UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 23, 2011 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station

SUBJECT:

SUMMARY

OF THE JUNE 15, 2011, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On June 15, 2011, the Nuclear Regulatory Commission (NRC) held a public meeting at the Davis-Besse Energy Education Center in Oak Harbor, OH. The meeting was between NRC Region III management and FirstEnergy Nuclear Operating Company management to discuss the NRC=s assessment of the safety performance of Davis-Besse Nuclear Power Station, Unit 1, for the period from January 1 through December 31, 2010. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML111450416 and ML111640063, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.

The NRC began the meeting with an overview of the NRC=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of the performance of Davis-Besse Nuclear Power Station, Unit 1, in calendar year 2010, which was documented in the March 4, 2011, end-of-cycle assessment letter, as ML110620142. As part of this regulatory performance meeting, FirstEnergy briefly responded to the NRC=s assessment. The FirstEnergy presentation can be found in ADAMS as ML111720990. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-346 License Nos. NPF-3

Enclosure:

As Stated cc w/encl: Distribution via ListServ

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 23, 2011 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station

SUBJECT:

SUMMARY

OF THE JUNE 15, 2011, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On June 15, 2011, the Nuclear Regulatory Commission (NRC) held a public meeting at the Davis-Besse Energy Education Center in Oak Harbor, OH. The meeting was between NRC Region III management and FirstEnergy Nuclear Operating Company management to discuss the NRC=s assessment of the safety performance of Davis-Besse Nuclear Power Station, Unit 1, for the period from January 1 through December 31, 2010. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML111450416 and ML111640063, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.

The NRC began the meeting with an overview of the NRC=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of the performance of Davis-Besse Nuclear Power Station, Unit 1, in calendar year 2010, which was documented in the March 4, 2011, end-of-cycle assessment letter, as ML110620142. As part of this regulatory performance meeting, FirstEnergy briefly responded to the NRC=s assessment. The FirstEnergy presentation can be found in ADAMS as ML111720990. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-346 License Nos. NPF-3

Enclosure:

As Stated cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress\EOC Mtg Summary\Davis-Besse 2010 EOC Public Meeting Summary.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME TBriley:dtp JRutkowski JCameron DATE 06/22/11 06/22/11 06/23/11 OFFICIAL RECORD COPY

Letter to FirstEnergy Nuclear Operating Company from J. Cameron dated June 23, 2011.

SUBJECT:

SUMMARY

OF THE JUNE 15, 2011, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT DISTRIBUTION:

RidsNrrDorlLpl3-2 Resource Daniel Merzke RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource

Enclosure Meeting Participants NRC J. Cameron, Chief, Branch 6, Division of Reactor Projects, Region III A. Wilson, Resident Inspector, Davis-Besse V. Mitlyng, Senior Public Affairs Officer, Region III FirstEnergy Nuclear Operating Company B. Allen, Site Vice President, Davis-Besse B. Boles, Director of Site Operations, Davis-Besse J. Dominy, Director of Maintenance, Davis-Besse C. Price, Director of Special Projects, Davis-Besse K. Byrd, Director of Performance Improvement, Davis-Besse Ohio Emergency Management Agency B. Martin, Radiological Analyst Ottawa County D. Jensen, Ottawa County Administrator