items of equipment or who perform services, implement and follow a l system for corrective action according to the supplier's approved procedures.

Individual corrective actions are documented by the supplier and are reviewed by Midland Project Quality Assurance Department or Audit and Management Systees. Recuests for suoplier's corrective actica may be initiated by Censumers P:wer Comp 2ny organi:sti:ns by use of a nencenformance report, in l which case the completion is documented and reported.

l l

i cr0780-0419d-13-167 I

l l

- .-.,---,-,.-,-,o- - .

p QUALI1 Y ASSURANCE PROGRAM POLICY Policy No 17 v Page 1 of 3 Revision 12 Consumers power @AM ASSNCE RECORDS Date 42/82 1.0 GENERAL Consumers Power Company and its suppliers compile records as specified in applicable procedures, codes, regulatory requirements, National Standards and SARs and transmit them to the appropriate storage facilities.

The Midland Project Administrative Department in conjunction with other support groups, eg, Environmental & Quality Assurance, determines and identifies the documents that are to be retained for the project, who must retain them and the duration they must be retained. These requirements are also placed on the suppliers through appropriate provisions in procurement documents and on Consumers Power Company departments through documented procedures.

Examples of the types of records retained include procurement documents, pro-cedures, nondestructive examination results, inspection and test results, material analyses, qualification results, calibration records, noncon-formances and corrective action results. Inspection and test records, as a l minimum , identify the inspector or data recorder, the type of observation, s the results, the acceptability and action taken in connection with any deficiencies noted.

The Management and Budget Department / Management System Section and the Transmission Department Services / Engineering Records Center, in conjunction with other line support departments, establishes and maintains the Records Management System with appropriate indexes for location of the records.

Additional controls include storage of records in secured areas, in a manner that precludes their loss or deterioration. Copies of required lifetime and nonpermanent records to be maintained by Consumers Power Company which are generated during the project are ultimately forwarded to the General Office or the Plant Document Control Center. Drawings and specifications are forwarded to the Engineering Records Center.

The Midland Project Administrative Manager is responsible for the preparation of the Midland Project Records Management Program and Procedures Manual which delineates a planned program for the project's record management program; identifies the records management organization and identifies responsibil-ities for identifying, receiving, indexing, storage and control of records.

These records include documents such as specifications, "as-built" engineering drawings, final manufacurers' drawings, instruction manuals, results of surveillance, audits, inspections and tests and closely related data such as qualification of personnel, procedures and equipment.

  • Provisions are included in the Manual for record retention period, storage location and transmittal requirements.

The Manual is reviewed and approved by the Vice President - Projects, d Engineering and Construction; the. Director - Environmental and Quality I

pr0780-Ot.19e-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 17 1 d Page 2 of 3 Revision 12 g QUALITY ASSURANCE RECORDS Date 4/2/82 Assurance; the Vice President - Nuclear Operations; the Director - Management and Budget; and the Director - Quality Assurance - Nuclear Operations.

The Procedure section of the manual is reviewed and approved by the Manager -

Midland Project Administrative Department, the Director - Environmental &

Quality Assurance (for compliance with the QA Program) and other affected department heads.

When specific design, construction, preoperatienal test and hot functienal test activities have been completed, the remaining records are forwarded for storage. Record copies or original records are retained in the General Office, or Plant Document Control Center or the Engineering Records Center, as applicable.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Criterion B, Paragraph 17, Quality Assurance Records
b. ANSI N45.2, Criterion 18, Quality Assurance Records
c. ANSI N45.2.9, Requirements for Collection, Storage and Maintenance of Quality Assurance Records for Nuclear Power Plants 3.0 POLICY 3.1 SUPPLIER RECORDS Consumers Power Company principal suppliers, their subtier suppliers and other suppliers are required to identify and classify Quality Assurance records in accordance with requirements established during the design phase by the Midland Project Office or plant staff with assistance from other l Consumers Power Company departments, the Architect-Engineer, NSSS Supplier or other principal suppliers. The suppliers are required to maintain record management systems in accordance with appropriate provisions of ANS1 N45.2.9,

" Requirements for Collection, Storage and Maintenance of Quality Assurance Records for Nuclear Power Plants." Upon completion of their contract, the suppliers either continue maintaining the records or forward them to Consumers Power Company for incorporation into the Consumers Power Company Records Management System. l O

pr0780-0419e-13-167

e QUALITY ASSURANCE PROGRAM POLICY Policy No 17 Page 3 of 3 Revision 12

, QUALITY ASSURANCE RECORDS Date 4/2/82 3.2 CONSUMERS POWER COMPANY RECORDS Records or copies of records necessary for plant operations are retained by the Plant Document Control Center. Design output documents are retained by the Engineering Records Center.

The Midland Project Departments, System Protection and Laboratory Services, Purchasing, Audit & Management Systems, and General Services and other appropriate departments prepare Department Procedures covering the requirements for the identification, indexing, retention, storage, retrieval and eventual transfer of those quality records which are to be stored by the Plant or General Office Document Control Centers and the Engineering Records Center, as applicable.

O O

pr07S0-0419e-13-167

m I QUALITY ASSURANCE PROGRAM POLICY Policy No 18 Page 1 of 3 Revision 12 Consumers power AUDITS Date 4/2/82 1.0 GENERAL The Director - Environmental & Quality Assurance, is responsible for development and management of the Consumers Power Company Quality Assurance Audit Program for the Midland Project. To implement the audit programs, he assigns specific audit responsibilities to Quality Assurance personnel in his organization. In addition, audits are implemented by Midland Project Quality Assurance. Audits to verify compliance to the requirements of the Quality Assurance Program are conducted by qualified personnel who have no responsibilities in the areas audited. The audits are performed in accordance with established schedules using an audit plan and audit checklists. Audit results are documented and the findings are resolved with the supervisory heads of the audited organizations. Follow-up action, including reaudit, is taken to verify that deficiencies are corrected. Audit results are reported to Management personnel involved in the Quality Assurance Program.

I 2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 18, Audits

[SV} b. ANSI N45.2, Criterion 19, Audits l

c. ANSI N45.2.12, Requirements for Auditing of Quality Assurance Programs for Nuclear Power Plants
d. ANSI N45.2.23, Qualification of Quality Assurance Program Audit Personnel for Nuclear Power Plants 3.0 POLICY 3.1 QUALITY ASSURANCE PROGRAM AUDITS Audits of the Quality Assurance Program for the Midland Nuclear Plant are l performed at least once every 24 months or once every second calendar year in accordance with schedules established by Environmental & Quality Assurance to verify that the requirements identified in the Quality Assurance Program l Manual for the Midland Nuclear Plant are being implemented by the rssponsible Consumers Power Company personnel. The audits are accomplished by an audit team consisting of Environmental & Quality Assurance personnel, selected employees from other Consumers Power Company departments or by an audit team of Quality Assurance personnel under contract to Consumers Power Company.

)

V pr0780-0419f-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 18 Page 2 of 3 Revision 12 C:msumers power AUDITS Date W82 The designated audit team is made up of personnel from departments other than the department being audited. Results of the corporate audits are provided to the Vice President - Projects, Engineering and Construction. It is the responsibility of the Vice President - Projects, Engineering and Construction, to evaluate and approve recommendations therefrom and to inform the President and Chief Operating Officer of the Company of pertinent audit r sults.

3.2 QUALIFIED SUPPLIER AUDITS Midland Project Quality Assurance provides Quality Assurance personnel to l conduct preaward evaluations of prospective Consumers Power Company principal suppliers. Preaward evaluations including audits, where required, are conducted to verify that the principal supplier's Quality Assurance Program meets the appropriate procurement and Quality Assurance requirements prior to placement of the order. Audit team representatives may be selected from other Consumers Power Company departments, based on the type of product or service to be purchased and the technical background required.

Postaward Audits, where required, of principal offsite suppliers and certain other suppliers are also conducted on a periodic basis or at least once within the life of the contract, whichaver is shorter. These audits are conducted to verify implementation of Quality Assurance requirements.

Additional audits may also be made when the supplier extensively reorganizes, when deficiencies or nonconformances are discovered or to verify implementa-tion of required corrective action.

3.3 DEPARTMENT AUDITS Audit & Management Systems performs audits of the Consumers Power Company departments having quality-related responsibilities. The audits are conducted to verify that the quality-related responsibilities assigned to the departments by the Vice Presidents are being carried out. The audits are l accomplished by evaluating compliance to Quality Assurance Program Procedures and compliance to Department Procedures issued by the Consumers Power Company departments involved in the Quality Assurance Program. The results of these j audits are documented and reported to the responsible Department Directors or Managers and follow-up action, including reaudits, is taken to verify closecut of items requiring corrective action.

