October 23, 2012 Summary of Telephone Conference Call Held Between the Nuclear Regulatory and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power Station, License
ML13025A027
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/14/2013
From: Cuadradodejesus S
License Renewal Projects Branch 1
To:
CUADRADO, S, 415-2946
References
Download: ML13025A027 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 14,2013 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 23,2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE DAVIS-BESSE NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION (TAC. NO.

ME4640)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC or the applicant) held a telephone conference call on October 23, 2012, to discuss and clarify the applicant's response to the staff's requests for additional information (RAI) 4.2.4-1 concerning the Davis-Besse license renewal application. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with the applicant. A brief description on the status of the items is also included.

The applicant had an opportunity to comment on this summary.

Sincerely, Docket No. 50-346

Enclosures:

1. List of Participants
2. List of Requests for Additional Information cc w/encls: Listserv

ML13025A027 OFFICE LA:DLR PM:RPB1 :DLR BC:RPB1 :DLR NAME YEdmonds SCuadrado de Jesus DMorey DATE 02/5/2013 02/14/2013 02/12/2013

SUMMARY

OF TELEPHONE CONFERENCE CALL DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS October 23, 2012 PARTICIPANTS AFFI LlATIONS Samuel Cuadrado de Jesus U.S. Nuclear Regulatory Commission (NRC)

Chris Sydnor NRC Allen Hiser NRC Steven Dort FirstEnergy Nuclear Operating Company (FENOC)

Larry Hinkle FENOC Dennis Blakely FENOC Mark Rinckel AREVA ENCLOSURE 1

SUMMARY

OF TELEPHONE CONFERENCE CAll DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION October 23,2012 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC or the applicant) held a telephone conference call on October 23,2012, to discuss and clarify the following response to request for additional information (RAI) concerning the Davis-Besse license renewal application (lRA).

Response to RAI 4.2.4-1: Pressure-Temperature (P-T) Limits Discussion: The purpose of the call was to discuss the applicant's response to the staff request for additional information (RAI) 4.2.4-1 submitted by FENOC letter dated August 24, 2012.

The staff stated that it could not find information in the applicant's response that addressed how future P-T limit curves would be developed for the period of extended operation taking into account the neutron embrittlement effects on the extended beltline region and the localized stresses of the inlet and outlet nozzles. The staff also stated that this information needs to be provided in lRA Sections 4.2.4 and A.2.2.4 (USAR Supplement).

The applicant stated that the Davis-Besse P-T limit curves are currently limited to 32 effective full power years, and that additional analysis is required to extend the curves in the future.

The applicant also stated that in order to provide clarification and address the staff's concern it will submit a supplemental response to RAI 4.2.4-1 and as part of the supplemental response it will incorporate the clarification into lRA Sections 4.2.4 and A.2.2.4, both titled "Pressure Temperature Limits." The staff agreed with the applicant determination of providing a supplemental response to RAI 4.2.4-1.

Action: The applicant will provide a supplemental response to RAI 4.2.4-1 ENCLOSURE 2

SUBJECT:

Summary of Telephone Conference Call conducted on October 23.2012 DISTRIBUTION: