May 12, 2005 LICENSEE: AmerGen Energy Company, LLC FACILITY: Clinton Power Station

SUBJECT:

SUMMARY

OF THE APRIL 21, 2005, PUBLIC MEETING TO DISCUSS THE CLINTON END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On April 21, 2005, a public meeting was held at the Vespasion Warner Public Library in Clinton, Illinois between the Nuclear Regulatory Commission (NRC) and the Clinton Power Station management and staff. The purpose of the meeting was to discuss NRCs assessment of the Clinton Stations performance for the period of January 1, 2004, through December 31, 2004.

The NRC presentation provided an overall assessment of the Clinton Stations performance as described in NRCs Annual Assessment Letter - Clinton Power Station, dated March 2, 2005, (reference ADAMS accession number ML050620335). The Clinton Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives.

Mr. Michael McDowell, Clinton Plant Manager, responded on behalf of the licensee and the Clinton Power Station. Mr. McDowell discussed Clintons performance and accomplishments in 2004 and Clintons focus areas for 2005.

The meeting notice, NRC presentation, and slides summarizing Mr. McDowells presentation can be found in ADAMS as ML050950460, ML051310350, and ML051310363 respectively. A list of meeting participants can be found in the attached Enclosure.

Before adjourning the meeting, the NRC provided the opportunity for members of the public to ask questions. Local media representatives talked with NRC and licensee representatives after the meeting.

/RA/

Mark Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-461 License Nos. NPF-62

Enclosure:

As Stated See Attached Distribution

LICENSEE: AmerGen Energy Company, LLC FACILITY: Clinton Power Station

SUBJECT:

SUMMARY

OF THE APRIL 21, 2005, PUBLIC MEETING TO DISCUSS THE CLINTON END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On April 21, 2005, a public meeting was held at the Vespasion Warner Public Library in Clinton, Illinois between the Nuclear Regulatory Commission (NRC) and the Clinton Power Station management and staff. The purpose of the meeting was to discuss NRCs assessment of the Clinton Stations performance for the period of January 1, 2004, through December 31, 2004.

The NRC presentation provided an overall assessment of the Clinton Stations performance as described in NRCs Annual Assessment Letter - Clinton Power Station, dated March 2, 2005, (reference ADAMS accession number ML050620335). The Clinton Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives.

Mr. Michael McDowell, Clinton Plant Manager, responded on behalf of the licensee and the Clinton Power Station. Mr. McDowell discussed Clintons performance and accomplishments in 2004 and Clintons focus areas for 2005.

The meeting notice, NRC presentation, and slides summarizing Mr. McDowells presentation can be found in ADAMS as ML050950460, ML051310350, and ML051310363 respectively. A list of meeting participants can be found in the attached Enclosure.

Before adjourning the meeting, the NRC provided the opportunity for members of the public to ask questions. Local media representatives talked with NRC and licensee representatives after the meeting.

/RA/

Mark Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-461 License Nos. NPF-62

Enclosure:

As Stated See Attached Distribution DOCUMENT NAME: G:\Branch TSS\EOC Mtg. Notices 2005\Mtg. Summaries\Clinton.wpd To receive a copy of this document, indicate in the box "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII NAME MRing:co DATE 05/12/05 OFFICIAL RECORD COPY AmerGen Energy Company, LLC cc w/encl: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Mr. George Gore 702 W. Washington St.

Urbana, IL. 61801

AmerGen Energy Company, LLC ADAMS Distribution:

GYS JBH1 KNJ RidsNrrDipmIipb GEG KGO BCD CAA1 DRPIII DRSIII PLB1 JRK1

Enclosure Meeting Participants M. Ring, NRC B. Dickson, NRC D. Tharp, NRC G. Stauffer, NRC R. Frantz, AmerGen B. Bement, AmerGen M. Turbak, Public Citizen M. McDowell, Clinton Power Station N. Hightower, Clinton Power Station C. Settles, Illinois Emergency Management Agency (IEMA)

Charlie Williamson, AmerGen M. Frazier, Herald Review B. Paulsen, AmerGen E. Brady-Lunny, The Pantagraph K. Barlow, Clinton Daily Journal