3.4 CONSTRUCTION AUDITS Audit & Management Systems audits the activities of onsite suppliers (ie, Architect-Engineer, Constructor, etc) and Consumers Power Company departments during construction. Audits are conducted in accordance with established schedules to verify that these suppliers or Consumers Power Company departments are implementing their own Quality Assurance Program and to verify the correct accomplishment of construction activities such as pr0780-0419f-13-167

QUALITY ASSURANCE PROGRAM POLICY Policy No 18 O @ Page 3 of 3 Revision 12 AUDITS Date 4/2/82 receiving, inspection, storage, handling, welding, concrete pouring, nondestructive examination, construction testing, preoperational and hot functional testing. In addition, these audits are supplemented by audits l conducted by Midland Project Quality Assurance. Audits of preoperational and hot functional testing are conducted jointly by, or in coordination with, Midland Project Quality Assurance and Audit & Management Systems. The l results of the audits are documented and corrective action is obtained when required.

\

l V

l pr0780-0419f-13-167 l

7- QUALITY ASSURANCE PROGRAM POLICY Policy No 19

(  ; Page 1 of 2 Revision 12 g PROGRAM REVIEW Date 4/2/82 1.0 GENERAL The Manager, Midland Project Quality Assurance assigns personnel within his l organization to review the Quality Assurance Programs of Consumers Power Company's Suppliers and lower-tier Suppliers. The Director - Environmental &

Quality Assurance assigns personnel within Audit and Management Systems to review the Quality Assurance Program of Consumers Power Company. The results of these reviews are reported to Consumers Power Company Vice Presidents responsible for the respective activities.

. 2.0 BASIS DOCUMENTS

a. NRC 10 CFR 50, Appendix B, Criterion 2, Quality Assurance Program
b. l ANSI N45.2, Criterion 2, Quality Assurance Program 3.0 POLICY 3.1 REVIEW DURING THE MIDLAND PROJECT n l

('/ ) Midland Project Quality Assurance monitors design and procurement activities l and maintains surveillance over construction and installation. Quality Assurance personnel or Quality Assurance personnel under contract to Consumers Power Company perform the following functions:

a. Review and approval of Consumers Power Company Principal Suppliers Quality Assurance Programs prior to commencement of activity.
b. Quality Assurance audits and surveillance of Suppliers to assure that the requirements contained in design and procurement documents, specifi-cations and Quality Assurance Programs are met,
c. Review of specifications, drawings, procedures, inspection checklists and other pertinent documents for Quality Assurance requirements.
d. Quality Assurance audits and surveillance at the Midland Nuclear Plant l site to evaluate the performance of contractors and subcontractors in implementing their Quality Assurance Programs.
e. Witnessing the performance of work activities and of construction and installation tests and inspections to assure that specified requirements are met and that required records are maintained.
f. Audits of the Consumers Power Company departments to assure that they are complying with the Quality Assurance Program for the Midland Nuclear Plant and Department Procedures.

(,_

4 N ,/ g. Review of nonconforming conditions to detect trends requiring corrective action.

pr0780-0419g-13-167

QUALITY ASSURANCE PROGRAAI POLICY Policy No 19 Page 2 of 2 Revision 12 PROGRAM REVIEW Date 4/2/82 These reviews, audits and surveillances are documented and reported to Management personnel and to the responsible Department Heads in accordance with Quality Assurance Program Policy No 20, " Program Reporting."

l 3.2 REVIEW OF CORPORATE QUALITY ASSURANCE PROGRMi The review of the Consumers Power Company Corporate Nuclear Quality Assurance Program is performed at least once every 24 months or once every second calendar year by an audit as described in Section 3.1 of Quality Assurance Program Policy No 18, " Audits." The audit is documented and reported to the Vice President - Projects Engineering and Construction and the Director -

Environmental & Quality Assurance. It is the responsibility of the Vice l President - Projects Engineering and Construction, to evalute and approve recommendations therefrom and to inform the President and Chief Executive Officer of the Company in accordance with Quality Assurance Program Policy No 20, " Program Reporting."

