March 02, 2005 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

ANNUAL ASSESSMENT LETTER - CLINTON POWER STATION (REPORT 05000461/200501)

Dear Mr. Crane:

On February 8, 2005, the NRC staff completed its end-of-cycle plant performance assessment of the Clinton Power Station. The end-of-cycle review for the Clinton Power Station involved the participation of the reactor technical divisions in evaluating performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2004. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Overall, the Clinton Power Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only reactor oversight process (ROP) baseline inspections at your facility through September 30, 2006.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2006. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle review meeting.

C. Crane In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Clinton Power Station Inspection/Activity Plan cc w/encl:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing

C. Crane last 12 months of the inspection plan are tentative and may be revised at the mid-cycle review meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

Clinton Power Station Inspection/Activity Plan cc w/encl:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing DOCUMENT NAME: G:\\Branch TSS\\EOC Ltrs\\eoc 030205\\Clinton.wpd To receive a copy of this document, indicate in the box "C" = Copy w ithout att achment/enclosure "E" = Copy w ith attachment/enclosure "N "

= No copy OFFICE RIII NAME MRing:co DATE 02/ /05 OFFICIAL RECORD COPY

C. Crane ADAMS Distribution:

AJM JBH1 RidsNrrDipmIipb GEG KGO BCD CAA1 DRPIII DRSIII PLB1 JRK1 ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)

Institute of Nuclear Power Operations (INPO)

Clinton Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 02/28/2005 08:15:08 Report 22 3

FPI

- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 05/02/2005 05/20/2005 Fire Protection IP 7111105T 1

3 FY 2005

- CLINTON INIT PREP 06/2005 Not Applicable 06/20/2005 06/24/2005 OL - INITIAL EXAM - CLINTON - JUN/JUL 2005 W90123 1

3 FY 2005

- CLINTON INIT EXAM 07/2005 Not Applicable 07/11/2005 07/22/2005 OL - INITIAL EXAM - CLINTON - JUN/JUL 2005 W90123 1

2 71114

- EP EXERCISE & EP PI INSP Baseline Inspections 10/03/2005 10/07/2005 Exercise Evaluation IP 7111401 1

Baseline Inspections 10/03/2005 10/07/2005 Performance Indicator Verification IP 71151 1

5 SSDPC

- SAFETY SYSTEM DESIGN & PERFORMANCE Baseline Inspections 11/14/2005 12/02/2005 Safety System Design and Performance Capability IP 7111121 1

2 71111.11

- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 11/14/2005 11/18/2005 Licensed Operator Requalification Program IP 7111111B 1

1 BI

- RAD ACCESS CONTROL,ALARA,INSTR, REMP Baseline Inspections 11/28/2005 12/02/2005 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 11/28/2005 12/02/2005 ALARA Planning and Controls IP 7112102 1

Baseline Inspections 11/28/2005 12/02/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1

Baseline Inspections 11/28/2005 12/02/2005 Radiological Environmental Monitoring Program IP 7112203 1

1 ISI

- CLINTON ISI INSPECTION Baseline Inspections 02/06/2006 02/10/2006 Inservice Inspection Activities - BWR IP 7111108G 1

1 IP 71121

- RP OUTAGE ACCESS CTRL & ALARA INSP Baseline Inspections 02/06/2006 02/10/2006 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 02/06/2006 02/10/2006 ALARA Planning and Controls IP 7112102 1

4 PI&R

- PROBLEM IDENITFICATION AND RESOLUTION Baseline Inspections 03/13/2006 03/31/2006 Identification and Resolution of Problems IP 71152B 1

1 71114

- BASELINE EP INSPECTION Baseline Inspections 03/20/2006 03/24/2006 Alert and Notification System Testing IP 7111402 1

Baseline Inspections 03/20/2006 03/24/2006 Emergency Response Organization Augmentation Testing IP 7111403 1

Baseline Inspections 03/20/2006 03/24/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1

Baseline Inspections 03/20/2006 03/24/2006 Performance Indicator Verification IP 71151 1

1 IP 71122

- RADWASTE PROCESSING & TRANSPORTATION Baseline Inspections 05/01/2006 05/05/2006 Radioactive Material Processing and Transportation IP 7112202 1

1 HS

- HEAT SINK INSPECTION Baseline Inspections 05/08/2006 05/12/2006 Heat Sink Performance IP 7111107B 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Clinton Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 02/28/2005 08:15:08 Report 22 1

IP 71121

- RP POST OUTAGE ACCESS CTRL/ALARA INSP Baseline Inspections 08/14/2006 08/18/2006 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 08/14/2006 08/18/2006 ALARA Planning and Controls IP 7112102 1

Baseline Inspections 08/14/2006 08/18/2006 Performance Indicator Verification IP 71151 1

2 M50.59

- MOD 50.59 INSPECTION Baseline Inspections 08/14/2006 09/01/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.