UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 April 6, 2015 LICENSEE: Exelon Generation Company, LLC FACILITY: Clinton Power Station

SUBJECT:

SUMMARY

OF THE APRIL 1, 2015, PUBLIC OUTREACH/OPEN HOUSE TO DISCUSS THE NRC 2014 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF CLINTON POWER STATION On April 1, 2015, from 4:00 p.m. to 7:00 p.m. (CDT), a public outreach/open house was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2014 End-of-Cycle plant performance assessment of the Clinton Power Station and with general information on the NRC. The outreach was held as part of the annual Business Expo conducted by the Chamber of Commerce of the town of Clinton, Illinois. The Expo was held at the Clinton High School and involved representatives of approximately 50 local businesses and government agencies staffing booths in the schools gymnasium.

Members of the public visited the various booths as dictated by their interests.

Representatives at the NRC booth had available for the public copies of the 2014 End-of-Cycle plant performance assessment of Clinton Power Station, the 2013-2014 Information Digest (NUREG-1350, volume 26), and other information brochures and fact sheets. The NRC representatives also discussed the Clinton Power Station or the NRC, in general, with over 30 members of the public, including a local radio station and a local newspaper. This outreach compared favorably with previous NRC open houses and public meetings to discuss the annual performance assessment of the plant, which had been conducted at the Clinton public library and for which few, if any, members of the public attended.

/RA/_______________________

Michael Kunowski, Branch Chief Branch 5 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

List of Meeting Attendees cc w/encl: Distribution via LISTSERV

CLINTON 2014 PERFORMANCE ASSESSMENT MEETING April 1, 2015 MEETING ATTENDANCE LIST NRC Attendees William Schaup, Senior Resident Inspector, Clinton Power Station Elba Sanchez-Santiago, Resident Inspector, Clinton Power Station Christopher Hunt, Acting Resident Inspector, Clinton Power Station Prema Chandrathil, Public Affairs Officer, Region III Office Mike Kunowski, Branch Chief, Region III Office Enclosure

LICENSEE: Exelon Generation Company, LLC FACILITY: Clinton Power Station

SUBJECT:

SUMMARY

OF THE APRIL 1, 2015, PUBLIC OUTREACH/OPEN HOUSE TO DISCUSS THE NRC 2014 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF CLINTON POWER STATION On April 1, 2015, from 4:00 p.m. to 7:00 p.m. (CDT), a public outreach/open house was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2014 End-of-Cycle plant performance assessment of the Clinton Power Station and with general information on the NRC. The outreach was held as part of the annual Business Expo conducted by the Chamber of Commerce of the town of Clinton, Illinois. The Expo was held at the Clinton High School and involved representatives of approximately 50 local businesses and government agencies staffing booths in the schools gymnasium.

Members of the public visited the various booths as dictated by their interests.

Representatives at the NRC booth had available for the public copies of the 2014 End-of-Cycle plant performance assessment of Clinton Power Station, the 2013-2014 Information Digest (NUREG-1350, volume 26), and other information brochures and fact sheets. The NRC representatives also discussed the Clinton Power Station or the NRC, in general, with over 30 members of the public, including a local radio station and a local newspaper. This outreach compared favorably with previous NRC open houses and public meetings to discuss the annual performance assessment of the plant, which had been conducted at the Clinton public library and for which few, if any, members of the public attended.

/RA/_______________________

Michael Kunowski, Branch Chief Branch 5 Division of Reactor Projects Docket No. 50-461 License No. NPF-62

Enclosure:

List of Meeting Attendees cc w/encl: Distribution via LISTSERV DISTRIBUTION:

See next page ADAMS Accession Number: ML15097A033 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII NAME MKunowski:mt DATE 04/06/15 OFFICIAL RECORD COPY

Memorandum from Michael Kunowski dated April 6, 2015

SUBJECT:

SUMMARY

OF THE APRIL 1, 2015, PUBLIC OUTREACH/OPEN HOUSE TO DISCUSS THE NRC 2014 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF CLINTON POWER STATION DISTRIBUTION w/encl:

Kimyata MorganButler RidsNrrDorlLpl3-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRSIII DRPIII Jim Clay Carmen Olteanu