O l

i l

i O

l pr0780-0419g-13-167 i

i i

m QUALITY ASSURANCE PROGRAM POLICY Policy No 20

) Page 1 of 2 Revision 12 Consumers power PROGRAM REPORTING Date 4/2/82 1.0 GENERAL Reports of nonconforming conditions are prepared by Consumers Power Company and l submitted to the NTC and to the responsible departments according to the requirements set forth in Title 10 Code of Federal Regulations, applicable ANSI Standards and Regulatory Guides. Consumers Power Company requires Suppliers: l (a) To report potentially significant nonconformances to Consumers Power Company for determination of 10 CFR 50.55(e) reportability to the NRC and (b) to comply with 10 CFR 21.

2.0 BASIS DOCUMENTS

a. NRC 10 CFR 21, Reporting of Defects and Noncompliance
b. NRC 10 CFR 50, Appendix B, Criterion 16, Corrective Action
c. h3C 10 CFR 50.55, Conditions of Construction Permits, Paragraph (e) d.

I ANSI N45.2, Criterion 17, Corrective Action f~%

5 1 3.0 POLICY Q

3.1 REPORTING DURING THE MIDLAND PROJECT l

3.1.1 Reports by Environmental & Quality Assurance Environmental & Quality Assurance prepares and issues a monthly status report to the Vice President - Projects, Engineering and Construction.

Audir and Management Systems performs audits of the Quality Assurance l Program and reports the results of the audits to the Director -

Environmental & Quality Assurance; to the Vice President - Projects, Engineering and Construction and to other members of Management who have l either functional or line responsibilities, or both, for the audited area or activity. These reports summarize quality-related problems and non-conforma 4.ees and describe the status of their resolution.

I Each biennium, a major audit of the Quality Assurance Program is con-ducted and reported to the Vice President - Projects, Engineering and Construction.

The Vice President - Projects, Engineering and Construction, is responsi-ble for transmitting pertinent quality-related problems and nonconferm-ances to the President and Chief Executive Officer.

/m 1 pr0780-0419h-13-167 l

QUALITY ASSURANCE PROGRAM POLICY Policy No 20 C([)'l Page 2 of 2 Revision 12

^ #

  • CC3UD2m POWtf 3.1.2 Reports by Midland Project Quality Assurance Midland Project Quality Assurance prepares and issues a monthly status report to the Vice President - Projects, Engineering and Construction.

Results of audits performed by Midland Project Quality Assurance are reported to the Vice President - Projects, Engineering and Construction, Director - Environmental & Quality Assurance, and to other members of Management who have either functional or line responsibilities for the audited area or activity. These reports summarize quality-related problems and nonconformances and describe the status of their resolution.

The Director - Environmental & Quality Assurance and the Manager, Midland Project Quality Assurance Department conduct quarterly quality assarance Management meetings with the of ficer in charge, the appropriate Midland Project Office members, and other personnel, as applicable, applicable.

3.1.3 Reporting Significant Conditions to the NRC Significant nonconformances are recorded on nonconformance reports and are controlled in accordance with Quality Assurance Program Policies No 15, " Control of Nonconforming 1tems" and No 16, " Corrective Action."

Each such nonconformance is promptly reviewed by the Midland Project j Quality Assurance Department or, when occurring during preoperational testing, by the Site Management Office to determine its reportability to the NRC under the requirements of 10 CFR 50.55(e) and 10 CFR 21. l As applicable, nonconformances which are reportable under 10 CFR 50.55(c) are orally reported to the NRC by Midland Project Quality Assurance within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after their occurrence. Each such oral report is fol-lowed within 30 days by a written report to the NRC from the officer in charge. Alro, as applicable, nonconformances which are reportable under 10 CFR 21 are orally reported to the KRC by Midland Project Quality Assurance within two days after their evaluation. Each such oral report is followed within five days by a written report to the NRC from the officer in charge.

3.1.4 Supplier Responsibilities Consumers Power Company requires Suppliers to report each potentially significant nonconformance to the responsible Quality Assurance organization and to the organization having project management responsibility. Each such nonconformance is reviewed and evaluated for reportability to the NRC in accordance with the process described in Paragraph 3.1.3, above. In addition, Consumers Power Company requires Suppliers to comply with 10 CFR 21 for all procurements issued by Consumers Power Company after January 6, 1978 in accordance with the provisions delineated in 10 CFR 21.

pr0780-0419h-13-167